Eaton Basics of Power System Design
Eaton Basics of Power System Design
UTILITY FEEDER #1 UTILITY FROM PSG-2A (SEE DWG E102) BUSWAY RISER
13.8 kV, 3Ø, + GND 60Hz METERING 4.16 kV, 3Ø, 60Hz (SEE DWG E106)
M
SPLICE IN PROPERTY LINE MANHOLE M1 4 6
M1-00 RBP-F3A T5-RBP-F3A PXM6000
N.O. (3)
(3) SINGLE PHASE POTHEADS (1/Ø) P=208A S=1804A METER
USG-1A "POINT A" 11.65KA SCA
M. H A PT'S
13.8kV, 1200A, AVAILABLE FROM UTILITY 8 AL 480V:120V
(4) GROUND STUDS (3-Ø, 1-GND) 250KA
50 kA SYM S.C. LO 300E /Ø.SPD
(2) UTILITY PT's MAIN CB
(15kV - 95KV BIL RATED)
(6) LIVE LINE INDICATORS (2/Ø) 14,400:120V 10A "RBS-F3A"
N.C.
E.O.
M. H P 2000 AF
7 1500kVA 1800 AT
LO F3D 4.16kV-480/277V LSG
TRIP M1 5.75% Z (3) 2000:5
TRIP S1 UTILITY
(3) PT'S CT's (2)
500:5 RHBP-F3A T4-RHBP-F3A
14,400:120V N.O. P=104A S=2082A
120:1 M. H A
(3) (3) 6 AL
27 59
TS RESIDENCE
M1 M1 VFI-3A
(3) (3) HALL B
SB 600A
(3) 800:5 (SEE DWG E105)
N.C.
STD (C100) M. H P
750kVA FR3 VFI PADMOUNT
5
SELECTOR SWITCH 55/65C 5.75% Z
EDR-5000-M1 1 TRIP M1 W/SURGE+LIGHTNING 4.16kV-60KV BIL
G R A TRIP S1 ARRESTERS 208/120V-20KV BIL
52-M1
M1A LO
1200A N.C. 52
(1) (3) (1) C/S
M1-L DFP-F3A T3-DFP-F3A
(1) N.O. P=139A S=1203A
50/51N 50/51 86 TRIP M1
86 M. H A
M1 M1 M1 TRIP S1 4 AL
T1
LO 200E DINING
TS SB
(3) 800:5 TS FACILITY
STD (C100) (SEE DWG E104)
(1) (3) N.C.
M. H P
51G 87 1000kVA
PXM6000 3
(3) 600:5 MR T1 T1 LO F3B 4.16kV-480/277V
METER
Set at 350:5 ETR-5000-T1 5.75% Z
(4) GROUND STUDS
TS TS TS
(3-Ø, 1-GND)
RHAP-F3A T2-RHAP-F3A
N.O. P=104A S=2082A
TRANSFORMER "T1" M. H A
2 AL
PRIMARY UNIT SUBSTATION STYLE M1-00
(1) "POINT C" F3A - RESIDENCE
13.8KV DELTA PRIMARY - 95KV BIL H2 63 VFI-2A
P/FA=479A 11.32KA SCA HALL A
4.16/2.4KV GROUNDED WYE - 60KV BIL T1 600A
WITHOUT MOTOR (SEE DWG E103)
EATON "PEAK" 55C/65C/75C H1 H3 71 49 P
N.C.
CU SCA & CABLE Z TO M. H 750kVA FR3 VFI PADMOUNT
7500/8400/9156 KVA KNAN X3 T1 T1 1 "POINT D" - 40,400 SCA
X0 T1 & T2-RHAP SELECTOR SWITCH 55/65C 5.75% Z
9375/10500/11445 KVA KNAF X1 W/SURGE+LIGHTNING 4.16kV-60KV BIL WITH UNLIMITED PRIMARY SCA
FR-3 FLUID FILLED, 6.5% MINIMUM Z
S/FA=1589A (1) (1)
X2 ARRESTERS 208/120V-20KV BIL & 50% MOTOR CONTRIBUTION
WITH SURGE + LIGHTNING ARRESTERS (1) 600:5 SEE XFMR TABLE 1.6-7 FOR
2000A BUSWAY M1-03
HI (C200) T2 ESTIMATING PURPOSES.
PSG-1A (4) GROUND STUDS "POINT B" T1 - 11.32KA (4) GROUND STUDS
CHILLER #1
(3-Ø, 1-GND) SCA WITHOUT MOTOR SCA, (3-Ø, 1-GND)
"BUS A" 4.16KV, CUP
2000A, 60KV BIL, SB CABLE % Z TO T1 & SB
(3) 2000:5 (3) 2000:5 (SEE DWG E107)
40KA SC RATED BUSWAY % Z
STD (C200) STD (C200)
M
EDR 1 (3) 600:5 MR
3000-S1 G R A PXM6000 Set at 600:5 M1-04
52-S1 EDR
(3) (1) LO METER
2000A N.C.
S1A 3000-F3
TRIP S1 52
51 86 C/S (1)
TRIP F1 TRIP S1 S1-L VFD-F2A
TRIP F2 S1 S1 50/51N
F3 G R A
TRIP F3 52-F3
TS SB F3A LO N.C.
(3) 2000:5 1200 52
TS 50/51 86 C/S DRAW-OUT
STD (C200) TRIP F3 F3-L
(1) F3 F3 DC TO AC
EBR
86 87 (3) (1) INVERTER
3000 (3) 2000:5 (3) 600:5
B1 B1 -B1 STD (C200) STD (C100)
(3) SB TS SB
TS AC TO DC
CONVERTER
TS SB TS SB
(3) 600:5 (3) 600:5 INTEGRAL
STD (C100) STD (C100) 24 PULSE
(3) (3)
XFMR
50/51 50/51
F1 G R A F2 G R A
(1) 52-F1 (1) 52-F2
LO LO
1200A N.C. 1200 N.C.
F1A F2A
52 (3) PT'S 52 CONTACTOR
50/51N 86 C/S 50/51N 86 C/S
TRIP F1 F1-L 4200V: TRIP F2 F2-L
F1 F1 F2 F2
120V
(1) 35:1 (1)
EDR EDR
3000-F1 (3) 600:5 MR 3000-F2 (3) 600:5 MR
(3) 400A
Set at 400:5 Set at 300:5
PXM6000 PXM6000
METER METER ISOLATION
(3) 2000:5 (3) 2000:5 E SWITCH
SB STD (C200) STD (C200)
SB
(4) GROUND STUDS (4) GROUND STUDS SC9000EP
(3-Ø, 1-GND) (3-Ø, 1-GND) MV-VFD
M1-02
M1-02
ENGINE
DIESEL
Open. S1 Cannot Close Until M1 is Closed. Include Key Interlocks as Shown.
N.O. CUP-F1A Provide MB-F1A Key Interlock With Generator Breaker "GB" and Tie Breaker
2
M. H A "LTA". Only the Single "MGTA" Key Can be Used to Close Any of these Breakers.
10
LO Provide Priority Load Shed Controls for Feeder Breakers in SUS-F1A Switchgear.
3
G Provide Interface With Generator Breaker "GB" to Enable Operation When Non-
N.C. Priority Loads have Been Shed.
M. H P FDR (SEE DWG E108)
9 "G" Provide All Magnum Breakers in SUS-F1A & RBS-F3A Switchgear With DT1150+
LO F1A 4 4000A BUSWAY TO
CLE 2000AF Trip Units Including Zone Selective Interlocking (ZSI) and Arc Flash Reduction
2000AT TIE CB "LTB" IN
600A Maintenance System (ARMS) in Compliance with Article 240.87 of the 2014 NEC.
PORTABLE "SUS-F1B"
LOAD BANK Provide Remote Touchscreen Panel With "Switchgear Dashboard Interface" to
P FA=461A 5 Monitor Operational Variables and Enable Arc Flash Reduction Maintenance Mode.
XFMR "ST-F1A"
CU 2500/3333kVA Wire All DT1150+ Trip Units Communications Ports to an Ethernet Gateway With
TOUCH 6
115C AA/FA 5 BACnet IP Connectivity. BMS Vendor Will Provide Field Wiring and Integrate Into
SCREEN
4.16KV-480/277V BMS System on a Separate Contract.
S FA=4000A Z=5.75%
2 3 2
MAIN CB TIE CB
MGTA (3) PT'S "GB" SECONDARY UNIT SUBSTATION "SUS-F1A"
"MB-F1A" 480V: EG BACNET IP "LTA"
LO E.O. 4000 AF 120V TO BMS LO E.O. 2000AF LO E.O. 4000 AF
4000 AT 2000AT 4000 AT
N.C. PXM6000 TO DT1150 N.O. LSG N.O.
LSG LSG
METER ETHERNET TRIP UNITS "DF5A"
01B (3) 4000:5 GATEWAY MAIN SWGR. BUS "A" 85KA, 480/277V, 4000A, 3-PH, 4W
01D 02A 02B 02C 02D 03A 03B 03C 03D 04A 04B 04C 04D
"DF1A" "DF2A" "DF3A" "DF4A" "DF6A" "DF7A" "DF8A" "DF9A" "DF1OA" "DF11A" "DF12A"
250KA/Ø E.O. 800AF E.O. 800AF E.O. 1600AF E.O. 1600AF E.O. 800AF E.O. 800AF E.O. 800AF E.O. 1600AF E.O. 800AF E.O. 800AF E.O. 800AF
SPD 600 AT 600 AT 1600 AT 1600 AT 800 AT 400 AT 600 AT 1600 AT 400 AT 500 AT 500 AT
LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG
SPARE SPARE SPARE SPARE
(SEE DWG E109)
FROM GEN A
NORMAL ATS-A GENERATOR
SOURCE SOURCE
BYPASS ATC-900
1600AF DSB-DF4A SEE SCHEDULE DSB-DF4A ISOLATION TRANSFER
1600AT 480V, 1600A, ATS CONTROL
FOR LOADS PP-DF6A 480V, 600A,
3Ø, 4W, 65 KAIC
120KA/Ø 800AF 3Ø, 3W, 65 KAIC
SPD 800AT
MAINTENANCE
225AF 400AF 800AF 600AF 400AF 225AF 400AF 480/277V, 800A, ISOLATION
175AT 250AT 800AT 600AT 250AT 200AT 250AT 3Ø, 4W, 65 KAIC BYPASS
MBP BIB RIB
SPARE SPACE 2X
SEE SCHEDULE PP-DF6A UPS1
FOR LOADS 300KVA
400A 150A 150A 150A 150A 400A 400A 150A 150A 150A 150A 150A 150A
FR10 SIZE4 SIZE4 SIZE4 SIZE4 SIZE5 SIZE5 SIZE4 SIZE4 SIZE4 SIZE4 SIZE4 SIZE4
261A FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR MIS
DC-DS-A
3R 3R 3R 3R
6 POLE 6 POLE 6 POLE 6 POLE
200 75 75 75 75 150 150 75 75 75 75 75 75
BAT-A
NCHWP-1 CWP-1 CWP-2 CWP-3 CWP-4 CHWP-1 CHWP-2 CT-1 CT-2 CT-3 CT-4 SA-1 EF-1
240FLA 96FLA 96FLA 96FLA 96FLA 180FLA 180FLA 96FLA 96FLA 96FLA 96FLA 96FLA 96FLA
PDU-1
480V-3Ø 600AF 120KA/Ø
600AF 400AF IFS-DF7A 3W,65kA 500AT
150A SPD
600AT DSB-DF2A 400AT
P=361A
120KA/Ø 480V, 600A, XFMR-DF8A P=361A
SPD 3Ø, 3W, 65 KAIC XFMR-DF7A P=90A 300KVA XFMR-UPS1
225A 75KVA 480-208/120V 300KVA
480- 480-208/120V
S=833A
208/120V S=208A
150AF 150AF 150AF 150AF 150AF 150AF 150AF S=833A 208/120V, 3Ø, 4W
"DF7AP"
40AT 15AT 90AT 100AT 90AT 100AT 100AT RP-DF8A
480/277V 225A
SPARE SPACE 2X 3Ø, 4W, 65KA 225A
1200AF 400AF 400AF
POW-R-COMMAND 1000AT 400AT 400AT
LIGHTING CONTROL 208/120V, 225A,
3Ø, 4W, 10 KAIC
POW-R-COMMAND 208/120V, 1200A, CDP-A CDP-B
10 2 4X 4X 3Ø, 4W, 65 KAIC 42 Circuit 42 Circuit
RECEPTACLE CONTROL
GYCOL FUEL HVAC HEAT COMFORT HEAT
PUMP PUMP AHU-1,2,3,4 REJ. COOLING REJ.
GCP-1 FOP-1 UNITS CH-1 UNITS SEE SCHEDULE IFS-DF7AP & DF7AS SEE SCHEDULE RP-DF8A SEE SCHEDULE PDU-1
HRU-1,2,3,4 HRU-5-9 FOR NORMAL & CONTROLLED LOADS FOR LOADS FOR CRITICAL LOADS
current flowing through the conductor Figure 6. Current Transformer Symbols (3) 120:1 (3) 13.8 kV, 1200 A, 50 kA SYM S.C.
(15 kV - 95 KV BIL RATED)
they surround induces a proportional In the case of Differential Protection (3) 800:5
SB
isolated low level signal (either 1 A or Circuits such as the 87-T1 Transformer
STD (C100)
The dots, X’s or boxes are used to denote current flowing out of it. When more
(4) GROUND STUDS
(3-Ø, 1-GND)
TS TS TS
P/FA=479 A
63
(1)
conductor generally face toward the out, the relay senses the “differential” H3 CU 71
T1
49
source of the current flow. The polarity and trips the circuit breakers at high 1
X0
X3 T1 T1
orientation for donut style CTs. quantity “(3)” next to the CTs. This STD (C200)
TS SB
one-line on Page 8 are shown this (3) 2000:5
STD (C200)
or the “GB” breaker.This may or may not SCA & CABLE Z TO M.H P
750 kVA FR3 VFI PADMOUNT
1 “POINT D” - 40,400 SCA
T1 & T2-RHAP SELECTOR SWITCH 55/65C 5.75% Z
1
DIESEL
2 3 2
MAIN CB TIE CB
MGT (3) PT’S “GB” SECONDARY UNIT SUBSTATION “SUS-F1A”
“MB-F1A” 480 V: EG BACNET IP “LTA”
LO E.O. 4000 AF 120 V TO BMS LO E.O. 2000AF LO E.O. 4000 AF
4000 AT 2000AT 4000 AT
N.C. PXM6000 TO DT1150 N.O. LSG N.O.
LSG LSG
METER ETHERNET TRIP UNITS “DF5A”
01B (3) 4000:5 GATEWAY MAIN SWGR. BUS “A” 85 KA, 480/277 V, 4000 A, 3-PH, 4W, (ALL BREAKERS RATED SC AT 85 KA)
01D 02A 02B 02C 02D 03A 03B 03C 03D 04A 04B 04C 04D
“DF1A” “DF2A” “DF3A” “DF4A” “DF6A” “DF7A” “DF8A” “DF9A” “DF1OA” “DF11A” “DF12A”
250KA/Ø E.O. 800AF E.O. 800AF E.O. 1600AF E.O. 800AF E.O. 800AF E.O. 800AF E.O. 800AF E.O. 800AF E.O. 800AF E.O. 800AF E.O. 800AF
SPD 600 AT 600 AT 1600 AT 600 AT 800 AT 400 AT 600 AT 600 AT 400 AT 500 AT 500 AT
LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG
SPARE SPARE SPARE SPARE
01D 02A 02B 02C 02D 03A 03B 03C 03D 04A 04B 04C 04D
“DF1A” “DF2A” “DF3A” “DF4A” “DF6A” “DF7A” “DF8A” “DF9A” “DF1OA” “DF11A” “DF12A”
250 KA/Ø E.O. 800AF E.O. 800AF E.O. 1600AF E.O. 1600AF E.O. 800AF E.O. 800AF E.O. 800AF E.O. 1600AF E.O. 800AF E.O. 800AF E.O. 800AF
SPD 600 AT 600 AT 1600 AT 1600 AT 800 AT 400 AT 600 AT 1600 AT 400 AT 500 AT 500 AT
LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG
SPARE SPARE SPARE SPARE
(SEE DWG E109)
FROM GEN A
NORMAL ATS-A GENERATOR
SOURCE SOURCE
BYPASS ATC-900
1600AF DSB-DF4A SEE SCHEDULE DSB-DF4A ISOLATION TRANSFER
1600AT 480V, 1600A, ATS CONTROL
FOR LOADS PP-DF6A 480 V, 600 A,
3Ø, 4W, 65 KAIC
120 KA/Ø 800AF 3Ø, 3W, 65 KAIC
SPD 800AT
400 A 150 A 150 A 150 A 150 A 400 A 400 A 150 A 150 A 150 A 150 A 150 A 150 A
FR10 SIZE4 SIZE4 SIZE4 SIZE4 SIZE5 SIZE5 SIZE4 SIZE4 SIZE4 SIZE4 SIZE4 SIZE4
261A FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR MIS
DC-DS-A
3R 3R 3R 3R
6 POLE 6 POLE 6 POLE 6 POLE
200 75 75 75 75 150 150 75 75 75 75 75 75
BAT-A
NCHWP-1 CWP-1 CWP-2 CWP-3 CWP-4 CHWP-1 CHWP-2 CT-1 CT-2 CT-3 CT-4 SA-1 EF-1
240FLA 96FLA 96FLA 96FLA 96FLA 180FLA 180FLA 96FLA 96FLA 96FLA 96FLA 96FLA 96FLA
PDU-1
480V-3Ø 600AF 120 KA/Ø
600AF 400AF IFS-DF7A 3W,65 kA 500AT
150 A SPD
600AT DSB-DF2A 400AT
P=361A
120KA/Ø 480V, 600A, XFMR-DF8A P=361A
SPD 3Ø, 3W, 65 KAIC XFMR-DF7A P=90A 300 KVA XFMR-UPS1
225 A 75KVA 480-208/120 V 300 KVA
480- 480-208/120 V
208/120 V S=833A
150AF 150AF 150AF 150AF 150AF 150AF 150AF S=208A S=833A
“DF7AP” 208/120 V, 3Ø, 4W
40AT 15AT 90AT 100AT 90AT 100AT 100AT RP-DF8A
480/277 V 225A
SPARE SPACE 2X 3Ø, 4W, 65KA 225A
1200AF 400AF 400AF
POW-R-COMMAND 1000AT 400AT 400AT
LIGHTING CONTROL 208/120 V, 225 A,
3Ø, 4W, 10 KAIC
208/120 V, 1200 A, CDP-A CDP-B
POW-R-COMMAND
10 2 4X 4X 3Ø, 4W, 65 KAIC 42 Circuit 42 Circuit
RECEPTACLE CONTROL
GYCOL FUEL HVAC HEAT COMFORT HEAT
PUMP PUMP AHU-1,2,3,4 REJ. COOLING REJ.
GCP-1 FOP-1 UNITS CH-1 UNITS SEE SCHEDULE IFS-DF7AP & DF7AS SEE SCHEDULE RP-DF8A SEE SCHEDULE PDU-1
HRU-1,2,3,4 HRU-5-9 FOR NORMAL & CONTROLLED LOADS FOR LOADS FOR CRITICAL LOADS
LOAD
As soon as generator power is available,
the ATS will transfer to the generator Figure 17. UPS-1 Connection Option 2
source and begin to feed the UPS’s
Figure 15. Integrated Facility inverter section.
System Switchboards
process is developing a schedule. conductor ampacity at 60 °C making it 12 20 4/0 230
less practical. It also means that the 10 30 250 255
The overcurrent protection of many equipment could be fed from 90 °C 8 50 300 285
loads, such as motors and distribution conductors, but only if applied at the
6 65 350 310
transformers, must conform to the 75 °C ratings due to the limitations of
the equipment ratings. 4 85 400 335
requirements of Articles 240, 430 and
450 of the National Electrical Code. 3 100 500 380
Particular consideration needs to The following tables are adjusted in 2 115 600 420
be given to the length and type of accordance with NEC 240.4(D) to show
1 130 700 460
conductors that will need to connect the actual allowable ampacities of copper
and aluminum conductors terminating in 1/0 150 750 475
the distribution equipment.
electrical distribution assemblies. 2/0 175 1000 545
As cable length increases, so does its
resistance in the circuit leading to a drop in A schedule based on the allowable
ampacity of copper conductors in Table 2. Ampacity of AL Conductors
the voltage at the end of the conductor run
feeding the loads. Cable lengths exceeding Table 1 is shown in Figure 19. Conductor Ampacity (Aluminum)
100 feet generally need to be upsized to It includes the relevant requirements Conductor Amperes Conductor Amperes
offset for voltage drop concerns. for secondary unit substation “SUS-F1A” Size at 75 ºC Size at 75 ºC
shown on the One-Line. This schedule
Cable length, size and the raceway they outlines the breaker frame sizes, trip 14 — 3/0 155
are installed in, also have an impact on settings and particulars of the trip 12 15 4/0 180
the impedance of the conductor in the units required. 10 25 250 205
circuit. Greater impedance helps to 8 40 300 230
reduce the available short circuit at the It also annotates the names for
the breakers as well as their circuit 6 50 350 250
terminals of the distribution equipment
or end load. nameplate designations. The cable 4 65 400 270
sizes and quantities are determined 3 75 500 310
by utilizing the tables in the NEC, 2 90 600 340
(as condensed into Table 1). 1 100 700 375
1/0 120 750 385
2/0 135 1000 445
1C MB-F1A 4000 4000 LSG + ZSI MAIN BREAKER "MB-F1A" Close Coupled
2A DF1A 800 600 LSIG + ZSI 3N SPARE Future OVERHEAD
2B DF2A 800 600 LSIG + ZSI 3N DSB-DF2A (2) sets (4)#350MCM +(1)#1G 2 3" UNDERGROUND
2C DF-3A 1600 1600 LSIG + ZSI 3 MCC-DF3A (4) sets (3)#600MCM + (1)#4/0G 4 4" UNDERGROUND
2D DF-4A 1600 1600 LSIG + ZSI 3N DSB-DF4A (4) sets (3)#600MCM + (1)#4/0G 4 4" UNDERGROUND
3A DF-5A 800 600 LSIG + ZSI 3N SPARE Future OVERHEAD
SUS - F1A
3B DF6A 800 800 LSIG + ZSI 3N PP-DF6A (2) sets (4)#600MCM + (1)#1/0G 2 3.5" UNDERGROUND
3C DF7A 800 400 LSIG + ZSI 3N IFS-DF7A (1) set (4)#600MCM + (1)#3G 1 3.5" UNDERGROUND
3D DF8A 800 600 LSIG + ZSI 3 XFMR-DF8A (2) sets (4)#350MCM +(1)#1G 2 3" UNDERGROUND
4A DF9A 800 600 LSIG + ZSI 3N SPARE Future OVERHEAD
4B DF10A 800 400 LSIG + ZSI 3N SPARE Future OVERHEAD
4C DF11A 800 500 LSIG + ZSI 3N SPARE Future OVERHEAD
4D DF12A 800 500 LSIG + ZSI 3 UPS1-INPUT-DF12A (2) sets (3)#250MCM +(1)#2G 2 2" UNDERGROUND
5C LTA 4000 4000 LSG + ZSI 3N TIE CB "LTA" 4000A Busway OVERHEAD
Note 1: Looking at the front of the Unit Substation; Right of the Main Breaker is BUS 1. The TIE Breaker is on the far Right of the Lineup and connects to
Switchgear "SUS-F1B" Through 4000A Busway
Code: “covers service conductors and Part II - Overhead Service Conductors Part III - Underground Service Conductors
equipment for the protection of services 230.24 - Clearances 230.32 - Depth of Burial & Protection
and their installation requirements”. Service Head Terminal Box, Meter or Other Enclosure
references that apply to incoming service Part V - Service Equipment General Utility
Meter
Article 250 - Grounding & Bonding
equipment. These range from conductor
Part VI - Service Equipment Disconnecting Means
types from overhead service utility drops Part VII - Service Equipment Overcurrent Protection
1000 A & Above Main CB at
to underground utility feeds and their 230-95 - Ground Fault Protection of Equipment
480/277 Vac to be Provided with
Equipment Ground Fault Protection
proper installation. Article 408 - Switchboards, Switchgear & Panelboards
Parts V, VI and VII of Article 230 spell out Article 240 - Overcurrent Protection
the common requirements for low- Articles 215 & 225 - Feeders
voltage service equipment <1000 Vac. Articles 210 & 225 - Branch Circuits 75 kVa
These parts cover locations permitted, HVAC
480–208/120 V
0–150 V 208/120 V 3 ft 3 ft 3 ft
151–600 V 480/277 V 3 ft 3 ft 6 in 4 ft
601–2500 V 4160 V 3 ft 4 ft 5 ft
2501–9000 V 13,800 V 4 ft 5 ft 6 ft
9001–25,000 V 34,500 V 5 ft 6 ft 9 ft
NEC Definition of Live Parts: “Energized conductive Components.”
NEC Definition of Energized: “Electrically Connected to, or is a source of voltage.”
MVTransformers with Snubber Capacitors or MV EPR Cables holding a capacitive charge are considered
“Live” until the voltage is bled off by grounding procedures.
Typical Typical
Spare
1 1 1 1 1 1 1
Automatic
1 4000 A Transfer Switch
Main CB
Gen. CB
Utility Emergency
CTs or Standby
Metering
PTs Generator
Utility 4000A at 480Y/277V
Service 100,000A Available Fault Current
Figure 23. Typical Power Distribution and Riser Diagram for a Commercial Office Building
a Include ground fault trip.
75 kVA
480–208/120 V
HVAC
Distribution Distribution Lighting
Panel Panel Panelboard
Load Load
NO
NC
K K
Typical Single-Ended Substation
Utility #1 Utility #2
Figure 40. Single Bus
Load Load
0.5
1 2 3 4
0
0.5
–1.0
Relationships
The following Figure 45 describes the
relationship between fault current peak Peak multiplication factor =
values, rms symmetrical values and rms
asymmetrical values depending on the
calculated X/R ratio. The table is based on
the following general formulas:
Where:
I = Symmetrical rms current
Ip = Peak current
e = 2.718
w = 2 p f
f = Frequency in Hz
t = Time in seconds
2.8
2.7
PEAK MAXIMUM ASYMMETRICAL
RMS SYMMETRICAL
2.5
2.4
2.3
2.2 1.8
R
TO
C
2.1 1.7
FA
N
PEAK MULTIPLICATION FACTOR =
I O
AT
2.0 1.6
IC
PL
I
LT
1.9 1.5
U
M
R
AK
CTO
1.8 1.4
PE
FA
N
TIO
1.7 L ICA 1.3
IP
U LT
1.6 SM 1.2
RM
1.5 1.1
1.4
1 1.5 2 2.5 3 4 5 6 7 8 9 10 15 20 25 30 40 50 60 70 80 90 100
CIRCUIT X/R RATIO (TAN PHASE)
7
5
12
10
5
8
100 100 100
6
4
4
3
90 90 90
3
80 80 80
IME
Ratio X/R
Ratio X/R
Ratio X/R
70 70 70
TIME
GT
IN
60 60 RT
ING
60 PA
ART
50 50 50
AC
T P
NT
AC
CO
40 40 40
NT
CO
30 30 30
5-CYCLE 5-CYCLE 5-CYCLE
BREAKER BREAKER BREAKER
20 20 20
10 10 10
1.0 1.1 1.2 1.3 1.4 1.0 1.1 1.2 1.3 1.4 1.0 1.1 1.2 1.3 1.4
Multiplying Factors for E / X Amperes Multiplying Factors for E / X Amperes Multiplying Factors for E / X Amperes
Figure 46. Three-phase Fault Multiplying Factors Figure 47. Line-to-Ground Fault Multiplying Factors Figure 48. Three-phase and Line-to-Ground Fault
that Include Effects of AC and that Include Effects of AC and Multiplying Factors that Include Effects of DC
DC Decrement DC Decrement Decrement Only
C. E/X x 1.6 ≤ rms closing and Table 9. Application Quick Check Table
latching capability of the breaker
Source Operating Voltage
and/or Transformer kV
MVA Rating
E/X x 2.7 ≤ Crest closing and Motor Load 2.4 4.16 6.6 12 13.8
latching capability of the breaker.
100% 0%
The ANSI standards do not require the 1 1.5 50VCP-W250 50VCP-W250 150VCP-W500 150VCP-W500 150VCP-W500
inclusion of resistances in the calculation 1.5 2 12 kA 10.1 kA 23 kA 22.5 kA 19.6 kA
of the required interrupting and close 2 2.5
and latch capabilities. Thus the calculated 2.5 3 50VCP-W250
values are conservative. However, when 3 3.75 36 kA
the capabilities of existing switchgear 3.75 5
are investigated, the resistances should 5 7.5 50VCP-W250
be included. 7.5 10 50VCP-W350 33.2 kA
10 a 10 49 kA
For single line-to-ground faults, the
symmetrical interrupting capability 10 12 a
12 15 50VCP-W350 75VCP-W500
is 1.15 x the symmetrical interrupting 41.3 kA
capability at any operating voltage, but 46.9 kA
not to exceed the maximum symmetrical 15 20
capability of the breaker. 20 a 20 BreakerType and symmetrical interrupting 150VCP-W750 150VCP-W750
capacity at the operating voltage 35 kA 30.4 kA
25
ANSI C37 provides further guidance for 30
medium voltage breaker application.
50 a 150VCP-W1000 150VCP-W1000
46.3 kA 40.2 kA
Reclosing Duty a Transformer impedance 6.5% or more, all other transformer impedances are 5.5% or more.
ANSI Standard C37.010 indicates the
reduction factors to use when circuit
breakers are used as reclosers. Eaton
VCP-W breakers are listed at 100% rating
factor for reclosing.
50VCP–W250 4.76 kV 29 kA 36 kA 58 kA I3
(29) = 33.2 kA I1
Note: Interrupting capabilities I1 and I2 at operating voltage must not exceed maximum symmetrical
interrupting capability Kl.
13.8 kV
50VPC-W250
6.9 kV
1
X X
= 25 = 35
R R
2 3
197A FL 173A FL
X''d = 20% X''d = 25%
3000 hp
1.0 PF 2500 hp
Syn. Ind.
Note: These are derating factors applied to the breaker and are the inverse of MF.
Page 53
A. System Diagram B. Impedance Diagram (Using “Short Cut” Method for Combining Impedances and Sources).
A B C
Utility Source 500 MVA
Major Contribution
Utility
Cables
Transformer
Switchboard Fault
1000 kV A
5.75%
480V Cables
Cable Fault
Switchboard Fault
F1 Zm
Zu 0.002 pu Zm 1.00 pu Zm 1.00 pu 1.00 pu
100 ft (30m)
3–350 kcmil Cable Zc
in Steel Conduit Zc Zc
A B C 0.0575 pu 0.027 pu 0.027 pu 0.027 pu
Switchboard Fault Zequiv
Mixed Load—Motors and Lighting F1
Each Feeder—100 ft (30m) of 3–350 kcmil
Cable in Steel Conduit Feeding Lighting and Zc 0.027 pu
250 kVA of Motors
Cable Fault
F2 F2
Cable Fault
Combining Series Impedances: ZTOTAL = Z1 + Z2 + ... +Zn
C. Conductor impedance from Table 61. 1 = 1 + 1 + ... 1
Combining Parallel Impedances:
Conductors: 3–350 kcmil copper, single ZTOTAL Z1 Z2 Zn
conductors Circuit length: 100 ft (30 m),
in steel (magnetic) conduit Impedance
Z = 0.0617 ohms/ 1,000 ft (304.8 m). 0.0595 pu
0.0777 pu
0.342 pu 0.0507 pu
ZTOT = 0.00617 ohms (100 circuit feet)
F1 F1 Es
D. Fault current calculations (combining
0.027 pu 0.027 pu
impedances arithmetically, using
approximate “Short Cut” method— F2
see Note 4, Page 53)
Voltage Drop Formulas If the receiving end voltage, load current and power factor (PF)
are known.
Approximate Method
Voltage Drop
ER is the receiving end voltage.
where abbreviations are same as below “Exact Method.” Exact Method 2—If receiving or sending mVA and its power
factor are known at a known sending or receiving voltage.
Exact Methods
Voltage drop
Exact Method 1—If sending end voltage and load PF are known.
where:
EVD = Voltage drop, line-to-neutral, volts
where:
ES = Source voltage, line-to-neutral, volts
ER = Receiving line-line voltage in kV
I = Line (Load) current, amperes
ES = Sending line-line voltage in kV
R = Circuit (branch, feeder) resistance, ohms
MVAR = Receiving three-phase mVA
X = Circuit (branch, feeder) reactance, ohms
MVAS = Sending three-phase mVA
cosq = Power factor of load, decimal
Z = Impedance between and receiving ends
sinq = Reactive factor of load, decimal
g = The angle of impedance Z
qR = Receiving end PF
qS = Sending end PF, positive when lagging
10,000
1000
2000
3000
4000
5000
6000
7000
8000
9000
100
200
300
400
500
600
700
800
900
70
80
90
.5 .6 .7 .8 .9 1 2 3 4 5 6 7 8 9 10 20 30 40 50 60
1000 1000
communications systems, and the like. In 900
800 4.16 kV 250 MVA
900
800
700 700
addition, economic loss from outages can 600 600
Thru Fault
able analysis and selection and application
30 30
Protection Curve
of each overcurrent protective device in 20 (More Than 10 in
Lifetime)
C 1,600A 20
TIME IN SECONDS
TIME IN SECONDS
5 5
the overcurrent disturbance so that the 4
20,000A
4
.04 .04
.03 .03
4.16 kV Fault
A
480V Fault
.02 .02
Max.
.01 .01
.5 .6 .7 .8 .9 1 2 3 4 5 6 7 8 9 10 20 30 40 50 60
70
80
90
100
200
300
400
500
600
700
800
900
1000
2000
3000
4000
5000
6000
7000
8000
9000
10,000
Figure 55. Time-Current Characteristic Curves for Typical Power Distribution System Protective Devices
Coordination Analysis
(1) Apparatus Fully insulated Lowest Partially graded Partially graded Partially graded
insulation
(2) Fault to Usually low Maximum value rarely Cannot satisfactorily be Low Negligible except when
ground current higher than three-phase reduced below one-half Petersen coil is short
short circuit current or one-third of values circuited for relay
for solid grounding purposes when it may
compare with solidly
grounded systems
(3) Stability Usually unimportant Lower than with other Improved over solid Improved over solid Is eliminated from
methods but can be grounding particularly grounding particularly consideration during
made satisfactory by use if used at receiving end if used at receiving end single line-to-ground faults
of high-speed breakers of system of system unless neutralizer is short
circuited to isolate fault by
relays
(4) Relaying Difficult Satisfactory Satisfactory Satisfactory Requires special
provisions but can be
made satisfactory
(5) Arcing Likely Unlikely Possible if reactance Unlikely Unlikely
grounds is excessive
(6) Localizing Effect of fault transmitted Effect of faults localized to Effect of faults localized to Effect of faults transmitted Effect of faults transmitted
faults as excess voltage on system or part of system system or part of system as excess voltage on as excess voltage on
sound phases to all parts where they occur where they occur unless sound phases to all sound phases to all
of conductively reactance is quite high parts of conductively parts of conductively
connected network connected network connected network
Because the method of grounding these conditions at any point in a system With selective ground fault isolation the
affects the voltage rise of the unfaulted is not effectively grounded. fault current should be at least 60% of the
phases above ground, ANSI C62.92 three-phase current at the point of fault.
classifies systems from the point of view The aforementioned definition is Damage to cable shields must be checked.
of grounding in terms of a coefficient of significance in medium-voltage Although this fact is not a problem
of grounding distribution systems with long lines and except in small cables, it is a good idea
with grounded sources removed during to supplement the cable shields returns
light load periods so that in some locations of ground fault current to prevent
in the system the X0/X1, R0/X1 may exceed damage, by installing an equipment
the defining limits. Other standards (cable grounding conductor.
and lightning arrester) allow the use of
This same standard also defines systems 100% rated cables and arresters selected The burdens on the current transformers
as effectively grounded when COG is less on the basis of an effectively grounded must be checked also (for saturation
than or equal to 0.8. Such a system would system only where the criteria in the above considerations), where residually
have X0/X1 less than or equal to 3.0 and are met. In effectively grounded system connected ground relays are used and the
R0/X1 less than or equal to 1.0. Any other the line-to-ground fault current is high and current transformers supply current to
grounding means that does not satisfy there is no significant voltage rise in the phase relays and meters.
unfaulted phases.
M2N
M1G
M2G
M1N
Feeder Feeder
TN
TG
a a
tion between the tie breaker and the
33-
two main circuit breakers is achieved by 52-T
4-Wire 4-Wire
pre-set current pickup and time delay Load
B5 B4 B4 B5 B4 B5 Load
settings between devices GFR/1, GFR/2 B4 B5
Digitrip Digitrip Digitrip
B4 B5
Main Bkr. Main Bkr. Main Bkr.
and GFR/T. Digitrip 52-1 52-T 52-2 Digitrip
ential scheme is shown in Figure 63. The Sensor Main Sensor Main
scheme typically relies upon the vector Main Breaker 52-1 Breaker 52-2 Main
sum of at least two neutral sensors in Breaker Breaker
52-1 52-2
combination with each breakers’ three-
phase sensors. To reduce the complexity Phase A, Tie Breaker Phase A,
of the drawing, each of the breakers’ Phase B, 52-T Phase B,
three-phase sensors have not been Phase C Phase C
shown. It is absolutely critical that the Neutral X
Neutral
sensors’ polarities are supplied as shown, Neutral Sensor X
the neutral sensor ratings of the mains Tie Breaker 52-T
Trip Unit
Trip Unit
and tie are the same, and that there are no Typical X
X
Typical X
X
Four-Wire Four-Wire
other grounds on the neutral bus made Feeder 52-1 52-T 52-2 Feeder
downstream of points shown. a a a
An infinite number of ground fault
protection schemes can be developed Four-Wire Load Four-Wire Load
Trip Unit Trip Unit Trip Unit
depending upon the number of alternate Main Breaker Tie Breaker Main Breaker
sources, the number of grounding points 52-1 52-T 52-2
and system interconnections involved.
Depending upon the individual system Figure 63. Dual Source System—Multiple Point Grounding
configuration, either mode of sensing
or a combination of all types may be To maintain maximum service continuity, The use of GFRs (or circuit breakers with
employed to accomplish the desired more than two levels (zones) of ground integral ground fault protection) that
end results. fault protection will be required, so that incorporate Zone Selective Interlocking,
ground fault outages can be localized and allows a coordinated response in a
The NEC (230.95) limits the maximum service interruption minimized. To obtain system by operating in a time delayed
setting of the ground fault protection used selectivity between different levels of mode for ground faults occurring most
on service equipment to 1200 A (and timed ground fault relays, time delay settings remote from the source. This time delayed
tripping at 3000 A for one second). In order should be employed with the GFR furthest mode is only actuated when the GFR
to prevent tripping of the main service downstream having the minimum time protecting the zone containing the fault
disconnect on a downstream feeder delay. This will allow the GFR nearest the sends a restraining signal to the upstream
ground fault, ground fault protection fault to operate first. GFRs. The absence of a restraining signal
must be provided on all the feeders. from a downstream GFR is an indication
With several levels of protection, this will to the next upstream GFR that a ground
reduce the level of protection for faults fault is within its zone of protection and it
within the upstream GFR zones. Zone will operate instantaneously to clear the
interlocking was developed for GFRs to fault with minimum damage and
overcome this problem. maximum service continuity.
2.30 3 2.55 3 2.55 3 2.55 3 2.55 3 2.55 3 2.55
2.40 3 2.55 3 2.55 6 5.10 3 2.55 3 2.55 6 5.10
3.30 3 2.55 3 2.55 6 5.10 3 2.55 3 2.55 6 5.10
4.00 3 2.55 6 5.10 6 5.10 3 2.55 6 5.10 6 5.10
4.16 6 5.10 6 5.10 6 5.10 6 5.10 6 5.10 6 5.10
4.76 6 5.10 6 5.10 9 7.65 6 5.10 6 5.10 9 7.65
4.80 6 5.10 6 5.10 9 7.65 6 5.10 6 5.10 9 7.65
6.60 6 5.10 6 5.10 9 7.65 6 5.10 6 5.10 9 7.65
6.90 6 5.10 6 5.10 9 7.65 6 5.10 9 7.65 9 7.65
7.20 6 5.10 6 5.10 10 8.40 6 5.10 9 7.65 10 8.40
8.32 9 7.65 9 7.65 12 10.20 9 7.65 9 7.65 12 10.20
8.40 9 7.65 9 7.65 12 10.20 9 7.65 9 7.65 12 10.20
11.00 9 7.65 9 7.65 15 12.70 9 7.65 10 8.40 15 12.70
11.50 9 7.65 10 8.40 18 15.30 9 7.65 12 10.20 18 15.30
12.00 10 8.40 10 8.40 18 15.30 10 8.40 12 10.20 18 15.30
12.47 10 8.40 12 10.20 18 15.30 10 8.40 12 10.20 18 15.30
13.20 12 10.20 12 10.20 18 15.30 12 10.20 12 10.20 18 15.30
13.80 12 10.20 12 10.20 18 15.30 12 10.20 15 12.70 18 15.30
14.40 12 10.20 12 10.20 21 17.00 12 10.20 15 12.70 21 17.00
18.00 15 12.70 15 12.70 27 22.00 15 12.70 18 15.30 27 22.00
20.78 18 15.30 18 15.30 30 24.40 18 15.30 21 17.00 30 24.40
22.00 18 15.30 18 15.30 30 24.40 18 15.30 21 17.00 30 24.40
22.86 18 15.30 21 17.00 — — 18 15.30 24 19.50 36 29.00
23.00 18 15.30 21 17.00 — — 18 15.30 24 19.50 36 29.00
24.94 21 17.00 24 19.50 — — 21 17.00 24 19.50 36 29.00
25.80 21 17.00 24 19.50 — — 21 17.00 24 19.50 36 29.00
26.40 21 17.00 24 19.50 — — 21 17.00 27 22.00 39 31.50
33.00 27 22.00 30 24.40 — — 27 22.00 36 29.00 45 36.50
34.50 30 24.40 30 24.40 — — 30 24.40 36 29.00 48 39.00
38.00 30 24.40 — — — — 30 24.40 36 29.00 — —
Table 23. Comparison of Specific Applications of Enclosures for Outdoor Nonhazardous Locations
Provides a Degree of Protection Against the Enclosure Type
Following Environmental Conditions 3 3R c 3S 4 4X 6 6P
Table 24. Comparison of Specific Applications of Enclosures for Indoor Hazardous Locations
Provides a Degree of Protection Against Class Enclosure Types Enclosure Type
Atmospheres Typically Containing 7 and 8, Class I Groups f 9, Class II Groups f
(For Complete Listing, See NFPA 497M) A B C D E F G 10
Acetylene I n
Hydrogen, manufactured gas I n
diethyl ether, ethylene, cyclopropane I n
Gasoline, hexane, butane, naphtha, propane, acetone, toluene, isoprene I n
Metal dust II n
Carbon black, coal dust, coke dust II n
Flour, starch, grain dust II n n
Fibers, flyings g III n
Methane with or without coal dust MSHA n
f For Class III type ignitable fibers or combustible flyings, see the National Electrical Code, Article 500.
g Due to the characteristics of the gas, vapor or dust, a product suitable for one class or group may not be suitable for another class or group unless so marked on
the product.
Note: If the installation is outdoors and/or additional protection is required by Table 22 and Table 23, a combination-type enclosure is required.
Referencing the first character, 4, in the IP rating and the row designated “IP4–” in the leftmost column in the
table; the blocks in Column “A” for NEMA Types 3, 3S, 4, 4X, 5, 6, 6P, 12, 12K and 13 are shaded. These NEMA
ratings meet and exceed the IEC protection requirements against access to hazardous parts and solid foreign
objects. Referencing the second character, 5, in the IP rating and the row designated “IP–5” in the rightmost
column in the table; the blocks in Column “B” for NEMA Types 3, 3S, 4, 4X, 6 and 6P are shaded. These NEMA
ratings meet and exceed the IEC requirements for protection against the ingress of water. The absence of shading
in Column “B” beneath the “NEMA Enclosure Type 5” indicates that Type 5 does not meet the IP45 protection
requirements against the ingress of water. Likewise, the absence of shading in Column “B” for NEMA Type 12,
12K and 13 enclosures indicates that these enclosures do not meet the IP45 requirements for protection against
the ingressof water. Only Types 3, 3S, 4, 4X, 6 and 6P have both Column “A” in the “IP4–” row and Column “B”
in the “IP–5” row shaded and could be used in an IP45 application.
The NEMA Enclosure Type 3 not only meets the IP45 Enclosure Rating, but also exceeds the IEC requirements
because the NEMA Type requires an outdoor corrosion test; a gasket aging test; a dust test; an external icing
test; and no water penetration in the rain test. Slight differences exist between the IEC and NEMA test methods,
but the IEC rating permits the penetration of water if “it does not deposit on insulation parts, or reach live parts.”
The IEC rating does not require a corrosion test; gasket aging test; dust test or external icing test. Because the
NEMA ratings include additional test requirements, this table cannot be used to select IP Designations for NEMA
rated enclosure specifications.
IEC 60529 specifies that an enclosure shall only be designated with a stated degree of protection indicated by
the first characteristic numeral if it also complies with all lower degrees of protection. Furthermore, IEC 60529
states that an enclosure shall only be designated with a degreeof protection indicated by the second characteristic
numeral if it also complies with all lower degrees of protection up to and including the secondcharacteristic
numeral 6. An enclosure designated with a second characteristic numeral 7 or 8 only is considered unsuitable
for exposure to water jets (designated by second characteristic numeral 5 or 6) and need not comply with
requirements for numeral 5 or 6 unless it is dual coded. Because the IEC protection requirements become more
stringent with increasing IP character value up through 6, once a NEMA Type rating meets the requirements for
an IP designation up through 6, it will also meet the requirements for all lower IP designations. This is apparent
from the shaded areas shown in the table.
30 83.3 72.2 36.1 28.9 7.22 4.16 2.41 1.44 1.39 1.31 1.26 0.75 0.50
45 125 108 54.1 43.3 10.8 6.25 3.61 2.17 2.08 1.97 1.88 1.13 0.76
75 208 180 90.2 72.2 18.0 10.4 6.01 3.61 3.47 3.28 3.14 1.89 1.26
112-1/2 312 271 135 108 27.1 15.6 9.02 5.41 5.21 4.92 4.71 2.84 1.89
150 416 361 180 144 36.1 20.8 12.0 7.22 6.94 6.56 6.28 3.78 2.52
225 625 541 271 217 54.1 31.2 18.0 10.8 10.4 9.84 9.41 5.67 3.78
300 833 722 361 289 72.2 41.6 24.1 14.4 13.9 13.1 12.6 7.56 5.04
500 1388 1203 601 481 120 69.4 40.1 24.1 23.1 21.9 20.9 12.6 8.39
750 2082 1804 902 722 180 104 60.1 36.1 34.7 32.8 31.4 18.9 12.6
1000 2776 2406 1203 962 241 139 80.2 48.1 46.3 43.7 41.8 25.2 16.8
1500 4164 3608 1804 1443 361 208 120 72.2 69.4 65.6 62.8 37.8 25.2
2000 — 4811 2406 1925 481 278 160 96.2 92.6 87.5 83.7 50.4 33.6
2500 — — 3007 2406 601 347 200 120 116 109 105 63.0 42.0
3000 — — 3609 2887 722 416 241 144 139 131 126 75.6 50.4
3750 — — 4511 3608 902 520 301 180 174 164 157 94.5 62.9
5000 — — — 4811 1203 694 401 241 231 219 209 126 83.9
7500 — — — — 1804 1041 601 361 347 328 314 189 126
10,000 — — — — 2406 1388 802 481 463 437 418 252 168
300 50,000 834 14,900 1700 16,600 722 12,900 2900 15,800 361 6400 1400 7800 289 5200 1200 6400
5% 100,000 834 15,700 1700 17,400 722 13,600 2900 16,500 361 6800 1400 8200 289 5500 1200 6700
150,000 834 16,000 1700 17,700 722 13,900 2900 16,800 361 6900 1400 8300 289 5600 1200 6800
250,000 834 16,300 1700 18,000 722 14,100 2900 17,000 361 7000 1400 8400 289 5600 1200 6800
500,000 834 16,500 1700 18,200 722 14,300 2900 17,200 361 7100 1400 8500 289 5700 1200 6900
Unlimited 834 16,700 1700 18,400 722 14,400 2900 17,300 361 7200 1400 8600 289 5800 1200 7000
500 50,000 1388 21,300 2800 25,900 1203 20,000 4800 24,800 601 10,000 2400 12,400 481 8000 1900 9900
5% 100,000 1388 25,200 2800 28,000 1203 21,900 4800 26,700 601 10,900 2400 13,300 481 8700 1900 10,600
150,000 1388 26,000 2800 28,800 1203 22,500 4800 27,300 601 11,300 2400 13,700 481 9000 1900 10,900
250,000 1388 26,700 2800 29,500 1203 23,100 4800 27,900 601 11,600 2400 14,000 481 9300 1900 11,200
500,000 1388 27,200 2800 30,000 1203 23,600 4800 28,400 601 11,800 2400 14,200 481 9400 1900 11,300
Unlimited 1388 27,800 2800 30,600 1203 24,100 4800 28,900 601 12,000 2400 14,400 481 9600 1900 11,500
750 50,000 2080 28,700 4200 32,900 1804 24,900 7200 32,100 902 12,400 3600 16,000 722 10,000 2900 12,900
5.75% 100,000 2080 32,000 4200 36,200 1804 27,800 7200 35,000 902 13,900 3600 17,500 722 11,100 2900 14,000
150,000 2080 33,300 4200 37,500 1804 28,900 7200 36,100 902 14,400 3600 18,000 722 11,600 2900 14,500
250,000 2080 34,400 4200 38,600 1804 29,800 7200 37,000 902 14,900 3600 18,500 722 11,900 2900 14,800
500,000 2080 35,200 4200 39,400 1804 30,600 7200 37,800 902 15,300 3600 18,900 722 12,200 2900 15,100
Unlimited 2080 36,200 4200 40,400 1804 31,400 7200 38,600 902 15,700 3600 19,300 722 12,600 2900 15,500
1000 50,000 2776 35,900 5600 41,500 2406 31,000 9800 40,600 1203 15,500 4800 20,300 962 12,400 3900 16,300
5.75% 100,000 2776 41,200 5600 46,800 2406 35,600 9800 45,200 1203 17,800 4800 22,600 962 14,300 3900 18,200
150,000 2776 43,300 5600 48,900 2406 37,500 9800 47,100 1203 18,700 4800 23,500 962 15,000 3900 18,900
250,000 2776 45,200 5600 50,800 2406 39,100 9800 48,700 1203 19,600 4800 24,400 962 15,600 3900 19,500
500,000 2776 46,700 5600 52,300 2406 40,400 9800 50,000 1203 20,200 4800 25,000 962 16,200 3900 20,100
Unlimited 2776 48,300 5600 53,900 2406 41,800 9800 51,400 1203 20,900 4800 25,700 962 16,700 3900 20,600
1500 50,000 4164 47,600 8300 55,900 3609 41,200 14,400 55,600 1804 20,600 7200 27,800 1444 16,500 5800 22,300
5.75% 100,000 4164 57,500 8300 65,800 3609 49,800 14,400 64,200 1804 24,900 7200 32,100 1444 20,000 5800 25,800
150,000 4164 61,800 8300 70,100 3609 53,500 14,400 57,900 1804 26,700 7200 33,900 1444 21,400 5800 27,200
250,000 4164 65,600 8300 73,900 3609 56,800 14,400 71,200 1804 28,400 7200 35,600 1444 22,700 5800 28,500
500,000 4164 68,800 8300 77,100 3609 59,600 14,400 74,000 1804 29,800 7200 37,000 1444 23,900 5800 29,700
Unlimited 4164 72,500 8300 80,800 3609 62,800 14,400 77,200 1804 31,400 7200 38,600 1444 25,100 5800 30,900
2000 50,000 — — — — — — — — 2406 24,700 9600 34,300 1924 19,700 7800 27,500
5.75% 100,000 — — — — — — — — 2406 31,000 9600 40,600 1924 24,800 7800 32,600
150,000 — — — — — — — — 2406 34,000 9600 43,600 1924 27,200 7800 35,000
250,000 — — — — — — — — 2406 36,700 9600 46,300 1924 29,400 7800 37,200
500,000 — — — — — — — — 2406 39,100 9600 48,700 1924 31,300 7800 39,100
Unlimited — — — — — — — — 2406 41,800 9600 51,400 1924 33,500 7800 41,300
2500 50,000 — — — — — — — — 3008 28,000 12,000 40,000 2405 22,400 9600 32,000
5.75% 100,000 — — — — — — — — 3008 36,500 12,000 48,500 2405 29,200 9600 38,800
150,000 — — — — — — — — 3008 40,500 12,000 52,500 2405 32,400 9600 42,000
250,000 — — — — — — — — 3008 44,600 12,000 56,600 2405 35,600 9600 45,200
500,000 — — — — — — — — 3008 48,100 12,000 60,100 2405 38,500 9600 48,100
Unlimited — — — — — — — — 3008 52,300 12,000 64,300 2405 41,800 9600 51,400
3000 50,000 — — — — — — — — 3609 30,700 14,000 44,700 2886 24,600 11,500 36,100
5.75% 100,000 — — — — — — — — 3609 41,200 14,000 55,200 2886 33,000 11,500 44,500
150,000 — — — — — — — — 3609 46,600 14,000 60,600 2886 37,300 11,500 48,800
250,000 — — — — — — — — 3609 51,900 14,000 65,900 2886 41,500 11,500 53,000
500,000 — — — — — — — — 3609 56,800 14,000 70,800 2886 45,500 11,500 57,000
Unlimited — — — — — — — — 3609 62,800 14,000 76,800 2886 50,200 11,500 61,700
3750 50,000 — — — — — — — — 4511 34,000 18,000 52,000 3608 27,200 14,400 41,600
5.75% 100,000 — — — — — — — — 4511 47,500 18,000 65,500 3608 38,000 14,400 52,400
150,000 — — — — — — — — 4511 54,700 18,000 72,700 3608 43,700 14,400 58,100
250,000 — — — — — — — — 4511 62,200 18,000 80,200 3608 49,800 14,400 64,200
500,000 — — — — — — — — 4511 69,400 18,000 87,400 3608 55,500 14,400 69,900
Unlimited — — — — — — — — 4511 78,500 18,000 96,500 3608 62,800 14,400 77,200
a Short-circuit capacity values shown correspond to kVA and impedances shown in this table. For impedances other than these, short-circuit currents are inversely
proportional to impedance.
b The motor’s short-circuit current contributions are computed on the basis of motor characteristics that will give four times normal current. For 208 V, 50% motor
load is assumed while for other voltages 100% motor load is assumed. For other percentages, the motor short-circuit current will be in direct proportion.
2500 5.75 0.86 5.69 6.61 75 4.45 3.90 2.14 1.83
112.5 5.17 4.81 1.89 2.54
150 3.89 3.59 1.49 2.41
Table 30. DOE 2016 Transformer Efficiencies— 225 4.90 4.73 1.28 3.69
Medium-Voltage Three-Phase Distribution 300 4.80 4.65 1.21 3.85
Transformers b 80 °C Rise Aluminum
kVA % Efficiency 15 4.19 2.94 2.98 0.99
30 2.50 1.76 1.78 0.99
Liquid- Dry Transformers 45 2.43 2.01 1.37 1.46
Filled
75 3.11 2.81 1.32 2.12
All 25–45 46–95 M96 kV 112.5 2.61 2.31 1.21 1.92
BILs kV BIL kV BIL BIL 150 2.80 2.64 0.93 2.85
225 3.35 3.20 0.99 3.23
15 98.65 97.5 97.18 —
30 98.83 97.9 97.63 —
45 98.92 98.1 97.86 —
75 99.03 98.33 98.13 —
112.5 99.11 98.52 98.36 —
150 99.16 98.65 98.51 —
225 99.23 98.82 98.69 98.57
300 99.27 98.93 98.81 98.69
500 99.35 99.09 98.99 98.89
750 99.40 99.21 99.12 99.02
1000 99.43 99.28 99.2 99.11
1500 99.48 99.37 99.3 99.21
2000 99.51 99.43 99.36 99.28
2500 99.53 99.47 99.41 99.33
b Based on transformer operating at 50% of
nameplate base kVA.
DELTA-DELTA Connection 1. Suitable for both ungrounded and effectively grounded sources.
2. Suitable for a three-wire service or a four-wire service with a mid-tap ground.
Phasor H2 X2
Diagram:
H1 H3 X1 X3
DELTA-WYE Connection 1. Suitable for both ungrounded and effectively grounded sources.
2. Suitable for a three-wire service or a four-wire grounded service with XO grounded.
Phasor H2 X2
Diagram: 3. With XO grounded, the transformer acts as a ground source for the secondary system.
4. Fundamental and harmonic frequency zero-sequence currents in the secondary lines
X1 X0 supplied by the transformer do not flow in the primary lines. Instead the zero sequence
currents circulate in the closed delta primary windings.
H1 H3 5. When supplied from an effectively grounded primary system does not see load
X3 unbalances and ground faults in the secondary system.
Angular Displacement (Degrees): 30
WYE-DELTA Connection 1. Suitable for both ungrounded and effectively grounded sources.
2. Suitable for a three-wire service or a four-wire delta service with a mid-tap ground.
Phasor H2 X2
Diagram: 3. Grounding the primary neutral of this connection would create a ground source for
the primary system.This could subject the transformer to severe overloading during
a primary system disturbance or load unbalance.
X1
4. Frequently installed with mid-tap ground on one leg when supplying combination
three-phase and single-phase load where the three-phase load is much larger than
H1 H3
X3 single-phase load.
Angular Displacement (Degrees): 30 5. When used in 25 kV and 35 kV three-phase four-wire primary systems, ferroresonance
can occur when energizing or de-energizing the transformer using single-pole switches
located at the primary terminals. With smaller kVA transformers the probability of
ferroresonance is higher.
WYE-WYE Connection 1. Suitable for both ungrounded and effectively grounded sources.
2. Suitable for a three-wire service only, even if XO is grounded.
Phasor H2 X2
Diagram: 3. This connection is incapable of furnishing a stabilized neutral and its use may
result in phase-to-neutral overvoltage (neutral shift) as a result of unbalanced
phase-to-neutral load.
X0
4. If a three-phase unit is built on a three-legged core, the neutral point of the primary
windings is practically locked at ground potential.
H1 H3 X1 X3
GROUNDED WYE-WYE Connection 1. Suitable for four-wire effectively grounded source only.
2. Suitable for a three-wire service or for four-wire grounded service with
Phasor H2 X2 XO grounded.
Diagram:
3. Three-phase transformers with this connection may experience stray flux tank
heating during certain external system unbalances unless the core configuration
H0 X0 (four or five legged) used provides a return path for the flux.
4. Fundamental and harmonic frequency zero-sequence currents in the secondary
H1 H3 X1 X3
lines supplied by the transformer also flow in the primary lines (and primary
neutral conductor).
Angular Displacement (Degrees): 0
5. Ground relay for the primary system may see load unbalances and ground
faults in the secondary system.This must be considered when coordinating
overcurrent protective devices.
6. Three-phase transformers with the neutral points of the high-voltage and low-
voltage windings connected together internally and brought out through an
HOXO bushing should not be operated with the HOXO bushing ungrounded
(floating).To do so can result in very high voltages in the secondary systems.
DELTA-DELTA Connection with Tap 1. Suitable for both ungrounded and effectively grounded sources.
2. Suitable for a three-wire service or a four-wire service with a mid-tap ground.
Phasor H2 X2
Diagram: 3. When using the tap for single-phase circuits, the single-phase load kVA should
X4 not exceed 5% of the three-phase kVA rating of the transformer.The three-phase
rating of the transformer is also substantially reduced.
H1 H3 X1 X3
300 55 — 58 67
500 56 — 60 67
750 57 67 64 67
1000 58 67 64 67
1500 60 67 65 68
2000 61 67 66 69
2500 62 67 68 71
3000 63 67 68 71
3750 64 67 70 73
5000 65 67 71 73
6000 66 68 72 74
7500 67 69 73 75
10,000 68 70 — 76
Figure 71. Generator Percentage Differential Relay (Phase Scheme) and Ground Differential Scheme
Using a Directional Relay
Step 1: Calculate Running Amperes ■ Delivery and rigging requirements Please see the generator set manufac
■ Genset derating due to high altitudes
turer’s application and installation
■ Motor loads:
or excessive ambient temperatures guidelines for proper application
200 hp motor. . . . . . . . . . . . . 156 A
❏ and operation of their equipment.
❏ 100 hp motor . . . . . . . . . . . . . . 78 A
❏ 60 hp motor . . . . . . . . . . . . . . . 48 A
■ Lighting load . . . . . . . . . . . . . . . . 68 A
■ Miscellaneous loads . . . . . . . . . . 95 A
■ Running amperes. . . . . . . . . . . . 445 A
■ Capacitor selection of calculation of the quantities covered Fused and unfused switches. . . . . 165%
by C37.06 Standard.
■ Where to install capacitors in a plant Molded case breaker or
distribution system Note that the definitions in C37.04 make equivalent . . . . . . . . . . . . . . . . . . 150%
■ Locating capacitors on reduced voltage
the switching of two capacitors banks in
close proximity to the switchgear bus a Insulated case breakers. . . . . . . . . 135%
and multi-speed starters
back-to-back mode of switching. This
■ Harmonic considerations Magnum DS power
classification requires a definite purpose
circuit breaker . . . . . . . . . . . . . . . 135%
■ Eliminating harmonic problems circuit breaker (breakers specifically
■ National Electrical Code requirements designed for capacitance switching). Contactors:
We recommend that such application be Open type. . . . . . . . . . . . . . . . . . . . 135%
referred to Eaton.
Medium-Voltage Enclosed type. . . . . . . . . . . . . . . . . 150%
Capacitor Switching A breaker specified for capacitor
switching should include as applicable: The NEC, Section 460.8(C), requires the
Capacitance switching constitutes severe disconnecting means to be rated not less
operating duty for a circuit breaker. At the 1. Rated maximum voltage. than 135% of the rated capacitor current
time the breaker opens at near current (for 600 V and below).
zero, the capacitor is fully charged. After 2. Rated frequency.
interruption, when the alternating voltage Refer to Eaton’s Power Factor Capacitors
3. Rated open wire line charging
on the source side of the breaker reaches and Harmonic Filters Design Guide for
switching current.
its opposite maximum, the voltage that switching device ampere ratings. They
appears across the contacts of the open 4. Rated isolated cable charging and re based on percentage of capacitor-
breaker is at least twice the normal peak shunt capacitor switching current. rated current as indicated (above). The
line-to-neutral voltage of the circuit. If a interrupting rating of the switch must
breakdown occurs across the open 5. Rated back-to-back cable charging be selected to match the system fault
contact, the arc is re-established. Due and back-to-back capacitor current available at the point of capacitor
to the circuit constants on the supply switching current. application. Whenever a capacitor bank
side of the breaker, the voltage across the 6. Rated transient overvoltage factor. is purchased with less than the ultimate
open contact can reach three times the kvar capacity of the rack or enclosure, the
normal line-to-neutral voltage. After 7. Rated transient inrush current and switch rating should be selected based on
it is interrupted and with subsequent its frequency. the ultimate kvar capacity—not the initial
alternation of the supply side voltage, installed capacity.
the voltage across the open contact is 8. Rated interrupting time.
Refer to Eaton’s Power Factor Capacitors
even higher. 9. Rated capacitive current switching life. and Harmonic Filters Design Guide for
10. Grounding of system and recommended selection of capacitor
capacitor bank. switching devices; recommended
maximum capacitor ratings for various
Load break interrupter switches are motor types and voltages; and for
permitted by ANSI/IEEE Standard C37.30 required multipliers to determine
to switch capacitance, but they must have capacitor kvar required for power
tested ratings for the purpose. factor correction.
Figure 74. Typical Large Hospital Electrical System—Type 1 Essential Electrical System
Type 1 Essential Electrical The transfer switches can be non-delayed Table 46. Type 1 EES Applicable Codes
automatic, delayed automatic or manual Description Standard Section
Systems (EES) transfer depending on the requirements
Type 1 essential electrical systems (EES) of the specific branch of the EES that they Sources NFPA 99 6.4.1
have the most stringent requirements for are feeding. It is permissible to feed Uses NFPA 99 6.4.1.1.8
providing continuity of electrical service multiple branches or systems of the EES Emergency NFPA 110 4.1
and will, therefore, be the focus of this from a single automatic transfer switch Power Supply
section. Type 1 EES requirements meet provided that the maximum demand on Classification
or exceed the requirements for Type 2 the EES does not exceed 150 kVA. This Distribution NFPA 99 6.4.2
facilities. configuration is typically seen in smaller NEC 517.30
healthcare facilities that must meet Type 1 General NFPA 99 6.4.2.2.1
Sources:Type 1 systems are required to EES requirements (see Figure 75). NEC 517.25 thru 517.31
have a minimum of two independent
Life Safety NFPA 99 6.4.2.2.3
sources of electrical power—a normal Branch NEC 517.32
source that generally supplies the entire
Normal Source Critical NFPA 99 6.4.2.2.4
facility and one or more alternate sources Branch NEC 517.33
that supply power when the normal source
Alternate Equipment NFPA 99 6.4.2.2.5
is interrupted.The alternate source(s) must Branch NEC 517.34
be an on-site generator driven by a prime Source
Wiring NFPA 99 6.4.2.2.6
mover unless a generator(s) exists as the NEC 517.30.(C)
normal power source. In the case where a G
generator(s) is used as the normal source,
it is permissible for the alternate source to
be a utility feed.
Alternate source generators must be
classified as Type 10, Class X, Level 1
gensets per NFPA 110 Tables 4.1(a) and
Non-Essential
4.2(b) that are capable of providing power Loads
to the load in a maximum of 10 seconds.
Typically, the alternate sources of power Entire Essential
are supplied to the loads through a Electric System
series of automatic and/or manual (150 kVA or Less)
transfer switches.
Figure 75. Small Healthcare Facility Electrical
System—Single EES Transfer Switch
Careful consideration should be used in Wet procedure locations—A wet Electronic line isolation monitors (LIM)
applying ground fault protection on the procedure location in a healthcare facility are used to monitor and display leakage
essential electrical system to prevent a is any patient care area that is normally currents to ground. When leakage current
ground fault that causes a trip of the subject to wet conditions while patients thresholds are exceeded, visible and/or
normal source to also cause a trip on the are present. By default, operating rooms audible alarms are initiated to alert
emergency source. Such an event could are considered wet procedure locations occupants of a possible hazardous
result in complete power loss of both unless a risk assessment is performed to condition. This alarm occurs without
normal and emergency power sources show otherwise. Other examples of wet interrupting power to allow for the safe
and could not be recovered until the procedure locations might include conclusion of critical procedures.
source of the ground fault was located anesthetizing locations, dialysis locations,
and isolated from the system. To prevent etc. (patient beds, toilets and sinks are not Table 48. Wet Procedure Location
this condition, NEC 700.27 removes the considered wet locations). These wet Applicable Codes
ground fault protection requirement for procedure locations require special Description Standard Section
the emergency system source. Typically, protection to guard against electric shock.
General NFPA 99 6.3.2.2.8
the emergency system generator(s) are The ground fault current in these areas NEC 517.20
equipped with ground fault alarms that must be limited to not exceed 5 mA.
GFCI Protection NFPA 99 6.3.2.2.8.8
do not automatically disconnect power
during a ground fault. Protection to patient and staff in wet Isolated Power NFPA 99 6.3.2.2.9, 6.3.2.6
procedure locations can be provided Systems NE 517.160
Table 47. Ground Fault Protection through the use of GFCI outlets, GFCI
Applicable Codes breakers or isolated power systems. If
Description Standard Section GFCI protection is utilized, each circuit
must have a dedicated GFCI outlet or
Services NEC 230.95 GFCI breaker. It is not permissible to use
Branch-Circuits NEC (see Article 210.13 a single GFCI device to protect multiple
100 Definition
for Applicability)
outlets. This limits interruption resulting
Feeders NEC 215.10 from a ground fault to a single outlet.
Additional Level NFPA 99 6.3.2.5 Isolated power systems provide power
NEC 517.17
to an area that is isolated from ground
Alternate Source NEC 700.27 (or ungrounded). This type of system
NEC 701.26
limits the amount of current that flows
to ground in the event of a single
line-to-ground fault and maintains
circuit continuity.
Utility
Utility G1 G2 Gx
Metering
Typical
Generator
Breaker
Service Main
Optional Closed
EP1 EP2 Typical EPX Transition
Panelboards Paralleling of
Generators and
Utility
Figure 77. Typical One-Line for a Paralleling Switchgear Lineup Feeding the Essential Electrical System (EES)
Transformer
Generators X = Number of Units
Utility G1 G2 Gx
Metering
Utility
Closed
Protective Typical
Transition
Relay Generator
Paralleling of
Generators and Breaker
Service Main Utility, Plus
Soft Loading/
Unloading
Normal Bus Emergency Bus
TIE Optional TIE
Optional Electrically Operated
Electrically Stored Energy
Field Installed Breakers
Operated
Cable or Busway
Stored F1 F2 Fx EF1 EF2 EFx
Energy
Breakers
Figure 78. Typical One-Line Healthcare Facility with Complete Generator Backup and Utility Interconnect
room (or other critical loads). either placed in parallel with the loads
The benefit of implementing cascaded directly on the equipment bus bars or
network protection is shown in externally by means of a short cable.
Figure 80. Combined, the two This reduces the cost of protection for
stages of protection at the service multiple sensitive loads.
entrance and branch panel locations
reduce the IEEE 62.41 recommended
5. Uninterruptible Power Supply test wave (C3–20 kV, 10 kA) to less than
(UPS, Gen. Sets, etc.) 200 V voltage, a harmless disturbance
4. Harmonic Distortion level for 120 V rated sensitive loads.
3. Voltage Regulation
2. Surge Protection
1. Grounding
Input—high energy
SPD
Figure 79. Power Quality Pyramid transient disturbance; IEEE Category
CP
SPD C3 Impulse 20,000V; 10,000A
20,000V
480V 120/208V
PEAK VOLTAGE
problems. All other forms of power IEEE C62.41[10] and C62.45 [10] 400V
208Y/120 Panelboard
(integrated versus side mounted SPD)
600
N 400
SPD
Integrated SPD
SPD (direct bus bar connection)
200
Waveform (UL 1449 Test Wave)[12] voltage) disturbances are generally site-
900 14 AWG or load-dependent. A variety of mitigating
800 209V (23%) 10 AWG
700 solutions are available depending upon
600 4 AWG the load sensitivity, fault duration/
673V (75%)
500 magnitude and the specific problems
400 encountered. It is recommended to install
300
200 monitoring equipment on the ac power
100 lines to assess the degree and frequency
0 of occurrences of voltage regulation
3 ft (914.4 mm) 1 ft (304.8 mm) problems.The captured data will allow
Lead Length Lead Length,
Loose Wiring Twisted Wires Twisted Wires
for the proper solution selection.
6-pulse rectifier
Harmonics a
Drives and rectifiers— Line reactors n Inexpensive n May require additional compensation
includes three-phase n For 6-pulse standard drive/rectifier, can reduce
UPS loads harmonic current distortion from 80% down to
about 35–40%
K-rated/drive isolation n Offers series reactance (similar to line reactors) n No advantage over reactors for reducing
transformer and provides isolation for some transients harmonics unless in pairs for shifting phases
dc choke n Slightly better than ac line reactors for 5th and n Not always an option for drives
7th harmonics n Less protection for input semiconductors
12-pulse convertor n 85% reduction versus standard 6-pulse drives n Cost difference approaches 18-pulse drive
and blocking filters, which guarantee
IEEE 519 compliance
Harmonic mitigating n Substantial (50–80%) reduction in harmonics n Harmonic cancellation highly dependent on
transformers/phase shifting when used in tandem load balance
n Must have even multiples of matched loads
Tuned filters n Bus connected—accommodates load diversity n Requires allocation analysis
n Provides PF correction n Sized only to the requirements of that system;
must be resized if system changes
Broadband filters n Makes 6-pulse into the equivalent of 18-pulse n Higher cost
n Requires one filter per drive
18-pulse converter n Excellent harmonic control for drives above 100 hp n High cost
n IEEE 519 compliant
n No issues when run from generator sources
It = Ir + Ic + Ig Id = Ih + Ix + Ir
Input Static Disconnect
Output
Contactor Switch Line Inductor
Contactor
Source Load
Ix
dc Filter Inductor Ig Id = Output Current
Field Coil ac
Ih = Harmonic Current
Driver dc ac Ix = Reactive Load Current
Ir = Real Load Current
Ih
Integrated Motor/Flywheel/
and Generator
Source Load
Normal Rectifier/Charger Output
Inverter
Breaker Breaker
ac dc
dc ac
Battery Breaker
Battery
Figure 87. Typical Static UPS, Double Conversion Type with Battery Backup
UPS Module
Source Load
Rectifier/
Normal Charger Inverter Output
Breaker Breaker
ac dc
dc ac
Battery
Breaker
Battery
Figure 88. Typical Static UPS, Standby Type with Battery Backup
UPS Module
Source Load
Inductor
Bidirectional
Inverter/Charger
dc
ac
Battery
Figure 89. Typical Static UPS, Line Interactive Type with Battery Backup
General
In the 1980s, Eaton embarked on a
comprehensive program centered
around designing and building electrical
distribution and control equipment
capable of meeting and exceeding the
seismic load requirements of the Uniform
Building Code (UBC) and California
Building Code (CBC). These codes
emphasize building design requirements.
Electrical equipment and distribution
system components are considered
attachments to the building. The entire
program has been updated to show
compliance with the 2015 International
Building Code (IBC) and the 2016 CBC
seismic requirements.
A cooperative effort with the equipment Figure 90. Typical Earthquake Ground Motion Map for the United States
user, the building designer and the
equipment installer ensures that the International Building Code (IBC) California Building Code
equipment is correctly anchored such On December 9, 1994, the International The 2001 CBC was based upon the 1997
that it can withstand the effects of an Code Council (ICC) was established as UBC. In August of 2006, it was repealed
earthquake. Eaton’s electrical distribution a nonprofit organization dedicated to by the California Building Standards
and control equipment has been tested developing a single set of comprehensive Commission (CBSC) and replaced by the
and seismically proven for requirements and coordinated codes.The ICC founders 2007 CBC, California Code of Regulations
in compliance with the IBC and CBC. Over —the Building Officials and Code (CCR),Title 24, Part 2 and used the 2006
100 different assemblies representing Administrators (BOCA), the International IBC as the basis for the code.The 2016
essentially all product lines have been Conference of Building Officials (ICBO), CBC is based upon the 2015 IBC, with
successfully tested and verified to seismic and the Southern Building Code Congress amendments as deemed appropriate by
requirements specified in the IBC and CBC. International (SBCCI)—created the ICC in the CBSC. Eaton’s seismic qualification
The equipment maintained structural response to technical disparities among program fully envelopes the requirements
integrity and demonstrated the ability to the three nationally recognized model of the 2016 CBC with many of the
function immediately after the seismic codes now in use in the U.S.The ICC offers distribution and control products having
tests. A technical paper, Earthquake a single, complete set of construction Seismic Certification Pre-approval with
Requirements and Eaton Distribution and codes without regional limitations—the the California Office of Statewide Health
Control Equipment Seismic Capabilities International Building Code. Planning and Development (OSHPD).
(SA12501SE), provides a detailed
explanation of the applicable seismic
codes and Eaton’s equipment qualification Uniform Building Code (UBC) Process
program.The paper may be found at 1997 was the final year in which the UBC According to Chapter 16 of the 2015 IBC,
www.eaton.com/seismic.Type in was published. It has since been replaced structure design, the seismic requirements
SA12501SE in the document search field. by the IBC. of electrical equipment in buildings may
be computed in two steps.The first step is
to determine the maximum ground
motion to be considered at the site.The
second step is to evaluate the equipment
mounting and attachments inside the
building or structure.These are then
evaluated to determine appropriate
seismic test requirements.The ground
motion, seismic requirements of the
equipment, and the seismic response
spectrum requirements are discussed
on Page 122, see Figure 92.
Acceleration (g peak)
not necessary. In addition, having the 6 (TRS) Acceleration = Maximum
5
low end of the spectra higher than Table Test Motion
4
realistically required forces the shake
table to move at extremely high 3
Acceleration (g)
actual acceleration of the C.G. of a piece
of equipment under seismic test. The
seismic response at the middle of base 1
mounted equipment close to its C.G. is at
least 50% higher than the floor input at
the equipment natural frequency. The
base accelerations associated with the
accelerations of FP/WP at the C.G. of the
equipment could then be computed as 0.1
4.48 /1.5 = 2.99 g. It is the equipment base 1 10 100
input acceleration that is measured and Frequency (Hz)
documented during seismic testing and is
the acceleration value shown on Eaton’s Eaton Seismic IBC 2015/CBC 2016
seismic certificates.
Figure 93. Required Response Spectrum Curve
Final Combined Requirements
To better compare all seismic levels and
determine the final envelope seismic
100% vs. 120%
requirements, the 2016 CBC and 2015 IBC
10
for California are plotted in Figure 93. All
curves are plotted at 5% damping.
An envelopment of the seismic levels in
the frequency range of 3.2 Hz to 100 Hz is
also shown. This level is taken as Eaton’s
Acceleration (g)
Eaton Equipment
building are usually energized 24 hours 0% 25% 35% 50% 75% 100%
a day, savings from lower losses can be Percentage of Load
substantial, and should be considered
DOE 2016 Efficient 150C TP-1 Efficient 150C DOE 2016 Efficient 115C
in all transformer specifications. One
method of obtaining reduced losses is to TP-1 Efficient 115C DOE 2016 Efficient 80C TP-1 Efficient 80C
Utility
Source
Typical Application: Three engine generator sets serve the load, plus one additional engine
generator set for redundancy to achieve N+1 level of performance. Open or Closed transition is available.
G1 G2 G3 G4
Paralleling Switchgear
with Distribution
Revenue
Metering
HMI
Touchscreen
52G1 52G2 52G3 52G4
Main D1 D2 D3 D4
Service
Optional Remote PC
with Software
LP1 BP1 LP2 BP2 LP3 BP3 LP4 BP4
Operations:
445 and 501 Hoes Lane
Piscataway, NJ 08854-4141
732-981-0060
www.ieee.org
2 Time-delay starting or closing relay A device that functions to give a desired amount of Used for providing a time-delay for re-transfer
time delay before or after any point of operation in a back to the normal source in an automatic
switching sequence or protective relay system, except transfer scheme.
as specifically provided by device functions 48, 62
and 79 described later.
6 Starting circuit breaker A device whose principal function is to connect —
a machine to its source of starting voltage.
19 Starting to running transition timer A device that operates to initiate or cause the Used to transfer a reduced voltage starter from
automatic transfer of a machine from the starting starting to running.
to the running power connection.
21 Distance relay A device that functions when the circuit admittance, —
impedance or reactance increases or decreases
beyond predetermined limits.
23 Temperature control device A device that functions to raise or to lower the Used as a thermostat to control space heaters in
temperature of a machine or other apparatus, or outdoor equipment.
of any medium, when its temperature falls below
or rises above, a predetermined level.
24 Volts per hertz relay A device that operates when the ratio of voltage ETR-5000 transformer protective relays,
to frequency is above a preset value or is below EGR-5000 generator protective relay.
a different preset value.The relay may have
any combination of instantaneous or time
delayed characteristics.
25 Synchronizing or synchronism A device that operates when two AC circuits are within In a closed transition breaker transfer, a
check device the desired limits of frequency, phase angle or voltage, 25 relay is used to ensure two-sources are
to permit or cause the paralleling of these two circuits. synchronized before paralleling. Eaton
EDR-5000 feeder protective relays, EGR-5000
generator protective relay.
27 Undervoltage relay A device which functions on a given value Used to protect a motor or other devices from
of undervoltage. a sustained under-voltage and/or initiate an
automatic transfer when a primary source of
power is lost. Eaton EDR feeder protective relay,
EMR-4000/EMR-5000 motor protective relays,
ETR-5000 transformer protective relay, EGR-5000
generator protective relay.
30 Annunciator relay A non-automatically reset device that gives a number Used to remotely indicate that a protective relay
of separate visual indications upon the functioning of has functioned, or that a circuit breaker has
protective devices, and which may also be arranged to tripped.Typically, a mechanical “drop” type
perform a lockout function. annunciator panel is used.
32 Directional power relay A relay that functions on a desired value of power Used to prevent reverse power from feeding
flow in a given direction, or upon reverse power an upstream fault. Often used when primary
resulting from arc back in the anode or cathode backup generation is used in a facility. Eaton
circuits of a power rectifier. EDR-5000 feeder protective relay, EMR-4000/
EMR-5000 motor protective relays, ETR-5000
transformer protective relay, EGR-5000 generator
protective relay.
33 Position switch A device that makes or breaks contact when the main Used to indicate the position of a drawout circuit
device or piece of apparatus, which has no device breaker (TOC switch).
function number, reaches a given point.
34 Master sequence device A device such as a motor-operated multi-contact —
switch, or the equivalent, or a programmable device,
that establishes or determines the operating sequence
of the major devices in equipment during starting and
stopping, or during sequential switching operations.
37 Undercurrent or underpower relay A relay that functions when the current or power Eaton EMR-3000, EMR-4000, EMR-5000 motor
flow decreases below a predetermined value. protective relays.
38 Bearing protective device A device that functions on excessive bearing —
temperature, or on other abnormal mechanical
conditions, such as undue wear, which may
eventually result in excessive bearing temperature.
40 Field relay A device that functions on a given or abnormally EGR-5000 generator protective relay.
high or low value or failure of machine field current,
or on an excessive value of the reactive component
of armature current in an AC machine indicating
abnormally high or low field excitation.
41 Field circuit breaker A device that functions to apply, or to remove, —
the field excitation of a machine.
59 Overvoltage relay A relay that functions on a given value of overvoltage. Used to trip a circuit breaker, protecting
downstream equipment from sustained
overvoltages. Eaton EDR-5000 feeder protective
relay and EMR-4000/EMR-5000 motor protective
relays, ETR-5000 transformer protective relay,
EGR-5000 generator protective relay.
60 Voltage or current balance relay A relay that operates on a given difference in voltage, —
or current input or output of two circuits.
62 Time-delay stopping or opening relay A time-delay relay that serves in conjunction with the Used in conjunction with a 27 device to delay
device that initiates the shutdown, stopping or opening tripping of a circuit breaker during a brief loss of
operation in an automatic sequence. primary voltage, to prevent nuisance tripping.
63 Pressure switch A switch that operates on given values or on a given Used to protect a transformer during a rapid
rate of change of pressure. pressure rise during a short circuit.This device
will typically act to open the protective devices
above and below the transformer.Typically
used with a 63-X auxiliary relay to trip the
circuit breaker.
64 Ground protective relay A relay that functions on a failure of the insulation of a Used to detect and act on a ground-fault
machine, transformer or of other apparatus to ground, condition. In a pulsing high resistance grounding
or on flashover of a DC machine to ground. system, a 64 device will initiate the alarm.
65 Governor A device consisting of an assembly of fluid, electrical or —
mechanical control equipment used for regulating the
flow of water, steam or other media to the prime mover
for such purposes as starting, holding speed or load,
or stopping.
66 Notching or jogging device A device that functions to allow only a specified Eaton EMR-3000/EMR-4000/EMR-5000 motor
number of operations of a given device, or equipment, protective relays.
or a specified number of successive operations within
a given time of each other. It also functions to energize
a circuit periodically or for fractions of specified time
intervals, or that is used to permit intermittent
acceleration or jogging of a machine at low speeds
for mechanical positioning.
67 AC directional overcurrent relay A relay that functions on a desired value of AC Eaton EDR-5000 feeder protective relay,
overcurrent flowing in a predetermined direction. EMR-4000/EMR-5000 motor protective relays,
ETR-5000 transformer protective relay, EGR-5000
generator protective relay.
69 Permissive control device A device that is generally a two-position manually Used as a remote-local switch for circuit
operated switch that in one position permits the closing breaker control.
of a circuit breaker, or the placing of equipment into
operation, and in the other position prevents the circuit
breaker to the equipment from being operated.
71 Level switch A switch that operates on given values, or on a given Used to indicate a low liquid level within a
rate of change of level. transformer tank in order to save transformers
from loss-of-insulation failure. An alarm contact
is available as a standard option on a liquid level
gauge. It is set to close before an unsafe
condition actually occurs.
72 DC circuit breaker A device that is used to close and interrupt a DC power —
circuit under normal conditions or to interrupt this
circuit under fault or emergency conditions.
73 Load-resistor contactor A device that is used to shunt or insert a step of load —
limiting, shifting or indicating resistance in a power
circuit; to switch a space heater in circuit; or to switch
a light or regenerative load resistor of a power rectifier
or other machine in and out of circuit.
74 Alarm relay A device other than an annunciator, as covered under —
device number 30, which is used to operate, or to
operate in connection with, a visible or audible alarm.
78 Phase-angle measuring relay A device that functions at a predetermined phase angle EDR-5000 feeder protective relay, EMR-4000/
between two voltages, between two currents, EMR-5000 motor protective relays, ETR-5000
or between voltage and current. transformer protective relay, EGR-5000
generator protective relay. (Note: For Voltage
Only—78 V.)
79 AC reclosing relay A relay that controls the automatic closing and locking Used to automatically reclose a circuit breaker
out of an AC circuit interrupter. after a trip, assuming the fault has been cleared
after the power was removed from the circuit.
The recloser will lock-out after a predetermined
amount of failed attempts to reclose. EDR-5000
feeder protective relay, ETR-5000 transformer
protective relay, EGR-5000 generator protective
relay.
81 Frequency relay A relay that functions on a predetermined value of Used to trip a generator circuit breaker in the
frequency—either under or over, or on normal system event the frequency drifts above or below a given
frequency—or rate of change frequency. value. Eaton EDR-5000 feeder protective relay
and EMR-4000/EMR-5000 motor protective
relays, ETR-5000 transformer protective relay,
EGR-5000 generator protective relay.
83 Automatic selective control or A relay that operates to select automatically between Used to transfer control power sources in a
transfer relay certain sources or conditions in equipment, or double-ended switchgear lineup.
performs a transfer operation automatically.
85 Carrier or pilot-wire relay A device that is operated or restrained by a signal —
transmitted or received via any communications
media used for relaying.
86 Locking-out relay An electrically operated hand, or electrically, reset Used in conjunction with protective relays to
relay that functions to shut down and hold an lock-out a circuit breaker (or multiple circuit
equipment out of service on the occurrence of breakers) after a trip.Typically required to be
abnormal conditions. manually reset by an operator before the breaker
can be reclosed.
87 Differential protective relay A protective relay that functions on a percentage or Used to protect static equipment, such as cable,
phase angle or other quantitative difference of two bus or transformers, by measuring the current
currents or of some other electrical quantities. differential between two points.Typically the
upstream and/or downstream circuit breaker will
be incorporated into the “zone of protection.”
Eaton EBR-3000 bus differential relay, ETR-4000/
ETR-5000 transformer protective relays,
EMR-5000 motor protective relay, EGR-5000
generator protective relay.
90 Regulating device A device that functions to regulate a quantity or —
quantities, such as voltage, current, power, speed,
frequency, temperature and load, at a certain value or
between certain (generally close) limits for machines,
tie lines or other apparatus.
91 Voltage directional relay A device that operates when the voltage across an —
open circuit breaker or contactor exceeds a given
value in a given direction.
94 Tripping or trip-free relay A relay that functions to trip a circuit breaker, contactor —
or equipment, or to permit immediate tripping by
other devices, or to prevent immediate reclosure of a
circuit interrupter, in case it should open automatically
even though its closing circuit is maintained closed.
Table 58. Comparison of Specific Applications of Enclosures for Outdoor Nonhazardous Locations
Provides a Degree of Protection Against the Enclosure Type
Following Environmental Conditions 3 3R c 3S 4 4X 6 6P
Table 59. Comparison of Specific Applications of Enclosures for Indoor Hazardous Locations
Provides a Degree of Protection Against Class Enclosure Types Enclosure Type
Atmospheres Typically Containing 7 and 8, Class I Groups f 9, Class II Groups f
(For Complete Listing, See NFPA 497M) A B C D E F G 10
Acetylene I n
Hydrogen, manufactured gas I n
diethyl ether, ethylene, cyclopropane I n
Gasoline, hexane, butane, naphtha, propane,
acetone, toluene, isoprene I n
Metal dust II n
Carbon black, coal dust, coke dust II n
Flour, starch, grain dust II n
Fibers, flyings g III n
Methane with or without coal dust MSHA n
f For Class III type ignitable fibers or combustible flyings, see the National Electrical Code, Article 500.
g Due to the characteristics of the gas, vapor or dust, a product suitable for one class or group may not be
suitable for another class or group unless so marked on the product.
Note: If the installation is outdoors and/or additional protection is required by Table 57 and
Table 58, a combination-type enclosure is required.
Referencing the first character, 4, in the IP rating and the row designated “IP4–” in the leftmost column in the
table; the blocks in Column “A” for NEMA Types 3, 3S, 4, 4X, 5, 6, 6P, 12, 12K and 13 are shaded. These NEMA
ratings meet and exceed the IEC protection requirements against access to hazardous parts and solid foreign
objects. Referencing the second character, 5, in the IP rating and the row designated “IP–5” in the rightmost
column in the table; the blocks in Column “B” for NEMA Types 3, 3S, 4, 4X, 6 and 6P are shaded. These NEMA
ratings meet and exceed the IEC requirements for protection against the ingress of water. The absence of shading
in Column “B” beneath the “NEMA Enclosure Type 5” indicates that Type 5 does not meet the IP45 protection
requirements against the ingress of water. Likewise, the absence of shading in Column “B” for NEMA Type 12,
12K and 13 enclosures indicates that these enclosures do not meet the IP45 requirements for protection against
the ingressof water. Only Types 3, 3S, 4, 4X, 6 and 6P have both Column “A” in the “IP4–” row and Column “B”
in the “IP–5” row shaded and could be used in an IP45 application.
The NEMA Enclosure Type 3 not only meets the IP45 Enclosure Rating, but also exceeds the IEC requirements
because the NEMA Type requires an outdoor corrosion test; a gasket aging test; a dust test; an external icing
test; and no water penetration in the rain test. Slight differences exist between the IEC and NEMA test methods,
but the IEC rating permits the penetration of water if “it does not deposit on insulation parts, or reach live parts.”
The IEC rating does not require a corrosion test; gasket aging test; dust test or external icing test. Because the
NEMA ratings include additional test requirements, this table cannot be used to select IP Designations for NEMA
rated enclosure specifications.
IEC 60529 specifies that an enclosure shall only be designated with a stated degree of protection indicated by
the first characteristic numeral if it also complies with all lower degrees of protection. Furthermore, IEC 60529
states that an enclosure shall only be designated with a degreeof protection indicated by the second characteristic
numeral if it also complies with all lower degrees of protection up to and including the secondcharacteristic
numeral 6. An enclosure designated with a second characteristic numeral 7 or 8 only is considered unsuitable
for exposure to water jets (designated by second characteristic numeral 5 or 6) and need not comply with
requirements for numeral 5 or 6 unless it is dual coded. Because the IEC protection requirements become more
stringent with increasing IP character value up through 6, once a NEMA Type rating meets the requirements for
an IP designation up through 6, it will also meet the requirements for all lower IP designations. This is apparent
from the shaded areas shown in the table.
Table 61. 60 Hz Impedance Data for Three-Phase Copper Cable Circuits, in Approximate Ohms per 1000 ft (305 m) at 75 °C (a) Three Single Conductors
Wire Size, In Magnetic Duct In Non-Magnetic Duct
AWG or 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
R X Z R X Z R X Z R X Z
8 0.811 0.0754 0.814 0.811 0.0860 0.816 0.811 0.0603 0.813 0.811 0.0688 0.814
8 (solid) 0.786 0.0754 0.790 0.786 0.0860 0.791 0.786 0.0603 0.788 0.786 0.0688 0.789
6 0.510 0.0685 0.515 0.510 0.0796 0.516 0.510 0.0548 0.513 0.510 0.0636 0.514
6 (solid) 0.496 0.0685 0.501 0.496 0.0796 0.502 0.496 0.0548 0.499 0.496 0.0636 0.500
4 0.321 0.0632 0.327 0.321 0.0742 0.329 0.321 0.0506 0.325 0.321 0.0594 0.326
4 (solid) 0.312 0.0632 0.318 0.312 0.0742 0.321 0.312 0.0506 0.316 0.312 0.0594 0.318
2 0.202 0.0585 0.210 0.202 0.0685 0.214 0.202 0.0467 0.207 0.202 0.0547 0.209
1 0.160 0.0570 0.170 0.160 0.0675 0.174 0.160 0.0456 0.166 0.160 0.0540 0.169
1/0 0.128 0.0540 0.139 0.128 0.0635 0.143 0.127 0.0432 0.134 0.128 0.0507 0.138
2/0 0.102 0.0533 0.115 0.103 0.0630 0.121 0.101 0.0426 0.110 0.102 0.0504 0.114
3/0 0.0805 0.0519 0.0958 0.0814 0.0605 0.101 0.0766 0.0415 0.0871 0.0805 0.0484 0.0939
4/0 0.0640 0.0497 0.0810 0.0650 0.0583 0.0929 0.0633 0.0398 0.0748 0.0640 0.0466 0.0792
250 0.0552 0.0495 0.0742 0.0557 0.0570 0.0797 0.0541 0.0396 0.0670 0.0547 0.0456 0.0712
300 0.0464 0.0493 0.0677 0.0473 0.0564 0.0736 0.0451 0.0394 0.0599 0.0460 0.0451 0.0644
350 0.0378 0.0491 0.0617 0.0386 0.0562 0.0681 0.0368 0.0393 0.0536 0.0375 0.0450 0.0586
400 0.0356 0.0490 0.0606 0.0362 0.0548 0.0657 0.0342 0.0392 0.0520 0.0348 0.0438 0.0559
450 0.0322 0.0480 0.0578 0.0328 0.0538 0.0630 0.0304 0.0384 0.0490 0.0312 0.0430 0.0531
500 0.0294 0.0466 0.0551 0.0300 0.0526 0.0505 0.0276 0.0373 0.0464 0.0284 0.0421 0.0508
600 0.0257 0.0463 0.0530 0.0264 0.0516 0.0580 0.0237 0.0371 0.0440 0.0246 0.0412 0.0479
750 0.0216 0.0495 0.0495 0.0223 0.0497 0.0545 0.0194 0.0356 0.0405 0.0203 0.0396 0.0445
Note: More tables on Page 140.
8 0.811 0.0577 0.813 0.811 0.0658 0.814 0.811 0.0503 0.812 0.811 0.0574 0.813
8 (solid) 0.786 0.0577 0.788 0.786 0.0658 0.789 0.786 0.0503 0.787 0.786 0.0574 0.788
6 0.510 0.0525 0.513 0.510 0.0610 0.514 0.510 0.0457 0.512 0.510 0.0531 0.513
6 (solid) 0.496 0.0525 0.499 0.496 0.0610 0.500 0.496 0.0457 0.498 0.496 0.0531 0.499
4 0.321 0.0483 0.325 0.321 0.0568 0.326 0.321 0.0422 0.324 0.321 0.0495 0.325
4 (solid) 0.312 0.0483 0.316 0.312 0.0508 0.317 0.312 0.0422 0.315 0.312 0.0495 0.316
2 0.202 0.0448 0.207 0.202 0.0524 0.209 0.202 0.0390 0.206 0.202 0.0457 0.207
1 0.160 0.0436 0.166 0.160 0.0516 0.168 0.160 0.0380 0.164 0.160 0.0450 0.166
1/0 0.128 0.0414 0.135 0.128 0.0486 0.137 0.127 0.0360 0.132 0.128 0.0423 0.135
2/0 0.102 0.0407 0.110 0.103 0.0482 0.114 0.101 0.0355 0.107 0.102 0.0420 0.110
3/0 0.0805 0.0397 0.0898 0.0814 0.0463 0.0936 0.0766 0.0346 0.0841 0.0805 0.0403 0.090
4/0 0.0640 0.0381 0.0745 0.0650 0.0446 0.0788 0.0633 0.0332 0.0715 0.0640 0.0389 0.0749
250 0.0552 0.0379 0.0670 0.0557 0.0436 0.0707 0.0541 0.0330 0.0634 0.0547 0.0380 0.0666
300 0.0464 0.0377 0.0598 0.0473 0.0431 0.0640 0.0451 0.0329 0.0559 0.0460 0.0376 0.0596
350 0.0378 0.0373 0.0539 0.0386 0.0427 0.0576 0.0368 0.0328 0.0492 0.0375 0.0375 0.0530
400 0.0356 0.0371 0.0514 0.0362 0.0415 0.0551 0.0342 0.0327 0.0475 0.0348 0.0366 0.0505
450 0.0322 0.0361 0.0484 0.0328 0.0404 0.0520 0.0304 0.0320 0.0441 0.0312 0.0359 0.0476
500 0.0294 0.0349 0.0456 0.0300 0.0394 0.0495 0.0276 0.0311 0.0416 0.0284 0.0351 0.0453
600 0.0257 0.0343 0.0429 0.0264 0.0382 0.0464 0.0237 0.0309 0.0389 0.0246 0.0344 0.0422
750 0.0216 0.0326 0.0391 0.0223 0.0364 0.0427 0.0197 0.0297 0.0355 0.0203 0.0332 0.0389
Table 63. 60 Hz Impedance Data for Three-Phase Aluminum Cable Circuits, in Approximate Ohms per 1000 Ft (305 m) at 90 °C (a) Three Single Conductors
Wire Size, In Magnetic Duct In Non-Magnetic Duct
AWG or 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
R X Z R X Z R X Z R X Z
Table 64. 60 Hz Impedance Data for Three-Phase Aluminum Cable Circuits, in Approximate Ohms per 1000 ft (30 m) at 90 °C (b) Three Conductor Cable
Wire Size, In Magnetic Duct and Steel Interlocked Armor In Non-Magnetic Duct and Aluminum Interlocked Armor
AWG or 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
R X Z R X Z R X Z R X Z
18 — — 14 — — — —
16 — — 18 — — — —
14 a 15 20 25 — — — —
12 a 20 25 30 20 20 25 12 a
10 a 30 35 40 25 30 35 10 a
8 40 50 55 30 40 45 8
6 55 65 75 40 50 60 6
4 70 85 95 55 65 75 4
3 85 100 110 65 75 85 3
2 95 115 130 75 90 100 2
1 110 130 150 85 100 115 1
1/0 125 150 170 100 120 135 1/0
2/0 145 175 195 115 135 150 2/0
3/0 165 200 225 130 155 175 3/0
4/0 195 230 260 150 180 205 4/0
250 215 255 290 170 205 230 250
300 240 285 320 190 230 255 300
350 260 310 350 210 250 280 350
400 280 335 380 225 270 305 400
500 320 380 430 260 310 350 500
600 355 420 475 285 340 385 600
700 385 460 520 310 375 420 700
750 400 475 535 320 385 435 750
800 410 490 555 330 395 450 800
900 435 520 585 355 425 480 900
1000 455 545 615 375 445 500 1000
1250 495 590 665 405 485 545 1250
1500 520 625 705 435 520 585 1500
1750 545 650 735 455 545 615 1750
2000 560 665 750 470 560 630 2000
a See NEC Section 240.4 (D).
Note: For complete details of using Table 65, see NEC Article 310 in its entirety.
Table 66. Correction Factors From NFPA 70-2014 (See Table 310.15 [B][2][a])
Ambient For ambient temperatures other than 30 °C (86 °F), multiply the allowable ampacities shown Ambient
Temperature °C above by the appropriate factor shown below. Temperature °F
Rated 0–2000 V (Excerpted from in the Allowable Ampacity (a) More Than Three Current-Carrying
Conductors in a Raceway or Cable.
NFPA 70-2014, 310.15) Table 310.15(B)(16) through Table
Where the number of current-carrying
310.15(B)(19), and Ampacity Table
Note: Fine Print Note (FPN) was changed 310.15(B)(20) and Table 310.15(B)(21) conductors in a raceway or cable
to Informational Note in the 2011 NEC. as modified by 310.15(B)(1) through exceeds three, or where single
(B)(7). conductors or multiconductor cables
are installed without maintaining
(A) General. Note: Table 310.15(B)(16) through spacing for a continuous length longer
(1) Tables or Engineering Supervision. Table 310.15(B)(19) are application tables for than 24.00-inch (600 mm) and are not
Ampacities for conductors shall be use in determining conductor sizes on loads installed in raceways, the allowable
permitted to be determined by tables calculated in accordance with Article 220.
ampacity of each conductor shall be
Allowable ampacities result from consideration
as provided in 310.15(B) or under reduced as shown in Table 310.15(B)(3)
of one or more of the following:
engineering supervision, as provided (a). Each current-carrying conductor
in 310.15(C). (1) Temperature compatibility with of a paralleled set of conductors
connected equipment, especially the shall be counted as a current-
Note: Informational Note No. 1: Ampacities
provided by this section do not take voltage connection points. carrying conductor.
drop into consideration. See 210.19(A), Note: Informational Note No. 1: See Annex B,
Informational Note No. 4, for branch circuits (2) Coordination with circuit and
Table B.310.15(B)(2)(11), for adjustment factors
and 215.2(A), Informational No. 2, for feeders. system overcurrent protection. for more than three current-carrying conductors
Note: Informational Note No. 2: For the (3) Compliance with the requirements of in a raceway or cable with load diversity.
allowable ampacities of Type MTW wire, see
product listings or certifications. See
Table 13.5.1 in NFPA 79-2007, Electrical Note: Informational Note No. 2: See 366.23(A)
Standard for Industrial Machinery. 110.3(B). for adjustment factors for conductors in
(4) Preservation of the safety benefits of sheet metal auxiliary gutters and 376.22(B)
(2) Selection of Ampacity. Where more for adjustment factors for conductors in
established industry practices and metal wireways.
than one ampacity applies for a given standardized procedures.
circuit length, the lowest value shall be
used. Exception: Where two different (1) General. For explanation of type (1) Where conductors are installed in
ampacities apply to adjacent portions letters used in tables and for cable trays, the provisions of 392.80
of a circuit, the higher ampacity shall recognized sizes of conductors for the shall apply.
be permitted to be used beyond the various conductor insulations, see (2) Adjustment factors shall not apply
point of transition, a distance equal to Table 310.104(A) and Table 310.104(B). to conductors in raceways having
10 ft (3.0 m) or 10 percent of the circuit For installation requirements, see a length not exceeding 24.00-inch
length figured at the higher ampacity, 310.1 through 310.15(A)(3) and the (600 mm).
whichever is less. various articles of this Code. For
flexible cords, see Table 400.4, Table (3) Adjustment factors shall not apply to
Note: See 110.14(C) for conductor temperature underground conductors entering or
400.5(A)(1) and Table 400.5(A)(2).
limitations due to termination provisions.
leaving an outdoor trench if those
conductors have physical protection
in the form of rigid metal conduit,
intermediate metal conduit, rigid
polyvinyl chloride conduit (PVC), or
reinforced thermosetting resin conduit
(RTRC) having a length not exceeding
10 ft (3.05 m), and if the number of
conductors does not exceed four.
Kilowatts
kVA —
Horsepower (output)
a For two-phase, three-wire circuits, the current in the common conductor is times that in either of the two other conductors.
Note: Units of measurement and definitions for E (volts), I (amperes), and other abbreviations are given below under Common Electrical Terms.
Learn more
Eaton.com/Consultants
Eaton
1000 Eaton Boulevard
Cleveland, OH 44122
United States
Eaton.com