Network Diagram: Engineering Field Office - 445 CD

The network diagram outlines the schedule and durations for various construction activities for a building project. It shows excavation and formwork taking place over 10 days to begin, followed by 59 days of steel works for foundation columns on the first floor. Various concrete, steel, and formwork activities are scheduled for subsequent floors along with other tasks like masonry, plumbing, electrical, and finishes over the full 445 day duration of the project. Safety monitoring is scheduled throughout.

Uploaded by

Jeffrey Dioquino
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views

Network Diagram: Engineering Field Office - 445 CD

The network diagram outlines the schedule and durations for various construction activities for a building project. It shows excavation and formwork taking place over 10 days to begin, followed by 59 days of steel works for foundation columns on the first floor. Various concrete, steel, and formwork activities are scheduled for subsequent floors along with other tasks like masonry, plumbing, electrical, and finishes over the full 445 day duration of the project. Safety monitoring is scheduled throughout.

Uploaded by

Jeffrey Dioquino
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

NETWORK DIAGRAM

ENGINEERING FIELD OFFICE – 445 CD

MOVE IN EXCAVATION - 10 CD FORMWORKS @ 1st FLOOR


10 CD

STEEL WORKS ON FTG. COLUMNS @ 1st FLOOR – 59 CD

CONSTRUCTION HEALTH AND SAFETY – 445 CD


ENGINEERING FIELD OFFICE – 445 CD

CONCRETE WORK CONCRETE WORKS ON FORMWORK @


ON FTG, COLUMNS BEAM, SLAB & COLUMNS @ 3rd FLR – 10 CD
@ 1st FLR – 52 CD 2nd AND 3rd FLR – 43 CD

FORMWORK @ STEEL WORKS ON BEAMS, COLUMNS &


2nd FLR – 13 CD SLAB @ 2nd TO 3rd FLR – 53 CD

CONSTRUCTION HEALTH AND SAFETY – 445 CD


CONCRETE WORKS ON FORMWORK @ 3RD FLR
BEAMS, COLUMNS AND 20 CD

SLAB @ 4TH & 5TH FLR


56 CD

STEEL WORKS ON BEAM, COLUMNS & SLAB


@ 4TH & 5TH FLR 86 CD
CONCRETE WORKS ON FORMWORK @ 4TH FLR MASONRY WORKS @ 1ST FLR
BEAMS, COLUMNS AND 20 CD 15 - CD
SLAB @ 5TH & ROOF DECK
FLR - 56 CD

STEEL WORKS ON BEAM, COLUMNS & SLAB


@ 5TH & ROOF DECK FLR 86 CD
ENGINEERING FIELD OFFICE – 445 CD

MASONRY - 46 CD PLUMBING WORKS @ 2ND FLR TO RD


46 CD

ELECTRICAL WORKS SEPTIC TANK STAIRS & RAMP


39 CD 17 CD 12 DAYS

CONSTRUCTION HEALTH AND SAFETY – 445 CD


ENGINEERING FIELD OFFICE – 445 CD

PLUMBING WORKS @ 2ND FLR TO RD WATER PROOFING @ TYILE WORKS – 60 CD


46 CD ROOF DECK – 5 CD

MECHANICAL WORKS PLASTERING – 65 CD


28 CD WATER PROOFING
1ST TO 5TH FLR – 6 CD

CONSTRUCTION HEALTH AND SAFETY – 445 CD


ENGINEERING FIELD OFFICE – 445 CD

DOORS AND AUXILIARY – 15 CD LANDSCAPE – 15 CD SITE CLEARING – 15 CD


WINDOWS – 15 CD

PAINTING WORKS – 45 CD

CONSTRUCTION HEALTH AND SAFETY – 445 CD