02 OQS Sampling Flow Chart

The document outlines the steps in a mining sampling flowchart, including: 1) Stripping, drilling, and top, bottom, and special ore sampling during mining preparation. 2) Mining sampling conducted every 500 tons and screening at screening stations. 3) Wet ore stock pile sampling of top, middle, and bottom sections. 4) Various crushing, grinding, splitting, and assaying steps to derive representative samples for analysis.

Uploaded by

Niel Hokii
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views

02 OQS Sampling Flow Chart

The document outlines the steps in a mining sampling flowchart, including: 1) Stripping, drilling, and top, bottom, and special ore sampling during mining preparation. 2) Mining sampling conducted every 500 tons and screening at screening stations. 3) Wet ore stock pile sampling of top, middle, and bottom sections. 4) Various crushing, grinding, splitting, and assaying steps to derive representative samples for analysis.

Uploaded by

Niel Hokii
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 8

PETEA SAMPLING FLOWCART

STRIPING MINING SCREENING STATION


WET ORE STOCK PILE (WOS)
(SS#10 & SS#9 EB)

Stripping Drill Hole Top Ore Mining Prepared Mining Sampling Special Bottom Ore Ore Reject WOS Sampling
Belt Sampling
Sampling Sampling Sampling Sampling (every ±500 ton) Sampling Sampling Sampling

Screen
2 inch Middle WOS Bottom WOS
500 ton Top WOS Sampling
Sampling Sampling
(2X Sampling every 250 Ton) (±50 Kg)
(±50 Kg) (±50 Kg)
±80 Kg

Kwartering

Timbang

+2"-6" -2"
(± 2 Kg) (± 2 Kg) Screening
2 Inch

MRAL

-2" +2"-6"

Drying
Kwartering

Sample Drum
Boyd Crusher
(-10 Mesh) -2" +2"-6"
(± 2 Kg) (± 2 Kg)
Weight

Pulverizing/CRM
(-200 Mesh)

MRAL TROMOL

Homogenisasi

Drying Screening
Pulp
-1" -6"+3"

Minipal Crussing
Weight -3"+1" Weight

Assay (Ni, Fe)


CRM
Crussing Proses sama dengan Sample -6"+3" Crussing
hanya dinamakan sample -3+1"

Screening Split Split


Mesh -200

Homogenisasi
75% Reject 25% Proses 25% Proses 75% Reject

Pulp
Screen 1/4" Screen 1/4"

Minipal

+1/4" -1/4" -1/4" +1/4"


Assay (Ni, Fe)

Crussing Split Split Crussing

1 Sample Pulp 1 Sample Pulp


1 Sa,ple Duplicat 1 Sa,ple Duplicat
1 Sample H20 1 Sample H20
1 Sample B 1 Sample B

-1" Sample -3" +1"Sample -6"+3" Sample

Sample B

PROCTECH
MINE SAMPLING FLOWCART

STRIPING MINING SCREENING STATION (SS#5, SS#8, SS#9, SS#11) WET ORE STOCK PILE (WOS)

Stripping Drill Hole Top Ore Mining Prepared Mining Sampling Special Bottom Ore Ore Reject WOS Sampling
Belt Sampling
Sampling Sampling Sampling Sampling (every ±500 ton) Sampling Sampling Sampling

Middle WOS Bottom WOS


350 ton Top WOS Sampling
2 Kg Sample Sampling Sampling
(2X Sampling every 175 Ton) (±50 Kg)
(±50 Kg) (±50 Kg)
±80 Kg

MRAL

Weight

Screen 1 "
Screening
1,25 Inch

Kwartering

-1" -1,25" +1.25"


(± 200 g)

MRAL
Drying

Sample Drum
Screen 1 "
Crussing (boyd Crusher)
-10 Mesh
Kwartering Weight

Pulverizing/CRM -1"
(-200 Mesh) (± 200 g)

TROMOL
Drying (>105 C)
Homogenisasi

Pulp Screening
Crushing (boyd Crusher)
-10 Mesh -1" -3"+1.5"

Minipal
Weight -1.5"+1" Weight
Pulverizing/CRM
(-200 Mesh)
Assay (Ni, Fe)
Crussing Same Process With Sample -3"+1.5", Crussing
but remark as sample -3+1.5"
Homogenisasi
Split Split

Pulp

Minipal
75% Reject 25% Proses 25% Proses 75% Reject

Assay (Ni, Fe) Screen 1/4" Screen 1/4"

+1/4" -1/4" -1/4" +1/4"

Crussing Split Split Crussing

1 Sample Pulp 1 Sample Duplicat 1 Sample Duplicat


1 Sample Duplicat 1 Sample H20 1 Sample H20
1 Sample H20
1 Sample B

-1" Sample -1.5" +1"Sample -3"+1.5" Sample

Sample B

PROCTECH
Belt cut Sampling

175 ton SSP


Equal 350 ton SSP
70-80 kg Sample
(2 kg sample to MRAL)
175 ton SSP

175 ton SSP


Equal 350 ton SSP
70-80 kg Sample
(2 kg sample to MRAL)
175 ton SSP

WB Test
(± 200 Kg Prep on Tromme
175 ton SSP - -1" Assay data (9 Elemen
- -1, -1.5, +1.5 H2O
Equal 350 ton SSP
70-80 kg Sample
175 ton SSP (2 kg sample to MRAL)

175 ton SSP


Equal 350 ton SSP
70-80 kg Sample
(2 kg sample to MRAL)
175 ton SSP

Test Test
(± 200 Kg Prep on Tromm
(± 200 Kg Prep
- -1" on Trommel)
Assay data (9 Eleme
- --1, -1.5,data
Assay +1.5(9H2O
Element
- H2O
est
± 200 Kg Prep on Trommel)
-1" Assay data (9 Element)
-1, -1.5, +1.5 H2O

Batch
Average several test (SumProduct s

Test
± 200 Kg Prep on Trommel)
g-1"
Prep on Trommel)
Assay data (9 Element)
--1, -1.5,data
Assay +1.5(9H2O
Element)
WOS
(SumProduct several Batch from SS#)
Belt cut Sampling

250 ton SSP


Equal 500 ton
70-80 kg sample
(2 kg sample to MRAL)
250 ton SSP

250 ton SSP Test


Equal 500 ton (± 200 Kg Prep on Tromme
EB 70-80 kg sample - -1, -3, -6 Assay data (9 Ele
(2 kg sample to MRAL) - -1, -3, -6 H2O
250 ton SSP

250 ton SSP

Equal 500 ton


70-80 kg sample
250 ton SSP (2 kg sample to MRAL)

Test
(± 200 Kg Prep on Tromme
- -1, -3,Test
-6 Assay data (9 Ele
- -1, -3, -6 H2O
(± 200 Kg Prep on Trommel)
- -1, -3, -6 Assay data (9
- -1, -3, -6 H2O

Test
(± 200 Kg Prep on Trommel)
- Assay data (9 Element
- H2O
st
200 Kg Prep on Trommel)
1, -3, -6 Assay data (9 Element)
1, -3, -6 H2O

st
200 Kg Prep on Trommel)
1, -3, -6 Assay data (9 Element)
1, -3, -6 H2O Batch
g Prep on Trommel) Average several test (SumProduct s
- -1, -3, -6 Assay data (9 Element)
- -1, -3, -6 H2O

g Prep on Trommel)
- Assay data (9 Element)
WOS
(SumProduct several Batch from SS#)