Kerala Water Authority: Office of The Superintending Engineer
Kerala Water Authority: Office of The Superintending Engineer
TENDER No.114/2020-21/KWA/PHC/D3/TVPM/RT2
The tender timeline is available in the critical date section of this tender published in
www.etenders.kerala.gov.in.
Bidders should have a Class II or above Digital Signature Certificate (DSC) to be procured from any
Registration Authorities (RA) under the Certifying Agency of India. Details of RAs will be available on
www.cca.gov.in. Once, the DSC is obtained, bidders have to register on www.etenders.kerala.gov.in
website for participating in this tender. Website registration is a one-time process without any registration
fees. However, bidders have to procure DSC at their own cost.
Bidders may contact e-Procurement support desk of Kerala State IT Mission over telephone at 0471-
2577088/188/388 or 0484-2336006, 2332262 or 0497-2764788, 2764188 or 0483-273294 or through
email:[email protected] or [email protected] for assistance in this regard.
i. Downloading of tender document: Tender document will be available for free download on
www.etenders.kerala.gov.in. However, tender document fees shall be payable at the time of bid
submission as stipulated in this tender document.
ii. Publishing of Corrigendum: All corrigenda shall be published on www.etenders.kerala.gov.in and
shall not be available elsewhere.
iii. Bid submission: Bidders have to submit their bids along with supporting documents to support their
eligibility, as required in this tender document on www.etenders.kerala.gov.in. Hard copies of all tender
documents and other supporting documents shall be submitted to the tendering authority within three days
of opening of the tender. However, the online submitted documents will always supersede the manually
submitted hard copies of documents for tender evaluation.
iv. Opening of Bids: On the date and time mentioned in critical date’s section.
The proposal shall contain the scanned copies of the following documents which every bidder has to
upload:
i) Document 1 : Scanned copy of duly filled and signed preliminary agreement prepared in Kerala Stamp
Paper worth Rs.200/-
ii) Document 2 : Scanned copy of documents to prove eligibility criteria
iii) Document 3: The NIT documents of the work downloaded from the website to agree with the tender
conditions
iv) Document : Any other documents as per the requirement of the tender conditions
v) …………….. (the number may vary with departments/ PSUs requirement)
vi)The Bidder shall complete the BoQ/Price schedule as per format given for download along with this
tender
Kerala Water Authority doesn’t take any responsibility for any technical snag or failure that has taken
place during document upload.
Note: The blank price bid should be downloaded and saved on bidder’s computer without changing file-
name otherwise price bid will not get uploaded. The bidder should fill in the details in the same file and
upload the same back to the website.
Fixed price: Prices quoted by the Bidder shall be fixed during the bidder's performance of the contract and
not subject to variation on any account. A bid submitted with an adjustable/ variable price quotation will
be treated as non - responsive and rejected.
D). Tender Fee and Earnest Money Deposit (EMD)
The Bidder shall pay, a tender fee and Earnest Money Deposit (EMD) or Bid Security amount as per the
tender documents. The Bid security is required to protect the purchaser against risk of Bidder’s conduct,
which would warrant the forfeiture of security.
Online Payment modes: The tender fee and EMD can be paid in the following manner through e-
Payment facility provided by the e-Procurement system:
State Bank of India Multi Option Payment System (SBI MOPS Gateway): Bidders are required to avail
Internet Banking Facility in any of below banks for making tender remittances in e-Procurement System.
During the online bid submission process, bidder shall select SBI MOPS option and submit the page,
to view the Terms and Conditions page. On further submitting the same, the e-Procurement system
will re-direct the bidder to MOPS Gateway, where two options namely SBI and Other Banks* will be
shown. Here,Bidder may proceed as per below:
a) SBI Account Holders shall click SBI option with its Net Banking Facility., where bidder can
enter their internet banking credentials and transfer the Tender Fee and EMD amount.
b) Other Bank Account Holders may click Other Banksoptionto view the bank selection page.
Here, bidders can select from any of the 54 Banks to proceed with its Net Banking Facility,
for remitting tender payments.
*Transaction Charges for Other Banks vide SBI Letter No. LHO/TVM/AC/2016-17/47 – 1% of transaction
value subject to a minimum of Rs. 50/- and maximum of Rs. 150/-
Any transaction charges levied while using any of the above modes of online payment has be borne by
the bidder. The supplier/contractor's bid will be evaluated only if payment status against bidder is
showing “Success” during bid opening.
For submission of bids, all interested bidders have to register online as explained above in this document.
After registration, bidders shall submit their bid online on www.etenders.kerala.gov.in along with online
payment of tender fee and EMD.
For page by page instructions on bid submission process, please visit www.etenders.kerala.gov.in and
click “Bidders Manual Kit” link on the home page.
It is necessary to click on “Freeze bid” link/ icon to complete the process of bid submission
otherwise the bid will not get submitted online and the same shall not be available for viewing/
opening during bid opening process.
The bidders have the opportunity to revise the rates or documents uploaded by him even after
submission, till the closing date of the render. Also the bidder can withdraw his offer before the closing
date. Resubmission will not be possible for withdrawn bids. The option is available from "my active bids"
link
CONTENTS
2. Special Conditions 20
5. Forms of Agreement 42
FORM No. 83
Name of Work:- KIIFB- CWSS to Vithura and Tholicode villages - Relaying of Distribution lines
of 200mm DI K9 pipe and 160mm pvc (10kg/cm2) pipe from Theviyodu
junction to Vithura Jersi farm due to Vithura-Bonacaud road widening
project
1.1 Electronic tenders are invited for and on behalf of the Managing Director, KWA, from
Registered contractors of Kerala Water Authority “Class B” for the work of “KIIFB- CWSS to
Vithura and Tholicode villages - Relaying of Distribution lines of 200mm DI K9 pipe and
160mm pvc (10kg/cm2) pipe from Theviyodu junction to Vithura Jersi farm due to
Vithura-Bonacaud road widening project”
1.2. The items and sub-heads of works to be done are enumerated in the subjoined schedule
unless otherwise specified, the tender must be for the whole or any individual work and part
tenders are liable to rejection. A contractor may tender for more than one work with the
earnest money deposit specified in each case, but shall not tender for any part of a work
only, unless specifically so required.
1.3. All works shall be done in conformity with the specifications and conditions of contract in
force in the KWA. In case of schedule rate contract, tenderers must quote their own rates
specifically for each item without reference to the departmental estimates or the current
schedule of rates and for percentage rate contract, only a single rate as an overall percentage
above or below or at the rate given in the schedule by a single entry at the bottom of the
schedule under the head quoted rate, may be made. The rates quoted shall be inclusive ones,
covering all the operations contemplated in the specifications and tender schedules and all
incidental work necessary for such operations such as shoring, bailing, form work,
scaffolding, etc. "The rates quoted shall be inclusive of tax".
(a) When tenders are delivered based on contractor's alternate designs, such tenders should
be accompanied by a schedule of quantities of materials to be used for each item of work
with complete detailed specifications and rate. In such cases the benefit of any savings in the
quantities of materials actually used up under each item of work during execution will accrue
to the department.
(b) The overall percentage rate accepted and specified in the agreement shall not be varied on
any account whatever.
1.4. The tenders shall be submitted electronically to the Superintending Engineer, Public Health
Circle, Kerala Water Authority, Thiruvananthapuram in the method available at the website
www.etenders.kerala.gov.in. All documents / attested copies shall be submitted
electronically by scanning and uploading. The tender documents in original / attested copy
of the documents shall be submitted within 3 days of the date of opening of tender. The
contractors can view the tender notice and the tender documents free of cost in website. On
1.20 The successful tenderer will have to carry out 25 per cent more of the estimated quantity
of every item at his agreed rates.
1.21. Any further information necessary can be obtained at the office of the undersigned on all
working days during office hours.
1.22. The work should be completed in all respects in 6 months from the date of work
order.`
1.23. Payment on lump sum basis or by final measurement at unit prices:
a) Final measurements need not be taken unless either the contractor or the Executive
1.42. The contractor shall employ engineering personnel as detailed below for a period of one to
two years according to the tenure of the contract. .
Cost of work executed No. of personnel to be Employed
2. SPECIAL CONDITIONS
Name of work:- KIIFB- CWSS to Vithura and Tholicode villages - Relaying of Distribution
lines of 200mm DI K9 pipe and 160mm pvc (10kg/cm2) pipe from
Theviyodu junction to Vithura Jersi farm due to Vithura-Bonacaud
road widening project
2.1.All works shall be done in conformity with the specification and condition in the contract
in force in KWA. The tenderer shall quote only single rate as an overall percentage above
or below or at the rates given in the schedule by a single entry at the bottom of the
schedule under the head ”quoted rate of the contractor". The rates quoted shall be
inclusive by covering all the operation contemplated in the specification and tender
schedule and all incidental work necessary for such operations such as shoring, bailing
out, form work, scaffolding, etc. The rates quoted shall be inclusive of tax. The contractor
should upload the declaration in the form attached.
2.2. The rates quoted by the contractor for the various items shall be inclusive of all tools and
plants required for the proper execution of work and all other incidental charges and
separate claim for these will not be entertained under any circumstances.
2.3. The quantities shown in the schedule are only approximate and are subject to variations and
the contractor is bound to do additional quantities of work if found necessary at his quoted
rates.
2.4. All the rates quoted should be inclusive of tax also.
2.5. All corrections and insertions in the original tender or schedule whether in the printed matter
or elsewhere shall be attested by the tenderer.
2.6. The contractor has to quote for the specification and unit noted in the schedule. No
correction of specification, unit or quantity is admissible and if they make any correction in
the specification, etc., the same will be rejected. If they have to note anything, they shall note
the same as a foot note at the bottom of the page.
2.7. The contractor should note his Division Register Number and amount of permanent earnest
Money deposited by him in his tender.
2.8. The contractor should produce the declaration in the form attached.
2.9. "The contractor is bound to carry out items of works which are not expressly or impliedly
described in the tender schedule, plans, specifications and agreement but which are found
necessary for the proper completion of the work during execution. Payment for such extra
items will be made on the basis of extra item conditions vide clause 23 (c) of form No.
GWD. 83."
2.10. For L.S. items the contractor will be paid only for the actual quantity of work done or
materials supplied and labour engaged at agreed rates for such items and as per condition
No.9 above for extra items but such payment will be limited to the lump sum quoted by the
contractor. If he fails to quote definite L.S rates for such items the L.S. amount provided in
the schedule will be operative in his case.
2.11. For materials issued for the work but not used and not returned to the store, tax at the
prevailing rates will be recovered in addition to the departmental recovery plus 20 percent
storage.
2.12. For cement and M.S., rods issued for the work but not used a penalty of Rs. 20.00 per 50
kilograms of cement and Rs. 2.50 per kilogram of M.S., rods will be recovered in addition to
the value, 20 percent storage and tax.
2.13. lt will be the responsibility of the contractor to obtain necessary land for stacking the
materials for arranging the work.
2.14. Metal of the required size alone should be brought to the site of the work. Breaking
boulders or rubble into metal will not be allowed either on or the side of the road. Metal
should be stacked on one side of the road only and in such a way as not to cause any hazards
to traffic. The stacks should be formed as per the standard profile current in the department.
2.15. Granite stone metal supplied should be sound, hard, tough and durable, free from any
decayed matter and of uniform colour and texture. Each piece should have sharp angular
edges. The metal should not also contain any quarry dust or earth.
2.16. Silicious gravel shall consist of only hard nodules not more than 40 mm. nor less than 6
mm dia, in any direction scraped from the hill sides and free from admixture of earth or
laterite chips.
2.17. Sand supplied should be clean, sharp and gritty to the touch, free from clay and other
impurities and obtained from running watercourses.
2.18. Variation in supply in each 200-meter length exceeding 1 per cent from the approved
indent will not ordinarily be allowed. But supplied above 1 percent over the stipulated
quantity in the particular 200 meter length may be accepted at the discretion of the Executive
Engineer and in that case each ,will be paid at 3/4 of the agreed rate. Similarly if supplies fall
short by more than 1 per cent recovery for this deficiency will be made at 1/4 of the agreed
rates. Excess supplies or deficiency in supplies over 10 percent however will be accepted
only at the discretion of the Executive Engineer subject to its being penalized at half of the
agreed rates. The maximum penalty shall however be limited to 10 per cent of the contract.
2.19. The contractor will have to make his own arrangements to convey the materials supplied by
the department and for stacking, of materials and site shed, etc. which are found necessary
for the proper execution of the work. He will also be responsible for the safe custody of the
materials till they are used on works.
2.20. The contractor should take out license for storing gun powder and explosives required for
rock blasting as per Explosive Act 1940.
2.21. Empty cement bags will not be taken back but its cost Re. 1 per bag will be recorded
towards value with the usual tax.
2.22. Recovery for M.S. rods shall be affected at agreed rates for the quantity actually used plus
wastage, if any. The percentage of wastage will be fixed by the Executive Engineer, but at
any rates it should not exceed 5 per cent of the actual usage.
2.23. If the department undertake the supply of any materials, no claim for extra payment due to
delay in supply of those materials will be entertained.
2.24. If materials other than those specified in the tender are issued by the department, recovery
will be affected at data rate plus storage plus tax or at current market rates at the time of
issue whichever is higher.
2.25. Hire charges of tar boiler and sprayer if supplied departmentally will be recovered at Rs. 5
per day for the whole period they are in the custody of the contractor.
2.26. Machinery like concrete mixer, pump set etc. if available will be supplied by the
department as per rule and hire charges recovered from the contractor at the prevailing
departmental rates. The contractor has to take the machinery from the store and return to the
same spot at his cost and responsibility.
2.27.A day means 8 working hours for purpose of calculation of hire charges of rollers, pump
sets and other machinery unless otherwise specified.
2.28. "The contractor has to take the roller from the
………………………………………………………… and return it to the same spot at his
own cost and responsibility"
2.29 "When power rollers (which term includes steam and diesel rollers) are hired out to
contractors, hire charges for the rollers (which include cost of lubricating oils, grease, small
stores and establishment charges but excludes cost of fuel), shall be recovered at the rate of
Rs. 137 per day or eight hours or part thereof, for the full period the roller is hired out to the
contractor including not-working days except, for authenticate periods of breakdown of the
roller for the full working hours of a day (that is 8 hours from 8 am to 5 pm. including one
hour's interval for lunch), and for Sundays and other public holidays, if there is no work on
these days".
("The daily rate of hire fixed by the Superintending Engineer shall be for a day of 8 hours or
part thereof, between 8 am and 5 pm with one hours interval for lunch")
(b) "If there is work on Sundays and other public holidays the hire charges for the roller,
shall be recovered at the rate of 1.20 times, the rate for normal working days".
2.30 "When power rollers are worked on any day, in excess or eight hours (that is outside the
normal working day between 8 am and 5 pm hire at the rate of 1 .20 times the hourly rate
applicable for that day, (based on the rate for 8 hours) shall be levied for every extra hour or
part thereof'
2.31 "The average out-turns expected from a power roller for a day of 8 hours is as fixed by the
Superintending Engineer for the various items of road work. A variation of plus or minus 12
1
/2 per cent may be allowed to this average. If the daily out turn from the roller falls outside
the permissible variations the contractor shall be charged at 11/2 times the rate of normal hire
for the day specified for the roller concerned. However, this clause shall not be applicable in
cases where variation is due to authenticated periods of breakdown of the roller or inclement
weather".
In addition to the hire charges, necessary water, split firewood, diesel oil (fuel oil) or
powering as the case may be required for the efficient working of the roller, shall be supplied
by the contractor".
2.32. If part payment is claimed for metal supply: 75 percent of the supply will only be made in
the part bill. The spreading and consolidation should be done within two months of supply.
2.33. The payment of the earth work items will be made as per level measurements or tape
measurements as per rules prevailing in the department.
2.34. AII items should be carried out as per the relevant specification in the M.D.S.S. and all
clause of preliminary specification should be complied with.
2.35. The moulds, shuttering, etc., required for the work should be made by the contractor and
got approved by the departmental officers at site before use.
2.36. Tribes of the locality should be employed to the extent possible. The contractor should pay
fair wages to the labour engaged on the work which will be fixed by the Government as
specified in G.O. 18/ 8597/55/LD., dated 7th March 1956 and any dues to the labour will be
recovered from his bill as fixed by the departmental officers.
2.37. The contractor alone is responsible for the safety of his labourers and damages, if any
payable under "Workmen's Compensation Act" will be to his debit.
2.38. It shall be contractor's responsibility to protect the public and his employees against
accident from any cause during execution of the work and he shall indemnify the
Government against any claims for injury to person or property resulting from any such
accident and he shall, where provisions of the "Workmen's Compensation Act" apply, take
steps to properly insure against any claims there under.
2.39. The contractor shall be liable for any loss caused to the Government on account of the
above work including any that may arise due to non fulfillment of the contract. He should
comply with the rules laid down in the Central P.W.D Contract regulations regarding fair
wages.
2.40. The work shall be completed in all respects and also at the rate of progress within the time
limit and stipulations in the Form No. 83 - Notice inviting tender failing which the contractor
is liable to be fined as stipulated in special condition No. 2.47.
2.41. Defects, if any noticed within 3 months (6 months in the cases of road works) from the date
of completion of the work will be got rectified by the contractor, in default of which this will
be attended by the department and the cost made good from the contractor.
2.42. The contractor should produce latest tax clearance certificate and also income-tax clearance
certificate for receiving final payment.
2.43. The contractor shall be responsible for payment of tax as per rules in force from time to
time and the rates quoted for various items remain unaffected by any changes that may be
made from time to time in the rate at which such tax is levied GST and income tax due to
Government from the contractor will be recovered from his bill for the work as per the advise
of the authorities concerned.
2.44. AlI sums due to the Government under or by virtue of this contract shall be recoverable
first from the security furnished by the contractor and if the same is found insufficient, such
deficit amount shall be recoverable under the provisions of the Revenue Recovery Act for the
time being in force as though the same were arrears of Land Revenue or any other manner as
the Government may deem fit.
2.45. The contractor agrees that before final payment shall be made on the contract, he will sign
and deliver to the Executive Engineer either in the measurement book or otherwise as
demanded, a valid release and discharge from any and all claims and demands whatsoever
for all matters arising out or connected with the contract. Provided that nothing in this clause
shall discharge or release the contractor from his liabilities under the contract it is further
expressly agreed that the Executive Engineer in supplying the final measurement certificate
need not be bound by the preceding measurement and payments. The final measurements, if
any, of the Executive Engineer shall be final, conclusive and binding on the contractor.
2.46. The tender notice and Form No. 83 Notice Inviting Tender shall form part of the
Agreement.
2.47. The date fixed by the Superintending Engineer for the commencement and completion of
works as entered in this agreement shall be strictly observed by the contractor who shall pay
damages at the rates of (1) one per cent on the estimated value of the contract for every day
not exceeding five days that work remains un commenced or unfinished after the proper date
and further to ensure good progress during the execution of works, the contractor shall be
bound unless the contract provides otherwise in all cases in which the time allowed for a
work exceed one month to complete. One fourth of the whole work to be done when one
fourth of the whole time allowed for it has elapsed, one half of the work when one half of
time has elapsed and three fourths of work when three fourth of time has elapsed and the
penalty for the failure in either of these cases shall likewise be that the contractor shall be
subject to pay daily damages at the rate of (1) one per cent on the estimated value of the
amount of work that should be completed by that time. Provided always that entire amount of
damages to be paid under the provisions of this clause shall not exceed in the whole amount
of retention (performance security deposit) plus the performance guarantee. All damages
payable under the provisions of this clause or clause 12 or of the conditions of contract shall
be considered as liquidated damages to be applied to the use of this Government without
reference to the actual loss sustained owing to the delay.
2.48. If during execution, the proportion of usage of material issued departmentally alone is
varied for which the price has been fixed in the tender the quoted rate of the item will be
allowed effecting short or excess of departmental materials actually used as well as labour
charges for handling the short or excess if any provided is in the same position.
2.49. The earnest money deposit of the unsuccessful tenderers will be refunded immediately after
tabulating the tenders keeping only the earnest money of the first two lowest tenderers the
earnest money of the remaining two unsuccessful tenderers will be refunded within a week
from the date of acceptance of tenders.
2.50. The contractor should engage at his own cost a diploma holder (Civil Engineering) with
sufficient practical experience for the proper execution and supervision of work costing from
Rs. 2 lakhs to 51akhs and one Engineering Graduate and one diploma holding (Civil
Engineering) for works costing Rs. 5 lakhs up to 10 lakhs and one Engineering Graduate and
two diploma holders for works costing over Rs. 10 lakhs one or two years according to the
tenure of contract.
2.51. AII other conditions and specifications of contract are the same as those current in the
department.
2.52. The method of measurements will be as per Indian standard 1200-1958.
2.53. AII concrete should be machine mixed and vibrated.
2.54. The tenderer/contractor must clearly understand that the settlement of claims either by part
bills or by final bill will be made only according to the availability of budget provision and
allotment of funds made with the Divisional Officer in charge of the work under the
respective head of account in which the work is sanctioned and arranged and also subject to
the seniority of such bills. No claim for interest or for damages whatsoever shall be made for
the belated settlement of claims of bills. No such claims shall be admitted by the
Government.
(a) The contractor shall pay not less than fair wages to labourers engaged by him on the
work:
"Fair Wages" means wage whether for time or piece work notified at the time of inviting
tenders for the work and where such wages have not been so notified, the wage prescribed by
the Central P.W.D. for the District in which the work is done.
(b) The contractors shall notwithstanding the provisions of any contract to the contrary cause
to pay a fair wage to labourers indirectly engaged on the work including any labour engaged
by his subcontractor in connection with the said work as if the labourers, had been
immediately employed by him.
(c) In respect of all labour directly or indirectly employed in the works for the performance
of the contractor's part of this agreement the contractor shall comply with or cause to be
complied with (the central P.W.D. Contractor's labour) regulations made by Government in
regard to payment of wages, wage period deductions from wages, recovery of wages not paid
and deductions unauthorizedly made maintenance of wages register, other terms of
employment, inspection and submission of periodical returns and all wage cards, publication
of scale of wages and returns and all other matters of a like nature.
(d) The Executive Engineer or Subdivision Officer concerned shall have the right to deduct
from the money due to the contractor and any sum required of estimated to be required for
making good the loss suffered by a worker or workers by reasons of non fulfillment of the
conditions of the contract for the benefit of the works, non payment of wages or deductions
made from his or their wages which are not justified by their terms of the contract or non
observance of the regulations.
(e) Vis-a-vis the Central Government, the contractor shall be primarily liable for all
payments to be made under and for the observance of the regulations aforesaid without
prejudice to his right to claim from these sub contractors.
(f) The regulation aforesaid shall be deemed to be a part of this contractor and breach thereof
shall be a breach of this contract.
due and payable to the contractor such sum of sums of money as may, the opinion of the said
Executive Engineer, be sufficient to meet such liability. The opinion of the Executive
Engineer shall be final in regard to all matters arising under this clause.
(e) 1 % of the amount of bill amount less cost of departmental materials will be recovered
along with other recoveries towards the contribution to "Kerala Construction Works Welfare
Fund Board"
2.57. The Tenderer should submit a preliminary Agreement executed and signed in Kerala Stamp
Paper worth Rs. 200/- along with Tender documents failing which the tender will be rejected.
2.58. GST as per rules will be deducted from Contractors part bill/ Final bill at the specified rate
as per the prevailing rules
Superintending Engineer
Contractor
Note: - If the contractor is found at any stage, to have suppressed any information required,
his earnest money for the work is liable to be forfeited and the contract entered into will
stand cancelled.
G.W.D. 84
Name ...................................................................................................................................
.............................................................................................................................................
3.1. The rates tendered by a Contractor for the work shall include the cost of –
(a) All labour and supervision thereof, all materials, tools, implements and plant of every
description ladders, cordage, tackle, etc, as well as the provision of safe and
substantial scaffolding required for the proper execution of the work in conformity
with the specifications for the various items of work;
(b) Supplying the requisite agency with necessary equipments, to set out the work as well
as to afford facilities for such examination of the work as the departmental Officers
may at any time consider desirable, as also to count, weigh and assist in the
measurement or check measurement of the work or materials.
(c) Providing and maintaining all temporary fences, shelters, lights watchmen and danger
signals and such other precautions as are necessary for the protection of the work or
materials, as well as to protect the public and those connected with the work from
accidents at the site of, or on account of the work;
(d) Al sheds, mortar mills and mixing platform of every kind required for the proper
execution of the work according to the specifications;
(e) All fees and royalties of materials; and
(f) Finally clearing away of all rubbish, surplus materials, plants etc., on completion of
the work and pressing and leveling off and restoring the site to a tidy condition, prior
to handing over the work to the Division Officer or his authorized assistant and also
its maintenance until so taken over.
3.2 In the case of supplies of materials such as rubble, broken stones, gravel, sand, etc.,
which may have to be measured prior to being used on the work, the contractor must
always stack or arrange them neatly on level ground or on ground cleared and leveled by
him for the purpose in such manner as may be ordered by the Officer-in-charge so that
they may be easily susceptible of inspection and measurement, the cost of such clearing,
leveling and stacking or arranging being included in the rates for work, Each stack must
be straight and of uniform section throughout and of the dimensions specified by the
Officer-in-charge. Materials not stacked or arranged in accordance with instructions
issued will not be measured and paid for.
3.3 The Contractor shall be bound to bear the expense of defense of any action or law
proceedings that may be brought by person for any injury sustained owing to neglect of
above precautions in connection with the execution of the work, and to pay any damages
and cost which may be awarded in consequence.
3.4 The Contractor shall also help himself out of any difficulties of penalties arising from
interference with private property in the execution of the contract.
3.5 The tenderer should state whether he has all the plant necessary for execution of the
work. If in the opinion of the Division Officer, Contractor’s own plant is neither
sufficient for the proper execution of the work, the department may supply other
available plant and recover reasonable hire for the same. The Division Officer’s decision
in the matter shall be final and binding on the Contractor.
3.6 The Contractor shall bear the running expenses inclusive of pay of the departmental staff
attached to such plant and cost of repairs of all KWA plant while in his possession on
hire as also the cost of restoring the same in good condition at the time of return, due
allowance being made for fair wear and tear.
3.7 All materials and plant that are to be made over to the Contractor by the Department shall
be handed over at him at the Division Office or Store Yards at Division Headquarters of
the KWA General Stores Trivandrum and the charges for their handling, loading and
unloading and conveyance to and from the respective work as also for stacking the
Part II Materials
FORM OF TENDER
once paid successfully and credited to Kerala Water Authority account will not be refunded even if the tender is
cancelled at a later stage or the tenderer fails to upload his tender. Preliminary agreement in the prescribed form in
Rs. 200/- Kerala Stamp Paper duly signed and sealed shall be uploaded without fail. The price bid shall be filled up
in the prescribed format provided in the tender document. For uploading the technical and price bids, the tenderer
has to remit the amount towards cost of tender documents as well as the prescribed EMD through SBI internet
banking or through SBI internet banking or through SBI MOPS mode of payment. Price bid /schedule shall be
submitted electronically only.
4.2 The technical bid and price bid will be opened by the Superintending Engineer / Authority at the time and
date specified for opening of tender.
4.3 The rate quoted by the contractor should be inclusive of hire charges for the tools and plant, all taxes etc.
and all other incidental charges and no extra claims on these account, will be admitted.
4.4 The contractor shall be bound to carry out all extra items not provided for in the schedule but found
necessary during execution of the work.
4.5 For LS items payment will be made on actual measurement limited to the amount agreed to by the tenderer.
4.6. Cement/ Tor steel / MS rods and other materials issued for the work should be stored suitably at the work
site or in a store approved by the Authority. Account of receipts and issues should be maintained at stores
and all facilities should be given by the contractor to the Authority officers for checking the stores at any
time fixed by the Authority. If any shortage is noticed, the contract is liable to be cancelled immediately and
suitable action will be taken against the contractor for the misuse of Authority materials.
4.7. Surplus materials supplied by the Authority should be returned to the Authority Stores as per the directions
of the Authority Officers immediately after the work is completed and the contractor should obtain suitable
receipts from the Store Keeper for the same.
4.8. FCC will not be paid unless contractors have produced Income Tax and tax clearance certificate.
4.9. Contractor is bound to give fair wages to labourers employed by him as per the standing rules of the
Government.
36
4.10 Contractor is bound to engage suitable experienced hands for the execution of work. He should also
see that the works are carried out in the presence of his authorized representatives, if he is not in a position to
present him at the work site during working hours.
4.11 If the Kerala Water Authority undertakes to supply certain materials, no claims for extra payment on account
of delay in the supply of these materials will be entertained.
4.12 The contractor shall examine whether there are any gas mains, electric or phone posts, cables, water main,
sewers, covered drains etc., coming in the line of the trench and shall not excavate in such localities before
such mains, cables or drains or sewer are diverted or otherwise arranged for.
4.13 The contractor shall be responsible for any damage which may be caused to power or phone posts or cables
or to building, walls or pipes etc., nearby on account of the excavation of the trench due to insufficient or
lack of shoring or due to the result of bailing out or pumping or stagnation of water. The contractor shall
make his own arrangements for supporting electric and telephone posts, electric and telephone cables,
existing water mains during excavation and no extra payment will be give for this.
4.14 The contractor shall examine and satisfy himself that the beds of the trenches are firm and suitable for laying
the pipes. Should any portion be found unsatisfactory, the contractor shall take necessary steps to make the
trench firm and suitable for laying pipes.
4.15 The Authority materials issued to the contractor shall be taken charge from stores by the contractor after
satisfying himself about their sound condition and granting receipt to the officer - in – charge and make
available the materials for the purpose of inspecting, weighing or testing the pipes and materials as the
officer-in-charge shall see fit to do.
4.16 All pipes, specials, valves etc., shall be transferred and stored adjacent to their final position of the work,
where they are to be used at such time as the officer - in – charge considers proper. This will usually be just
before they are to be laid in the trenches.
4.17 The pipes, specials and valves etc., shall be handled very carefully during loading, unloading, conveying,
lowering operations as per the directions of the Authority officers under their approved modes and with
approved instruments and should be satisfied that they are not defective.
4.18 If any of the materials issued to the contractor in good condition become there after damage before/ when or
after being placed in the work, the contractor shall be liable for the damage and shall be charged at the rate fixed by
the Authority as per rule.
4.19 No payment will be made for additional pumping for bailing out water that may be required due to the fault
of the contractor by way of inefficiency or delay in carrying out the works, defective works etc.,
4.43 The contractor shall be bound to carry out works up to 10% in excess of the quantity specified, if required
during actual execution, on the same terms and conditions
4.44. Not applicable
4.45 The monetary benefit due to any reduction declared by Government of India/ State in the statutory
duties and levies after the tender submission should be passed on to Kerala Water Authority. For affecting
this, the detailed break up of their purchase cost showing clearly the basic prices, Taxes, transportation etc.,
shall invariably be noted. In cases where these are not mentioned, any reduction shall be assessed by Kerala
Water Authority with the present market rate of the material.
4.46 Pipes and other construction materials shall be stacked at site only in consultation with the Executive
Engineer concerned and will not be stacked more than 5 days before commencement of work. The excess cut
4.47 The Bar Charts, Work Plan, Work Schedule in the agreement shall be submitted for all works so as to
monitor the progress of the works. The as laid map of pipe line works shall be submitted by the contractor along
with the bill and the same shall be verified by the concerned officers before making payment. The as laid maps
shall be kept in the Division office separately for future reference and one copy along with the agreement.
4.48 Works should be carried out causing minimum hindrance to traffic and inconvenience to the public. In cases
where traffic is not blocked, trenching, pipe laying, back filling and rectification are to be done
simultaneously.
If any of the conditions above are in contradiction to any of the clauses in the Form 83, Special
conditions, Form 84, the clause/conditions of the additional tender conditions shall prevail.
Superintending Engineer
Within fourteen days after the date when the acceptance of the tender has been intimated to him, the tenderer shall
deposit a sum sufficient to make to the balance which together with the amount of earnest money deposited shall be
created as security for the proper fulfillment of the same and shall execute an agreement for the work in the
stipulated manner. If he fails to do this or in the case of the contract to maintain a specified rate of progress (to be
specified in each case in the tender schedule) the earnest money and performance guarantee shall be forfeited to
KWA and fresh tenders shall be called for or the matter otherwise disposed off. If as a result of such measures due
to the default of the tenderer to pay the required deposit to KWA results in any loss to KWA, the same will be
recovered from him as arrears of revenue. The original contractor shall have no claim whatever to the sum that may
be due to the contractor on this or any other subsisting contracts or under the Revenue Recovery Act or otherwise
the KWA may decide.
1. The contractor hereby agrees and undertakes to perform/fulfill all the operations and obligations with the
execution of the said contract work
………………………………………………………………………………………………………………………
………………………is awarded in favour of the contractor.
2. If the contractor does not come forward to execute the original agreement after the said work is awarded and
selection notice issued in his favour commits breach of any of the conditions of the contract as stipulated in the NIT
as quoted above within the period stipulated therein the KWA may rearrange the work otherwise or loss so
sustained by the KWA can be realized from the contractor under Revenue Recovery Act as if arrears of land
revenue as assessed, taking into consideration the prevailing PWD rate and after giving due notice to contractor.
The acquisition taken by such authority officer or officers shall be final and conclusive and shall be binding on the
contractor.
3. The tenderer further agrees that any amount found due to the KWA under or by virtue of this agreement shall be
recoverable from the contractor from his EMD and his properties movable and immovable as arrears of Land
Revenue under the provisions of the Revenue Recovery Act for the time being or in any other manner as the KWA
may deem fit in this regard.
4. The contractor further assures it is clearly understood that the settlement of claims either by part bills or by final
bills will be made only according to the availability budget provision and allotment of funds to the divisional officer
in charge of the work under respective heads of account in which the work is sanctioned and arranged and also
subject to seniority of such bills. No claim for interest or for damages whatsoever shall be made for the belated
settlement of claims of bills.
IN WITNESS WHERE OF Sri.--------------------------(here the name of the officers of the KWA) for on behalf of the
Kerala Water Authority (KWA) and Sri …………………
the tenderer have set their hands on the day and year firm above written signed by Sri -----------------------------------
------------------------officer / officers of Kerala Water Authority.
Superintending Engineer
In the presence of witness
1.
2.
1.
2.
Note:- The form should be presented in Rs. 200/- valid stamp paper of Govt. of Kerala.
AGREEMENT entered into ......................... day of the..... ..... Two Thousand and
............................................................. between.........................................................................
of the one part and the Superintending Engineer, Kerala Water Authority PH Circle,
Thiruvananthapuram for and on behalf of Kerala Water Authority of the other part for the work of
…………………… ………………………… ……………………………
………………………………………………………………………………………………. by the former
for the use of the Kerala Water Authority as per accompanying, plan, specification and conditions of
contract approved by the Superintending Engineer, Kerala Water Authority, PH circle,
Thiruvananthapuram – 33. Signed and delivered by the above mentioned.
Sri... .......... ... ............. ... .............. ........ .......................... ... ................. the contractor
In presence
1.
2.
Signed and delivered by the Superintending Engineer, Kerala Water Authority, PH Circle,
Thiruvananthapuram -33 and on behalf of the Kerala Water Authority.
Superintending Engineer
1.
2.
A
.1 All materials shall be supplied by the contractor in a phased manner as per the phased supply schedule
prepared by the agreement executing authority. Quantity and time of each supply shall be specifically
mentioned in this schedule in tune with the time of completion.
.2 Schedule for phased supply of pipes and specials shall be prepared by the agreement executing authority
based on the following criteria:
.3 Each supply of material shall be done by the Contractor only after getting written instruction from the
Executive Engineer concerned.
.4 The Executive Engineer in - charge shall direct the Contractor to place supply order in each phase after
evaluating actual progress of laying of pipes supplied in the previous phase.
5 Agreement executing authority shall have the authority to modify the schedule for phased supply of remaining
materials during the progress of work, if there is variation from the targeted progress.
.6 On each supply, Contractor may submit bills for materials supplied not exceeding 80% of estimate rate
/quoted rate of materials, whichever is less.
Additional special conditions regarding GST
B
The direction contained in the Government circular no.18/2019/Fin dated 01/03/2019(attached) as per
letter no. KWA/HO/WN/KNR/33/97 dated 07/05/2019 of Managing Director, KWA is applicable to this
tender also. It shall also become part of NIT.
“All bidders should have a valid GST registration. The amount quoted shall be exclusive of GST which may be
paid or become payable on the completed work within the scope of this tender. In other words, the amount
quoted shall be exclusive of GST prevailing as on the due date of the tender and taxes at applicable rates shall be
deducted from the payment to the contractor as per rules without further correspondence. The deductions from
contractor’s payment shall include Income Tax and Labour Welfare Fund as per the rate in force. However this
shall not mean that only this amount shall be deducted. The payment and deduction shall be made as per
Circular no 18/2019/Fin dated 1.3.2019 of the Finance (Industries and Public work- B) department, Government
of Kerala. (copy of the circular is attached for reference)Any tax rules issued by Government and implemented
in KWA as and when will be applicable to this tender also.
Superintending Engineer