0% found this document useful (0 votes)
319 views

Final Estimation For Rate Preparation

This document provides an estimate for construction works including: 1. Excavation for foundations, trenches and drains totaling 434.98 cubic meters 2. Providing cement concrete at foundation level totaling 207.90 cubic meters 3. Formwork for structures and beams totaling 872.90 square meters

Uploaded by

manoj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
319 views

Final Estimation For Rate Preparation

This document provides an estimate for construction works including: 1. Excavation for foundations, trenches and drains totaling 434.98 cubic meters 2. Providing cement concrete at foundation level totaling 207.90 cubic meters 3. Formwork for structures and beams totaling 872.90 square meters

Uploaded by

manoj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

DETAILED ESTIMATE

L- B- H/D-
SINO ITEM DESCRIPTION N QTY UNIT QTY UNIT
FEET FEET FEET

Excavation for all types and sizes of foundations,


trenches and drains or for any other purpose
including disposal of excavated stuff upto 1.5 m
1
lift and lead upto 50m (at least 5m away from
the excavated area), including dressing and
leveling of pits.

FOUNDATION - PEB STRUCTURE 26 8 8 8 13312 cft 376.955904 CU.M


FOR COMPOUND WALL PILE 40 0.75 0.75 8 180 cft 5.09706 CU.M
PLINTH BEAM - PEB STRUCTURE 2 212 1 1.5 636 cft 18.009612 CU.M
5 68 1 1.5 510 cft 14.44167 CU.M
PLINTH BEAM - FOR COMPOUND WALL 2 370 0.75 1 555 cft 15.715935 CU.M
2 112 0.75 1 168 cft 4.757256 CU.M

15361 cft 434.97744 CU.M

Providing and laying nominal mix cement


concrete with crushed stone aggregate using
2 concrete mixer in foundation, plinth and at
ground level excluding cost of form work.MIX-
1:3:6

FOR FOUNDATION-PEB STRUCTURE 26 8 8 0.5 832 cft 23.559744 CU.M


PLINTH BEAM - PEB STRUCTURE 2 212 1 0.5 212 cft 6.003204 CU.M
5 68 1 0.5 170 cft 4.81389 CU.M
PLINTH BEAM - FOR COMPOUND WALL 2 370 0.75 0.5 277.5 cft 7.8579675 CU.M
2 112 0.75 0.5 84 cft 2.378628 CU.M
FOR BASEMENT 1 212 68 0.4 5766.4 cft 163.287149 CU.M

7341.9 cft 207.90058 CU.M

Providing and fixing formwork including


centering, shuttering, strutting, staging,
3
propping bracing etc. complete and including its
removal at all levels,

FOR FOUNDATION-PEB STRUCTURE 2 26 8 2 832 sq.ft 77.376 SQ.M


2 26 8 2 832 sq.ft 77.376 SQ.M
PEDESTAL COLUMN upto plinth level 2 26 2.25 10 1170 sq.ft 108.81 SQ.M
2 26 1.5 10 780 sq.ft 72.54 SQ.M
PLINTH BEAM - PEB STRUCTURE
2 2 212 1.5 1272 sq.ft 118.296 SQ.M
2 5 68 1.5 1020 sq.ft 94.86 SQ.M
LINTEL BEAM - PEB STRUCTURE
2 2 212 1.5 1272 sq.ft 118.296 SQ.M
2 5 68 1.5 1020 sq.ft 94.86 SQ.M
PLINTH BEAM - FOR COMPOUND WALL 2 1 370 1 740 sq.ft 68.82 SQ.M
2 2 112 1 448 sq.ft 41.664 SQ.M

9386 S.FT 872.898 SQ.M

Providing and laying nominal mix reinforcement


cement concrete with crushed stone aggregate
4 using concrete mixer in all works upto plinth
level excluding cost of reinforcement and form
work.

m20- 1:1½:3 (1 cement : 1½ coarse sand : 3 graded


stone aggregate 20mm nominal size).
FOR FOUNDATION-PEB STRUCTURE 26 8 8 2 3328 cft 94.238976 CU.M
PEDESTAL COLUMN upto plinth level 26 2.25 1.5 10 877.5 cft 24.8481675 CU.M
PLINTH BEAM - PEB STRUCTURE 1 764 0.75 1.5 859.5 cft 24.3384615 CU.M
LINTEL BEAM - PEB STRUCTURE 1 764 0.75 0.5 286.5 cft 8.1128205 CU.M
FOR COMPOUND WALL PILE 40 0.75 0.75 10 225 cft 6.371325 CU.M
PLINTH BEAM - FOR COMPOUND WALL 1 594 0.75 0.75 334.125 cft 9.46141763 CU.M

5910.625 cft 167.37117 CU.M

Providing and placing in position reinforcement


for R.C.C. work including straightening, cutting,
5
bending, binding etc. complete as per drawings
including cost of binding wire all complete:

taking steel reinforcement as


thermo mechanically treated bars 14776.5625 kg 14.7765625 MT
0.25%of steel quantity

Brick work -Cement Mortar 1:6 (1


6
cement : 6 coarse sand)
PEB STRUTURE - UPTO 10' LEVEL 1 764 0.75 10 5730 cft 162.25641 CU.M
COMPOUND WALL - 7' 1 594 0.75 7 3118.5 cft 88.3065645 CU.M
8848.5 cft 250.56297 CU.M
12mm thick cement plaster of mix: In Cement
7
Mortar 1:5 (1 cement : 5 fine sand)

PEB STRUTURE - UPTO 10' LEVEL 2 1 764 10 15280 sft 1421.04 SQ.M
COMPOUND WALL - 7' 2 1 594 7 8316 sft 773.388 SQ.M
23596 sft 2194.428 SQ.M

Steel work in tubular structure in built-up


sections, trusses and frame work including
cutting, hoisting, fixing in position upto a height
of 5m above plinth level, consisting of columns
8 trusses, roof and bottom purlins, base plate, 22KG / SQ.M 29495.136 KG 29.495136 MT
holding down bolts, wind ties bracing (if
required), bolts, nuts and washers for fastening
etc. complete with applying a priming coat of red
oxide zinc chromate primer
Providing corrugated G.I. sheet roofing
including vertical/ curved surfaces fixed with
galvanized iron, J or L hooks, bolts and nuts
8mm diameter with bitumen and G.I. limpet
washers or with G.I. limpet washers filled with
9
white lead including painting with primer and
paint on overlapping of sheets complete
excluding the cost of purlins rafters and trusses.
(Zinc coating not
less than 272 gms/sqm)

0.45 mm thick sheet with zinc coating


FOR ROOF 2 212 40 16960 sq.ft 1577.28 SQ.M
FOR SIDE 2 212 12 5088 sq.ft 473.184 SQ.M
FOR SIDE 2 68 12 1632 sq.ft 151.776 SQ.M
RIDGE 1 212 212 RFT 64.6176 RM
GUTTER 2 212

10 Painting-WHITE WASH
PEB STRUTURE - UPTO 10' LEVEL 2 1 764 10 15280 sq.ft 1421.04 SQ.M
COMPOUND WALL - 7' 2 1 594 10 11880 sq.ft 1104.84 SQ.M

11 EXAUST FAN 12 12 NOS


12 UPVC WINDOW 30 6 4 720 SQ.FT
13 ROLLING SHUTTER-(20'0"*15') 4 4 NOS
ABSTRACT ESTIMATE
SINO ITEM DESCRIPTION QTY UNIT RATE AMOUNT

Excavation for all types and sizes of


foundations, trenches and drains or for any other
purpose including disposal of excavated stuff
1 434.977437 CU.M ₹ 1.00 ₹ 434.98
upto 1.5 m lift and lead upto 50m (at least 5m
away from the excavated area), including
dressing and leveling of pits.

Providing and laying nominal mix cement


concrete with crushed stone aggregate using
2 concrete mixer in foundation, plinth and at
ground level excluding cost of form work.MIX-
1:3:6
207.900582 CU.M ₹ 1.00 ₹ 207.90

Providing and fixing formwork including


centering, shuttering, strutting, staging, propping
3
bracing etc. complete and including its removal
at all levels
872.898 SQ.M ₹ 1.00 ₹ 872.90
Providing and laying nominal mix reinforcement
cement concrete with crushed stone aggregate
4 using concrete mixer in all works upto plinth
level excluding cost of reinforcement and form
work.
m20- 1:1½:3 (1 cement : 1½ coarse sand : 3
167.371168 CU.M ₹ 1.00 ₹ 167.37
graded stone aggregate 20mm nominal size).

Providing and placing in position reinforcement


for R.C.C. work including straightening, cutting,
5
bending, binding etc. complete as per drawings
including cost of binding wire all complete:

thermo mechanically treated bars 14.7765625 MT ₹ 1.00 ₹ 14.78

Brick work -Cement Mortar 1:6 (1


6
cement : 6 coarse sand)
250.562975 CU.M ₹ 1.00 ₹ 250.56

12mm thick cement plaster of mix: In Cement


7
Mortar 1:5 (1 cement : 5 fine sand)
2194.428 SQ.M ₹ 1.00 ₹ 2,194.43
Steel work in tubular structure in built-up
sections, trusses and frame work including
cutting, hoisting, fixing in position upto a height
of 5m above plinth level, consisting of columns
8 trusses, roof and bottom purlins, base plate, 29.495136 MT ₹ 1.00 ₹ 29.50
holding down bolts, wind ties bracing (if
required), bolts, nuts and washers for fastening
etc. complete with applying a priming coat of
red oxide zinc chromate primer

Providing corrugated G.I. sheet roofing


including vertical/ curved surfaces fixed with
galvanized iron, J or L hooks, bolts and nuts
8mm diameter with bitumen and G.I. limpet
washers or with G.I. limpet washers filled with
9
white lead including painting with primer and
paint on overlapping of sheets complete
excluding the cost of purlins rafters and trusses.
(Zinc coating not
less than 272 gms/sqm)

0.45 mm thick sheet with zinc coating 2202.24 SQ.M ₹ 1.00 ₹ 2,202.24
RIDGE 64.6176 RM ₹ 1.00 ₹ 64.62

Painting new exterior surface (two or more


coats) with paint as per manufacturer's
10 specifications to give protective and decorative 2525.88 SQ.M ₹ 1.00 ₹ 2,525.88
finish including cleaning washing of surface etc.
complete with
11 EXAUST FAN 12 NOS ₹ 1.00 ₹ 12.00
12 UPVC WINDOW 720 SQ.FT ₹ 1.00 ₹ 720.00
13 ROLLING SHUTTER-(20'0"*15') 4 NOS ₹ 1.00 ₹ 4.00

ESTIMATED AMOUNT ₹ 9,701.15

MISELLENOUS

L.S FOR ELECTRICAL WORKS

L.S FOR PLUMBING


L.S FOR ELEVATED TANK AND BORE
L.S FOR SUMP AND SEPTIC
L.S FOR STEEL STRUCTURE PAINTING
L.S ALUMINIUM WORK FOR OFFICE

You might also like