PHLD 5 800 Manual
PHLD 5 800 Manual
Version:18.1
Thank you very much for choosing our products.
Please read this manual carefully before using this product, and please pay
attention to the following items:
1. Unpacking acceptance: If the product and accessories are found to be
inconsistent with the packing list when the product is unpacked, please contact us.
2. Installation and use: The installation, environment, operation, adjustment and
other matters should be clearly understood in advance in order to maximize the
working efficiency and service life of the balancing machine.
3. The power supply used in this machine is three-phase AC 380V, 50HZ. In
order to protect personal safety, the workshop protection grounding should be firmly
connected with the protective grounding of the machine.
4. During the installation and use, if there are any requirements, opinions and
suggestions for this balancing machine, please contact our consulting service
department, we will be happy to answer and solve the problems in your production
and use.
Attention:
(1) It is strictly prohibited to reprint part or all of the contents of this operating
manual.
(2) The contents of this operating manual are subject to change without notice.
Table of Contents
1.Warning.......................................................................................................................1
1.1 Firm Foundation.............................................................................................. 1
1.2 Be Careful of Electric Shock........................................................................... 1
1.3 Risk of Rotation............................................................................................... 2
2.Balancing Machine Working Conditions.................................................................... 2
3.Technical Parameters and Performance Characteristics............................................. 3
3.1 Technical Parameters....................................................................................... 3
3.2 Main Performance Indicators...........................................................................3
4. Machine Hoisting and Installation............................................................................. 4
4.1 Hoisting............................................................................................................4
4.2 Installation....................................................................................................... 4
5.Main Structure Overview............................................................................................6
5.1 Electronic Measuring Unit...............................................................................6
5.2 Safety Cover.................................................................................................... 6
5.3 Adapter.............................................................................................................6
5.4 Bed Base.......................................................................................................... 7
5.5 Power Switch................................................................................................... 7
6.Operating Steps...........................................................................................................8
6.1 Mount the Tooling Fixture............................................................................... 8
6.2 Mount the workpiece....................................................................................... 8
6.3 Input Rotor Parameters.................................................................................... 8
6.4 Put down the Safety Cover.............................................................................. 8
6.5 Power on & Measurement............................................................................... 8
6.6 Power off..........................................................................................................8
7.Maintenance................................................................................................................9
8.Common Faults & Handling.....................................................................................10
Appendix 1 Balance Glossary......................................................................................12
Appendix 2 Balance Precision Grade for Typical Rigid Rotor....................................14
Appendix 3 Balance Precision & Calculation............................................................. 16
I
1.Warning
c: The fluctuation of the power supply voltage should not exceed ± 10% of the
nominal value;
Specification Parameters
4.1 Hoisting
Use a crane for hoisting. Keep the steel wires away from the bearing pedestals
and roller frames. Put wood pieces or furry stuff between the machine and steel wires
to prevent scratching the surface paint during the hoisting.
4.2 Installation
The balancing machine has to be installed to the required foundation and work
Please check the machine levelness in both the vertical and horizontal directions
with a level gauge after the installation, generally it shall be within 0.2/1000. The
machine bed has to be in good contact with the foundation. There shouldn’t be gasket,
wood pieces or other staff in between. Fasten the machine with the foundation with
anchor bolts. Calibration is recommended after the installation if it is found low
accuracy.
Please reserve a certain space around the machine during the installation,
providing convenience for future hoisting or maintenance.
It requires an AC power supply of 380V 3 Phase 50Hz. Make sure the earth wire
is well grounded to the earth wire in the workshop before switching on the machine.
Please connect the power of measuring instrument, the sensors and the
photoelectric head to the socket accordingly and correctly.
Safety cover
Power switch
Control
Button
Bed base
Prevent debris from flying out and hurting people when the workpiece is
rotating.
5.3 Adapter
The machine base is made of cast iron, which is the basis for placing the
components of the balancing machine.
First, clean the mounting contact surface of the machine adapter and the tooling
fixture, install the fixture on the machine adapter, and adjust the concentricity so that
the axial runout is within 0.02mm.
Clean the fixture and the workpiece, mount the workpiece on the fixture, and
tighten the fastening screws.
According to the bearing mode of the rotor mounted on the balancing machine
and the actual dimensions of a, b, c, r1, r2, input the parameters sequentially into the
electronic measuring unit, and select add weight or remove weight. (For details,
please refer to Electronic Measuring System Instruction)
Put down the safety cover to ensure personal safety and prevent accidents.
If it is turned on for the first time, please jog first to check the speed and
direction (Face the balancer and see the rotational direction the workpiece, the
workpiece should be rotated counterclockwise).
7.1 The balancing machine must always be kept clean, and the surface of the
adapter should be frequently coated with oil to prevent rust.
7.2 The electronic measuring unit is a key component of the balancing machine.
It must be protected from vibration and moisture. It should be kept properly. After the
work is completed, the switch of the electric measuring box should be turned off.
7.3 If the electronic measuring unit is not used for a long period of time, it
should be powered on regularly for a few hours.
Precisi
Mm /
on Rotor Type
sec
Grade
Low-speed crankshafts used in boat diesels with odd-number
G4000 4000
cylinders and rigid installation.
G1600 1600 Crankshafts used in two-stroke large engines with rigid
installation.
Crankshafts used in four-stroke large engines with rigid
G630 630 installation.
Crankshafts used in boat diesels with rigid installation
High-speed crankshaft used in four-cylinder diesels with rigid
G250 250
installation.
High-speed Crankshafts used in four-cylinder or multi-cylinder
G100 100 diesels.
Engines of cars, trucks and locomotives.
Automobile wheels, wheel hubs, the entire wheel, drive shafts,.
G40 40 Four-cylinder or six-cylinder crankshafts used in four-stroke
high-speed engines with flexible installation.
The drive- parts with special requirement(propellers,
universal-joint drive shafts);
Dis-integrator parts, agricultural machinery parts, automobile
G16 16
engine parts.
Four-cylinder or six-cylinder crankshafts with special balance
requirements.
Calculation steps:
Fox example: There is a disc-shaped rotor. It comes with a Rpm of 2000r/min, weight
of 10kg and the rotor diameter of 300mm. It requires outer circle weight removal &
balancing with precision grade G6.3. So please calculate: To make the rotor
acceptable, what is the Permissible Residual Unbalance (eper)?