Work: Waterproofing Works For The Proposed 'Residential & Commercial Complex at Mohili, Sakinaka Mumbai 400 072' Contractor
Work: Waterproofing Works For The Proposed 'Residential & Commercial Complex at Mohili, Sakinaka Mumbai 400 072' Contractor
WO No
Work: Waterproofing Works For The Proposed 'Residential & Commercial Complex at Mohili, Sakinaka Mumbai 400 072'
Contractor:
6 Recovery of Mobilization Advance paid will be recovered from each R.A. bill at the rate of 12.5 % of gross invoice
Mobilization Advance value (including GST) so as to recover 100% of advance paid at the completion of 80% of Contract
Price.
7 38 Retention Money An amount of 7.5 % of gross invoice value (including taxes) of each Running Account Bill will be
deducted by the Owner towards Retention Money amounting to maximum 7.5% of the Contract Price.
50% of retention money will be released with final bill payment and the balance will be retained in the
form of retention bank guarantee in approved format to be released after the expiry of the Defects
Liability Period duly certified by Engineer-in-Charge.
8 31 Liquidated Damages for Time is the essence of Contract. In case of any delay in the completion of Works, for reasons
Delay attributable to the Contractor, beyond the Time for Completion, an amount equal to 1% of the
Contract Price for every week or part thereof delay, subject to maximum of 10% of Contract Price will
be recoverable from the Contractor as liquidated damages. The liquidated damages are recoverable
from the Contractor whether or not actual damage or loss is proved to have been caused thereby. The
liquidated damages recovered by the Owner from the Contractor are for the delay and not as penalty.
9 13 Performance Security Within fifteen (15) days of receipt of the Letter of Intent, the Contractor shall furnish Performance
Security in the form of an irrevocable bank guarantee from a nationalized bank or from a reputed
commercial bank acceptable to the Owner for an amount of five (5) percent of the Contract Price. The
approved format provided along with tender documents or any other form approved by the Owner
shall be used for the Bank Guarantee. The Bank Guarantee shall be valid up to 3 months beyond the
Completion Period.
10 34 Defect Liability Period 12 Months from the date of issue of virtual completion certificate or Two Monsoons , whichever is
later.
11 20.6 Recovery rate for excess Material consumed in excess of theoretical consumption shall be recovered at prevailing landed
consumption market price + 25 % towards processing charges.
(Applicable for Owner
supplied free issue
material)
12 42 Procurement of basic The process for reconciliation of the basic rates and actual rates, at which the basic rate materials are
rate material If procured by contractor, will be as agreed between owner and the contractor.
applicable Contractor shall forward quotes to owner before purchase of basic rate materials not less than
7 days of order placement. Owner's purchase team will review and approve the quote for
procurement. Additionally Owner may also enter into Long Term Contracts ( LTS) for basic rate
materials. The rates quoted by these LTS partners shall also be available to the contractor, who may
choose to buy from these partners or elsewhere. However, any price differential over the price quoted
by he LTS partners would have to explicitly justified by the contractor.
Payment/ Recovery of difference rate on basic rate material - Difference between actual
procurement rate approved by purchase and basic rate mentioned in BOQ + wastage factor (%)
specified in BOQ will be paid/ recovered.
Payment of wastage material beyond specified % mentioned BOQ - Contractor shall get
reconciliation statement approved by EIC/ Consultant/Architect. Approved procurement rate will be
paid for approved wastage quantity.
13 40 R A Bill frequency. 1) Contractor shall submit not more than one R.A. bill for every 30 days with all supporting documents
Adhoc / advance. such as joint measurement sheets, reconciliation statement etc, as required by the EIC.
period for certification 2) No adhoc / advance against R A bill will be paid.
& payment. 3) Payment of RA Bill shall be made within 21 days from the date of certificate & that of final Bill within
45 days from the date of certification. (No interest shall be paid on delayed payments).
4) Any quantity variation as well as extra item to be executed on site shall be informed to EIC in
advance and approval shall be obtained.
5) All joint measurement sheets duly signed by concerned EIC or Site Engineer shall submitted to the
billing department within seven days from the submission of R.A bill.
Annex A : SCC 1 of 11
Landcare Realty LLP
WO No
Work: Waterproofing Works For The Proposed 'Residential & Commercial Complex at Mohili, Sakinaka Mumbai 400 072'
Contractor:
15 Labour Cess In Contractor's scope if applicable & the same shall be shown separately in the summary.
16 42.1 Changes This is a firm rate contract, quantity may vary to any extent. No escalation in rates is applicable for
what so ever reasons during the completion period or authorised extention of time except for the
Basic Rate Materials under this contract if applicable.
17 19 Power and Water The Contractor shall be responsible, at his own cost, for the provision of power, water and other
services he may require. Owner may provide water and/or power (if available and to the extent
available at the discretion of the Owner) to use for the purpose of the Works at one point on
chargeable basis (at applicable charges). Contractor shall, at his own cost, shall provide necessary
arrangements for further distrubution and necessary water and power meters for measuring the
quantities consumed.
18 QRO items QRO items of BOQ are subject to re-negotiation by the Client prior to executing such items.
19 Scaffolding/Staging Rates are inclusive of scaffolding required to carry out the work. If scaffolding will be provided by
Client, charges will be debited to contractor.
20 Safety The contractor shall follow the applicable construction safety guidelines in Construction Safety Manual
while execution of the works as applicable.
21 Labour accomodation Contractor shall make his own arrangements for labour accommodation outside the Site premises.
23 Space for office / stores Only space for Contractor's office/ store shall be provided by the Owner free of cost. Barricading with
lockable arrangements shall be done by the contractor at his own cost.
24 Dewatering One time dewatering if required before handing over the Area to the Contractor will be in Owner's
scope
25 Inspection All stage wise inspection by EIC shall be carried out as per Approved Manufacturer's Methodology and
Checklists Enclosed.
26 Testing Contractor shall bear all the charges for laboratory testing of the material. List of test to be conducted
shall be submitted by contractor. Testing shall be done from the approved testing lab, when ever
required & as per instruction of engineer in charge/Owner's QA & QC team as per the QAP materials
(Annexure C) & applicable technical specifications.
27 Contractor's All Risk Contractor shall take his own 'Contractors All Risk Policy' including the third party liability.
Policy
28 The Contractor shall submit for Owner's approval project specific Work Methodology for key
activities, Quality Plan, Health Safety & Environment (HSE) Plan, Project Schedule, Logistics
Plan and such other documents as required with respect to "Work", in line with the Owner's
Technical Specification, Quality Assurance Plan, Construction Safety Manual & other
applicable professional standards & IS Codes etc
29 Waterproof Guarantee Contractor Shall furnish Guarantee for Waterproofing works for the entire structure including
Waterproofing works done by earlier agency for a period of Ten years from the date of Completion on
Rs 100/- Stamp paper in format approved by Owner.
Annex A : SCC 2 of 11
Landcare Realty LLP
WO No
Work: Waterproofing Works For The Proposed 'Residential & Commercial Complex at Mohili, Sakinaka Mum
Contractor:
#NAME?
GST 18% extra as applicable
6 The rate shall include installation for water line for curing with pumping arrangement as well as lighting arrangement on each floor and after completion of work contractor
shall hand over the entire system to the company in working condition.
7 GI/PVC Spout at require location with required slope & protection.
8 Curing for 10 days or as per manufacturers requirement.
9 Only plan area will be measured and paid. No extra will be paid for forming Wattas (gola) at the junction of slab and wall/parapet/column if not specified in the individual BOQ
items.
10 All works to be as per MOEF guideline/Norms.
11 The rates shall be considered inclusive of coordination with other specialised agency, loading, unloading, transport, madadi, insurances, PF,ESIC, MLWF or other Labour
Compliances, local issues, debris disposal, scaffolding etc in relation to the works.
12 All Slab, sunks, other - Cleaning the surface to our requirements, ponding the slab with water for 48 hours to identify the existing leaking spots, marking the same and
grouting all leaking spots, construction joints, honeycomb locations, cracks etc., with non shrink cementitious grout to full saturation, making small fillets (wattas) around the
periphery junctions etc. complete.
13 Ultratech , ACC (43 Grade) or any other brand of Cement approved by the Owner shall be used for all activities
14 Machine Grade Crushed sand shall be used for Filling and Zone -2 River sand (coarse sand) shall be used for top finishing works
15 The Density of Broken Light weight blocks to be used for filling shall not exceed 650 Kg/Cum
1 Water Tank
1.1 Water Tank (Horizontal Surface)
1.1.1 Surface preparation SQM 494.00 50 24,700
All surface area should cleaned up to visible of hair cracks / aggregate texture. Cleaning of RCC member
should be done by hacking tool, wire brush, wire grinder & air blower etc. Open cracks & construction Aquabond CR-
joints should be sealed with cement mortar with additive AquaBond CR-2000 . All clean & treated area 2000/ Conplast
should tested for water tighness by flooding water. All wet spots & water leakage area should mark for WL / Cebex 100
treatment.
Providing and applying Vandex BB 75 or approved equivalent waterproofing system of M/s. A A Nayak
Constructions Pvt Ltd in two coats by trowelling @ 3kgs/sqm. The 1st coat of Vandex BB 75 shall be
applied to the prepared surface. Whilst the 1st coat is still “green” a second coat comprising of Vandex
BB 75 or approved equivalent. The slurry coatings shall be applied with a stiff masonary brush or stiff Vandex BB 75 of
broom and worked into every irregularity on the surface shall be done by means of trowelling or by spray Vandex/
only. Treatment to floor slabs shall be carried out by trowel application using a steel trowel into Blue Dex of BLU.
hardenced concrete slab surface including curing, cleaning etc complete. Actual treatment area shall be
considered for measurement.
1.1.3 Protection layer/ Screed ― Not required for this waterproof treatment
All surface area should cleaned up to visible of hair cracks / aggregate texture. Cleaning of RCC member
should be done by hacking tool, wire brush, wire grinder & air blower etc. Open cracks & construction Aquabond CR-
joints should be sealed with cement mortar with additive AquaBond CR-2000 . All clean & treated area 2000/ Conplast
should tested for water tighness by flooding water. All wet spots & water leakage area should mark for WL / Cebex 100
treatment.
Providing and applying Vandex BB 75 or approved equivalent waterproofing system of M/s. A A Nayak
Constructions Pvt Ltd in two coats by trowelling @ 3kgs/sqm. The 1st coat of Vandex BB 75 / Blue Dex
shall be applied to the prepared surface. Whilst the 1st coat is still “green” a second coat comprising of
Vandex BB 75 of
Vandex BB 75 / Blue Dex. The slurry coatings shall be applied with a stiff masonary brush or stiff broom Vandex/
and worked into every irregularity on the surface shall be done by means of trowelling or by spray only.
Blue Dex of BLU.
Treatment to floor slabs shall be carried out by trowel application using a steel trowel into hardenced
concrete slab surface including curing, cleaning etc complete. Actual treatment area shall be considered
for measurement.
1.1.3 Protection layer/ Plaster ― Not required for this waterproof treatment
Annex B : BOQ 4 of 11
Landcare Realty LLP
WO No
Work: Waterproofing Works For The Proposed 'Residential & Commercial Complex at Mohili, Sakinaka Mumbai 400 072'
Contractor:
All surface area should cleaned up to visible of hair cracks / aggregate texture. Cleaning of RCC member
should be done by hacking tool, wire brush, wire grinder & air blower etc. Open cracks & construction Aquabond CR-
joints should be sealed with cement mortar with additive AquaBond CR-2000 . All clean & treated area 2000/ Conplast
should tested for water tighness by flooding water. All wet spots & water leakage area should mark for WL / Cebex 100
treatment.
Providing and applying Vandex BB 75 or approved equivalent waterproofing system of M/s. A A Nayak
Constructions Pvt Ltd in two coats by trowelling @ 3kgs/sqm. The 1st coat of Vandex BB 75 / Blue Dex
shall be applied to the prepared surface. Whilst the 1st coat is still “green” a second coat comprising of Vandex BB 75 of
Vandex BB 75 / Blue Dex. The slurry coatings shall be applied with a stiff masonary brush or stiff broom
Vandex/Blue SQM 1,460.00 650 949,000
and worked into every irregularity on the surface shall be done by means of trowelling or by spray only. Dex of BLU
Treatment to floor slabs shall be carried out by trowel application using a steel trowel into hardenced
concrete slab surface including curing, cleaning etc complete. Actual treatment area shall be considered
for measurement.
Providing and applying Coal Tax Epoxy R 816 CE or approved equivalent, Solvent based Epoxy Coal tar
Coating in 2 or 3 coats used to protect Concrete Structures in corrosive environment having excellent
Chemical resistance with the approximate coverage is 5 sq.mtr/litre/coat @ 150 microns. Practical R 816 CE of
coverage depends on the site conditions including all tools and tackles, lead and lift, labour etc complete. Ardex
Actual treatment area shall be considered for measurement. Endura/Shalikot SQM 1,460.00 300 438,000
e CT of STP Ltd.
2.1.3 Protection layer/ Screed ― Not required for this waterproof treatment 59
All surface area should cleaned up to visible of hair cracks / aggregate texture. Cleaning of RCC member
should be done by hacking tool, wire brush, wire grinder & air blower etc. Open cracks & construction Aquabond CR-
joints should be sealed with cement mortar with additive AquaBond CR-2000 . All clean & treated area 2000/ Conplast
should tested for water tighness by flooding water. All wet spots & water leakage area should mark for WL / Cebex 100
treatment.
Providing and applying Coal Tax Epoxy R 816 CE or equivalent, Solvent based Epoxy Coal tar Coating in 2
or 3 coats used to protect Concrete Structures in corrosive environment having excellent Chemical
resistance with the approximate coverage is 5 sq.mtr/litre/coat @ 150 microns. Practical coverage R 816 CE of
depends on the site conditions including all tools and tackles, lead and lift, labour etc complete. Ardex
SQM 974.00 300 292,200
(Measurement of actual treatment area to be considered for payment) Endura/Shalikot
e CT of STP Ltd.
2.2.3 Protection layer/ Screed ― Not required for this waterproof treatment
3 Toilets
3.1 Toilets (Horizontal Surface)
3.1.1 Surface preparation SQM 1,650.00 45 74,250
All surface area should cleaned up to visible of hair cracks / aggregate texture. Cleaning of RCC member
should be done by hacking tool, wire brush, wire grinder & air blower etc. Open cracks & construction Aquabond CR-
joints should be sealed with cement mortar with additive AquaBond CR-2000 . All clean & treated area 2000/ Conplast
should tested for water tighness by flooding water. All wet spots & water leakage area should mark for WL / Cebex 100
treatment.
Providing and applying GS Flexi 201 or equivalent Brush applied Cementitious elastomeric acrylic water
proof coating of M/s. A A Nayak Const. Pvt Ltd, in 2 coats. The Waterproofing System is capable of
forming a waterproof barrier around or inside the concrete, complete. Membrane should have following
minimum properties: GS Flexi 201 of
Greenseal/Blue
i) Adhesive strength 0.6N/mm2 HY Seal of
ii) Pot Life - 60 Minutes
BLU/WPM 004
iii) Tensile bond Strength - > 1 N/mm² of Ardex Endura.
iv) Mixed Material Density - 1.65-1.75 g/cc
v) Toxicity - Non toxic
Actual treatment area shall be considered for measurement.
Annex B : BOQ 5 of 11
Landcare Realty LLP
WO No
Work: Waterproofing Works For The Proposed 'Residential & Commercial Complex at Mohili, Sakinaka Mumbai 400 072'
Contractor:
All surface area should cleaned up to visible of hair cracks / aggregate texture. Cleaning of RCC member
should be done by hacking tool, wire brush, wire grinder & air blower etc. Open cracks & construction Aquabond CR-
joints should be sealed with cement mortar with additive AquaBond CR-2000 . All clean & treated area 2000/ Conplast
should tested for water tighness by flooding water. All wet spots & water leakage area should mark for WL / Cebex 100
treatment.
4 Terrace
4.1 Terrace Area Waterproofing: BRICKBAT/BLOCKBAT WP
4.1.1 Surface preparation SQM 33,891.00 45 1,525,095
All surface area should cleaned up to visible of hair cracks / aggregate texture. Cleaning of RCC member
should be done by hacking tool, wire brush, wire grinder & air blower etc. Open cracks & construction Aquabond CR-
joints should be sealed with cement mortar with additive AquaBond CR-2000 . All clean & treated area 2000/ Conplast
should tested for water tighness by flooding water. All wet spots & water leakage area should mark for WL / Cebex 100
treatment.
5 Landscape
5.1 Landscape Area Waterproofing
5.1.1. Surface preparation SQM 12,428.00 45 559,260
Annex B : BOQ 6 of 11
Landcare Realty LLP
WO No
Work: Waterproofing Works For The Proposed 'Residential & Commercial Complex at Mohili, Sakinaka Mumbai 400 072'
Contractor:
All surface area should cleaned up to visible of hair cracks / aggregate texture. Cleaning of RCC member
should be done by hacking tool, wire brush, wire grinder & air blower etc. Open cracks & construction Aquabond CR-
joints should be sealed with cement mortar with additive AquaBond CR-2000 . All clean & treated area 2000/ Conplast
should tested for water tighness by flooding water. All wet spots & water leakage area should mark for WL / Cebex 100
treatment.
6 Modifoam Filling
Providing and filling in position modifoam of density 20Kg/ Cum with welded mesh (GI 2"x2" 180 GSM)
and all accessories with contractors materials, tools, tackels, equipments, consumables with all lead, lifts CUM QRO 8,000
etc. complete to the satifaction of EIC. Gaps to be filled with Cement and crush sand mortor (1:4)
6.1
Subtotal (Item No. 6)
#NAME?
GST 18% extra as applicable
Annex B : BOQ 7 of 11
Landcare Realty LLP
WO No
Work: Waterproofing Works For The Proposed 'Residential & Commercial Complex at Mohili, Sakinaka Mumbai 400 072'
Contractor:
4 P.P.C. Chemical test & physical test Every new brand of cement & IS 1489-1991/ IS 4032-1985
every six-month compulsory
& M.T.C is must
6 WATER chemical test • To be tested on every change IS 456 [latest revision] External LAB
of source & monthly in monsoon Clause 5.4
8 AAC BLOCKS 1] Dimensions M.T.C is must / new brand all IS 2185 [part-3]-1984 & NFP Initially from external
2] Water thru capillary rise parameters initially ; thereafter 14306 lab
3] compressive strength for 1 & 3 every truck load External lab/
4] density there after internal lab
for 1 & 3
9 READY MIX MORTAR] 1] Compressive strength Every new brand/MTC is must Initially from external
lab there after
internal lab
10 Waterproofing 1. Crack Bridging Test. Initially once from external lab IS:15489 External Lab
2. Tensile bond strength by supplier and MTC for every lot ASTM D 2370,
3. Elongation ASTM 5329
4. Puncture resistance, All tests a
5. UV Resistance. For all types of membrane ASTM D
6.Penetration test 4833
7. Water Permeability Rate Test no-5 for UV Coating
8. Water absorption.
11 External & Internal Paints MTC for batch/lot Sample at site for brand Source/ brand
approval/Coverage/ approval must
Appearance & MTC must for
every lot/batch & if required
external test
Approved by
Landcare Realty LLP
WO No
Work: Waterproofing Works For The Proposed 'Residential & Commercial Complex at Mohili, Sakinaka Mumbai 400 072'
Contractor:
2 Sewage Treatment Tank Trowel Applied Efflorescence Free Cementitious Vandex BB 75 of Vandex/Blue Dex of BLU
Coating
Epoxy Coal Tar Coating as protective layer R 816 CE of Ardex Endura/Shalikote CT of STP