1.simulation Model To Reduce Tech & Non Tech Loss
1.simulation Model To Reduce Tech & Non Tech Loss
Keywords: electrical energy, simulation, system dynamics, meter reading and illegal usage. Thus, this research will
scenario model. develop a simulation model for to reduce the technical and
non-technical losses.
Abstract Electrical losses are mainly caused by technical and non-
technical factor. One of the possibilities that cause
The reliability of electricity distribution systems plays an distribution losses is network configuration, for instance,
important role to guarantee the sustainability of electrical when its length tends to keep increasing, or when the
power supply to consumer. The main reason why we should configuration is overload [3]. Electricity distribution flow can
sustain the electrical power supply is to reduce “blackout”. be seen in Figure 1. From this image, we can see that
Based on the above problems, a comprehensive study is technical losses are incurred in MVN, LVN, TRF, and in
required to help the electricity company to reach HHC. The technical losses are caused by error in meter
interoperability of their electricity distribution system. The reading and illegal usage.
method used in this research is System Dynamics Simulation,
based on consideration that this framework enables us to MVN Losses
inspection and Automatic Meter Reading (AMR) usage. Figure 1. Electricity distribution flow
people to use other source of energy [6]. Distribution losses total trafo 50
power trafo 50
correction factor
can be reduced by choosing the right transformer and feeder, power trafo 100
MVN
resistance loss factor
total trafo 100 total
distribution network reconfiguration, and placing shunt feeder
power
capacitor in the right [7]. Each network service unit need to total trafo 160 power trafo 160
power trafo 630
be improved either internal or external. Several factors can power trafo 200
affect the performance of electricity distribution system such total trafo 200 power trafo 250
power trafo 315
total trafo 630
as providing knowledge about the electricity distribution and total trafo 250
total trafo 315
socializing company’s program about energy saving to the
local community periodically to reduce operational cost and
Figure 2. MVN sub model flow diagram
increase company income [8].
In this research, we utilized system dynamics as a method for
the model development. The development of System 3.2 Low Voltage Network (LVN) and Household
Dynamics model, there are several steps needs to be done [9]: Connection (HHC) Sub model
1. Problem articulation: in this phase, modeller has to find the The nodes in LVN are the poles where household connections
problem and determine the significant variables to give are connected. Modeling LVN is similar to MVN, only with
understanding in designing policy to cope with the problem. different level of voltage. The LVN and HHC flow diagram
2. Dynamics hypothesis: in this phase, modeller needs to can be seen in Figure 3. HHC losses are calculated the same
develop a theory of how the problem arises. Modeller also way, assuming that consumers load current is on each of the
needs to build a causal diagram explaining causal household connection’s end. Simulation result shows that
relationships among variables, and convert them into level LVN losses in Pamekasan are ranging between 400.000-
and rate (stock and flow) diagram. 480.000 kWH, while the HHC losses are ranging between
3. Formulation: in this phase, modeller has to define equation 310.000 – 375.000 kWH.
describing relationships among system variables, estimates length of LVN <l equivalent>
parameter, and determine initial condition.
4. Testing: this phase is a testing process for the model, <feeder current> losses
<correction factor>
system. <total
LVN
resistance <loss factor>
5. Policy formulation and evaluation: this phase is a suggested feeder
power>
length of HHC
policy formulation and evaluation process. If the structure and correction factor
behaviour of the model represents the actual system, it can be length of HHC
<feeder current>
used to design and evaluate policy by altering the parameter <output voltage>
power>
<correction factor>
When the significant variables of electricity distribution
system are obtained, the causal loop diagram can be
developed by using those variables. The system dynamics Figure 3. LVN and HHC Sub Model
model is developed with 24 month of timeframe. The sub
models developed in this research are: 3.3 Transformer Sub model
Transformer losses are classified into Ferro (Fe) and cuprum
3.1 Medium Voltage Network (MVN) Sub model (Cu) losses. Ferro losses are determined by voltage and have
The MVN is modelled to a main feeder, which the nodes are a constant value. Cuprum losses are equal to squared loading
distribution transformator placed in that main feeder, level. Transformer losses are caused by Fe losses, Cu losses,
utility factor, correction factor, and loss factor. Utility factor
is the ratio between the electricity power generated and feeder non-technical losses are between 870.723 kWH – 1.849.640
production capacity within the operation hour of generator. kWH as seen in Figure 6.
There are about 471 transformers in Pamekasan. Simulation <susut JTM>
<Time>
result shows that transformer losses obtained in this model is <susut SR>
This sub model is developed to analyze electricity distribution <susut Trafo 50> total <susut Trafo 630>
susut susut pemakaian
losses viewed from electricity supply from PLN and Trafo ilegal
<susut Trafo 100>
electricity consumption (demand). The losses can be <susut Trafo 315>
determined by looking at the difference between electricity <susut Trafo 160> <susut Trafo 250>
supply and its consumption. This sub model can also <susut Trafo 200>
determine the Pamekasan Utility. Figure 5. Technical, non-technical losses, and total losses
Flow diagram of supply and demand sub model can be seen submodel
in Figure 4. Simulation result shows that electricity losses
viewed from supply and demand side is ranging between 2,5
– 3,8 million kWH.
initial supply initial demand
<Time>
supply
produced Demand
rate of supply kwh kwh309
rate of demand
Pamekasan
seasonal effect Utilization
electricity
supply losses
total based on
expense supply <Pamekasan Design
and Capacity>
demand
electricity price per kwh
percentage
of losses
expense
Figure 6. Total losses, technical losses, and non-technical
losses
expense losses
Figure 4. Supply and Demand sub model
4 Model Validation
3.5 Design Capacity Submodel Model validation is a testing process whether the developed
model represents the actual system. There are two ways of
This submodel is developed to determine the maximum
testing [11]: Means Comparison, stated by E1 as equation (1),
production capacity in Pamekasan. Based on the data from
and Variance Error, stated by E2 as equation (2). It stated that
Pamekasan PLN, the feeders in Pamekasan are: APG, ARL,
a model is validated if E1 ≤ 5% and E2 ≤ 30%.
BYA, CBR, GZL, PGT, PLG, PRP, and SMD. These entire
feeders are contributing to total installed capacity (Pamekasan
E1
S A (1)
Design Capacity).
A
Design capacity value is calculated from feeder power, days
in a month, power factor, and conversion factor from KVA to Ss Sa
E 2 (2)
kWH. Simulation result shows that capacity in Pamekasan is
Sa
about 30 million kWH.
Whereas:
3.6 Total Losses Submodel S = average value of simulation
A = average data
Total technical losses submodel is the total of MVN, LVN,
and HHC losses as seen in Figure 5. Non-technical losses can Ss = standard deviation of simulation
be calculated by subtracting total losses from the measuring Sa = standard deviation of data
result with the technical losses obtained from the simulation.
Non-technical losses are mainly caused by error in 4.1 Total Technical Losses
administration, and illegal usage. The simulation result
Comparison between data and simulation result of total
shows that the technical losses can be reduced by increasing
technical losses can be seen in Figure 7.
power factor (Cos ) and cross sectional is addition.
The total losses value obtained from simulation results are E1 = |1.433.159,239 – 1.502.278,641| /1.433.159,239 = 0,04
ranging between 2.271.210 kWH – 3.832.100 kWH, technical E2 = |185.553,085 – 157.209,02| / 185.553,085 = 0,15
losses are between 1.361.640.5kWH – 1.982.460 kWH, while
sectional area. In this scenario, the proposed cross sectional
From the E1 and E2 calculation we can see that E1 ≤ 5% and area is 150 mm2 PVC insulated copper cable.
E2 ≤ 30%, which means the model is valid.
5.2 Effect of MVN Cross Sectional Addition to LVN
and HHC
The cross sectional addition in MVN will eventually bring
effect to low voltage network (LVN) and household
connection (HHC). As a result of the cross sectional addition
in MVN, the resistance in LVN and HHC is decreased, which
means the losses will also be decreased. The simulation result
shows that the technical losses in LVN are decreased to
300,000 kWH per month, and technical losses in HHC are
decreased to 200,000 kWH.
From the E1 and E2 calculation we can see that E1 ≤ 5% kVar capasitor = (3)
and E2 ≤ 30%, which means the developed model is (existing power pp*(TAN (ARCCOS(existing cos ))-TAN(ARCCOS(proposed cos ))))
validated. 1000
References
[1] A. Saepudin. “Strategic steps to overcome energy crisis”,
Jakarta, 2012.
[2] Sohn Associates Limited, “Electricity distribution
system losses”, London, 2009.
[3] A. Handoyo, “Analysis techniques to determine
electricity distribution losses on PLN Company,
Semarang District,” 2006.
[4] Y. Al-Mahroqi, I. Metwally, A. Al-Hinai and A. Al-
Badi, ”Reduction of Power Losses in Distribution
Systems”, World Academy of Science, Engineering and
Technology, 6, pp. 498-505, 2012.
[5] J. Navani, N. Sharma and S. Sapra, “Technical and non-
technical losses in power system and its economic
consequence in Indian economy”, International Journal
of Electronics and Computer Science Engineering, 1,
(2), pp. 757-761, 2012.
[6] N. Onat, “Transmission and distribution losses of
Turkey's power system”, Advances in Energy Planning,
Environmental Education and Renewable Energy
Sources, pp. 170-175, (2010).
[7] K. Murthy and M. Raju, “Electrical energy loss in rural
distribution feeders-A case study”, Journal of
Engineering and Applied Sciences, Vol. 4 No. 2, pp. 33-
37, 2009.
[8] M. Singgih and E. Anggraini, “Analysis of electricity
distribution efficiency by considering the operational
risk”, 2008.
[9] J. D. Sterman, “Business Dynamics: Systems Thinking
and Modeling for a Complex World”, New York: Irwin
McGraw-Hill, 2000.
[10] R. Mulyadi, “Tips to decrease electricity distribution
losses in PT PLN-Jakarta Raya and Tangerang”, 2011.
[11] Y. Barlas, “Formal aspects of model validity and
validation in system dynamics”, System Dynamics
Review, Vol. 12, No. 3, pp. 186-210, 1996.