Design of Main Bridge of Chaotianmen Yangtze River Bridge: 2nd Design Department, BRDI, Wuhan, China
Design of Main Bridge of Chaotianmen Yangtze River Bridge: 2nd Design Department, BRDI, Wuhan, China
Key words: Half-through steel tied truss arch, design, analysis, anti-corrosion coating
system, steel truss installation
- 409 -
Duan: DESIGN OF MAIN BRIDGE OF CHAOTIANMEN YANGTZE RIVER BRIDGE
1. GENERAL INTRODUCTION
The Chongqing Chaotianmen Yangtze River Bridge is located 1.2 km downstream
Chaotianmen in Chongqing, China. This bridge is an important passage connecting the
central urban business regions on both banks of the Yangtze River. Total length of the
bridge is 1741m, of which the 932m main bridge is a (190+552+190) m half-through steel
tied arch truss structure; the 314m northern approach bridge and 495m southern approach
are all prestressed concrete continuous girders.
The bridge has double decks, of which the 36.5m upper deck has dual three-lane and
sidewalks on both side, and the lower carries two lines municipal light railways and two
lanes to either side (Figure 1).
3. STRUCTURAL DESIGN
3.1 General layout and main structural characteristics
The main bridge is a three span continuous steel tied arch truss structure with a span length
of 190+552+190m and a width of 36.5m. The main truss with two pieces of truss is 29m
- 410 -
Duan: DESIGN OF MAIN BRIDGE OF CHAOTIANMEN YANGTZE RIVER BRIDGE
wide. The end span is a steel truss of variable height, and the middle span is a tied steel arch
truss. The height between the arch top and the middle support is 142m, the outline of the
lower arch chord is a quadratic parabola with 128m arch rise, and the rise-span ratio is
1/4.3125. The upper chord of arch is also a quadratic parabola transiting to the circle curve
of 700m radius on upper chord of end truss span. The main truss adopts “N” shaped truss of
variable height, the arch truss height is 14m at mid-span, 73.13m at middle pier(stiffened
chord of arch rib is 40.65m), and11.83m at end pier. Due to the big difference of arch truss
height, considering general arrangement and the aesthetic factor, the truss panels have three
lengths: 12m, 14m, and 16m.
Two levels of ties are set in the middle span, at 11.83m spacing. The upper tie is not
through the whole main truss and only connected to the lower arch chord; while the lower
tie goes through the whole truss including the middle chord at the stiffened leg and the
lower chord in the end span. The upper tie is “H” sectioned; and the lower tie has “王”
shape section assisted with cables. The steel tie end is connected to the lower chord panel
joints of arch rib, assistant cables to be anchored at end node of the tie. The function of
assistant cables is to reduce the forces of lower steel tie, so as to optimize the dimensions of
steel components.
The support system of main bridge adopts hinged bearing system. In longitudinal direction,
hinged fixed bearings are arranged at middle pier on north side, and movables on the rest
piers. In transversal section, fixed bearings are arranged on the middle support, and
movables on side supports, two transversal restrictions bearings are designed at the middle
of the lower crossbeam of side supports. The central transversal restrictions can make the
transversal displacement induced by thermal forces of main truss to both sides
well-proportioned, so as to avoid the rail deformation. The main bridge has spherical cast
steel hinged bearing system with huge capacity; the maximum bearing force for middle
support is 145000KN, which has the largest bearing capacity in China.
- 411 -
Duan: DESIGN OF MAIN BRIDGE OF CHAOTIANMEN YANGTZE RIVER BRIDGE
adjacent members have large dimension and thickness, so monolithic panel joints are
adopted here; splicing panel joints are adopted on the rest parts of main truss.
- 412 -
Duan: DESIGN OF MAIN BRIDGE OF CHAOTIANMEN YANGTZE RIVER BRIDGE
3.6 Pre-camber
The pre-camber of the main truss camber is set and adjusted in accordance with the reverse
deflection curve value due to dead load plus static live load. From the analysis result,
pre-camber is not necessary for the end span, the pre-camber for middle span to be set as
following: at the panel joints of stiffened legs, the transversal truss top should be
heightened; at the tie zone, transversal truss to be heightened, or suspension rod to be
shortened, or adjust centerline of steel members.
- 413 -
Duan: DESIGN OF MAIN BRIDGE OF CHAOTIANMEN YANGTZE RIVER BRIDGE
support system after bridge completion. The structural static stability analysis results show
that the stability safe coefficient is 6.8 in bridge completion phase, meeting the
requirements in standards.
4.3 Dynamic Analysis
The structural dynamic analysis adopts the same model as static stability analysis; see Table
2 for main analysis results of the completed bridge.
Self-vibration
Self-vibration
NO circle
Vibration mode frequency
. frequency
(HZ)
(rad/s)
Transversal bending
1
of truss, arch 0.1978 1.2428
Longitudinal vibration
2
+ arch vertical bending 0.2756 1.7316
5. ANTI-CORROSION COATING
The anti-corrosion coating for steel truss conforms to the coating system in Code The
Protection coating for steel railway bridge (TB/T 1527-2004). And the paint class, painting
layer, and dry film thickness in the coating system has been adjusted. See Table 3 for
coating system of the steel truss.
Coating Min. thickness
Coating item
No. for total dry film
1 Zinc Rich Epoxy 2×40μm
2 Epoxy MIO 2×40μm
Polysiloxane (for chord, tie)
3 2×35μm
Acrylic Aliphatic Polyurethane
6. TRUSS INSTALLATION
The end span should be installed by cantilever method, on trestles and temporary piers.
First, two panels of steel truss to be installed on the trestles by means of tower crane beside
end pier; next, the erection gantry to be assembled on the upper chord of steel truss; then
the erection gantry install the steel trusses in sequence with assistance of temporary piers
from end pier to mid pier, by cantilever method. While installing steel truss, some balanced
- 414 -
Duan: DESIGN OF MAIN BRIDGE OF CHAOTIANMEN YANGTZE RIVER BRIDGE
weight should be used on the end span to make sure that the stability coefficient is larger
than 1.3.
The steel truss of mid span will be installed by symmetric full cantilever method with the
assistance of sling pylon, and closed at mid-span. The steel truss will be installed first, and
then the arch rib truss and suspension robs installed step by step until the mid-span is
closed. The sling pylon is 100m high, having two levels of cable; the anchor points of
former cable are at 144m and 216m from the pier, back cable anchored at 166m and 178m,
the spacing between anchor points on the pylon is 2m. While installing middle span, weight
should be forced on the 48m region of end span to make the safe coefficient larger than 1.3.
The lower chord of arch rib truss should be closed prior to the upper chord.
After arch truss closed, the temporary tie should be installed and stressed, and then the sling
cables and sling pylon should be removed; erection gantry goes backward, the deck crane
walks on the upper deck to install ties and upper crossbeams in sequence until mid span is
closed. The upper tie should be closed prior to the lower tie; the provisional ties should be
removed after while. Then the deck crane goes backward from mid-span to install
crossbeam, plane bracing, and longitudinal girder of lower deck, and install upper and
lower steel bridge deck. To eliminate the effect of common-action of orthotropic steel plate
and main truss, some temporary connection between steel plate and crossbeam will be
made; the permanent connection should not be done until all members are installed
completely. The assistant cables are installed and stressed after all bridge members
completed. After bridge finishing, auxiliary facilities and pavement completed, the assistant
cables and suspension rob force will be adjusted to meet design requirements.
7. CONCLUSION
The steel girder of Chaotianmen Yangtze River Bridge was begun to install in Augest,
2006, the main arch was closed on January 18th, 2008, and the tie-bar was closed on May
18th, 2008. Now, this bridge project has entered the after-installation stage, and the whole
bridge will be completed by the end of 2008. Chaotianmen Yangtze River Bridge will be
the longest arch bridge in the world. Nowadays, there are more and more application of
steel tied arch truss bridges in China; the design and construction of Chaotianmen Yangtze
River Bridge can give valuable experience for bridges of the same type.
- 415 -
- 416 -