0% found this document useful (0 votes)
233 views2 pages

SPEC. FOR BLACK START PHILOSOPHY rg6s911381004 - 001

This document provides the black start philosophy for Trains 6 and 7 of the RasGas Onshore Expansion Project Phase 2. It states that black start power for starting the gas turbines in Trains 6 and 7 will be supplied from the RasGas grid using connections to the main substations. Once started, the gas turbines will synchronize to the grid and operate in a power sharing mode. It also describes backup emergency power connections that will supply up to 3 MW each to Trains 6 and 7 from the Train 5 main substation to allow for a safe shutdown if the main substation power is unavailable.

Uploaded by

Muthiah Murugan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
233 views2 pages

SPEC. FOR BLACK START PHILOSOPHY rg6s911381004 - 001

This document provides the black start philosophy for Trains 6 and 7 of the RasGas Onshore Expansion Project Phase 2. It states that black start power for starting the gas turbines in Trains 6 and 7 will be supplied from the RasGas grid using connections to the main substations. Once started, the gas turbines will synchronize to the grid and operate in a power sharing mode. It also describes backup emergency power connections that will supply up to 3 MW each to Trains 6 and 7 from the Train 5 main substation to allow for a safe shutdown if the main substation power is unavailable.

Uploaded by

Muthiah Murugan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

Job No. Doc. No. Rev.

Project Specification RG6-S-91-1381-004 1


Date : Sep. 02, 2005 Sheet 1 of 2

RasGas Onshore Expansion Project Phase 2 Prp'd : T. Konda


(Train 6&7 EPC) Chk'd : R. Kaida / S. Onodera
Black Start Philosophy App'd : Y. Okazaki

CONTENTS

Page

1. SCOPE............................................................................................................................................... 2

2. TRAIN 6 AND 7 BLACK START OPERATION.................................................................................. 2

3. OTHER EMERGENCY POWER CONNECTIONS............................................................................. 2

FOR AS BUILT

For Information For Review For Approval For Construction X For As Built

Rev Date Page Description Prpd Chkd Appd


E Sep. 02. ‘05 All Issued for Approval T.K R.K / S.O Y.O
0 Dec. 15. ‘05 All Issued for Construction T. Konda R. Kaide / S. Onodera Y. Okazaki
1 Feb. 25. ‘08 All AS BUILT for Train-6 K. Iwasa H. Yatabe S. Onodera
RasGas Onshore Expansion Project Phase 2 (Train 6&7 EPC) RG6-S-91-1381-004 Rev. 1
Black Start Philosophy Sheet 2 of
2
1. SCOPE

This specification describes Black Start Philosophy for Trains 6 and 7 for the RASGAS ONSHORE
EXPANSION PROJECT PHASE 2 (TRAIN 6&7 EPC).

2. Train 6 and 7 Black Start Operation

No “black start” power generation or new emergency power generation system will be provided for
RasGas Train-6 & 7.

“Black Start” power required for starting the GTG’s in Train 6 and 7 will be supplied from the
RasGas grid utilizing the 132/34.5 kV step down transformer connection to the 33 kV buss in the
respective Main Substations (SS-04 or SS-05).
The connection between the RasGas grid and Substations SS-04 and SS-05 is always monitored
and controlled by the RasGas ELICS Power Management system.

Once Trains 6 and 7 GTG’s are started, they will be synchronized to the RasGas grid and begin
operation in a power sharing mode with the RasGas grid, monitoring and control is from the
RasGas ELICS.

3. OTHER EMERGENCY POWER CONNECTIONS

Emergency power demands within Trains 6 and 7 have not been detailed to date, however it is
anticipated that these demands will not exceed 3 MW per Train.

This demand will be met by the installation of two 6.6 kV feeders (one for each Train) from
RasGas Train 5 Main Substation SS-03 to Trains 6 and 7, Main Substations SS-04 and SS-05.

The intended purpose of these two circuits are to supply emergency power for a safe and orderly
shutdown of the Frame 9 Turbines (for N2, C3 and MR Compressors), should the 33 kV
Switchboard in SS-04 and SS-05 not be available.

For the purpose of the RasGas Power Management System these circuit will not be considered as
supplying “normal Operating Power” to Trains 6 and 7.
Loading on these circuits will be accounted for in Substation SS-03, RasGas Train 5.

You might also like