The document is an estimation of costs for a construction project to build a single storey residential building. It includes detailed computations and pricing for structural concrete work, masonry works, formworks and falseworks, scaffolding, beams, roofing works, doors and windows, tile works, and painting works. References are provided from various construction material suppliers in the Philippines to obtain unit prices for materials. The project involves the construction of foundations, columns, beams, floors, and roofing for the residential building.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
73 views

3030 Ce514 Course Culminating Activity

The document is an estimation of costs for a construction project to build a single storey residential building. It includes detailed computations and pricing for structural concrete work, masonry works, formworks and falseworks, scaffolding, beams, roofing works, doors and windows, tile works, and painting works. References are provided from various construction material suppliers in the Philippines to obtain unit prices for materials. The project involves the construction of foundations, columns, beams, floors, and roofing for the residential building.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 31

PROJECT: CONSTRUCTION OF A SINGLE STOREY

RESIDENTIAL BUILDING

GROUP NAME:
2BY2
CLASSCODE:
3030
GROUP MEMBERS:
GUINDALOS, KRISHA L.
ACOSTA JOSHUA F.

1
2
DETAILED ESTIMATION

PRICE REFERENCE: https://www.theprojectestimate.com/ready-mix-concrete-price-list/

3
PRICE REFERENCE: https://philconprices.com

4
PRICE REFERENCE: https://philconprices.com

5
PRICE REFERENCE: https://philconprices.com

6
PRICE REFERENCE: https://philconprices.com

7
PRICE REFERENCE: https://philconprices.com

8
PRICE REFERENCE: https://philconprices.com

9
PRICE REFERENCE: TG HOME BUILDERS, Ferguson RD. Guisad, Baguio City

10
PRICE REFERENCE: TG HOME BUILDERS, Ferguson RD. Guisad, Baguio City

11
PRICE REFERENCE: TG HOME BUILDERS, Ferguson RD. Guisad, Baguio City

12
PRICE REFERENCE: Acosta Electrical Supplies, Shanum St., Baguio City

13
PRICE REFERENCE: Acosta Electrical Supplies, Shanum St., Baguio City

14
PRICE REFERENCE: Acosta Electrical Supplies, Shanum St., Baguio City

15
PRICE REFERENCE: TG HOME BUILDERS, Ferguson RD. Guisad, Baguio City

16
PRICE REFERENCE: https://philconprices.com

17
PRICE REFERENCE: TG HOME BUILDERS, Ferguson RD. Guisad, Baguio City

18
PRICE REFERENCE: https://mchomedepot.com/

19
20
21
DETAILED COMPUTATIONS

STRUCTURAL CONCRETE

22
TOTAL VOLUME= 2.9775 + 4.39245 +10.2202= 17.57195 cu.m

23
MASONRY WORKS

24
25
FORMWORKS AND FALSEWORK
FOOTING
FORMS
AT = 18.66 m2
No. of Plywood:
Use: 2"X2"X14'
nplywood =6.48 pcs or 7 pcs- 4'X8'X1/2" Marine Plywood

BRACING
Use: 2"X2"X Commercial Length
Area of Forms =18.66 m2
Factor: 2"X2" =2.71 BF/m2
BFT = 237.13 BF

Using 2"X2"X14' Rough Lumber, ROL


ROL 2"X2"X14'=.67 BF/ pc
n2"X2"X14'=50.81 pcs or 51 pcs 2"X2"X14' ROL
BFT =238 BF

COLUMN
Designation Dimension Height (m) Quantity
C-1
Foundation to Main Factor 0.3m x 0.3m 1.5 10
Main Factor to 2nd Floor Level 0.3m x 0.3m 3 10
C-2
Foundation to Main Factor 0.250m x 0.250m 1.5 2
Main Factor to 2nd Floor Level 0.250m x 0.250m 5.1 2

PLYWOOD
Area of C1 = 2.1 m2 = 21 m2
=4.20 m2 = 42 m2
Area of C2=1.8 m2 = 3.6 m2
=6.12 m2 = 12.24 m2
AT=78.84 m2
No. of Plywood:
Use: 4'X8'X0.5' Marine Plywood
nplywood 27.375 pcs or 24 pcs 4' X 8' X 0.5' Marine Plywood

BRACING
Use: 2"X2"X14'
Area of Forms =78.84 m2
Factor for 2" X 2" =12.71 BF/m2
BFT =1002.06 BF or 1003 BF
Using 2" X 2" X14' Rough Lumber, ROL
ROL = 4.67 BF/pc
n2"X2"X14' =214.93 pcs or 215 pcs 2" X 2" X14'

26
SCAFFOLDING
Use: 2" X 3" X 14'
Ht. of Column =43.20 m
Vertical=7.00 BF/m
Horizontal=31.6712 BF/m
Bracing=17.50 BF/m
BFT =1742.47 BF or 1743 BF
Factor for 2"X3"= 7.00 BF/m2
n2"X2"X14' = 249.00 pcs or 249 pcs 2" X 2" X 14' ROL

BEAMS
Designation Dimension Total Length Area
Grade Beam
GB-1 0.25m x 0.3m 25.493 24.2184 m2
GB-2 0.25m x 0.3m 20.086 19.0903 m3
CB-1 0.25m x 0.3m 7.5 7.125 m2
2nd Flr Beam
B-1 0.25m x 0.35m 25. 493 26.7677 m2
B-2 0.25m x 0.35m 20.086 21.0903 m2
B-3 0.20m x 0.35m 0.5 0.6 m2
EB-1 0.20m x 0.35m 8.093 8.093 m2
CB-2 0.20m x 0.35m 5 5 m2
Total Length= 111.9 m2

No. of Plywood
Commercial Length of Plywood: 4' X 8' X 1/4" = 1.2m X 2.4m
nplywood= 8.8458 pcs or 39-pcs 4' X 8' X 1/4" Marine Plywood

BRACING
Use: 2" X 2" X commercial length
Area of Forms = 111.88 m2
Factor for 2" X 2" = 12.71 BF/m2
BFT =1421.94 BF or 1422 BF

Using 2" X 2" X 14' Rough Lumber, ROL


ROL =4.67 BF/pc
n2"X2"X14' =304.71 pcs or 305 pcs 2" X 2" X 14'

SCAFFOLDING
Use: 2" X 3" X 14'
Lbeam =112.25 m
BFT =1459.26 BF or 1460 BF
n2"X2"X14' = 208.47 pcs or 209 pcs 2" X 3" X 14' ROL

27
ROOFWORKS

Area of Roofs= (8.6*6.8)+(1/2*1.293*8.6)= 64.0399 sq.m


Gutter=8.6 l.m
Flashing= (8.093+6.8)+8.6= 23.493 l.m.

DOOR AND WINDOW ESTIMATE

28
TILE WORKS

29
PAINTING WORKS

30