0% found this document useful (0 votes)
47 views

Regional Office Iv-B: Itemized Quantities and Cost Estimates On Other Sheet

This document is a change order for a road widening project in Roxas, Palawan, Philippines. It details increases and decreases to various project items and additional new items needed to suit actual field conditions. The contractor agreed to the changes. The original contract amount was 189,128,456.17 PHP and is being increased by 3,856,654.62 PHP to a new revised contract amount of 192,985,110.79 PHP due to the itemized changes in the change order. The changes were requested by both the contractor and project engineer to match actual site conditions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
47 views

Regional Office Iv-B: Itemized Quantities and Cost Estimates On Other Sheet

This document is a change order for a road widening project in Roxas, Palawan, Philippines. It details increases and decreases to various project items and additional new items needed to suit actual field conditions. The contractor agreed to the changes. The original contract amount was 189,128,456.17 PHP and is being increased by 3,856,654.62 PHP to a new revised contract amount of 192,985,110.79 PHP due to the itemized changes in the change order. The changes were requested by both the contractor and project engineer to match actual site conditions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 45

Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


REGIONAL OFFICE IV-B
EDSA, Quezon City

CONTRACT ID : : 18EO0018
PROJECT NAME : : ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE
K0092+744 - K0094+844 (KM 92+744 - KM 94+857): K0094+875 - K0095+205 (KM 94+875 - KM 95+203)

LOCATION : : ROXAS, PALAWAN

TO: MARCBILT CONSTRUCTION INCORPORATED, Contractor, you are hereby directed to make the herein changes from the original plans and specifications, or do the following work not included in the plans,
specifications and contract.

DESCRIPTION OF WORK TO BE DONE : INCREASE IN ITEMS - 103(6)a, 104(1)b1, 405(1)b3, 407(8), 505(2)a, 506(1), 603(4)a
DECREASE IN ITEMS - 100(1), 102(2), 103(1)a, 103(3), 104(1)a1, 105(1)a, 200(1), 311(1)e1, 404(1)a, 405(2)b, 500(1)b3, 508(1), 603(4)a, 612(1)
DELETED ITEMS - 600(5), 602(3)b
ADDITIONAL ITEMS - 311(1)a, 404A(1)a, 612(2), 607(3)c, 625(2)3

REASON FOR CHANGE : To suit actual field condition.


CHANGE REQUESTED BY : Contractor and DPWH Project Engineer

ITEMIZED QUANTITIES AND COST ESTIMATES ON OTHER SHEET


I, the undersigned contractor have given careful consideration to the change
proposed and hereby agree, if this proposal is approved , that we will provide all Original Contract Amount ……………………………………… : P 189,128,456.17
equipment, furnish all materials except as may otherwise be noted above and Amount in Change Order No. 1……………………………… : P 192,985,110.79
perform all services necessary for the above specified and will accept as full payment Difference in Cost this Change Order ……………...(+) : P 3,856,654.62
therefore in accordance with terms and conditions in the Contract.
Available Amount per CAF/OBR….......................... : P 3,865,813.44
Revised Contract Amount …..............................
……………...(+) : P 192,985,110.79

NOTE: THE CONTRACTOR HEREBY WAIVED NOT TO COLLECT EXCESS NOTE : This Change Order is not
UNOBLIGATED AMOUNT EQUIVALENT TO P'15,850.05 effective until approved. By reason of this proposed Change ____ days extension of contract
time will be allowed. The total contract time to date, including this Change
ACCEPTED : Order is ____ days.

PREPARED and SUBMITTED BY :


CHARLES WILLIAM T. TAN
Vice President
MARCBILT CONSTRUCTION ELIZALDE V. OLEGA
INCORPORATED
Project Engineer

CHECKED : RECOMMENDING APPROVAL: APPROVED :

DOMINIC G. SERRANO ARMANDO G. ESTRELLA, CESO IV WILFREDO S. MALLARI


Chief, Construction Division Assistant Regional Director OIC - Regional Director
ITEMIZED COST OF REVISION
CONTRACT ID : : 18EO0018
PROJECT NAME : : ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE
: K0092+744 - K0094+844 (KM 92+744 - KM 94+857): K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
LOCATION : ROXAS, PALAWAN
CONTRACTOR : MARCBILT CONSTRUCTION INCORPORATED
SUMMARY OF QUANTITIES FOR CHANGE ORDER NO. 01
ORIGINAL CONTRACT CHANGE ORDER NO. 01
ITEM NO. DESCRIPTION UNIT
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT
Part A Facilities for the Engineer
A.1.1(6) Provision of Combined Field Office, Laboratory and Living Quarters Building fo Month 12.90 55,440.00 715,176.00 12.90 55,440.000 715,176.00

A.1.1(11) Provision of Furniture/Fixtures, Equipment & Appliances for the Field Office f L.S. 1.00 215,600.00 215,600.00 1.00 215,600.000 215,600.00

A.1.1(14) Provision of Laboratory Testing Equipment, Apparatus and Publications for th L.S. 1.00 123,201.56 123,201.56 1.00 123,201.560 123,201.56

A.1.1(15) Operation & Maintenance of Temporary Field Office, Laboratory and Living Qua Month 12.90 23,654.40 305,141.76 12.90 23,654.400 305,141.76

Part A1.2 Vehicles for the Engineer -


A.1.2(4) Provision of 4x2 Pick-up Type Service Vehicle for the Engineer on Rental Basis Month 12.90 80,080.00 1,033,032.00 12.90 80,080.000 1,033,032.00
A.1.2(6) Operation and Maintenance of 4x2 Pick Up type Service Vehicle for the Engine Month 12.90 82,544.00 1,064,817.60 12.90 82,544.000 1,064,817.60
Part A1.3 Assistance for the Engineer -
A.1.3(3) Provision of Survey Personnel for the Assistance to the Engineer Month 12.90 60,060.00 774,774.00 12.90 60,060.00 774,774.00
Part A1.4 Photographs -
A.1.4(1) Provision of Progress Photographs Month 12.90 3,080.00 39,732.00 12.90 3,080.000 39,732.00
Part B Other General Requirements -
B.2 Medical Room and First Aid Facilities L.S. 1.00 190,713.60 190,713.60 1.00 190,713.600 190,713.60
B.5 Project Billboard/Signboard each 2.00 7,746.20 15,492.40 2.00 7,746.20 15,492.40
B.7 Occupational Safety and Health Program Month 12.90 44,495.26 573,988.85 12.90 44,495.260 573,988.85
B.9 Mobilization and Demobilization L.S. 1.00 906,939.26 906,939.26 1.00 906,939.260 906,939.26
Part C Earthworks -
100(1) Clearing and Grubbing ha. 6.72 204,222.15 1,372,372.85 5.88 204,222.150 1,200,826.24
100(3)a2 Individual Removal of Trees (150 - 300 mm dia.) each 191.00 2,025.64 386,897.24 191.00 2,025.640 386,897.24
101(1) Removal of Actual Structures/Obstruction\ l.s. 1.00 1,037,501.70 1,037,501.70 1.00 1,037,501.700 1,037,501.70
102(2) Removal of Structures and Obstruction (PCCP) cu.m. 24,174.84 302.58 7,314,823.09 - 302.58 -
103(1)a Surplus Common Excavation cu.m. 1,065.60 304.26 324,219.46 - 304.260 -
103(3) Structural Excavation cu.m. 276.34 1,460.63 403,630.49 220.00 1,460.630 321,338.60
103(6)a Foundation Fill cu.m. 501.26 328.65 164,739.10 2,803.00 328.650 921,205.95
104(1)a1 Pipe Culvert and Drain Excavation cu.m. 12,671.61 377.44 4,782,772.48 12,521.70 377.440 4,726,190.45
104(1)b1 Embankment from Roadway Excavation cu.m. 913.14 1,788.16 1,632,840.42 6,383.38 1,788.160 11,414,497.63
105(1)a Embankment from Borrow sq.m. 31,496.93 17.54 552,456.15 29,498.00 17.540 517,394.92
Part D Subgrade Preparation,Common Material -
200(1) Subbase and Base Course cu.m. 10,098.35 1,997.59 20,172,362.98 9,487.00 1,997.590 18,951,136.33

TOTAL SHEET 1 = 44,103,224.99 45,435,598.09

Page 2 of 45
ITEMIZED COST OF REVISION
CONTRACT ID : : 18EO0018
PROJECT NAME : : ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE
: K0092+744 - K0094+844 (KM 92+744 - KM 94+857): K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
LOCATION : ROXAS, PALAWAN
CONTRACTOR : MARCBILT CONSTRUCTION INCORPORATED
SUMMARY OF QUANTITIES FOR CHANGE ORDER NO. 01
ORIGINAL CONTRACT CHANGE ORDER NO. 01
ITEM NO. DESCRIPTION UNIT
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT
Part E Surface Course
311(1)a PCCP (Unreinforced) 0.15 m thick sq.m. 1,572.02 - 3,482.00 1,572.017 5,473,763.19
311(1)e1 Portland Cement Concrete Pavement (0.28m thk.) sq.m. 30,770.87 3,134.66 96,456,215.35 29,418.00 3,134.660 92,215,427.88
Part F Bridge Structures -
404A(1)a Epoxy-Coated Reinforcing Steel Bars (Dowell for Existing PCCP) kg. 250.00 - 8,002.00 250.00 2,000,500.00
404(1)a Reinforcing Steel Grade 40 kg. 59,375.65 63.69 3,781,635.15 53,642.00 63.690 3,416,458.98
405(1)b3 Structural Concrete, Class A (27.58 Mpa), 28 days cu.m. 39.16 14,083.37 551,504.77 191.00 14,083.370 2,689,923.67
405(2)b Structural Concrete,Class B (27.58 Mpa) cu.m. 1,209.46 12,944.67 15,656,060.58 834.00 12,944.670 10,795,854.78
407(8) Lean Concrete, Class B (16.50 Mpa) cu.m. 0.98 12,514.60 12,264.31 3.57 12,514.60 44,677.12
Part G Drainage and Slope Protection Structures -
500(1)b3 RCCP, 910mm diameter Class IV l.m. 98.00 8,187.21 802,346.58 84.00 8,187.210 687,725.64
505(2)a Grouted Riprap Class "A" cu.m. 253.80 8,576.84 2,176,801.99 521.00 8,576.840 4,468,533.64
506(1) Stone Masonry cu.m. 794.34 10,076.59 8,004,238.50 929.00 10,076.590 9,361,152.11
508(1) Handlaid Rock Embankment cu.m. 3.32 7,384.95 24,518.03 - 7,384.95 -
Part H Miscellaneous Structures -
600(5) Concrete Curb, Cast in Place l.m. 4,849.00 1,303.15 6,318,974.35 - 1,303.150 -
602(3)b Kilometer Post, Pre Cast each 3.00 6,971.07 20,913.21 - 6,971.070 -
603(3)a1 Metal Guardrail (Metal Beam) Including Post l.m. 1,717.00 5,744.28 9,862,928.76 1,701.00 5,744.280 9,771,020.28
603(4)a Metal End Beam Piece, Fish Tail each 32.00 1,625.66 52,021.12 54.00 1,625.660 87,785.64
612(1) Reflectorized Thermoplastic Pavement Marking (White) sq.m. 1,467.00 889.44 1,304,808.48 913.30 889.440 812,325.55
612(2) Reflectorized Thermoplastic Pavement Markings Yellow sq.m. 789.32 - 630.60 789.320 497,745.19
607(3)c Internally Illuminated (Solar) Pavement Levellec Marker/Studs Flush Type Omnic each 10,300.00 - 468.00 10,300.000 4,820,400.00
625(2)3 Linear Delineartor System each 1,134.69 - 358.00 1,134.690 406,219.02

TOTAL SHEET 2 = 145,025,231.18 147,549,512.70


NOTE: THE CONTRACTOR HEREBY WAIVED NOT TO COLLECT TOTAL SHEET (1+2) = 189,128,456.17 192,985,110.79
EXCESS UNOBLIGATED AMOUNT EQUIVALENT TO P'15,850.05

CONCURRED : PREPARED and SUBMITTED :


Original Contract Amount
………………………………………………………………..:
………………… P 189,128,456.17
Amount in Change………………………………………………………………..:
Order No. 1………… P 192,985,110.79
Difference in Cost this Change Order…………………………..…( + )..: P 3,856,654.62
CHARLES WILLIAM T. TAN Project Engineer Available Amount per CAF/OBR…......................
…………………………………..: P 3,865,813.44
Vice President Project Engineer ………………………..…..:
Revised Contract Amount ….............................. P 192,985,110.79
MARCBILT CONSTRUCTION INCORPORATED

CHECKED BY : RECOMMENDING APPROVAL : APPROVED :

DOMINIC G. SERRANO ARMANDO G. ESTRELLA, CESO IV WILFREDO S. MALLARI


Chief, Construction Division Assistant Regional Director OIC - Regional Director

Page 3 of 45
ITEMIZED COST OF REVISION
(AS STAKE PLAN)

CONTRACT ID : 18EO0018
PROJECT NAME : ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE
K0092+744 - K0094+844 (KM 92+744 - KM 94+857): K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
LOCATION : ROXAS, PALAWAN
CONTRACTOR : MARCBILT CONSTRUCTION INCORPORATED

CHANGE ORDER NO. 1

ORIGINAL
ITEM NO. DESCRIPTION UNIT CONTRACT QTY REVISED QUANTITY REMARKS
QUANTITY
Part A Facilities for the Engineer
Provision of Combined Field Office, Laboratory and Living Quarters Building for the Engineers
A.1.1(6) Month 12.90 12.90
(Rental Basis)
A.1.1(11) Provision of Furniture/Fixtures, Equipment & Appliances for the Field Office for the Engineer L.S. 1.00 1.00
A.1.1(14) Provision of Laboratory Testing Equipment, Apparatus and Publications for the Engineer L.S. 1.00 1.00
Operation & Maintenance of Temporary Field Office, Laboratory and Living Quarters Building
A.1.1(15) Month 12.90 12.90
for the Engineer
Part A1.2 Vehicles for the Engineer
A.1.2(4) Provision of 4x2 Pick-up Type Service Vehicle for the Engineer on Rental Basis Month 12.90 12.90
A.1.2(6) Operation and Maintenance of 4x2 Pick Up type Service Vehicle for the Engineer Month 12.90 12.90
Part A1.3 Assistance for the Engineer
A.1.3(3) Provision of Survey Personnel for the Assistance to the Engineer Month 12.90 12.90
Part A1.4 Photographs
A.1.4(1) Provision of Progress Photographs Month 12.90 12.90
Part B Other General Requirements
B.2 Medical Room and First Aid Facilities L.S. 1.00 1.00
B.5 Project Billboard/Signboard each 2.00 2.00
B.7 Occupational Safety and Health Program Month 12.90 12.90
B.9 Mobilization and Demobilization L.S. 1.00 1.00
Part C Earthworks
100(1) Clearing and Grubbing ha. 6.72 5.88 To be cleared
100(3)a2 Individual Removal of Trees (301 - 500 mm dia.) each 191.00 191.00 To be removed
101(1) Removal of Structures & Obstruction l.s. 1.00 1.00 To be removed
102(2) Surplus Common Excavation cu.m. 24,174.84 - To be Excavated
103(1)a Structure Excavation, Common Soil cu.m. 1,065.60 - Deleted
103(3) Foundation Fill cu.m. 276.34 220.00 0.10 m Compacted Volume
103(6)a Pipe Culvert and Drain Excavation (Common Soil) cu.m. 501.26 2,803.00 To be Excavated
104(1)a1 Embankment from Roadway Excavation (Common Soil) cu.m. 12,671.61 12,521.70 Compacted Volume
104(1)b1 Embankment from Borrow (Common Soil) cu.m. 913.14 6,383.38 Deleted
105(1)a Subgrade Preparation (Common Material) sq.m. 31,496.93 29,498.00 Roadbed Excavation
Part D Subbase and Base Course
200(1) Aggregate Subbase Course cu.m. 10,098.35 9,487.00 0.20 m Thick Compacted Volume
Part E Surface Course
311(1)a PCCP (Unreinforced) 0.15 m thick sq.m. 3,482.00 0.15m thick Pavement
311(1)e1 Portland Cement Concrete Pavement (0.28m thk.) sq.m. 30,770.87 29,418.00 0.28m thick Pavement
Part F Bridge Structures
404A(1)a Epoxy-Coated Reinforcing Steel Bars (Dowell for Existing PCCP) kg. 8,002.00 For PCCP dowels
404(1)a Reinforcing Steel Grade 40 kg. 59,375.65 53,642.00 For Line Canal and RCBC
405(1)b3 Structural Concrete, Class A (27.58 Mpa), 28 days cu.m. 39.16 191.00 For RCBC
405(2)b Structural Concrete,Class B (27.58 Mpa) cu.m. 1,209.46 834.00 For Line Canal
407(8) Lean Concrete, Class B (16.50 Mpa) cu.m. 0.98 3.57 For RCBC
Part G Drainage and Slope Protection Structures
500(1)b3 RCCP, 910mm diameter Class IV l.m. 98.00 84.00 To be Installed
505(2)a Grouted Riprap Class "A" cu.m. 253.80 521.00 For Slope Protection
506(1) Stone Masonry cu.m. 794.34 929.00 For Slope Protection
508(1) Handlaid Rock Embankment cu.m. 3.32 - Deleted
Part H Miscellaneous Structures
600(5) Concrete Curb, Cast in Place l.m. 4,849.00 - Deleted
602(3)b Kilometer Post, Pre Cast each 3.00 - Deleted
603(3)a1 Metal Guardrail (Metal Beam) Including Post l.m. 1,717.00 1,701.00 To be Installed
ITEMIZED COST OF REVISION
(AS STAKE PLAN)

CONTRACT ID : 18EO0018
PROJECT NAME : ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE
K0092+844 - KO94+739 KO: K0094+998 - K0095+245
LOCATION : ROXAS, PALAWAN
CONTRACTOR : MARCBILT CONSTRUCTION INCORPORATED

CHANGE ORDER NO. 1

AS STAKE PLAN
ITEM UNIT PRICE IN ORIGINAL CONTRACT REVISED QUANTITY AND AMOUNT
DESCRIPTION UNIT ADDITIVE DEDUCTIVE
NO. PESOS
QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT
Part A Facilities for the Engineer
Provision of Combined Field Office, Laboratory and Living Quarters
A.1.1(6) Month 55,440.00 12.90 715,176.00 - - - - 12.90 715,176.00
Building for the Engineers (Rental Basis)
Provision of Furniture/Fixtures, Equipment & Appliances for the Field
A.1.1(11) L.S. 215,600.00 1.00 215,600.00 - - - - 1.00 215,600.00
Office for the Engineer
Provision of Laboratory Testing Equipment, Apparatus and
A.1.1(14) L.S. 123,201.56 1.00 123,201.56 - - - - 1.00 123,201.56
Publications for the Engineer
Operation & Maintenance of Temporary Field Office, Laboratory and
A.1.1(15) Month 23,654.40 12.90 305,141.76 - - - - 12.90 305,141.76
Living Quarters Building for the Engineer
Part A1.2 Vehicles for the Engineer
Provision of 4x2 Pick-up Type Service Vehicle for the Engineer on
A.1.2(4) Month 80,080.00 12.90 1,033,032.00 - - - - 12.90 1,033,032.00
Rental Basis
Operation and Maintenance of 4x2 Pick Up type Service Vehicle for
A.1.2(6) Month 82,544.00 12.90 1,064,817.60 - - - - 12.90 1,064,817.60
the Engineer
Part A1.3 Assistance for the Engineer
A.1.3(3) Provision of Survey Personnel for the Assistance to the Engineer Month 60,060.00 12.90 774,774.00 - - - - 12.90 774,774.00
Part A1.4 Photographs
A.1.4(1) Provision of Progress Photographs Month 3,080.00 12.90 39,732.00 - - - - 12.90 39,732.00
Part B Other General Requirements
B.2 Medical Room and First Aid Facilities L.S. 190,713.60 1.00 190,713.60 - - - - 1.00 190,713.60
B.5 Project Billboard/Signboard each 7,746.20 2.00 15,492.40 - - - - 2.00 15,492.40
B.7 Occupational Safety and Health Program Month 44,495.26 12.90 573,988.85 - - - - 12.90 573,988.85
B.9 Mobilization and Demobilization L.S. 906,939.26 1.00 906,939.26 - - - - 1.00 906,939.26
Part C Earthworks
100(1) Clearing and Grubbing ha. 204,222.15 6.72 1,372,372.85 - - 0.72 147,039.95 6.00 1,225,332.90
100(3)a2 Individual Removal of Trees (301 - 500 mm dia.) each 2,025.64 191.00 386,897.24 - - - - 191.00 386,897.24
101(1) Removal of Structures & Obstruction l.s. 1,037,501.70 1.00 1,037,501.70 - - - - 1.00 1,037,501.70
102(2) Surplus Common Excavation cu.m. 302.58 24,174.84 7,314,823.09 720.84 218,111.77 - - 24,895.68 7,532,934.85
103(1)a Structure Excavation, Common Soil cu.m. 304.26 1,065.60 324,219.46 - - 1,065.60 324,219.46 - -
103(3) Foundation Fill cu.m. 1,460.63 276.34 403,630.49 - - 56.34 82,291.89 220.00 321,338.60
103(6)a Pipe Culvert and Drain Excavation (Common Soil) cu.m. 328.65 501.26 164,739.10 2,301.74 756,466.85 - - 2,803.00 921,205.95
104(1)a1 Embankment from Roadway Excavation (Common Soil) cu.m. 377.44 12,671.61 4,782,772.48 4,329.07 1,633,964.18 - - 17,000.68 6,416,736.66
104(1)b1 Embankment from Borrow (Common Soil) cu.m. 1,788.16 913.14 1,632,840.42 - - 913.14 1,632,840.42 - -
105(1)a Subgrade Preparation (Common Material) sq.m. 17.54 31,496.93 552,456.15 - - 1,691.93 29,676.45 29,805.00 522,779.70
Part D Subbase and Base Course
200(1) Aggregate Subbase Course cu.m. 1,997.59 10,098.35 20,172,362.98 - - 611.53 1,221,588.93 9,486.82 18,950,774.05
Part E Surface Course
311(1)a PCCP (Unreinforced) 0.15 m thick sq.m. 1,572.02 - 3,482.00 5,473,763.19 - - 3,482.00 5,473,763.19
311(1)e1 Portland Cement Concrete Pavement (0.28m thk.) sq.m. 3,134.66 30,770.87 96,456,215.35 - - 3,074.87 9,638,671.99 27,696.00 86,817,543.36
Part F Bridge Structures
404A(1)a Epoxy-Coated Reinforcing Steel Bars (Dowell for Existing PCCP) kg. 250.00 - 4,461.00 1,115,250.00 - - 4,461.00 1,115,250.00
404(1)a Reinforcing Steel Grade 40 kg. 63.69 59,375.65 3,781,635.15 - - 5,733.65 365,176.17 53,642.00 3,416,458.98
405(1)b3 Structural Concrete, Class A (27.58 Mpa), 28 days cu.m. 14,083.37 39.16 551,504.77 151.84 2,138,418.90 - - 191.00 2,689,923.67
405(2)b Structural Concrete,Class B (27.58 Mpa) cu.m. 12,944.67 1,209.46 15,656,060.58 - - 375.46 4,860,205.80 834.00 10,795,854.78
407(8) Lean Concrete, Class B (16.50 Mpa) cu.m. 12,514.60 0.98 12,264.31 2.59 32,412.81 - - 3.57 44,677.12
Part G Drainage and Slope Protection Structures
500(1)b3 RCCP, 910mm diameter Class IV l.m. 8,187.21 98.00 802,346.58 - - 14.00 114,620.94 84.00 687,725.64
505(2)a Grouted Riprap Class "A" cu.m. 8,576.84 253.80 2,176,801.99 267.20 2,291,731.65 - - 521.00 4,468,533.64
506(1) Stone Masonry cu.m. 10,076.59 794.34 8,004,238.50 181.66 1,830,513.34 - - 976.00 9,834,751.84
508(1) Handlaid Rock Embankment cu.m. 7,384.95 3.32 24,518.03 - - 3.32 24,518.03 - -
Part H Miscellaneous Structures
600(5) Concrete Curb, Cast in Place l.m. 1,303.15 4,849.00 6,318,974.35 - - 4,849.00 6,318,974.35 - -
602(3)b Kilometer Post, Pre Cast each 6,971.07 3.00 20,913.21 - - 3.00 20,913.21 - -
603(3)a1 Metal Guardrail (Metal Beam) Including Post l.m. 5,744.28 1,717.00 9,862,928.76 - - 441.00 2,533,227.48 1,276.00 7,329,701.28
603(4)a Metal End Beam Piece, Fish Tail each 1,625.66 32.00 52,021.12 22.00 35,764.52 - - 54.00 87,785.64
612(1) Reflectorized Thermoplastic Pavement Marking (White) sq.m. 889.44 1,467.00 1,304,808.48 - - 605.10 538,200.14 861.90 766,608.34
612(2) Reflectorized Thermoplastic Pavement Markings Yellow sq.m. 789.32 - 630.60 497,745.19 - - 630.60 497,745.19
Internally Illuminated (Solar) Pavement Levellec Marker/Studs Flush
607(3)c each 10,300.00 - 468.00 4,820,400.00 - - 468.00 4,820,400.00
Type Omnic
625(2)3 Linear Delineartor System each 1,134.69 - 358.00 406,219.02 - - 358.00 406,219.02

TOTAL AMOUNT 189,128,456.17 21,250,761.42 27,852,165.21 182,527,052.37

BALANCE = 10,467,217.24

Conforme: Submitted: Cheked: Recommending Approval:

MARCBILT CONSTRUCTION INCORPORATED ELIZALDE V. OLEGA DOMINIC G. SERRANO ARMANDO G. ESTRELAL, CESO IV
Project Engineer III/Engineer III Chief, Construction Division Assistant Regional Director

By: Approved:

WILFREDO S. MALLARI
Regional Director
ITEMIZED COST OF REVISION (AS STAKED)
PROJECT: Road Widening of Puerto Pricesa North Road (two lanes to six lanes including drainage),
K0092+744 - K0094+844 (KM 92+744 - KM 94+857)
K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
LOCATION: Roxas, Palawan
ORIGINAL / C.O. # 1 (As-Staked) - Construction Limits : K0092+744 - K0094+844; K0094+875 - K0095+205, L = 2,430.00 L.M.

SUMMARY OF QUANTITIES FOR AS-STAKED / C.O. # 1


ORIGINAL CONTRACT QUANTITY C.O. #1 / AS-STAKED
ITEM NO. DESCRIPTION UNIT
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT
Part A FACILITIES FOR THE ENGINEER
A.1.1 Offices
Provisionand Laboratory
of Combined for Office,
Field the Engineer
Laboratory and
Living Quarters Building for the Engineer (Rental Month 12.90 55,440.00 715,176.00 12.90 55,440.00 715,176.00
A.1.1(6) Basis)
Provision of Furnitures/ Fixtures, Equipment & L.S. 1.00 215,600.00 215,600.00 1.00 215,600.00 215,600.00
A.1.1(11) Appliances for the Field Office for the Engineer
Provision of the Laboratory Testing Equipment, L.S. 1.00 123,201.56 123,201.56 1.00 123,201.56 123,201.56
A.1.1(14) Apparatus and Publications for the Engineer

Operation & Maintenance of Temporary Field Office, Month 12.90 23,654.40 305,141.76 12.90 23,654.40 305,141.76
A.1.1(15) Laboratory and Living Quarters Bldg. for the Engineer
A.1.2 Vehicles for the Engineer
Provision of 4x2 Pick Up Type Service Vehicle for the
Month 12.90 80,080.00 1,033,032.00 12.90 80,080.00 1,033,032.00
A.1.2(4) Engineer on Bare Rental Basis
Operation and Maintenance of 4x2 Pick Up type Month 12.90 82,544.00 1,064,817.60 12.90 82,544.00 1,064,817.60
A.1.2(6) service Vehicle for the Engineer
A.1.3 Assistance to the Engineer
Provision of Survey Personnel for the Assistance to the Month 12.90 60,060.00 774,774.00 12.90 60,060.00 774,774.00
A.1.3(3) Engineer
A.1.4 Photographs
A.1.4(1) Provision of Progress Photographs Month 12.90 3,080.00 39,732.00 12.90 3,080.00 39,732.00
Part B Other General Requirements
B.2 Medical Room and First Aid Facilities L.S. 1.00 190,713.60 190,713.60 1.00 190,713.60 190,713.60
B.5 Project Billboard/Signboard each 2.00 7,746.20 15,492.40 2.00 7,746.20 15,492.40
B.7 Occupational Safety and Health Program Month 12.90 44,495.26 573,988.85 12.90 44,495.26 573,988.85
B.9 Mobilization and Demobilization L.S. 1.00 906,939.26 906,939.26 1.00 906,939.26 906,939.26
Part C Earthworks
ITEMIZED COST OF REVISION (AS STAKED)
PROJECT: Road Widening of Puerto Pricesa North Road (two lanes to six lanes including drainage),
K0092+744 - K0094+844 (KM 92+744 - KM 94+857)
K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
LOCATION: Roxas, Palawan
ORIGINAL / C.O. # 1 (As-Staked) - Construction Limits : K0092+744 - K0094+844; K0094+875 - K0095+205, L = 2,430.00 L.M.

SUMMARY OF QUANTITIES FOR AS-STAKED / C.O. # 1


ORIGINAL CONTRACT QUANTITY C.O. #1 / AS-STAKED
ITEM NO. DESCRIPTION UNIT
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT
100(1) Clearing and Grubbing ha. 6.72 204,222.15 1,372,372.85 6.00 204,222.15 1,225,332.90
100(3)a2 Individual Removal of trees, Small (301-500mm dia.) each 191.00 2,025.64 386,897.24 191.00 2,025.64 386,897.24
101(1) Removal of Structures and Obstructions L.S. 1.00 1,037,501.70 1,037,501.70 1.00 1,037,501.70 1,037,501.70
102(2) Surplus Common Excavation cu.m. 24,174.84 302.58 7,314,823.09 #REF! 302.58 #REF!
103(1)a Structure Excavation (Common soil) cu.m. 1,065.60 304.26 324,219.46 304.26 0.00
103(3) Foundation Fill cu.m. 276.34 1,460.63 403,630.49 #REF! 1,460.63 #REF!
103(6)a Pipe Culvert and Drain Excavation, Common Soil cu.m. 501.26 328.65 164,739.10 #REF! 328.65 #REF!
104(1)a Embankment from Roadway Excavation, Common Soil cu.m. 12,671.61 377.44 4,782,772.48 #REF! 377.44 #REF!
104(1)b1 Embankment from Borrow, Common Soil cu.m. 913.14 1,788.16 1,632,840.42 1,788.16 0.00
105(1)a Subgrade Preparation, Common Material sq.m. 31,496.93 17.54 552,456.15 29,805.00 17.54 522,779.70
Part D Sub-Base and Base Course
200(1) Aggregates Sub-base Course (0.20m thk) cu.m. 10,098.35 1,997.59 20,172,362.98 8,434.56 1,997.59 16,848,792.71
Part E Surface Course
311(1)e1 PCC Pavement (Unreinforced) 0.28m. Thick, 14 days sq.m. 30,770.87 3,134.66 96,456,215.35 27,695.99 3,134.66 86,817,512.01
Part F Bridge Structures
404(1)a Reinforcing Steel, Grade 40 Kg. 59,375.65 63.69 3,781,635.15 59,375.65 63.69 3,781,635.15
405(1)b3 Structural Concrete, Class A, 27.58 MPa, 28 days cu.m. 39.16 14,083.37 551,504.77 39.16 14,083.37 551,504.77
405(2)b Structural Concrete, Class B, 20.68 MPa cu.m. 1,209.46 12,944.67 15,656,060.58 #REF! 12,944.67 #REF!
407(8) Lean Concrete, Class B, 16.50 Mpa cu.m. 0.98 12,514.60 12,264.31 0.98 12,514.60 12,264.31
Part G Drainage and Slope Protection Structures
500(1)b3 Pipe Culverts, 910mm dia. (Class IV) l.m. 98.00 8,187.21 802,346.58 #REF! 8,187.21 #REF!
505(2)a Grouted Riprap, Class "A" cu.m. 253.80 8,576.84 2,176,801.99 8,576.84 0.00
506(1) Stone Masonry cu.m. 794.34 10,076.59 8,004,238.50 #REF! 10,076.59 #REF!
508(1) Hand-Laid Rock Embankment cu.m. 3.32 7,384.95 24,518.03 3.32 7,384.95 24,518.03
Part H Miscellaneous Structures
600(1) Concrete Curb (Cast in Place) l.m. 4,849.00 1,303.15 6,318,974.35 4,849.00 1,303.15 6,318,974.35
602(3)b Kilometer Post (Precast) each 3.00 6,971.07 20,913.21 3.00 6,971.07 20,913.21
ITEMIZED COST OF REVISION (AS STAKED)
PROJECT: Road Widening of Puerto Pricesa North Road (two lanes to six lanes including drainage),
K0092+744 - K0094+844 (KM 92+744 - KM 94+857)
K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
LOCATION: Roxas, Palawan
ORIGINAL / C.O. # 1 (As-Staked) - Construction Limits : K0092+744 - K0094+844; K0094+875 - K0095+205, L = 2,430.00 L.M.

SUMMARY OF QUANTITIES FOR AS-STAKED / C.O. # 1


ORIGINAL CONTRACT QUANTITY C.O. #1 / AS-STAKED
ITEM NO. DESCRIPTION UNIT
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT
603(3)a1 l.m. 1,717.00 5,744.28 9,862,928.76 1,717.00 5,744.28 9,862,928.76
Metal Guardrail (Metal Beam) Including Post (W-Beam)
603(4)a Metal End Piece, Fish Tail each 32.00 1,625.66 52,021.12 32.00 1,625.66 52,021.12
Reflectorized Thermoplastic Pavement Markings, sq.m. 1,467.00 889.44 1,304,808.48 1,467.00 889.44 1,304,808.48
612(1) White
TOTAL ORIGINAL CONSTRUCTION COST 189,128,456.17 C.O. #1 / AS-STAKED COST #REF!

Original Construction Cost 189,128,456.17


Net Amount in this revision (C.O. # 1) #REF!
Difference in Cost this Change #REF!
CONTRACT ID 18E00018
PROJECT NAME Road Widening of Puerto Pricesa North Road (two lanes to six lanes including drainage),
K0092+744 - K0094+844; K0094+875 - K0095+205
LOCATION Roxas, Palawan
CONTRACTOR PREMIUM MEGASTRUCTURES INC.

BACK-UP COMPUTATION

100(1) Clearing and Grubbing (with Stripping) = 6.00 Ha.


See Computation
Area = 6.00 ha.

100(3)b Individual Removal of Trees, Small (301mm - 500mm. dia) = 191.00 Each
Computation
N = 191.00 each

101(1) Removal of Structures & Obstruction = 1.00 l.s.


Computation
Lot = 1.00 l.s

102(2) Surplus Common Excavation = 24,895.68 Cu.m.


See Computation
Volume = 24,895.68 cu.m.

103(1)a Structure Excavation, Common Soil = - Cu.m.


See Computation
Volume = (Slope Protection)
Volume = cu.m.
say = cu.m.

103(3) Foundation Fill = 220.00 cu.m.


See Computation
Total Vol. = 103(3) RCPC + 103(3) LC
Total Vol. = 12.67 + 207
Total Vol. = 219.67 cu.m.
say = 220.00 cu.m.

103(6)a Pipe Culvert & Drain Excavation (Common Soil) = 2,803.00 cu.m.
See Computation
Volume = 2,587.50 cu.m. Lined Canal
Volume = 57.98 cu.m. RCPC
103(6) RCBC = 157.47 RCBC

Total = 2,802.95 cu.m.


Say = 2,803.00 cu.m.

104(1)a1 Embankment from Roadway Excavation (Common Soil) = 17,000.68 cu.m.


See Computation
Volume = 17,000.68 cu.m.

104(1)b1 Embankment from Borrow (Common Soil) = - cu.m.


See Computation
Volume = cu.m.

105(1)a Subgrade Preparation (Common Material) = 29,805.00 sq.m.


See Computation
Area = 29,805.00 sq.m.

200(1) Aggregate Sub-base Course = 9,486.82 cu.m.


Computation
Station of PCCP (0.28m) Length
92+844.00 - 93+617.65 RL (B/S) = 773.65 l.m.
93+622.35 94+078.00 RL (B/S) = 455.65 l.m.
94+078.00 94+156.00 RL (L/S) = 78.00 l.m.
94+156.00 94+306.00 RL (B/S) = 150.00 l.m.
94+420.00 94+815.50 RL (B/S) = 395.50 l.m.
94+917.00 95+245.00 RL (B/S) = 328.00 l.m.
92+954.00 93+617.65 LL (B/S) = 663.65 l.m.
93+622.35 94+093.00 LL (B/S) = 470.65 l.m.
94+093.00 94+162.00 LL (B/S) = 69.00 l.m.
94+162.00 94+739.00 LL (B/S) = 577.00 l.m.
94+998.00 95+245.00 LL (B/S) = 247.00 l.m.
4,208.10 l.m.
Station of Concrete Shoulder
93+058.00 - 93+198.00 RL = 140.00 l.m.
93+728.00 - 93+915.00 RL = 187.00 l.m.
94+545.00 - 94+740.00 RL = 195.00 l.m.
92+984.00 - 93+058.00 LL = 74.00 l.m.
93+069.00 - 93+245.00 LL = 176.00 l.m.
93+257.00 - 93+480.00 LL = 223.00 l.m.
93+664.00 - 93+911.00 LL = 247.00 l.m.
93+927.00 - 94+070.00 LL = 143.00 l.m.
94+168.00 94+228.00 LL = 60.00 l.m.
94+232.00 - 94+537.00 LL = 305.00 l.m.
93+038.00 93+058.00 RL = 20.00 l.m.
94+913.00 94+998.00 RL = 85.00 l.m.
93+536.00 93+597.00 RL = 61.00 l.m.
Total = 1,916.00 l.m.
V = [0.2 x w x Lp] + [1.1904 x Ls] + [0.66 x Lc]
Where :
w = width of PCCP (0. cu.m.
Lp = length of PCCP (0.28m)
Ls = length of shoulder
Lc = length of canal

V = [0.2 x w x Lp] + [1.1904 x Ls] + [0.66 x Lc]


= 5,586.59 + 2,833.27 + 1,155.00
Volume = 9,486.82 cu.m.

311(1)a PCCP (Unreinforced) 0.15 m thick = 3,482.00 sq.m.

93+058.00 - 93+198.00 RL = 140.00 l.m.


93+734.00 - 93+912.00 RL = 178.00 l.m.
94+545.00 - 94+740.00 RL = 195.00 l.m.
92+984.00 - 93+058.00 LL = 74.00 l.m.
93+069.00 - 93+245.00 LL = 176.00 l.m.
93+257.00 - 93+480.00 LL = 223.00 l.m.
93+664.00 - 93+911.00 LL = 247.00 l.m.
93+927.00 - 94+070.00 LL = 143.00 l.m.
94+168.00 94+228.00 LL = 60.00 l.m.
94+232.00 - 94+537.00 LL = 305.00 l.m.
1,741.00

Area = 2.00m x Length


Area = 2.00m x 1741m
Area = 3,482.00 sq.m.
311(1)e1 PCCP (Unreinforced) - Using Concrete Paver, 0.28m. Thick = 27,696.00 sq.m.
Computation
Area = 27,695.99 sq.m.
say = 27,696.00 sq.m.

404(1)a Reinforcing Steel, Grade 40 = 53,642.00 kgs.


Computation
Weight = 34,141.18 kgs. Lined Canal
Weight = 11,763.08 kgs. RCBC
Weight = 7,738.14 kgs. Slope Protection
Total = 53,642.40 kgs.
say = 53,642.00 kgs.

404A(1)a Epoxy-Coated Reinforcing Steel Bars (Dowell for Existing PCCP) = 4,461.00 kgs.
Computation
Proj. Length = 2,825.00 l.m.
Total No. of Drilled Dowell Bars = 2,825.00 ÷ 0.60 x 1 +1
Total No. of Drilled Dowell Bars = 4,709.00 pcs.
Length of Dowell Bar = 0.60 m. 16mm dia.
Weight of Dowell Bar = 4,709.00 x 1.579 x 0.60
Weight of Dowell Bar = 4,461.31 kgs.

405(1)a3 Structural Concrete, Class A (20.68 Mpa), 28 days = 191.00 Cu.m.


See Detailed Computation
Volume = 104.65 Cu.m. RCBC
SLOPE PROTECTION

Volume = 86.00 cu.m.

Total = 190.65 Cu.m.


say = 191.00 Cu.m.

405(2)a Structural Concrete, Class B (20.68 Mpa) = 834.00 cu.m.


See Computation
Volume = 834.00 Cu.m.

407(8) Lean Concrete, Class B (16.5 Mpa) = 3.57 cu.m.


See Computation
Volume = 3.57 Cu.m.

500(1)b3 Pipe Culverts, 910 mm diameter (Class IV) = 84.00 l.m.


See Drainage Schedule
N = 84.00 l.m.

505(2)a Grouted Riprap Class A = 521.00 cu.m.


See Computation
Volume = 176.00 Cu.m. Lined Canal
Volume = 345.11 Cu.m. Slope Protection
TOTAL = 521.11 Cu.m.
SAY = 521.00 Cu.m.

506(1) Stone Masonry = 976.00 cu.m.


See Computation
Volume = 506 SP + 506 HW
Volume = 873.44 + 102.63
Volume = 976.07 cu.m.
say = 976.00 cu.m.

508(1) Hand-laid Rock Embankment = - cu.m.

Item Deleted

600(5)a Concrete Curb (Cast in Place) = -

Item Deleted
602(3)b Kilometer Post (Precast) = 3.00 each
Computation
N = 3.00 each

603(3)a1 Metal Guardrail (Metal Beam) Including Post (W-Beam) = 1,276.00 l.m.
See Computation
Length = 1,276.35 l.m.
say = 1,276.00 l.m.

603(4)a Metal Beam End Piece, (Fish Tail) = 54.00 each


See Computation
N = 54.00 each

612(1) Reflectorized Thermoplastic Pavement Markings (White) = 861.90 sq.m.


Computation
Outer Length = 3,809.00 l.m.
Solid White (Outside Lane)
Area = 3,809.00 x 0.10 x 1.00 lanes
Area = 380.90 sq.m.
Inner Length = 4,810.00
Broken White (Inner and Middle Lane)
Area = 4,810.00 x 3.00 x 0.15 / 9.0 m x 2.00 lanes
Area = 481.00 sq.m.

Area Total = 861.90 sq.m.

612(2) Reflectorized Thermoplastic Pavement Markings (Yellow) = 630.60 sq.m.


Computation
Total Length = 2,102.00 l.m.

Area = 2,102.00 x 0.15 x 2.00 lanes


Area = 630.60 sq.m.

607(3)c Internally Illuminated (Solar) Pavement Levellec Marker/Studs Flush Type Omnic = 468.00 each
Computation
Total Length = 2,102.00 l.m.

N = 2,102.00 ÷ 4.50 +1
N = 468.11 each
say = 468.00 each

625(2)3 Linear Delineartor System = 358.00 each


See Detailed Computation
N = 1 x No. of Guardrail Post
N = 358.00 each
C.O.#1 / AS - STAKE
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

Computation for RCBC

93+520 1 - 4.00m x 3.00m RCBC

kg.of reinf. for single barrel per meter


(W1) = 652.10 kg. Span = 3.00 m
cu.m. of concrete per meter for single
barrel (v1) = 4.66 cu.m. Length = 14.80 m
kg.of reinf. for wing wall and apron slab
(W2) = 1,056.00 kg. T = 0.30 (See attached Table)
cu.m. of wing wall and apron slab (v2) = 17.84 cu.m. L = 5.73 (See attached Table)
M = 4.55
length @ Left side (L) = 7.50 m. length @ Right side (L) = 7.30 m.
TOTAL LENGTH = 14.80 m.

Computation for 103(3), 103(6)a, 404(1)a and 405(1)b3 for RCBC

407(8) = [(((1 x Span) +(2 x T)) x Length) + (M2 x 2 -Sides)] x 0.10


= [(((1 x 3) + (2 x 0.3)) x 14.8) + ((2 x 4.55 x 2)] x 0.10
= ( 53.28 + 18.2 ) x 0.05
407(8) = 3.57 cu.m.

103(6)a = [(1.414M x 0.50) + (2M + L) x 0.50] x Length


= [(1.414 x 4.55 x 0.50) + ((2 x 4.55) + 5.73 ) x 0.50] x 14.8
= ( 3.22 + 7.42 ) x 14.8
103(6)a = 157.47 cu.m.

404(1) = (W1 x L) + (W2 x 2) 405(1)b3 = (v1 x L) + (v2 x 2)


= (652.1 x 7.5) + (1056 x 2) = (4.66 x 14.8) + (17.84 x 2)
404(1) = 11,763.08 kgs. 405(1)b3 = 104.65 cu.m.

ITEM 404 RCBC


Page 15 of 45
C.O.#1 / AS - STAKE
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

COMPUTATION FOR ITEM 103(3) AND ITEM 103(6)a (RCPC)

1.25

ITEM 103-3

0.10 1.00

ITEM 103(3) - FOUNDATION FILL (Lined Canal)

STATION LIMIT LOCATION LENGTH


93 + 058.00 93 + 198.00 RL 140.00
93 + 728.00 93 + 915.00 RL 187.00
94 + 545.00 94 + 740.00 RL 195.00
92 + 984.00 93 + 058.00 LL 74.00
93 + 069.00 93 + 245.00 LL 176.00
93 + 257.00 93 + 480.00 LL 223.00
93 + 680.00 93 + 942.00 LL 262.00
93 + 927.00 94 + 070.00 LL 143.00
94 + 168.00 94 + 228.00 LL 60.00
94 + 232.00 94 + 537.00 LL 305.00
TOTAL = 2,070.00

Volume Lc = Length x Width x Thickness


= 2070 x 1.0 x 0.10
Volume Lc = 207.00 cu.m.

ITEM 103(6)a - PIPE CULVERT AND DRAIN EXCAVATION (Lined Canal)

Volume Lc = Length x Width x Height


= 2070 x 1.0 x 1.25
Volume Lc = 2,587.50 cu.m.
C.O.#1 / AS - STAKE
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

ITEM 404 - REINFORCING STEEL


1.00 m.

0.15 m. 0.15 m.
Grouted Riprap
0.50 m.
0.30 m.
SHOULDER
0.20 m.
0.15 thk Class B Concrete with
10mm dia. Vert. & Hor. Bars Spaced 1.15 m.
@ 0.20m. O.C. Eachway

0.15 m.
0.10 m. thk. Foundation Fill 0.10 m.

DETAIL OF LINED CANAL

Lined Canal Length = 1,765.00 l.m.


Horizontal Bars (10 mm dia.) = (length x 15.00 pcs. ) x 0.616 kg./m.
Horizontal Bars (10 mm dia.) = (1765 m. x 15.00 pcs.) x 0.616 kg./m.
Horizontal Bars (10 mm dia.) = 16,308.60 kg.

Length of Bars = 3.00 m.


Vertical Bars (10mm dia.) Spaced 0.20m = ((length of lined canal/0.20) +1 ) x length of bars x 0.616 kg./m.
Vertical Bars (10mm dia.) Spaced 0.20m = ( (1765m. / 0.20 ) + 1) x 3.00 m. x 0.616 kg./m.
Vertical Bars (10mm dia.) Spaced 0.20m = 16,310.45 kg.

Staggered Headwall
Horizontal Bars = 1.00 pc - 10mm dia x 0.50 m. = 0.50 m.
Vertical Bars = 3.00 pc - 10mm dia x 0.30 m. = 0.90 m.
1.40 m.
No. Headwall = 1,765.00 pcs.
404( staggered headwall) = (1765pcs. X 1.4 m. x 0.616 kg./m.)
Total length of bars for headwall = 1,522.14 kg

Total 404 Lined Canal = 34,141.18 kg


SAY = 34,141.00 kg
C.O.#1 / AS - STAKE
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

ITEM 405(2)a - STRUCTURAL CONCRETE "CLASS B"


Lined Canal
A1 = (0.15 x 1.15) x 2 V LC = ALC x Length of Lined Canal
= 0.345 sq.m. V LC = 0.45 x 1765
A2 = 0.15 x 0.70 V LC = 794.25 cu.m.
= 0.105 sq.m.
ALC = A1 + A2
= 0.45 sq.m.

Stagered Headwall V Total = VLC + VHW


V HW = (0.15 x 0.30 x 0.50) x No. of Headwall V Total = 794.25 + 39.71
V HW = (0.15 x 0.30 x 0.50) x 1765 V Total = 833.96 cu.m.
V HW = 39.71 cu.m. SAY = 834.00 cu.m.

ITEM 505(2)a - GROUTED RIPRAP, CLASS "A"

Total Quantity = LENGTH OF LINED CANAL x 0.20 x 0.50


Total Quantity = 1765.00 m. x 0.20 m. x 0.50 m.
Total Quantity = 176.50 cu.m.
say = 176.00 cu.m.
COMPUTATION FOR SLOPE PROTECTION
COMPUTATION ITEM 404(1)a - REINFORCING STEEL, GRADE 40
BAR UNIT REINFORCING STEEL
TOTAL
BAR BENDING DIAGRAM DETAILS SPACING QUANTITY LENGTH (m.) WEIGHT
MARK DIA. (mm.) LENGTH (m.) GRADE 40 (Kg.) GRADE 60 (Kg.)
(mm.) (pcs.) (Kg./m.)

200

1 12mm Ø 200 400 2.90 1160.00 0.888 1,030.08

2300

400

VERTICAL BARS

200

2 16mm Ø 200 400 2.90 1160.00 1.579 1,831.64

2300

400

VERTICAL BARS

2,050

3 16mm Ø 200 400 2.35 940.00 1.579 1,484.26


150 150

TOP BARS

2,050

150 150 3 12mm Ø 200 400 2.35 940.00 0.888 834.72

BOTTOM BARS

4 12mm Ø 250 18 80.00 1440.00 0.888 1,278.72

80,000.00
HORIZONTAL BARS

5 12mm Ø 250 18 80.00 1440.00 0.888 1,278.72

80,000.00
TIE BARS
. 7,738.14 -

COMPUTATION FOR ITEM 405(1)a3 - Structural Concrete

0.25

12 mm dia. Horizontal Bar @ 250 o.c.

12 mm dia. Horizontal Bar @ 200 o.c. 16 mm dia. Vertical Bar @ 200 o.c.

12 mm dia. Bar @ 250 o.c.

16 mm dia. Top Bar @ 200 o.c.

0.40 1.50

0.25

2.15
12 mm dia. Bot. Bar @ 200 o.c.

STATION LANE Length


From To
STA. 092+844.00 - STA. 092+924.00 LS 80.00

TOTAL 80.00 l.m.

Volume 405(1)a = Area x length


Volume 405(1)a = { (2.15 x 0.25 ) + ( 0.25 x 2.15) } x 80.00
Volume 405(1)a = 86.00 cu.m.
Say = 86.00 cu.m.
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

100(1) - CLEARING AND GRUBBING 105(1)a - SUBGRADE PREAPARATION


LENGTH DISTANCE AREA LENGTH DISTANCE AREA
STATION REMARKS
LEFT RIGHT m LEFT RIGHT LEFT RIGHT m LEFT RIGHT
092+744.00 1.66 BEGINNING OF 1st
16.00 16.00 SECTION
092+760.00 2.93
20.00 20.00
092+780.00 2.51
20.00 20.00
092+800.00 2.81
20.00 20.00
092+820.00 2.62
20.00 20.00
092+840.00 11.78 5.03
20.00 227.40 20.00 147.50
092+860.00 10.96 9.72
20.00 243.90 20.00 194.40
092+880.00 13.43 9.72
20.00 274.50 20.00 194.40
092+900.00 14.02 9.72
20.00 329.00 20.00 184.20
092+920.00 18.88 8.70
20.00 351.40 20.00 163.90
092+940.00 16.26 7.69
20.00 196.70 352.10 20.00 160.00
092+960.00 19.67 18.95 8.52 8.31
20.00 350.70 313.00 20.00 167.00 180.30
092+980.00 15.40 12.35 8.18 9.72
20.00 320.70 255.30 20.00 169.50 186.00
093+000.00 16.67 13.18 8.77 8.88
20.00 316.30 265.20 20.00 184.90 133.80
093+020.00 14.96 13.34 9.72 4.50
20.00 281.30 279.50 20.00 141.80 85.10
093+040.00 13.17 14.61 4.46 4.01
20.00 276.00 284.60 20.00 70.40 76.30
093+060.00 14.43 13.85 2.58 3.62
20.00 296.50 271.90 20.00 48.50 70.00
093+080.00 15.22 13.34 2.27 3.38
20.00 265.70 276.60 20.00 54.10 131.00
093+100.00 11.35 14.32 3.14 9.72
20.00 235.70 288.30 20.00 118.40 184.20
093+120.00 12.22 14.51 8.70 8.70
20.00 306.00 288.60 20.00 174.00 174.00
093+140.00 18.38 14.35 8.70 8.70
20.00 347.70 288.80 20.00 174.00 151.40
093+160.00 16.39 14.53 8.70 6.44
20.00 299.50 274.10 20.00 174.00 106.80
093+180.00 13.56 12.88 8.70 4.24
20.00 261.00 256.60 20.00 174.10 80.20
093+200.00 12.54 12.78 8.71 3.78
20.00 239.90 271.10 20.00 170.10 64.80
093+220.00 11.45 14.33 8.30 2.70
20.00 247.10 305.80 20.00 108.90 51.90
093+240.00 13.26 16.25 2.59 2.49
20.00 248.00 296.30 20.00 62.60 122.10
093+260.00 11.54 13.38 3.67 9.72
20.00 256.20 268.90 20.00 120.90 194.40
093+280.00 14.08 13.51 8.42 9.72
20.00 285.30 267.40 20.00 171.20 182.70
093+300.00 14.45 13.23 8.70 8.55
20.00 287.60 276.20 20.00 174.00 182.70
093+320.00 14.31 14.39 8.70 9.72
20.00 298.60 288.90 20.00 174.00 164.90
093+340.00 15.55 14.50 8.70 6.77
20.00 321.10 258.00 20.00 174.00 164.90
093+360.00 16.56 11.30 8.70 9.72
20.00 314.60 278.20 20.00 174.00 118.30
093+380.00 14.90 16.52 8.70 2.11
SUB -TOTAL 6,252.20 7,631.60 2,980.40 3,850.20

SUB -TOTAL 100(1) = 6252.2 + 7631.6 = 13,883.80


SUB -TOTAL 105(1)a = 2980.4 + 3850.2 = 6,830.60
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

100(1) - CLEARING AND GRUBBING 105(1)a - SUBGRADE PREAPARATION


LENGTH DISTANCE AREA LENGTH DISTANCE AREA
STATION REMARKS
LEFT RIGHT m LEFT RIGHT LEFT RIGHT m LEFT RIGHT
093+380.00 14.90 16.52 8.70 2.11
20.00 299.30 297.40 20.00 174.00 58.50
093+400.00 15.03 13.22 8.70 3.74
20.00 310.00 279.20 20.00 173.00 67.65
093+420.00 15.97 14.70 8.60 3.03
20.00 312.70 281.60 20.00 183.20 120.55
093+440.00 15.30 13.46 9.72 9.03
20.00 290.80 345.70 20.00 194.40 127.50
093+460.00 13.78 21.11 9.72 3.72
20.00 283.00 428.10 20.00 194.40 122.80
093+480.00 14.52 21.70 9.72 8.56
20.00 304.80 351.40 20.00 147.60 124.20
093+500.00 15.96 13.44 5.04 3.86
20.00 305.90 291.70 20.00 83.30 61.10
093+520.00 14.63 15.73 3.29 2.25
20.00 291.80 308.30 20.00 54.80 50.70
093+540.00 14.55 15.10 2.19 2.82
20.00 283.10 286.80 20.00 47.10 61.70
093+560.00 13.76 13.58 2.52 3.35
20.00 271.90 277.40 20.00 53.90 72.80
093+580.00 13.43 14.16 2.87 3.93
20.00 277.30 280.60 20.00 56.10 86.60
093+600.00 14.30 13.90 2.74 4.73
20.00 282.30 283.50 20.00 54.60 83.80
093+620.00 13.93 14.45 2.72 3.65
20.00 292.80 299.00 20.00 53.90 66.40
093+640.00 15.35 15.45 2.67 2.99
20.00 298.40 305.30 20.00 75.40 60.40
093+660.00 14.49 15.08 4.87 3.05
20.00 258.90 282.60 20.00 138.90 86.30
093+680.00 11.40 13.18 9.02 5.58
20.00 247.40 249.50 20.00 167.60 153.00
093+700.00 13.34 11.77 7.74 9.72
20.00 289.50 282.10 20.00 164.40 194.40
093+720.00 15.61 16.44 8.70 9.72
20.00 329.40 367.90 20.00 169.70 194.40
093+740.00 17.33 20.35 8.27 9.72
20.00 350.60 357.70 20.00 169.70 184.20
093+760.00 17.73 15.42 8.70 8.70
20.00 346.40 310.10 20.00 174.00 174.00
093+780.00 16.91 15.59 8.70 8.70
20.00 319.60 317.70 20.00 174.00 174.00
093+800.00 15.05 16.18 8.70 8.70
20.00 293.30 318.10 20.00 184.20 174.00
093+820.00 14.28 15.63 9.72 8.70
20.00 278.20 287.30 20.00 194.40 174.00
093+840.00 13.54 13.10 9.72 8.70
20.00 266.00 244.40 20.00 194.40 177.00
093+860.00 13.06 11.34 9.72 9.00
20.00 283.60 262.40 20.00 194.43 107.80
093+880.00 15.30 14.90 9.72 1.78
20.00 307.10 294.50 20.00 124.53 40.90
093+900.00 15.41 14.55 2.73 2.31
20.00 311.60 301.60 20.00 53.40 111.60
093+920.00 15.75 15.61 2.61 8.85
20.00 316.90 297.20 20.00 45.60 185.70
093+940.00 15.94 14.11 1.95 9.72
20.00 284.50 298.40 20.00 46.60 194.40
093+960.00 12.51 15.73 2.71 9.72
20.00 250.70 315.60 20.00 56.50 194.40
093+980.00 12.56 15.83 2.94 9.72
20.00 256.30 303.40 20.00 126.60 194.40
094+000.00 13.07 14.51 9.72 9.72
20.00 298.60 291.10 20.00 184.20 194.40
094+020.00 16.79 14.60 8.70 9.72
SUB -TOTAL 9,392.70 9,697.60 4,108.86 4,073.60

SUB -TOTAL 100(1) = 9392.7 + 9697.6 = 19,090.30


SUB -TOTAL 105(1)a = 4108.86 + 4073.6 = 8,182.46

094+020.00 16.79 14.60 8.70 9.72


20.00 356.30 298.80 20.00 174.00 194.40
094+040.00 18.84 15.28 8.70 9.72
20.00 387.40 284.00 20.00 174.00 194.40
094+060.00 19.90 13.12 8.70 9.72
20.00 389.10 191.40 20.00 174.00 138.60
094+080.00 19.01 6.02 8.70 4.14
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

100(1) - CLEARING AND GRUBBING 105(1)a - SUBGRADE PREAPARATION


20.00 256.10 117.90 20.00 130.50 85.00
094+100.00 6.60 5.77 4.35 4.36
20.00 135.40 120.60 20.00 87.00 84.70
094+120.00 6.94 6.29 4.35 4.11
20.00 184.20 124.00 20.00 87.00 63.60
094+140.00 11.48 6.11 4.35 2.25
20.00 185.80 124.20 20.00 87.00 45.80
094+160.00 7.10 6.31 4.35 2.33
20.00 231.30 192.00 20.00 140.70 54.60
094+180.00 16.03 12.89 9.72 3.13
20.00 293.70 245.20 20.00 194.40 74.60
094+200.00 13.34 11.63 9.72 4.33
20.00 257.70 255.70 20.00 121.00 63.50
094+220.00 12.43 13.94 2.38 2.02
20.00 263.60 278.00 20.00 77.70 77.90
094+240.00 13.93 13.86 5.39 5.77
20.00 250.50 270.10 20.00 115.90 106.80
094+260.00 11.12 13.15 6.20 4.91
20.00 246.10 241.20 20.00 144.80 94.00
094+280.00 13.49 10.97 8.28 4.49
20.00 277.10 270.40 20.00 172.50 126.20
094+300.00 14.22 16.07 8.97 8.13
20.00 280.60 20.00 184.40
094+320.00 13.84 9.47
20.00 270.50 20.00 191.90
094+340.00 13.21 9.72
20.00 267.50 20.00 175.30
094+360.00 13.54 7.81
20.00 271.00 20.00 169.10
094+380.00 13.56 9.10
20.00 280.20 20.00 188.20
094+400.00 14.46 9.72
SUB -TOTAL 5,084.10 3,013.50 2,789.40 1,404.10

SUB -TOTAL 100(1) = 5084.1 + 3013.5 = 8,097.60


SUB -TOTAL 105(1)a = 2789.4 + 1404.1 = 4,193.50
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

100(1) - CLEARING AND GRUBBING 105(1)a - SUBGRADE PREAPARATION


LENGTH DISTANCE AREA LENGTH DISTANCE AREA
STATION REMARKS
LEFT RIGHT m LEFT RIGHT LEFT RIGHT m LEFT RIGHT
094+400.00 14.46 9.72 -
20.00 294.70 20.00 194.40
094+420.00 15.01 13.30 9.72 9.72
20.00 300.40 274.20 20.00 194.40 194.40
094+440.00 15.03 14.12 9.72 9.72
20.00 292.40 279.70 20.00 176.60 175.50
094+460.00 14.21 13.85 7.94 7.83
20.00 256.40 247.20 20.00 100.40 118.80
094+480.00 11.43 10.87 2.10 4.05
20.00 254.50 226.50 20.00 78.20 72.50
094+500.00 14.02 11.78 5.72 3.20
20.00 292.50 250.60 20.00 134.80 52.00
094+520.00 15.23 13.28 7.76 2.00
20.00 277.70 258.50 20.00 108.10 32.60
094+540.00 12.54 12.57 3.05 1.26
20.00 256.90 244.40 20.00 109.30 38.20
094+560.00 13.15 11.87 7.88 2.56
20.00 277.90 247.80 20.00 176.00 122.80
094+580.00 14.64 12.91 9.72 9.72
20.00 295.60 286.20 20.00 194.40 194.40
094+600.00 14.92 15.71 9.72 9.72
20.00 304.60 318.50 20.00 194.40 194.40
094+620.00 15.54 16.14 9.72 9.72
20.00 313.20 326.40 20.00 194.40 194.40
094+640.00 15.78 16.50 9.72 9.72
20.00 314.00 327.30 20.00 194.40 194.40
094+660.00 15.62 16.23 9.72 9.72
20.00 311.60 314.90 20.00 194.40 194.40
094+680.00 15.54 15.26 9.72 9.72
20.00 308.80 304.70 20.00 194.40 186.00
094+700.00 15.34 15.21 9.72 8.88
20.00 301.30 301.60 20.00 194.40 186.00
094+720.00 14.79 14.95 9.72 9.72
20.00 297.50 288.70 20.00 194.40 194.40
094+740.00 14.96 13.92 9.72 9.72
20.00 291.80 20.00 194.40 194.40
094+760.00 15.26 9.72 9.72
20.00 304.70 20.00 194.40 186.00
094+780.00 15.21 9.72 8.88
20.00 301.60 20.00 194.40 186.00
094+800.00 14.95 9.72 9.72
20.00 288.70 20.00 194.40 194.40
094+815.00 13.92 9.72 9.72
5.00 34.80 5.00 24.30 24.30
094+820.00
20.00 20.00
094+840.00
17.00 17.00
094+857.00

094+880.00
20.00 20.00
094+900.00
20.00 20.00
094+917.00 14.11 1.59 2.54
3.00 43.40 3.00 7.19 7.77
094+920.00 14.82 3.20 2.64
20.00 284.10 20.00 61.60 47.00
094+940.00 13.59 2.96 2.06
20.00 277.00 20.00 45.50 46.00
094+960.00 14.11 1.59 2.54
20.00 289.30 20.00 47.90 51.80
094+980.00 14.82 3.20 2.64
18.00 260.37 18.00 43.11 46.62
094+998.00 15.12 14.11 1.59 2.54
22.00 320.76 318.23 22.00 52.69 56.98
095+020.00 14.04 14.82 3.20 2.64
20.00 272.60 284.10 20.00 61.60 47.00
095+040.00 13.22 13.59 2.96 2.06
SUB -TOTAL 5,543.36 7,475.30 3,948.89 3,433.47

SUB -TOTAL 100(1) = 5543.36 + 7475.3 = 13,018.66


SUB -TOTAL 105(1)a = 3948.89 + 3433.47 = 7,382.36
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

100(1) - CLEARING AND GRUBBING 105(1)a - SUBGRADE PREAPARATION


LENGTH DISTANCE AREA LENGTH DISTANCE AREA
STATION REMARKS
LEFT RIGHT m LEFT RIGHT LEFT RIGHT m LEFT RIGHT
095+040.00 13.22 13.59 2.96 2.06
20.00 282.80 256.40 20.00 62.00 103.70
095+060.00 15.06 12.05 3.24 8.31
20.00 281.00 271.30 20.00 71.60 166.80
095+080.00 13.04 15.08 3.92 8.37
20.00 282.60 284.80 20.00 101.30 158.40
095+100.00 15.22 13.40 6.21 7.47
20.00 309.20 283.80 20.00 156.30 155.00
095+120.00 15.70 14.98 9.42 8.03
20.00 311.90 300.70 20.00 189.70 167.90
095+140.00 15.49 15.09 9.55 8.76
20.00 310.40 302.50 20.00 182.40 156.00
095+160.00 15.55 15.16 8.69 6.84
20.00 308.90 283.00 20.00 171.30 165.60
095+180.00 15.34 13.14 8.44 9.72
20.00 304.40 282.00 20.00 176.80 194.40
095+200.00 15.10 15.06 9.24 9.72
5.00 75.58 70.35 5.00 46.20 48.60
095+205.00 15.13 13.08 9.24 9.72
20.00 284.70 282.10 20.00 176.80 194.40
095+225.00 13.34 15.13 8.44 9.72
20.00 284.90 281.80 20.00 176.80 194.40
095+245.00 15.15 13.05 9.24 9.72
SUB -TOTAL 3,036.38 2,898.75 1,511.20 1,705.20

SUB -TOTAL 100(1) = 3036.38 + 2898.75 = 5,935.13


SUB -TOTAL 105(1)a = 1511.2 + 1705.2 = 3,216.40

TOTAL 100(1) = 13883.8 + 8097.6 + 13018.66 + 5935.13 + 19090.3 = 60,025.49


TOTAL 105(1)a = 6830.6 + 4193.5 + 7382.36 + 3216.4 + 8182.46 = 29,805.32

ITEM 100(1) - CLEARING AND GRUBBING

100(1) = 60025.49/10,000
= 6.00
say = 6.00 ha. 6

ITEM 105(1)a - SUBGRADE PREPARATION, COMMON MATERIAL

105(1)a = 29,805.32 29805.45


say = 29,805.00 sq.m.
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

COMPUTATION FOR ITEM 102(2), ITEM 104(1)a1 AND ITEM 104(1)b1


AREA (LEFT) DISTANCE VOLUME (LEFT) AREA (RIGHT) DISTANCE VOLUME (RIGHT)
STATION REMARKS
CUT FILL m CUT FILL CUT FILL m CUT FILL
092+744.00 BEGINNING OF 1st
16.00 0.00 0.00 16.00 0.00 0.00 SECTION
092+760.00
20.00 0.00 0.00 20.00 0.00 0.00
092+780.00
20.00 0.00 0.00 20.00 0.00 0.00
092+800.00
20.00 0.00 0.00 20.00 0.00 0.00
092+820.00
20.00 0.00 0.00 20.00 0.00 0.00
092+840.00
20.00 0.00 0.00 20.00 322.80 0.00
092+860.00 32.28 -
20.00 0.00 0.00 20.00 640.70 13.60
092+880.00 31.79 1.36
20.00 0.00 0.00 20.00 686.30 13.70
092+900.00 36.84 0.01
20.00 0.00 0.00 20.00 708.90 0.20
092+920.00 34.05 0.01
20.00 0.00 0.00 20.00 685.50 1.00
092+940.00 34.50 0.09
20.00 353.70 1.30 20.00 704.80 2.70
092+960.00 35.37 0.13 35.98 0.18
20.00 431.00 2.40 20.00 721.50 1.80
092+980.00 7.73 0.11 36.17 -
20.00 132.00 2.00 20.00 695.10 3.80
093+000.00 5.47 0.09 33.34 0.38
20.00 106.30 0.90 20.00 688.80 33.20
093+020.00 5.16 - 35.54 2.94
20.00 72.30 17.00 20.00 367.10 168.60
093+040.00 2.07 1.70 1.17 13.92
20.00 29.30 175.70 20.00 22.40 292.40
093+060.00 0.86 15.87 1.07 15.32
20.00 14.00 337.80 20.00 21.84 296.10
093+080.00 0.54 17.91 1.11 14.29
20.00 103.70 233.10 20.00 367.54 142.90
093+100.00 9.83 5.40 35.64 -
20.00 162.20 54.00 20.00 714.90 0.00
093+120.00 6.39 - 35.85 -
20.00 106.20 0.00 20.00 699.70 0.00
093+140.00 4.23 - 34.12 -
20.00 76.50 0.00 20.00 688.00 2.60
093+160.00 3.42 - 34.68 0.26
20.00 93.30 0.00 20.00 362.60 56.00
093+180.00 5.91 - 1.58 5.34
20.00 132.80 0.00 20.00 29.50 168.00
093+200.00 7.37 - 1.37 11.46
20.00 116.40 0.00 20.00 24.60 275.50
093+220.00 4.27 - 1.09 16.09
20.00 51.40 120.60 20.00 20.50 498.60
093+240.00 0.87 12.06 0.96 33.77
20.00 20.60 150.20 20.00 377.20 337.70
093+260.00 1.19 2.96 36.76 -
20.00 64.80 30.40 20.00 749.30 0.00
093+280.00 5.29 0.08 38.17 -
20.00 132.40 0.80 20.00 418.50 7.80
093+300.00 7.95 - 3.68 0.78
20.00 155.90 0.00 20.00 57.10 158.60
093+320.00 7.64 - 2.03 15.08
20.00 135.30 0.00 20.00 37.00 245.30
093+340.00 5.89 - 1.67 9.45
20.00 119.20 0.00 20.00 52.10 94.50
093+360.00 6.03 - 3.54 -
20.00 114.60 0.00 20.00 42.60 223.20
093+380.00 5.43 - 0.72 22.32
SUB -TOTAL 2,723.90 1,126.20 10,906.88 3,037.80

SUB -TOTAL CUT = 2723.9 + 10906.88 = 13,630.78


SUB -TOTAL FILL = 1126.2 + 3037.8 = 4,164.00

093+380.00 5.43 - 0.72 22.32


20.00 104.90 0.00 20.00 16.60 333.80
093+400.00 5.06 - 0.94 11.06
20.00 94.90 0.60 20.00 16.90 263.60
093+420.00 4.43 0.06 0.75 15.30
20.00 91.50 0.60 20.00 55.20 153.20
093+440.00 4.72 - 4.77 0.02
20.00 99.70 0.00 20.00 111.90 0.20
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

COMPUTATION FOR ITEM 102(2), ITEM 104(1)a1 AND ITEM 104(1)b1


AREA (LEFT) DISTANCE VOLUME (LEFT) AREA (RIGHT) DISTANCE VOLUME (RIGHT)
STATION REMARKS
CUT FILL m CUT FILL CUT FILL m CUT FILL
093+460.00 5.25 - 6.42 -
20.00 105.70 0.00 20.00 143.50 0.50
093+480.00 5.32 - 7.93 0.05
20.00 69.60 75.90 20.00 91.30 142.50
093+500.00 1.64 7.59 1.20 14.20
20.00 27.80 194.80 20.00 20.80 371.40
093+520.00 1.14 11.89 0.88 22.94
20.00 19.70 228.20 20.00 19.90 419.40
093+540.00 0.83 10.93 1.11 19.00
20.00 17.50 200.90 20.00 22.80 314.50
093+560.00 0.92 9.16 1.17 12.45
20.00 20.10 173.20 20.00 30.60 238.70
093+580.00 1.09 8.16 1.89 11.42
20.00 21.80 174.60 20.00 37.50 223.70
093+600.00 1.09 9.30 1.86 10.95
20.00 21.10 178.00 20.00 32.60 243.90
093+620.00 1.02 8.50 1.40 13.44
20.00 20.60 208.40 20.00 23.60 345.80
093+640.00 1.04 12.34 0.96 21.14
20.00 24.50 219.60 20.00 22.20 390.20
093+660.00 1.41 9.62 1.26 17.88
20.00 42.30 97.20 20.00 32.00 228.30
093+680.00 2.82 0.10 1.94 4.95
20.00 82.10 1.00 20.00 376.30 49.50
093+700.00 5.39 - 35.69 -
20.00 108.30 0.00 20.00 756.00 0.00
093+720.00 5.44 - 39.91 -
20.00 118.20 0.20 20.00 767.90 0.00
093+740.00 6.38 0.02 36.88 -
20.00 119.30 0.20 20.00 720.30 0.00
093+760.00 5.55 - 35.15 -
20.00 120.80 0.00 20.00 737.50 0.00
093+780.00 6.53 - 38.60 - END OF 1st SECTION
20.00 115.40 0.00 20.00 760.70 0.00
093+800.00 5.01 - 37.47 -
20.00 96.60 0.00 20.00 759.20 0.00
093+820.00 4.65 - 38.45 -
20.00 108.90 0.00 20.00 742.80 0.00
093+840.00 6.24 - 35.83 -
20.00 97.80 0.00 20.00 393.40 0.80
093+860.00 3.54 - 3.51 0.08
20.00 73.50 0.00 20.00 39.30 204.90
093+880.00 3.81 - 0.42 20.41
20.00 44.00 27.30 20.00 10.80 404.30
093+900.00 0.59 2.73 0.66 20.02
20.00 15.30 115.30 20.00 32.70 203.00
093+920.00 0.94 8.80 2.61 0.28
20.00 14.10 180.80 20.00 372.70 2.80
093+940.00 0.47 9.28 34.66 -
20.00 12.30 168.50 20.00 702.10 0.00
093+960.00 0.76 7.57 35.55 -
20.00 14.20 162.80 20.00 706.40 0.00
093+980.00 0.66 8.71 35.09 -
20.00 54.00 87.10 20.00 704.70 0.00
094+000.00 4.74 - 35.38 -
20.00 100.40 0.00 20.00 686.80 0.00
094+020.00 5.30 - 33.30 -
20.00 123.60 0.00 20.00 717.60 0.00
094+040.00 7.06 - 38.46 -
SUB -TOTAL 2,200.50 2,495.20 10,664.60 4,535.00

SUB -TOTAL CUT = 2200.5 + 10664.6 = 12,865.10


SUB -TOTAL FILL = 2495.2 + 4535 = 7,030.20
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

COMPUTATION FOR ITEM 102(2), ITEM 104(1)a1 AND ITEM 104(1)b1


AREA (LEFT) DISTANCE VOLUME (LEFT) AREA (RIGHT) DISTANCE VOLUME (RIGHT)
STATION REMARKS
CUT FILL m CUT FILL CUT FILL m CUT FILL
094+040.00 7.06 - 38.46 -
20.00 128.10 0.00 20.00 738.20 0.00
094+060.00 5.75 - 35.36 -
20.00 144.60 0.00 20.00 364.10 2.30
094+080.00 8.71 - 1.05 0.23
20.00 125.50 0.00 20.00 19.40 3.00
094+100.00 3.84 - 0.89 0.07
20.00 91.70 0.00 20.00 18.00 2.80
094+120.00 5.33 - 0.91 0.21
20.00 112.40 0.00 20.00 14.20 2.30
094+140.00 5.91 - 0.51 0.02
20.00 117.00 0.00 20.00 10.40 9.90
094+160.00 5.79 - 0.53 0.97
20.00 110.70 0.00 20.00 12.90 155.10
094+180.00 5.28 0.76 14.54
20.00 113.00 0.00 20.00 18.90 215.40
094+200.00 6.02 1.13 7.00
20.00 70.80 88.00 20.00 17.80 215.40
094+220.00 1.06 8.80 0.65 14.54
20.00 342.40 98.70 20.00 22.10 245.40
094+240.00 33.18 1.07 1.56 10.00
20.00 650.30 18.70 20.00 30.20 195.10
094+260.00 31.85 0.80 1.46 9.51
20.00 675.40 9.20 20.00 24.60 98.00
094+280.00 35.69 0.12 1.00 0.29
20.00 734.10 1.70 20.00 23.00 3.10
094+300.00 37.72 0.05 1.30 0.02
20.00 735.40 0.60 20.00 13.00 0.20
094+320.00 35.82 0.01
20.00 699.50 0.10 20.00 0.00 0.00
094+340.00 34.13 -
20.00 679.30 2.00 20.00 0.00 0.00
094+360.00 33.80 0.20
20.00 672.70 2.20 20.00 0.00 0.00
094+380.00 33.47 0.02
20.00 588.80 0.20 20.00 0.00 0.00
094+400.00 25.41 -
20.00 495.40 0.00 20.00 47.20 0.00
094+420.00 24.13 - 4.72 -
20.00 477.80 0.00 20.00 124.20 0.00
094+440.00 23.65 - 7.70 -
20.00 344.00 1.70 20.00 126.10 1.00
094+460.00 10.75 0.17 4.91 0.10
20.00 113.50 33.40 20.00 55.90 5.00
094+480.00 0.60 3.17 0.68 0.40
20.00 37.60 45.50 20.00 13.30 15.20
094+500.00 3.16 1.38 0.65 1.12
20.00 73.20 16.90 20.00 10.20 139.50
094+520.00 4.16 0.31 0.37 12.83
20.00 51.30 106.00 20.00 8.20 236.80
094+540.00 0.97 10.29 0.45 10.85
20.00 38.40 104.40 20.00 10.70 130.70
094+560.00 2.87 0.15 0.62 2.22
20.00 62.50 1.50 20.00 360.70 22.20
094+580.00 3.38 35.45 -
20.00 85.00 0.00 20.00 708.10 0.00
094+600.00 5.12 35.36 -
20.00 114.30 0.00 20.00 750.30 0.00
094+620.00 6.31 39.67 -
20.00 134.10 0.00 20.00 752.80 0.00
094+640.00 7.10 35.61 -
20.00 145.00 0.00 20.00 754.60 0.00
094+660.00 7.40 39.85 -
20.00 134.10 0.00 20.00 736.20 0.00
094+680.00 6.01 33.77 -
20.00 155.40 0.00 20.00 688.40 0.50
094+700.00 9.53 35.07 0.05
SUB -TOTAL 9,253.30 530.80 6,473.70 1,698.90

SUB -TOTAL CUT = 9253.3 + 6473.7 = 15,727.00


SUB -TOTAL FILL = 530.8 + 1698.9 = 2,229.70

094+700.00 9.53 - 35.07 0.05


20.00 251.20 0.00 20.00 447.90 0.60
094+720.00 15.59 - 9.72 0.01
19.00 254.13 0.00 19.00 165.78 0.10
094+739.00 11.16 - 7.73
21.00 117.18 0.00 21.00 81.17 0.00
094+760.00
20.00 0.00 0.00 20.00 0.00 0.00
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

COMPUTATION FOR ITEM 102(2), ITEM 104(1)a1 AND ITEM 104(1)b1


AREA (LEFT) DISTANCE VOLUME (LEFT) AREA (RIGHT) DISTANCE VOLUME (RIGHT)
STATION REMARKS
CUT FILL m CUT FILL CUT FILL m CUT FILL
094+780.00
20.00 0.00 0.00 20.00 0.00 0.00
094+800.00
20.00 0.00 0.00 20.00 0.00 0.00
094+820.00
20.00 20.00
094+840.00
17.00 17.00
094+857.00

094+880.00
20.00 20.00
094+900.00
20.00 20.00 63.40
094+920.00 6.34
20.00 20.00 264.60
094+940.00 20.12
20.00 20.00 401.90
094+960.00 20.07
20.00 20.00 429.00
094+980.00 22.83
18.00 18.00 386.46
094+998.00 0.44 17.77 0.98 20.11
22.00 15.62 349.69 22.00 19.47 394.13
095+020.00 0.98 14.02 0.79 15.72
20.00 20.60 251.80 20.00 13.00 284.70
095+040.00 1.08 11.16 0.51 12.75
20.00 21.10 211.10 20.00 11.30 241.10
095+060.00 1.03 9.95 0.62 11.36
20.00 28.70 107.90 20.00 13.00 133.30
095+080.00 1.84 0.84 0.68 1.97
20.00 41.80 11.20 20.00 30.80 26.60
095+100.00 2.34 0.28 2.40 0.69
20.00 61.20 2.80 20.00 54.10 8.00
095+120.00 3.78 - 3.01 0.11
20.00 75.30 0.00 20.00 49.40 2.30
095+140.00 3.75 - 1.93 0.12
20.00 376.10 0.70 20.00 42.70 2.40
095+160.00 33.86 0.07 2.34 0.12
20.00 674.50 0.80 20.00 64.60 1.20
095+180.00 33.59 0.01 4.12 -
20.00 692.00 0.70 20.00 95.70 0.00
095+200.00 35.61 0.06 5.45 -
5.00 178.05 0.30 5.00 27.25 0.00
095+205.00 35.61 0.06 5.45 -
SUB -TOTAL 2,807.48 936.99 1,116.17 2,639.79

SUB -TOTAL CUT = 2807.48 + 1116.17 = 3,923.65


SUB -TOTAL FILL = 936.99 + 2639.79 = 3,576.78

TOTAL CUT = 13630.78 + 12865.1 + 15727 + 3923.65 = 46,146.53


TOTAL FILL = 4164 + 7030.2 + 2229.7 + 3576.78 = 17,000.68
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

COMPUTATION FOR ITEM 102(2), ITEM 104(1)a1 AND ITEM 104(1)b1


AREA (LEFT) DISTANCE VOLUME (LEFT) AREA (RIGHT) DISTANCE VOLUME (RIGHT)
STATION REMARKS
CUT FILL m CUT FILL CUT FILL m CUT FILL

ITEM 104(1)a1 - EMBANKMENT FROM ROADWAY EXCAVATION

104(1)a1 = FILL
= 17,000.68 cu.m.
say = 17,000.00 cu.m.

ITEM 102(2) - SURPLUS COMMON EXCAVATION

102 (2) = CUT-FILL/0.8


= 24,895.68 cu.m.
say = 24,895.00 cu.m.
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

COMPUTATION FOR ITEM 200 - AGGREGATE SUB-BASE COURSE


AREA (m²) DISTANCE VOLUME (mᶾ)
STATION REMARKS
LEFT RIGHT m LEFT RIGHT
092+744.00
16.00 0.00 0.00
092+760.00
20.00 0.00 0.00
092+780.00
20.00 0.00 0.00
092+800.00
20.00 0.00 0.00
092+820.00
20.00 0.00 0.00
092+840.00
20.00 0.00 22.20
092+860.00 2.22
20.00 0.00 44.40
092+880.00 2.22
20.00 0.00 44.40
092+900.00 2.22
20.00 0.00 42.20
092+920.00 2.00
20.00 0.00 40.00
092+940.00 2.00
20.00 22.20 42.10
092+960.00 2.22 2.21
20.00 44.40 44.30
092+980.00 2.22 2.22
20.00 44.40 44.40
093+000.00 2.22 2.22
20.00 44.40 42.20
093+020.00 2.22 2.00
20.00 44.40 42.20
093+040.00 2.22 2.22
20.00 44.40 44.40
093+060.00 2.22 2.22
20.00 44.40 44.40
093+080.00 2.22 2.22
20.00 44.40 44.40
093+100.00 2.22 2.22
20.00 42.20 42.20
093+120.00 2.00 2.00
20.00 40.00 40.00
093+140.00 2.00 2.00
20.00 40.00 40.00
093+160.00 2.00 2.00
20.00 40.00 42.20
093+180.00 2.00 2.22
20.00 40.00 44.40
093+200.00 2.00 2.22
20.00 40.00 44.40
093+220.00 2.00 2.22
20.00 42.20 44.40
093+240.00 2.22 2.22
20.00 44.40 44.40
093+260.00 2.22 2.22
20.00 44.40 44.40
093+280.00 2.22 2.22
20.00 42.20 44.40
093+300.00 2.00 2.22
20.00 40.00 44.40
093+320.00 2.00 2.22
20.00 40.00 44.40
093+340.00 2.00 2.22
20.00 40.00 44.40
093+360.00 2.00 2.22
20.00 40.00 44.40
093+380.00 2.00 2.22
SUB -TOTAL 908.40 1,150.00

SUB -TOTAL = 908.4 + 1150 = 2,058.40


AREA (m²) DISTANCE VOLUME (mᶾ)
STATION REMARKS
LEFT RIGHT m LEFT RIGHT
093+380.00 2.00 2.22
20.00 40.00 44.40
093+400.00 2.00 2.22
20.00 42.20 44.40
093+420.00 2.22 2.22
20.00 44.40 44.40
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

COMPUTATION FOR ITEM 200 - AGGREGATE SUB-BASE COURSE


093+440.00 2.22 2.22
20.00 44.40 44.40
093+460.00 2.22 2.22
20.00 44.40 44.40
093+480.00 2.22 2.22
20.00 44.40 44.40
093+500.00 2.22 2.22
20.00 44.40 44.40
093+520.00 2.22 2.22
20.00 44.40 44.40
093+540.00 2.22 2.22
20.00 44.40 44.40
093+560.00 2.22 2.22
20.00 44.40 44.40
093+580.00 2.22 2.22
20.00 44.40 44.40
093+600.00 2.22 2.22
20.00 44.40 44.40
093+620.00 2.22 2.22
20.00 44.40 44.40
093+640.00 2.22 2.22
20.00 44.40 44.40
093+660.00 2.22 2.22
20.00 44.40 44.40
093+680.00 2.22 2.22
20.00 44.40 44.40
093+700.00 2.22 2.22
20.00 42.20 44.40
093+720.00 2.00 2.22
20.00 40.00 44.40
093+740.00 2.00 2.22
20.00 40.00 42.20
093+760.00 2.00 2.00
20.00 40.00 40.00
093+780.00 2.00 2.00
20.00 40.00 40.00
093+800.00 2.00 2.00
20.00 42.20 40.00
093+820.00 2.22 2.00
20.00 44.40 40.00
093+840.00 2.22 2.00
20.00 44.40 42.20
093+860.00 2.22 2.22
20.00 44.40 44.40
093+880.00 2.22 2.22
20.00 44.40 44.40
093+900.00 2.22 2.22
20.00 44.40 44.40
093+920.00 2.22 2.22
20.00 44.40 44.40
093+940.00 2.22 2.22
20.00 44.40 44.40
093+960.00 2.22 2.22
20.00 44.40 44.40
093+980.00 2.22 2.22
20.00 44.40 44.40
094+000.00 2.22 2.22
20.00 42.20 44.40
094+020.00 2.00 2.22
SUB -TOTAL 1,390.00 1,398.80

SUB -TOTAL = 1390 + 1398.8 = 2,788.80


AREA (m²) DISTANCE VOLUME (mᶾ)
STATION REMARKS
LEFT RIGHT m LEFT RIGHT
094+020.00 2.00 2.22
20.00 40.00 44.40
094+040.00 2.00 2.22
20.00 40.00 44.40
094+060.00 2.00 2.22
20.00 40.00 30.20
094+080.00 2.00 0.80
20.00 28.00 16.00
094+100.00 0.80 0.80
20.00 16.00 16.00
094+120.00 0.80 0.80
20.00 16.00 16.00
094+140.00 0.80 0.80
20.00 16.00 16.00
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

COMPUTATION FOR ITEM 200 - AGGREGATE SUB-BASE COURSE


094+160.00 0.80 0.80
20.00 30.20 30.20
094+180.00 2.22 2.22
20.00 44.40 44.40
094+200.00 2.22 2.22
20.00 44.40 44.40
094+220.00 2.22 2.22
20.00 44.40 44.40
094+240.00 2.22 2.22
20.00 44.40 44.40
094+260.00 2.22 2.22
20.00 44.40 44.40
094+280.00 2.22 2.22
26.00 57.72 57.72
094+306.00 2.22 2.22
14.00 31.08
094+320.00 2.22
20.00 44.40
094+340.00 2.22
20.00 44.40
094+360.00 2.22
20.00 44.40
094+380.00 2.22
20.00 44.40
094+400.00 2.22
20.00 44.40
094+420.00 2.22 2.22
20.00 44.40 44.40
094+440.00 2.22 2.22
20.00 44.40 44.40
094+460.00 2.22 2.22
20.00 44.40 44.40
094+480.00 2.22 2.22
20.00 44.40 44.40
094+500.00 2.22 2.22
20.00 44.40 44.40
094+520.00 2.22 2.22
20.00 44.40 44.40
094+540.00 2.22 2.22
20.00 44.40 44.40
094+560.00 2.22 2.22
20.00 44.40 44.40
094+580.00 2.22 2.22
20.00 44.40 44.40
094+600.00 2.22 2.22
20.00 44.40 44.40
094+620.00 2.22 2.22
20.00 44.40 44.40
094+640.00 2.22 2.22
20.00 44.40 44.40
094+660.00 2.22 2.22
SUB -TOTAL 1,291.80 1,025.72

SUB -TOTAL = 1291.8 + 1025.72 = 2,317.52


AREA (m²) DISTANCE VOLUME (mᶾ)
STATION REMARKS
LEFT RIGHT m LEFT RIGHT
094+660.00 2.22 2.22
20.00 44.40 44.40
094+680.00 2.22 2.22
20.00 44.40 44.40
094+700.00 2.22 2.22
20.00 44.40 44.40
094+720.00 2.22 2.22
19.00 42.18 42.18
094+739.00 2.22 2.22
21.00
094+760.00
20.00
094+780.00
20.00
094+800.00
20.00
094+820.00
20.00
094+840.00
17.00
094+857.00
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

COMPUTATION FOR ITEM 200 - AGGREGATE SUB-BASE COURSE


094+880.00
20.00
094+900.00
20.00
094+920.00
20.00
094+940.00
20.00
094+960.00
20.00
094+980.00
18.00
094+998.00 2.22 2.22
22.00 48.84 48.84
095+020.00 2.22 2.22
20.00 44.40 44.40
095+040.00 2.22 2.22
20.00 44.40 44.40
095+060.00 2.22 2.22
20.00 44.40 44.40
095+080.00 2.22 2.22
20.00 44.40 44.40
095+100.00 2.22 2.22
20.00 44.40 44.40
095+120.00 2.22 2.22
20.00 44.40 44.40
095+140.00 2.22 2.22
20.00 44.40 44.40
095+160.00 2.22 2.22
20.00 44.40 44.40
095+180.00 2.22 2.22
20.00 44.40 44.40
095+200.00 2.22 2.22
5.00 11.10 11.10
095+205.00 2.22 2.22
SUB -TOTAL 634.92 634.92

SUB -TOTAL = 634.92 + 634.92 = 1,269.84

TOTAL ITEM 200 = 2058.4 + 2788.8 + 2317.52 + 1269.84 = 8,434.56 mᶾ


C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

COMPUTATION FOR ITEM 311(1)e1 - PCCP (Unreinforced) 0.28m thick, 14 days


STATION LANE LENGTH
WIDTH AREA
FROM TO Left Side Right Side (m) (sq.m.)
(m)

STA. 92+844.00 STA. 93+617.00 B/S 773.00 6.70 5,179.10


STA. 93+621.00 STA. 94+077.00 R/S 456.00 3.35 1,527.60
STA. 93+621.00 STA. 94+306.00 L/S 685.00 3.35 2,294.75
STA. 94+155.00 STA. 94+306.00 R/S 151.00 3.35 505.85
STA. 94+421.00 STA. 94+814.00 B/S 393.00 6.70 2,633.10
STA. 94+913.00 STA. 95+117.00 B/S 204.00 6.70 1,366.80

STA. 92+958.00 STA. 93+617.00 B/S 659.00 6.70 4,415.30


STA. 93+621.00 STA. 94+096.00 B/S 475.00 6.70 3,182.50
STA. 94+096.00 STA. 94+166.00 R/S 70.00 3.35 234.50
STA. 94+166.00 STA. 95+001.00 B/S 835.00 6.70 5,594.50
STA. 95+007.00 STA. 95+116.00 B/S 109.00 6.70 730.30
TOTAL 4,810.00 27664.30 sq.m.

RCBC Widening

LEFT SIDE RIGHT SIDE


STA. DIST. WIDENING AREA STA. DIST. WIDENING AREA
STA. 93+602.65 0 STA. 93+601.35 0
15.00 9.75 16.30 10.6
STA. 93+617.65 1.3 STA. 93+617.65 1.3
STA. 93+622.35 0.9 STA. 93+622.35 0.9
10.20 4.59 15.00 6.75
STA. 93+632.55 0 STA. 93+637.35 0
14.34 sq.m. 17.35 sq.m.

TOTAL AREA = 27,695.99 sq.m.


C.O.#1 / AS - STAKE
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

Computation for ITEM 506- STONE MASONRY

ITEM 506 - Stone Masonry (for Slope Protection)


STATION L H (Left) Area (Left) Volume (Left) H (Right) Area (Right) Volume (Right)

STA. 93+038.00 2.7 2.59


STA. 93+058.00 20.00 2.7 2.59 51.80

STA. 94+913.00 3.7 4.66


STA. 94+920.00 7.00 3.7 4.66 32.62
STA. 94+940.00 20.00 3.7 4.66 93.20
STA. 94+960.00 20.00 3.8 4.90 95.60
STA. 94+980.00 20.00 3.7 4.66 95.60
STA. 94+998.00 18.00 3.7 4.66 83.88

STA. 93+536.00 - 3.50 4.20


STA. 93+540.00 4.00 - - 3.40 3.98 16.36
STA. 93+560.00 20.00 - - 3.40 3.98 79.60
STA. 93+580.00 20.00 3.70 4.66 3.30 3.76 77.40
STA. 93+597.00 17.00 3.70 4.66 79.22 3.44 4.07 66.56

STA. 93+604.00 3.10 3.35 0.00


STA. 93+615.00 11.00 3.10 3.35 36.85 0.00 0.00

STA. 93+624.00 2.70 2.59 0.00 0.00


STA. 93+649.00 25.00 2.70 2.59 64.75 0.00 0.00

AREA = [( 0.30 + 0.60H)/ 2 ] x H VOLUME 506 SP = 873.44

Computation for ITEM 505(a)- Grouted Riprap, Class A


STATION L H (Left) Area (Left) Volume (Left) H (Right) Area (Right) Volume (Right)
STA. 94+998.00 3.90 1.50
STA. 95+000.00 2.00 3.80 1.47 2.97
STA. 95+020.00 20.00 3.85 1.49 29.60
STA. 95+040.00 20.00 3.90 1.50 29.90
STA. 95+060.00 20.00 3.95 1.52 30.20
STA. 95+068.00 8.00 3.90 1.50 12.08

STA. 93+534.00 3.60 1.41


STA. 93+540.00 6.00 3.55 1.40 8.43
STA. 93+560.00 20.00 3.50 1.38 27.80
STA. 93+580.00 20.00 3.65 1.43 28.10
STA. 93+600.00 20.00 3.60 1.41 28.40
STA. 93+603.00 3.00 3.60 1.41 4.23

STA. 93+640.00 4.00 1.53


STA. 93+660.00 20.00 3.95 1.52 30.50
STA. 93+673.00 13.00 4.05 1.55 19.96

STA. 95+003.00 4.50 1.68


STA. 95+020.00 17.00 4.50 1.68 28.56
STA. 95+040.00 20.00 3.50 1.38 30.60
STA. 95+060.00 20.00 2.90 1.20 25.80
STA. 95+067.00 7.00 2.50 1.08 7.98
SUB -TOTAL = 240.36 SUB -TOTAL = 104.75
AREA = [ (0.40 x 0.60) + (0.30 x 0.30) + (0.30 x H) ]
TOTAL VOLUME = 345.11 cu.m.
103(6)
STATION line Diameter LENGTH TOTAL Depth
1 STA. 93 + 045.00 1 x 0.91 dia. x 12.00 m. 12.00 m. 0.6
2 STA. 93 + 241.00 1 x 0.91 dia. x 12.00 m. 12.00 m. 0.3
3 STA. 93 + 912.00 1 x 0.91 dia. x 12.00 m. 12.00 m. 0.4
4 STA. 94 + 219.00 1 x 0.91 dia. x 12.00 m. 12.00 m. 0.45
5 STA. 94 + 536.00 1 x 0.91 dia. x 12.00 m. 12.00 m. 0.45
6 STA. 94 + 913.00 1 x 0.91 dia. x 12.00 m. 12.00 m. 0.5
7 STA. 94 + 957.00 1 x 0.91 dia. x 12.00 m. 12.00 m. 0.5
8 0.00 m. 0.5
9 0.00 m. 0.4
10 0.00 m. 0.4
11 0.00 m. 0.4
12 0.00 m. 0.4
13 STA. + 13.00 1 x 0.91 dia. x 13.00 m. 13.00 m. 13
14 STA. + 14.00 1 x 0.91 dia. x 14.00 m. 14.00 m. 14
15 STA. + 15.00 1 x 0.91 dia. x 15.00 m. 15.00 m. 15
16 STA. + 16.00 1 x 0.91 dia. x 16.00 m. 16.00 m. 16
17 STA. + 17.00 1 x 0.91 dia. x 17.00 m. 17.00 m. 17
18 STA. + 18.00 1 x 0.91 dia. x 18.00 m. 18.00 m. 18
19 STA. + 19.00 1 x 0.91 dia. x 19.00 m. 19.00 m. 19
20 STA. + 20.00 1 x 0.91 dia. x 20.00 m. 20.00 m. 20
21 STA. + 21.00 1 x 0.91 dia. x 21.00 m. 21.00 m. 21
22 STA. + 22.00 1 x 0.91 dia. x 22.00 m. 22.00 m. 22
23 STA. + 23.00 1 x 0.91 dia. x 23.00 m. 23.00 m. 23
24 STA. + 24.00 1 x 0.91 dia. x 24.00 m. 24.00 m. 24
25 STA. + 25.00 1 x 0.91 dia. x 25.00 m. 25.00 m. 25
26 STA. + 26.00 1 x 0.91 dia. x 26.00 m. 26.00 m. 26
27 STA. + 27.00 1 x 0.91 dia. x 27.00 m. 27.00 m. 27
28 STA. + 28.00 1 x 0.91 dia. x 28.00 m. 28.00 m. 28
29 STA. + 29.00 1 x 0.91 dia. x 29.00 m. 29.00 m. 29
506, Headwall
LEFT RIGHT
Height Length Height Length Remarks
2.8 3.7 2.82 3.7 Extend Both Sides. Provide Headwall on Both Sides
2.32 4.04 2.37 3.9 Extend Both Sides. Provide Headwall on Both Sides
3.47 3.15 3.5 3.15 Extend Both Sides. Provide Headwall on Both Sides
2.87 3.65 2.9 3.65 Extend Both Sides. Provide Headwall on Both Sides
2.3 3.95 2.37 3.95 Extend Both Sides. Provide Headwall on Both Sides
2.37 3.95 Extend Both Sides. Provide Headwall on Both Sides
2.37 3.95 Extend Both Sides. Provide Headwall on Both Sides

13 13 13 13 Extended Both Sides. Headwall Both Sides


14 14 14 14 Extended Both Sides. Headwall Both Sides
15 15 15 15 Extended Both Sides. Headwall Both Sides
16 16 16 16 Extended Both Sides. Headwall Both Sides
17 17 17 17 Extended Both Sides. Headwall Both Sides
18 18 18 18 Extended Both Sides. Headwall Both Sides
19 19 19 19 Extended Both Sides. Headwall Both Sides
20 20 20 20 Extended Both Sides. Headwall Both Sides
21 21 21 21 Extended Both Sides. Headwall Both Sides
22 22 22 22 Extended Both Sides. Headwall Both Sides
23 23 23 23 Extended Both Sides. Headwall Both Sides
24 24 24 24 Extended Both Sides. Headwall Both Sides
25 25 25 25 Extended Both Sides. Headwall Both Sides
26 26 26 26 Extended Both Sides. Headwall Both Sides
27 27 27 27 Extended Both Sides. Headwall Both Sides
28 28 28 28 Extended Both Sides. Headwall Both Sides
29 29 29 29 Extended Both Sides. Headwall Both Sides

2307 110986 -16.8999999999942


2323.9 111002.9
L/S R/S L R
1 1.3 2.82 49 Sta. 96 + 302.00
2 0.8 0.85 2.32 2.37 423 Sta. 96 + 676.00
3 1.95 3.47 518 Sta. 96 + 771.00
4 1.35 2.87 596 Sta. 96 + 849.00
5 0.85 2.37 1037 Sta. 97 + 290.00
6 1.52 1.52 1115 Sta. 97 + 368.00
7 1.52 1.52 1187 Sta. 97 + 440.00
8 2.03 2.03 1388 Sta. 97 + 641.00
9 2.03 2.03 46 Sta. 98 + 046.00
10 2.03 2.03 307 Sta. 98 + 307.00
11 2.03 2.03 711 Sta. 98 + 711.00
12 2.03 2.03

36 108715 1 x 0.91m dia. 1


128 108807 1 x 1.52m dia. 2
276 108955 2 x 1.52m dia. 3
636 109315 1 x 0.91m dia. 4
1155 109834 1 x 0.91m dia. 5
1322 110001 1 x 0.91m dia. 6
1380 110059 1 x 0.91m dia. 7
1696 110375 2 x 1.52m dia. 8
1973 110652 2 x 1.22m dia. 9
2066 110745 1 x 0.91m dia. 10
2202 110881 1 x 0.91m dia. 11
1559 110238 2
C.O. #1 / AS-STAKED
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

ITEM 500(1)b3 - RCCP, 0.91 m. Dia., Class IV & ITEM 500(1)b6 - RCCP, 1.52 m. Dia., Class IV
500(1)b3 - 0.91 500(1)b5 - 1.22 500(1)b6 - 1.52
STATION DESCRIPTION 103(3) 103(6) 506 REMARKS
dia., L.m. dia, L.m. dia., L.m.
STA. 93 + 045.00 1 x 0.91 dia. x 12.0 m. 1.81 10.87 18.31 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
STA. 93 + 241.00 1 x 0.91 dia. x 12.0 m. 1.81 5.44 14.06 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
STA. 93 + 912.00 1 x 0.91 dia. x 12.0 m. 1.81 7.25 23.15 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
STA. 94 + 219.00 1 x 0.91 dia. x 12.0 m. 1.81 8.15 18.97 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
STA. 94 + 536.00 1 x 0.91 dia. x 12.0 m. 1.81 8.15 13.88 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
STA. 94 + 913.00 1 x 0.91 dia. x 12.0 m. 1.81 9.06 7.13 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
STA. 94 + 957.00 1 x 0.91 dia. x 12.0 m. 1.81 9.06 7.13 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
TOTAL 12.67 cu.m. 57.98 cu.m. 102.63 cu.m. 84.00 cu.m. .00 cu.m. .00 cu.m.
C.O.#1 / AS - STAKE
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

COMPUTATION FOR ITEM 103(3) AND ITEM 103(6)a (RCPC)

103(3) = W x t x L 103(6)= WxdxL


w1 = WIDTH OF FOUNDATION w1 = WIDTH OF EXCAVATION
w1 = 1.93 m. for 0.91m. dia. RCCP, single barrel w1 = 1.93 m. for 0.91m. dia. RCCP, single barrel
w1 = 2.274 m. for 1.22m. dia. RCCP, single barrel w1 = 2.274 m. for 1.22m. dia. RCCP, single barrel
w1 = 3.613 m. for 0.91m. dia. RCCP, double barrel w1 = 3.613 m. for 0.91m. dia. RCCP, double barrel
w1 = 4.307 m. for 1.22m. dia. RCCP, double barrel w1 = 4.307 m. for 1.22m. dia. RCCP, double barrel
w1 = 6.022 M. for 1.22m. dia. RCCP, triple barrel w1 = 6.022 M. for 1.22m. dia. RCCP, triple barrel
t= 0.10 m. thickness of foundation d= average depth of excavation
L = Length of Rccp L= Length of Rccp

COMPUTATION FOR ITEM 103(3) and ITEM 103(6), RCCP

STA. 93 + 045.00 (1 - 0.91 m. dia. x 12.00 m.)


103-3 = 1.81 cu.m.
d= 0.60 m.
103- 6 = 10.87 cu.m.

STA. 93 + 241.00 (1 - 0.91 m. dia. x 12.00 m.)


103-3 = 1.81 cu.m.
d= 0.30 m.
103- 6 = 5.44 cu.m.

STA. 93 + 912.00 (1 - 0.91 m. dia. x 12.00 m.)


103-3 = 1.81 cu.m.
d= 0.40 m.
103- 6 = 7.25 cu.m.

STA. 94 + 219.00 (1 - 0.91 m. dia. x 12.00 m.)


103-3 = 1.81 cu.m.
d= 0.45 m.
103- 6 = 8.15 cu.m.

STA. 94 + 536.00 (1 - 0.91 m. dia. x 12.00 m.)


103-3 = 1.81 cu.m.
d= 0.45 m.
103- 6 = 8.15 cu.m.

STA. 94 + 913.00 (1 - 0.91 m. dia. x 12.00 m.)


103-3 = 1.81 cu.m.
d= 0.50 m.
103- 6 = 9.06 cu.m.

STA. 94 + 957.00 (1 - 0.91 m. dia. x 12.00 m.)


103-3 = 1.81 cu.m.
d= 0.50 m.
103- 6 = 9.06 cu.m.

Total Qty. of Item 103(3) (RCPC) = 12.67 cu.m.

Total Qty. of Item 103(6) (RCPC) = 57.98 cu.m.


C.O.#1 / AS - STAKE
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

ITEM 506(1) : STONE MASONRY (RCPC HEADWALL)

0.30

D + 2t
D, mØ

D
x RCPC

H
A + 0 .5 D
A
B=0.60H W

1. Sta. 93 + 045.00 - (1 - 0.91 m. dia. x 12.00 m.)

Where: W = 3.70 m Where: W = 3.70 m


H = 2.80 m H = 2.82 m
B = 1.68 m B = 1.69 m
A = 0.61 m A = 0.61 m
(B - 0.30) (H - 1.065) (B - 0.30) (H - 1.065)
X = + 0.30 X = + 0.30
H H
(1.68 - 0.30)(2.8 - 1.065) (1.69 - 0.30)(2.82 - 1.065)
X = + 0.30 X = + 0.30
2.80 2.82
(1.38 x 1.74) (1.39 x 1.76)
= + 0.30 = + 0.30
2.8 2.82
X = 1.16 X = 1.17

0.30 + 1.68 0.30 + 1.69


VOLUMEHEADWALL = 2.8 x 3.7 x ( ) VOLUMEHEADWALL = 2.82 x 3.7 x ( )
2 2

= 10.26 cu.m. = 10.38 cu.m.

2 (1.13) 2
VOLUMERCPIPE = ∏ (1.13) x ( 1.16 ) X 1 VOLUMERCPIPE = ∏ x ( 1.17 ) X 1
4 4

= 1 sq.m. x 1.16 m. x 1 = 1 sq.m. x 1.17 m. x 1

= 1.16 cu.m. = 1.17 cu.m.

VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= 10.26 - 1.16 = 10.38 - 1.17
VOLUME ITEM 506 = 9.10 cu.m. VOLUME ITEM 506 = 9.21 cu.m.

VOLUME TOTAL = 18.31 cu.m.

2. Sta. 93 + 241.00 - (1 - 0.91 m. dia. x 12.00 m.)

Where: W = 4.04 m Where: W = 3.90 m


H = 2.32 m H = 2.37 m
B = 1.39 m B = 1.42 m
A = 0.61 m A = 0.61 m
(B - 0.30) (H - 1.065) (B - 0.30) (H - 1.065)
X = + 0.30 X = + 0.30
H H
(1.39 - 0.30)(2.32 - 1.065) (1.42 - 0.30)(2.37 - 1.065)
X = + 0.30 X = + 0.30
2.32 2.37
(1.09 x 1.26) (1.12 x 1.31)
= + 0.30 = + 0.30
2.32 2.37
X = 0.89 X = 0.92

0.30 + 1.39 0.30 + 1.42


VOLUMEHEADWALL = 2.32 x 4.04 x ( ) VOLUMEHEADWALL = 2.37 x 3.9 x ( )
2 2

= 7.92 cu.m. = 7.95 cu.m.

2 2
VOLUMERCPIPE = ∏ (1.13) x ( 0.89 ) X 1 VOLUMERCPIPE = ∏
(1.13)
x ( 0.92 ) X 1
4 4

= 1 sq.m. x 0.89 m. x 1 = 1 sq.m. x 0.92 m. x 1

= 0.89 cu.m. = 0.92 cu.m.

VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= 7.92 - 0.89 = 7.95 - 0.92
VOLUME ITEM 506 = 7.03 cu.m. VOLUME ITEM 506 = 7.03 cu.m.

VOLUME TOTAL = 14.06 cu.m.


C.O.#1 / AS - STAKE
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

ITEM 506(1) : STONE MASONRY (RCPC HEADWALL)

3. Sta. 93 + 912.00 - (1 - 0.91 m. dia. x 12.00 m.)

Where: W = 3.15 m Where: W = 3.15 m


H = 3.47 m H = 3.50 m
B = 2.08 m B = 2.10 m
A = 0.61 m A = 0.61 m
(B - 0.30) (H - 1.065) (B - 0.30) (H - 1.065)
X = + 0.30 X = + 0.30
H H
(2.08 - 0.30)(3.47 - 1.065) (2.1 - 0.30)(3.5 - 1.065)
X = + 0.30 X = + 0.30
3.47 3.50
(1.78 x 2.41) (1.8 x 2.44)
= + 0.30 = + 0.30
3.47 3.5
X = 1.54 X = 1.55

0.30 + 2.08 0.30 + 2.1


VOLUMEHEADWALL = 3.47 x 3.15 x ( ) VOLUMEHEADWALL = 3.5 x 3.15 x ( )
2 2

= 13.01 cu.m. = 13.23 cu.m.

2 2
VOLUMERCPIPE = ∏ (1.13) x ( 1.54 ) X 1 VOLUMERCPIPE = ∏
(1.13)
x ( 1.55 ) X 1
4 4

= 1 sq.m. x 1.54 m. x 1 = 1 sq.m. x 1.55 m. x 1

= 1.54 cu.m. = 1.55 cu.m.

VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= 13.01 - 1.54 = 13.23 - 1.55
VOLUME ITEM 506 = 11.47 cu.m. VOLUME ITEM 506 = 11.68 cu.m.

VOLUME TOTAL = 23.15 cu.m.

4. Sta. 94 + 219.00 - (1 - 0.91 m. dia. x 12.00 m.)

Where: W = 3.65 m Where: W = 3.65 m


H = 2.87 m H = 2.90 m
B = 1.72 m B = 1.74 m
A = 0.61 m A = 0.61 m
(B - 0.30) (H - 1.065) (B - 0.30) (H - 1.065)
X = + 0.30 X = + 0.30
H H
(1.72 - 0.30)(2.87 - 1.065) (1.74 - 0.30)(2.9 - 1.065)
X = + 0.30 X = + 0.30
2.87 2.90
(1.42 x 1.81) (1.44 x 1.84)
= + 0.30 = + 0.30
2.87 2.9
X = 1.20 X = 1.21

0.30 + 1.72 0.30 + 1.74


VOLUMEHEADWALL = 2.87 x 3.65 x ( ) VOLUMEHEADWALL = 2.9 x 3.65 x ( )
2 2

= 10.58 cu.m. = 10.80 cu.m.

2 (1.13) 2
VOLUMERCPIPE = ∏ (1.13) x ( 1.20 ) X 1 VOLUMERCPIPE = ∏ x ( 1.21 ) X 1
4 4

= 1 sq.m. x 1.2 m. x 1 = 1 sq.m. x 1.21 m. x 1

= 1.20 cu.m. = 1.21 cu.m.

VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= 10.58 - 1.2 = 10.8 - 1.21
VOLUME ITEM 506 = 9.38 cu.m. VOLUME ITEM 506 = 9.59 cu.m.

VOLUME TOTAL = 18.97 cu.m.


C.O.#1 / AS - STAKE
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

ITEM 506(1) : STONE MASONRY (RCPC HEADWALL)

5. Sta. 94 + 536.00 - (1 - 0.91 m. dia. x 12.00 m.)

Where: W = 3.95 m Where: W = 3.95 m


H = 2.30 m H = 2.37 m
B = 1.38 m B = 1.42 m
A = 0.61 m A = 0.61 m
(B - 0.30) (H - 1.065) (B - 0.30) (H - 1.065)
X = + 0.30 X = + 0.30
H H
(1.38 - 0.30)(2.3 - 1.065) (1.42 - 0.30)(2.37 - 1.065)
X = + 0.30 X = + 0.30
2.30 2.37
(1.08 x 1.24) (1.12 x 1.31)
= + 0.30 = + 0.30
2.3 2.37
X = 0.88 X = 0.92

0.30 + 1.38 0.30 + 1.42


VOLUMEHEADWALL = 2.3 x 3.95 x ( ) VOLUMEHEADWALL = 2.37 x 3.95 x ( )
2 2

= 7.63 cu.m. = 8.05 cu.m.

2 2
VOLUMERCPIPE = ∏ (1.13) x ( 0.88 ) X 1 VOLUMERCPIPE = ∏
(1.13)
x ( 0.92 ) X 1
4 4

= 1 sq.m. x 0.88 m. x 1 = 1 sq.m. x 0.92 m. x 1

= 0.88 cu.m. = 0.92 cu.m.

VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= 7.63 - 0.88 = 8.05 - 0.92
VOLUME ITEM 506 = 6.75 cu.m. VOLUME ITEM 506 = 7.13 cu.m.

VOLUME TOTAL = 13.88 cu.m.

6 Sta. 94 + 913.00 - (1 - 0.91 m. dia. x 12.00 m.)

Where: W = - m Where: W = 3.95 m


H = - m H = 2.37 m
B = - m B = 1.42 m
A = 0.61 m A = 0.61 m
(B - 0.30) (H - 1.065) (B - 0.30) (H - 1.065)
X = + 0.30 X = + 0.30
H H
(0 - 0.30)(0 - 1.065) (1.42 - 0.30)(2.37 - 1.065)
X = + 0.30 X = + 0.30
- 2.37
(0.30) 1.12
(1.07) 1.31
(-0.3 x -1.07) (1.12 x 1.31)
= + 0.30 = + 0.30
0 2.37
X = #DIV/0! X = 0.92

0.30 + 0 0.30 + 1.42


VOLUMEHEADWALL = 0x0x ( ) VOLUMEHEADWALL = 2.37 x 3.95 x ( )
2 2

= - cu.m. = 8.05 cu.m.

(1.13) 2 (1.13) 2
VOLUMERCPIPE = ∏ x ( #DIV/0! ) X 1 VOLUMERCPIPE = ∏ x ( 0.92 ) X 1
4 4

= ### = 1 sq.m. x 0.92 m. x 1

= #DIV/0! cu.m. = 0.92 cu.m.

VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= #DIV/0! = 8.05 - 0.92
VOLUME ITEM 506 = #DIV/0! cu.m. VOLUME ITEM 506 = 7.13 cu.m.

VOLUME TOTAL = 7.13 cu.m.

7. Sta. 94 + 957.00 - (1 - 0.91 m. dia. x 12.00 m.)

Where: W = - m Where: W = 3.95 m


H = - m H = 2.37 m
B = - m B = 1.42 m
A = 0.61 m A = 0.61 m
(B - 0.30) (H - 1.065) (B - 0.30) (H - 1.065)
X = + 0.30 X = + 0.30
H H
(0 - 0.30)(0 - 1.065) (1.42 - 0.30)(2.37 - 1.065)
X = + 0.30 X = + 0.30
- 2.37
(0.30) 1.12
(1.07) 1.31
(-0.3 x -1.07) (1.12 x 1.31)
= + 0.30 = + 0.30
0 2.37
X = #DIV/0! X = 0.92

0.30 + 0 0.30 + 1.42


VOLUMEHEADWALL = 0x0x ( ) VOLUMEHEADWALL = 2.37 x 3.95 x ( )
C.O.#1 / AS - STAKE
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

ITEM 506(1) : STONE MASONRY (RCPC HEADWALL)


VOLUMEHEADWALL = 0x0x ( ) VOLUMEHEADWALL = 2.37 x 3.95 x ( )
2 2

= - cu.m. = 8.05 cu.m.

(1.13) 2 (1.13) 2
VOLUMERCPIPE = ∏ x ( #DIV/0! ) X 1 VOLUMERCPIPE = ∏ x ( 0.92 ) X 1
4 4

= ### = 1 sq.m. x 0.92 m. x 1

= #DIV/0! cu.m. = 0.92 cu.m.

VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= #DIV/0! = 8.05 - 0.92
VOLUME ITEM 506 = #DIV/0! cu.m. VOLUME ITEM 506 = 7.13 cu.m.

VOLUME TOTAL = 7.13 cu.m.

VOLUME TOTAL = 102.63 cu.m.


C.O.#1 / AS - STAKE
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN

ITEM 603(3)a1 - Metal Guardrail Including Post (W-Beam)

No. of Span STATION LIMIT LOCATION LENGTH No. of Post


1 92 + 868.00 92 + 909.91 RS 41.91 12.00
3 92 + 977.00 93 + 022.72 RS 45.72 13.00
4 93 + 203.00 93 + 263.96 RS 60.96 17.00
5 93 + 271.00 93 + 354.82 RS 83.82 23.00
6 93 + 373.00 93 + 418.72 RS 45.72 13.00
7 93 + 535.00 93 + 595.96 RS 60.96 17.00
8 93 + 647.00 93 + 692.72 RS 45.72 13.00
9 94 + 164.00 94 + 198.29 RS 34.29 10.00
10 94 + 207.00 94 + 222.24 RS 15.24 5.00
11 94 + 230.00 94 + 294.77 RS 64.77 18.00
12 94 + 437.00 94 + 539.87 RS 102.87 28.00
15 94 + 913.00 95 + 103.50 RS 190.50 51.00
16 95 + 111.00 95 + 160.53 RS 49.53 14.00
18 95 + 168.00 95 + 183.24 RS 15.24 5.00
19 95 + 187.00 95 + 209.86 RS 22.86 7.00
20 95 + 217.00 95 + 224.62 RS 7.62 3.00
21 93 + 247.00 93 + 254.62 LS 7.62 3.00
22 93 + 540.00 93 + 616.20 LS 76.20 21.00
23 93 + 635.00 93 + 676.91 LS 41.91 12.00
24 94 + 546.00 94 + 580.29 LS 34.29 10.00
25 95 + 007.00 95 + 113.68 LS 106.68 29.00
26 95 + 120.00 95 + 161.91 LS 41.91 12.00
27 95 + 166.00 95 + 246.01 LS 80.01 22.00
TOTAL = 1276.35 L.m. 358.00 pcs

ITEM 603(4)a - Metal Beam End Piece, Fish Tail

Total Quantity = Total No. of Span x 2


Total Quantity = 27.0 x 2
Total Quantity = 54.0 each

You might also like