Regional Office Iv-B: Itemized Quantities and Cost Estimates On Other Sheet
Regional Office Iv-B: Itemized Quantities and Cost Estimates On Other Sheet
CONTRACT ID : : 18EO0018
PROJECT NAME : : ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE
K0092+744 - K0094+844 (KM 92+744 - KM 94+857): K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
TO: MARCBILT CONSTRUCTION INCORPORATED, Contractor, you are hereby directed to make the herein changes from the original plans and specifications, or do the following work not included in the plans,
specifications and contract.
DESCRIPTION OF WORK TO BE DONE : INCREASE IN ITEMS - 103(6)a, 104(1)b1, 405(1)b3, 407(8), 505(2)a, 506(1), 603(4)a
DECREASE IN ITEMS - 100(1), 102(2), 103(1)a, 103(3), 104(1)a1, 105(1)a, 200(1), 311(1)e1, 404(1)a, 405(2)b, 500(1)b3, 508(1), 603(4)a, 612(1)
DELETED ITEMS - 600(5), 602(3)b
ADDITIONAL ITEMS - 311(1)a, 404A(1)a, 612(2), 607(3)c, 625(2)3
NOTE: THE CONTRACTOR HEREBY WAIVED NOT TO COLLECT EXCESS NOTE : This Change Order is not
UNOBLIGATED AMOUNT EQUIVALENT TO P'15,850.05 effective until approved. By reason of this proposed Change ____ days extension of contract
time will be allowed. The total contract time to date, including this Change
ACCEPTED : Order is ____ days.
A.1.1(11) Provision of Furniture/Fixtures, Equipment & Appliances for the Field Office f L.S. 1.00 215,600.00 215,600.00 1.00 215,600.000 215,600.00
A.1.1(14) Provision of Laboratory Testing Equipment, Apparatus and Publications for th L.S. 1.00 123,201.56 123,201.56 1.00 123,201.560 123,201.56
A.1.1(15) Operation & Maintenance of Temporary Field Office, Laboratory and Living Qua Month 12.90 23,654.40 305,141.76 12.90 23,654.400 305,141.76
Page 2 of 45
ITEMIZED COST OF REVISION
CONTRACT ID : : 18EO0018
PROJECT NAME : : ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE
: K0092+744 - K0094+844 (KM 92+744 - KM 94+857): K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
LOCATION : ROXAS, PALAWAN
CONTRACTOR : MARCBILT CONSTRUCTION INCORPORATED
SUMMARY OF QUANTITIES FOR CHANGE ORDER NO. 01
ORIGINAL CONTRACT CHANGE ORDER NO. 01
ITEM NO. DESCRIPTION UNIT
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT
Part E Surface Course
311(1)a PCCP (Unreinforced) 0.15 m thick sq.m. 1,572.02 - 3,482.00 1,572.017 5,473,763.19
311(1)e1 Portland Cement Concrete Pavement (0.28m thk.) sq.m. 30,770.87 3,134.66 96,456,215.35 29,418.00 3,134.660 92,215,427.88
Part F Bridge Structures -
404A(1)a Epoxy-Coated Reinforcing Steel Bars (Dowell for Existing PCCP) kg. 250.00 - 8,002.00 250.00 2,000,500.00
404(1)a Reinforcing Steel Grade 40 kg. 59,375.65 63.69 3,781,635.15 53,642.00 63.690 3,416,458.98
405(1)b3 Structural Concrete, Class A (27.58 Mpa), 28 days cu.m. 39.16 14,083.37 551,504.77 191.00 14,083.370 2,689,923.67
405(2)b Structural Concrete,Class B (27.58 Mpa) cu.m. 1,209.46 12,944.67 15,656,060.58 834.00 12,944.670 10,795,854.78
407(8) Lean Concrete, Class B (16.50 Mpa) cu.m. 0.98 12,514.60 12,264.31 3.57 12,514.60 44,677.12
Part G Drainage and Slope Protection Structures -
500(1)b3 RCCP, 910mm diameter Class IV l.m. 98.00 8,187.21 802,346.58 84.00 8,187.210 687,725.64
505(2)a Grouted Riprap Class "A" cu.m. 253.80 8,576.84 2,176,801.99 521.00 8,576.840 4,468,533.64
506(1) Stone Masonry cu.m. 794.34 10,076.59 8,004,238.50 929.00 10,076.590 9,361,152.11
508(1) Handlaid Rock Embankment cu.m. 3.32 7,384.95 24,518.03 - 7,384.95 -
Part H Miscellaneous Structures -
600(5) Concrete Curb, Cast in Place l.m. 4,849.00 1,303.15 6,318,974.35 - 1,303.150 -
602(3)b Kilometer Post, Pre Cast each 3.00 6,971.07 20,913.21 - 6,971.070 -
603(3)a1 Metal Guardrail (Metal Beam) Including Post l.m. 1,717.00 5,744.28 9,862,928.76 1,701.00 5,744.280 9,771,020.28
603(4)a Metal End Beam Piece, Fish Tail each 32.00 1,625.66 52,021.12 54.00 1,625.660 87,785.64
612(1) Reflectorized Thermoplastic Pavement Marking (White) sq.m. 1,467.00 889.44 1,304,808.48 913.30 889.440 812,325.55
612(2) Reflectorized Thermoplastic Pavement Markings Yellow sq.m. 789.32 - 630.60 789.320 497,745.19
607(3)c Internally Illuminated (Solar) Pavement Levellec Marker/Studs Flush Type Omnic each 10,300.00 - 468.00 10,300.000 4,820,400.00
625(2)3 Linear Delineartor System each 1,134.69 - 358.00 1,134.690 406,219.02
Page 3 of 45
ITEMIZED COST OF REVISION
(AS STAKE PLAN)
CONTRACT ID : 18EO0018
PROJECT NAME : ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE
K0092+744 - K0094+844 (KM 92+744 - KM 94+857): K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
LOCATION : ROXAS, PALAWAN
CONTRACTOR : MARCBILT CONSTRUCTION INCORPORATED
ORIGINAL
ITEM NO. DESCRIPTION UNIT CONTRACT QTY REVISED QUANTITY REMARKS
QUANTITY
Part A Facilities for the Engineer
Provision of Combined Field Office, Laboratory and Living Quarters Building for the Engineers
A.1.1(6) Month 12.90 12.90
(Rental Basis)
A.1.1(11) Provision of Furniture/Fixtures, Equipment & Appliances for the Field Office for the Engineer L.S. 1.00 1.00
A.1.1(14) Provision of Laboratory Testing Equipment, Apparatus and Publications for the Engineer L.S. 1.00 1.00
Operation & Maintenance of Temporary Field Office, Laboratory and Living Quarters Building
A.1.1(15) Month 12.90 12.90
for the Engineer
Part A1.2 Vehicles for the Engineer
A.1.2(4) Provision of 4x2 Pick-up Type Service Vehicle for the Engineer on Rental Basis Month 12.90 12.90
A.1.2(6) Operation and Maintenance of 4x2 Pick Up type Service Vehicle for the Engineer Month 12.90 12.90
Part A1.3 Assistance for the Engineer
A.1.3(3) Provision of Survey Personnel for the Assistance to the Engineer Month 12.90 12.90
Part A1.4 Photographs
A.1.4(1) Provision of Progress Photographs Month 12.90 12.90
Part B Other General Requirements
B.2 Medical Room and First Aid Facilities L.S. 1.00 1.00
B.5 Project Billboard/Signboard each 2.00 2.00
B.7 Occupational Safety and Health Program Month 12.90 12.90
B.9 Mobilization and Demobilization L.S. 1.00 1.00
Part C Earthworks
100(1) Clearing and Grubbing ha. 6.72 5.88 To be cleared
100(3)a2 Individual Removal of Trees (301 - 500 mm dia.) each 191.00 191.00 To be removed
101(1) Removal of Structures & Obstruction l.s. 1.00 1.00 To be removed
102(2) Surplus Common Excavation cu.m. 24,174.84 - To be Excavated
103(1)a Structure Excavation, Common Soil cu.m. 1,065.60 - Deleted
103(3) Foundation Fill cu.m. 276.34 220.00 0.10 m Compacted Volume
103(6)a Pipe Culvert and Drain Excavation (Common Soil) cu.m. 501.26 2,803.00 To be Excavated
104(1)a1 Embankment from Roadway Excavation (Common Soil) cu.m. 12,671.61 12,521.70 Compacted Volume
104(1)b1 Embankment from Borrow (Common Soil) cu.m. 913.14 6,383.38 Deleted
105(1)a Subgrade Preparation (Common Material) sq.m. 31,496.93 29,498.00 Roadbed Excavation
Part D Subbase and Base Course
200(1) Aggregate Subbase Course cu.m. 10,098.35 9,487.00 0.20 m Thick Compacted Volume
Part E Surface Course
311(1)a PCCP (Unreinforced) 0.15 m thick sq.m. 3,482.00 0.15m thick Pavement
311(1)e1 Portland Cement Concrete Pavement (0.28m thk.) sq.m. 30,770.87 29,418.00 0.28m thick Pavement
Part F Bridge Structures
404A(1)a Epoxy-Coated Reinforcing Steel Bars (Dowell for Existing PCCP) kg. 8,002.00 For PCCP dowels
404(1)a Reinforcing Steel Grade 40 kg. 59,375.65 53,642.00 For Line Canal and RCBC
405(1)b3 Structural Concrete, Class A (27.58 Mpa), 28 days cu.m. 39.16 191.00 For RCBC
405(2)b Structural Concrete,Class B (27.58 Mpa) cu.m. 1,209.46 834.00 For Line Canal
407(8) Lean Concrete, Class B (16.50 Mpa) cu.m. 0.98 3.57 For RCBC
Part G Drainage and Slope Protection Structures
500(1)b3 RCCP, 910mm diameter Class IV l.m. 98.00 84.00 To be Installed
505(2)a Grouted Riprap Class "A" cu.m. 253.80 521.00 For Slope Protection
506(1) Stone Masonry cu.m. 794.34 929.00 For Slope Protection
508(1) Handlaid Rock Embankment cu.m. 3.32 - Deleted
Part H Miscellaneous Structures
600(5) Concrete Curb, Cast in Place l.m. 4,849.00 - Deleted
602(3)b Kilometer Post, Pre Cast each 3.00 - Deleted
603(3)a1 Metal Guardrail (Metal Beam) Including Post l.m. 1,717.00 1,701.00 To be Installed
ITEMIZED COST OF REVISION
(AS STAKE PLAN)
CONTRACT ID : 18EO0018
PROJECT NAME : ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE
K0092+844 - KO94+739 KO: K0094+998 - K0095+245
LOCATION : ROXAS, PALAWAN
CONTRACTOR : MARCBILT CONSTRUCTION INCORPORATED
AS STAKE PLAN
ITEM UNIT PRICE IN ORIGINAL CONTRACT REVISED QUANTITY AND AMOUNT
DESCRIPTION UNIT ADDITIVE DEDUCTIVE
NO. PESOS
QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT
Part A Facilities for the Engineer
Provision of Combined Field Office, Laboratory and Living Quarters
A.1.1(6) Month 55,440.00 12.90 715,176.00 - - - - 12.90 715,176.00
Building for the Engineers (Rental Basis)
Provision of Furniture/Fixtures, Equipment & Appliances for the Field
A.1.1(11) L.S. 215,600.00 1.00 215,600.00 - - - - 1.00 215,600.00
Office for the Engineer
Provision of Laboratory Testing Equipment, Apparatus and
A.1.1(14) L.S. 123,201.56 1.00 123,201.56 - - - - 1.00 123,201.56
Publications for the Engineer
Operation & Maintenance of Temporary Field Office, Laboratory and
A.1.1(15) Month 23,654.40 12.90 305,141.76 - - - - 12.90 305,141.76
Living Quarters Building for the Engineer
Part A1.2 Vehicles for the Engineer
Provision of 4x2 Pick-up Type Service Vehicle for the Engineer on
A.1.2(4) Month 80,080.00 12.90 1,033,032.00 - - - - 12.90 1,033,032.00
Rental Basis
Operation and Maintenance of 4x2 Pick Up type Service Vehicle for
A.1.2(6) Month 82,544.00 12.90 1,064,817.60 - - - - 12.90 1,064,817.60
the Engineer
Part A1.3 Assistance for the Engineer
A.1.3(3) Provision of Survey Personnel for the Assistance to the Engineer Month 60,060.00 12.90 774,774.00 - - - - 12.90 774,774.00
Part A1.4 Photographs
A.1.4(1) Provision of Progress Photographs Month 3,080.00 12.90 39,732.00 - - - - 12.90 39,732.00
Part B Other General Requirements
B.2 Medical Room and First Aid Facilities L.S. 190,713.60 1.00 190,713.60 - - - - 1.00 190,713.60
B.5 Project Billboard/Signboard each 7,746.20 2.00 15,492.40 - - - - 2.00 15,492.40
B.7 Occupational Safety and Health Program Month 44,495.26 12.90 573,988.85 - - - - 12.90 573,988.85
B.9 Mobilization and Demobilization L.S. 906,939.26 1.00 906,939.26 - - - - 1.00 906,939.26
Part C Earthworks
100(1) Clearing and Grubbing ha. 204,222.15 6.72 1,372,372.85 - - 0.72 147,039.95 6.00 1,225,332.90
100(3)a2 Individual Removal of Trees (301 - 500 mm dia.) each 2,025.64 191.00 386,897.24 - - - - 191.00 386,897.24
101(1) Removal of Structures & Obstruction l.s. 1,037,501.70 1.00 1,037,501.70 - - - - 1.00 1,037,501.70
102(2) Surplus Common Excavation cu.m. 302.58 24,174.84 7,314,823.09 720.84 218,111.77 - - 24,895.68 7,532,934.85
103(1)a Structure Excavation, Common Soil cu.m. 304.26 1,065.60 324,219.46 - - 1,065.60 324,219.46 - -
103(3) Foundation Fill cu.m. 1,460.63 276.34 403,630.49 - - 56.34 82,291.89 220.00 321,338.60
103(6)a Pipe Culvert and Drain Excavation (Common Soil) cu.m. 328.65 501.26 164,739.10 2,301.74 756,466.85 - - 2,803.00 921,205.95
104(1)a1 Embankment from Roadway Excavation (Common Soil) cu.m. 377.44 12,671.61 4,782,772.48 4,329.07 1,633,964.18 - - 17,000.68 6,416,736.66
104(1)b1 Embankment from Borrow (Common Soil) cu.m. 1,788.16 913.14 1,632,840.42 - - 913.14 1,632,840.42 - -
105(1)a Subgrade Preparation (Common Material) sq.m. 17.54 31,496.93 552,456.15 - - 1,691.93 29,676.45 29,805.00 522,779.70
Part D Subbase and Base Course
200(1) Aggregate Subbase Course cu.m. 1,997.59 10,098.35 20,172,362.98 - - 611.53 1,221,588.93 9,486.82 18,950,774.05
Part E Surface Course
311(1)a PCCP (Unreinforced) 0.15 m thick sq.m. 1,572.02 - 3,482.00 5,473,763.19 - - 3,482.00 5,473,763.19
311(1)e1 Portland Cement Concrete Pavement (0.28m thk.) sq.m. 3,134.66 30,770.87 96,456,215.35 - - 3,074.87 9,638,671.99 27,696.00 86,817,543.36
Part F Bridge Structures
404A(1)a Epoxy-Coated Reinforcing Steel Bars (Dowell for Existing PCCP) kg. 250.00 - 4,461.00 1,115,250.00 - - 4,461.00 1,115,250.00
404(1)a Reinforcing Steel Grade 40 kg. 63.69 59,375.65 3,781,635.15 - - 5,733.65 365,176.17 53,642.00 3,416,458.98
405(1)b3 Structural Concrete, Class A (27.58 Mpa), 28 days cu.m. 14,083.37 39.16 551,504.77 151.84 2,138,418.90 - - 191.00 2,689,923.67
405(2)b Structural Concrete,Class B (27.58 Mpa) cu.m. 12,944.67 1,209.46 15,656,060.58 - - 375.46 4,860,205.80 834.00 10,795,854.78
407(8) Lean Concrete, Class B (16.50 Mpa) cu.m. 12,514.60 0.98 12,264.31 2.59 32,412.81 - - 3.57 44,677.12
Part G Drainage and Slope Protection Structures
500(1)b3 RCCP, 910mm diameter Class IV l.m. 8,187.21 98.00 802,346.58 - - 14.00 114,620.94 84.00 687,725.64
505(2)a Grouted Riprap Class "A" cu.m. 8,576.84 253.80 2,176,801.99 267.20 2,291,731.65 - - 521.00 4,468,533.64
506(1) Stone Masonry cu.m. 10,076.59 794.34 8,004,238.50 181.66 1,830,513.34 - - 976.00 9,834,751.84
508(1) Handlaid Rock Embankment cu.m. 7,384.95 3.32 24,518.03 - - 3.32 24,518.03 - -
Part H Miscellaneous Structures
600(5) Concrete Curb, Cast in Place l.m. 1,303.15 4,849.00 6,318,974.35 - - 4,849.00 6,318,974.35 - -
602(3)b Kilometer Post, Pre Cast each 6,971.07 3.00 20,913.21 - - 3.00 20,913.21 - -
603(3)a1 Metal Guardrail (Metal Beam) Including Post l.m. 5,744.28 1,717.00 9,862,928.76 - - 441.00 2,533,227.48 1,276.00 7,329,701.28
603(4)a Metal End Beam Piece, Fish Tail each 1,625.66 32.00 52,021.12 22.00 35,764.52 - - 54.00 87,785.64
612(1) Reflectorized Thermoplastic Pavement Marking (White) sq.m. 889.44 1,467.00 1,304,808.48 - - 605.10 538,200.14 861.90 766,608.34
612(2) Reflectorized Thermoplastic Pavement Markings Yellow sq.m. 789.32 - 630.60 497,745.19 - - 630.60 497,745.19
Internally Illuminated (Solar) Pavement Levellec Marker/Studs Flush
607(3)c each 10,300.00 - 468.00 4,820,400.00 - - 468.00 4,820,400.00
Type Omnic
625(2)3 Linear Delineartor System each 1,134.69 - 358.00 406,219.02 - - 358.00 406,219.02
BALANCE = 10,467,217.24
MARCBILT CONSTRUCTION INCORPORATED ELIZALDE V. OLEGA DOMINIC G. SERRANO ARMANDO G. ESTRELAL, CESO IV
Project Engineer III/Engineer III Chief, Construction Division Assistant Regional Director
By: Approved:
WILFREDO S. MALLARI
Regional Director
ITEMIZED COST OF REVISION (AS STAKED)
PROJECT: Road Widening of Puerto Pricesa North Road (two lanes to six lanes including drainage),
K0092+744 - K0094+844 (KM 92+744 - KM 94+857)
K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
LOCATION: Roxas, Palawan
ORIGINAL / C.O. # 1 (As-Staked) - Construction Limits : K0092+744 - K0094+844; K0094+875 - K0095+205, L = 2,430.00 L.M.
Operation & Maintenance of Temporary Field Office, Month 12.90 23,654.40 305,141.76 12.90 23,654.40 305,141.76
A.1.1(15) Laboratory and Living Quarters Bldg. for the Engineer
A.1.2 Vehicles for the Engineer
Provision of 4x2 Pick Up Type Service Vehicle for the
Month 12.90 80,080.00 1,033,032.00 12.90 80,080.00 1,033,032.00
A.1.2(4) Engineer on Bare Rental Basis
Operation and Maintenance of 4x2 Pick Up type Month 12.90 82,544.00 1,064,817.60 12.90 82,544.00 1,064,817.60
A.1.2(6) service Vehicle for the Engineer
A.1.3 Assistance to the Engineer
Provision of Survey Personnel for the Assistance to the Month 12.90 60,060.00 774,774.00 12.90 60,060.00 774,774.00
A.1.3(3) Engineer
A.1.4 Photographs
A.1.4(1) Provision of Progress Photographs Month 12.90 3,080.00 39,732.00 12.90 3,080.00 39,732.00
Part B Other General Requirements
B.2 Medical Room and First Aid Facilities L.S. 1.00 190,713.60 190,713.60 1.00 190,713.60 190,713.60
B.5 Project Billboard/Signboard each 2.00 7,746.20 15,492.40 2.00 7,746.20 15,492.40
B.7 Occupational Safety and Health Program Month 12.90 44,495.26 573,988.85 12.90 44,495.26 573,988.85
B.9 Mobilization and Demobilization L.S. 1.00 906,939.26 906,939.26 1.00 906,939.26 906,939.26
Part C Earthworks
ITEMIZED COST OF REVISION (AS STAKED)
PROJECT: Road Widening of Puerto Pricesa North Road (two lanes to six lanes including drainage),
K0092+744 - K0094+844 (KM 92+744 - KM 94+857)
K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
LOCATION: Roxas, Palawan
ORIGINAL / C.O. # 1 (As-Staked) - Construction Limits : K0092+744 - K0094+844; K0094+875 - K0095+205, L = 2,430.00 L.M.
BACK-UP COMPUTATION
100(3)b Individual Removal of Trees, Small (301mm - 500mm. dia) = 191.00 Each
Computation
N = 191.00 each
103(6)a Pipe Culvert & Drain Excavation (Common Soil) = 2,803.00 cu.m.
See Computation
Volume = 2,587.50 cu.m. Lined Canal
Volume = 57.98 cu.m. RCPC
103(6) RCBC = 157.47 RCBC
404A(1)a Epoxy-Coated Reinforcing Steel Bars (Dowell for Existing PCCP) = 4,461.00 kgs.
Computation
Proj. Length = 2,825.00 l.m.
Total No. of Drilled Dowell Bars = 2,825.00 ÷ 0.60 x 1 +1
Total No. of Drilled Dowell Bars = 4,709.00 pcs.
Length of Dowell Bar = 0.60 m. 16mm dia.
Weight of Dowell Bar = 4,709.00 x 1.579 x 0.60
Weight of Dowell Bar = 4,461.31 kgs.
Item Deleted
Item Deleted
602(3)b Kilometer Post (Precast) = 3.00 each
Computation
N = 3.00 each
603(3)a1 Metal Guardrail (Metal Beam) Including Post (W-Beam) = 1,276.00 l.m.
See Computation
Length = 1,276.35 l.m.
say = 1,276.00 l.m.
607(3)c Internally Illuminated (Solar) Pavement Levellec Marker/Studs Flush Type Omnic = 468.00 each
Computation
Total Length = 2,102.00 l.m.
N = 2,102.00 ÷ 4.50 +1
N = 468.11 each
say = 468.00 each
1.25
ITEM 103-3
0.10 1.00
0.15 m. 0.15 m.
Grouted Riprap
0.50 m.
0.30 m.
SHOULDER
0.20 m.
0.15 thk Class B Concrete with
10mm dia. Vert. & Hor. Bars Spaced 1.15 m.
@ 0.20m. O.C. Eachway
0.15 m.
0.10 m. thk. Foundation Fill 0.10 m.
Staggered Headwall
Horizontal Bars = 1.00 pc - 10mm dia x 0.50 m. = 0.50 m.
Vertical Bars = 3.00 pc - 10mm dia x 0.30 m. = 0.90 m.
1.40 m.
No. Headwall = 1,765.00 pcs.
404( staggered headwall) = (1765pcs. X 1.4 m. x 0.616 kg./m.)
Total length of bars for headwall = 1,522.14 kg
200
2300
400
VERTICAL BARS
200
2300
400
VERTICAL BARS
2,050
TOP BARS
2,050
BOTTOM BARS
80,000.00
HORIZONTAL BARS
80,000.00
TIE BARS
. 7,738.14 -
0.25
12 mm dia. Horizontal Bar @ 200 o.c. 16 mm dia. Vertical Bar @ 200 o.c.
0.40 1.50
0.25
2.15
12 mm dia. Bot. Bar @ 200 o.c.
094+880.00
20.00 20.00
094+900.00
20.00 20.00
094+917.00 14.11 1.59 2.54
3.00 43.40 3.00 7.19 7.77
094+920.00 14.82 3.20 2.64
20.00 284.10 20.00 61.60 47.00
094+940.00 13.59 2.96 2.06
20.00 277.00 20.00 45.50 46.00
094+960.00 14.11 1.59 2.54
20.00 289.30 20.00 47.90 51.80
094+980.00 14.82 3.20 2.64
18.00 260.37 18.00 43.11 46.62
094+998.00 15.12 14.11 1.59 2.54
22.00 320.76 318.23 22.00 52.69 56.98
095+020.00 14.04 14.82 3.20 2.64
20.00 272.60 284.10 20.00 61.60 47.00
095+040.00 13.22 13.59 2.96 2.06
SUB -TOTAL 5,543.36 7,475.30 3,948.89 3,433.47
100(1) = 60025.49/10,000
= 6.00
say = 6.00 ha. 6
094+880.00
20.00 20.00
094+900.00
20.00 20.00 63.40
094+920.00 6.34
20.00 20.00 264.60
094+940.00 20.12
20.00 20.00 401.90
094+960.00 20.07
20.00 20.00 429.00
094+980.00 22.83
18.00 18.00 386.46
094+998.00 0.44 17.77 0.98 20.11
22.00 15.62 349.69 22.00 19.47 394.13
095+020.00 0.98 14.02 0.79 15.72
20.00 20.60 251.80 20.00 13.00 284.70
095+040.00 1.08 11.16 0.51 12.75
20.00 21.10 211.10 20.00 11.30 241.10
095+060.00 1.03 9.95 0.62 11.36
20.00 28.70 107.90 20.00 13.00 133.30
095+080.00 1.84 0.84 0.68 1.97
20.00 41.80 11.20 20.00 30.80 26.60
095+100.00 2.34 0.28 2.40 0.69
20.00 61.20 2.80 20.00 54.10 8.00
095+120.00 3.78 - 3.01 0.11
20.00 75.30 0.00 20.00 49.40 2.30
095+140.00 3.75 - 1.93 0.12
20.00 376.10 0.70 20.00 42.70 2.40
095+160.00 33.86 0.07 2.34 0.12
20.00 674.50 0.80 20.00 64.60 1.20
095+180.00 33.59 0.01 4.12 -
20.00 692.00 0.70 20.00 95.70 0.00
095+200.00 35.61 0.06 5.45 -
5.00 178.05 0.30 5.00 27.25 0.00
095+205.00 35.61 0.06 5.45 -
SUB -TOTAL 2,807.48 936.99 1,116.17 2,639.79
104(1)a1 = FILL
= 17,000.68 cu.m.
say = 17,000.00 cu.m.
RCBC Widening
ITEM 500(1)b3 - RCCP, 0.91 m. Dia., Class IV & ITEM 500(1)b6 - RCCP, 1.52 m. Dia., Class IV
500(1)b3 - 0.91 500(1)b5 - 1.22 500(1)b6 - 1.52
STATION DESCRIPTION 103(3) 103(6) 506 REMARKS
dia., L.m. dia, L.m. dia., L.m.
STA. 93 + 045.00 1 x 0.91 dia. x 12.0 m. 1.81 10.87 18.31 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
STA. 93 + 241.00 1 x 0.91 dia. x 12.0 m. 1.81 5.44 14.06 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
STA. 93 + 912.00 1 x 0.91 dia. x 12.0 m. 1.81 7.25 23.15 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
STA. 94 + 219.00 1 x 0.91 dia. x 12.0 m. 1.81 8.15 18.97 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
STA. 94 + 536.00 1 x 0.91 dia. x 12.0 m. 1.81 8.15 13.88 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
STA. 94 + 913.00 1 x 0.91 dia. x 12.0 m. 1.81 9.06 7.13 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
STA. 94 + 957.00 1 x 0.91 dia. x 12.0 m. 1.81 9.06 7.13 12.0 l.m. - - Extend Both Sides. Provide Headwall on Both Sides
TOTAL 12.67 cu.m. 57.98 cu.m. 102.63 cu.m. 84.00 cu.m. .00 cu.m. .00 cu.m.
C.O.#1 / AS - STAKE
DETAILED QUANTITY COMPUTATION
ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD (TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE)
K0092+744 - K0094+844 (KM 92+744 - KM 94+857) ; K0094+875 - K0095+205 (KM 94+875 - KM 95+203)
ROXAS, PALAWAN
0.30
D + 2t
D, mØ
D
x RCPC
H
A + 0 .5 D
A
B=0.60H W
2 (1.13) 2
VOLUMERCPIPE = ∏ (1.13) x ( 1.16 ) X 1 VOLUMERCPIPE = ∏ x ( 1.17 ) X 1
4 4
VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= 10.26 - 1.16 = 10.38 - 1.17
VOLUME ITEM 506 = 9.10 cu.m. VOLUME ITEM 506 = 9.21 cu.m.
2 2
VOLUMERCPIPE = ∏ (1.13) x ( 0.89 ) X 1 VOLUMERCPIPE = ∏
(1.13)
x ( 0.92 ) X 1
4 4
VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= 7.92 - 0.89 = 7.95 - 0.92
VOLUME ITEM 506 = 7.03 cu.m. VOLUME ITEM 506 = 7.03 cu.m.
2 2
VOLUMERCPIPE = ∏ (1.13) x ( 1.54 ) X 1 VOLUMERCPIPE = ∏
(1.13)
x ( 1.55 ) X 1
4 4
VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= 13.01 - 1.54 = 13.23 - 1.55
VOLUME ITEM 506 = 11.47 cu.m. VOLUME ITEM 506 = 11.68 cu.m.
2 (1.13) 2
VOLUMERCPIPE = ∏ (1.13) x ( 1.20 ) X 1 VOLUMERCPIPE = ∏ x ( 1.21 ) X 1
4 4
VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= 10.58 - 1.2 = 10.8 - 1.21
VOLUME ITEM 506 = 9.38 cu.m. VOLUME ITEM 506 = 9.59 cu.m.
2 2
VOLUMERCPIPE = ∏ (1.13) x ( 0.88 ) X 1 VOLUMERCPIPE = ∏
(1.13)
x ( 0.92 ) X 1
4 4
VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= 7.63 - 0.88 = 8.05 - 0.92
VOLUME ITEM 506 = 6.75 cu.m. VOLUME ITEM 506 = 7.13 cu.m.
(1.13) 2 (1.13) 2
VOLUMERCPIPE = ∏ x ( #DIV/0! ) X 1 VOLUMERCPIPE = ∏ x ( 0.92 ) X 1
4 4
VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= #DIV/0! = 8.05 - 0.92
VOLUME ITEM 506 = #DIV/0! cu.m. VOLUME ITEM 506 = 7.13 cu.m.
(1.13) 2 (1.13) 2
VOLUMERCPIPE = ∏ x ( #DIV/0! ) X 1 VOLUMERCPIPE = ∏ x ( 0.92 ) X 1
4 4
VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE VOLUME ITEM 506 = VOLUMEHEADWALL - VOLUMERCPIPE
= #DIV/0! = 8.05 - 0.92
VOLUME ITEM 506 = #DIV/0! cu.m. VOLUME ITEM 506 = 7.13 cu.m.