RD11 5.1 Management Use Case en R0
RD11 5.1 Management Use Case en R0
DESIGN OVERVIEW
IT Space Architecture
FACILITY POWER BLOCK DIAGRAM
The IT space is supported by 2N power distribution to the rows and dual
rack power distribution in the racks. These A and B power feeds have
independent UPS systems in the Facility Power Space. The IT space was
constructed of independent power and cooling blocks. The primary type of
block consists of (16) 8kW Netshelter SX racks, (2) 1.5kW Networking racks,
4 Chilled Water Air handlers (InRow RC 500 series), and power distribution
units.
At the room level, we introduce additional systems for humidification control
and supplying water to the RCs. The rows are configured in a hot aisle/cold
aisle fashion with containment. The separation of cool supply air and hot
return air increases cooling efficiency in the data center. The redundant
coolers within the rows produce greater availability and eliminate the need
for perimeter units,
IT SPACE DESIGN
IT Space Specifications
- The IT Space is designed in blocks
containing 2 rows of IT racks around a
common hot aisle Name Value Unit
- InRow RC cooling units are placed within
Data Center Load 1000 kW
the rows in order to provide N+1 cooling to
Density per Rack (IT) 8 kW
the IT racks
Density per Rack (Networking) 1.5 kW
- Each block of 2 rows has chilled water
supplied by the Mechanical Space Square footage of IT Space 5070 Sq ft
Facility Power
FACILITY POWER BLOCK DIAGRAM
ELECTRICAL DESIGN
MV Transformers 2N
Facility Cooling
The mechanical space supports cooling for a 1MW data center design.
This design affords optimal availability levels with a double-ended chilled
FACILITY COOLING BLOCK DIAGRAM
water loop. Most downstream components are configured for a 2N level of
redundancy.
The design has a highly efficient heat rejection methodology by utilizing
two 340 ton water cooled chillers in a 2N configuration, and each chiller is
paired with redundant cooling towers. The chillers are sized to run at
Tower
partial loads and have variable speed compressors allowing the chillers to
operate at peak efficiency to provide more energy savings throughout the
life of the data center. A pair of plate frame heat exchangers is provided
Tower
with three way valves between the chillers and cooling towers for improved
efficiency. This type of economization creates two loops, one for the IT
space and one for heat rejection. Economizers reduce energy
consumption and thereby operation cost, providing significant energy
savings over the life of the data center, relative to geographic location and
number of available free cooling days.
Multiple pairs of chilled water and condenser water pumps in a 2(N+1)
redundant configuration are implemented to provide better control, fault
tolerance and efficiency. The secondary chilled water pumps operate at
variable speed thereby allowing for adjustments in flow rate based upon
peak and off peak cooling demands. VFD control of pumps in the design
allows for more precise control of the pump thereby maintaining desired
pressure and rate of flow.
MECHANICAL DESIGN
This reference design can be modified as
- With Efficiency and criticality in mind,
redundant chilled water plants with cooling
towers and economizers are present in the FACILITY COOLING ATTRIBUTES
design.
- Chilled water from Chiller A and B are
Name Value
joined into one loop to supply the IT Space. Chiller configuration 2N
The coolers (InRow RCs) are N+1 redundant Chiller Size 340 tons
to be failure resistant and concurrently N+1 Primary and
Chilled Water Pumps
Secondary
maintainable.
- Chilled Water pumps between Thermal Economizer 2N
Storage Tanks and the cooling units are Storage Tank Configuration 2N © 2013 Schneider Electric. All rights reserved.
supported by the Symmetra MW UPS to Cooling Tower Configuration 2N
provide back up chilled water in the event of
interruption of power to the Chillers.
-Cooling units include InRow RCs fed from
headers
The StruxureWare for Data Centers suite overview The various elements in the StruxureWare for Data
demonstrates Schneider Electric’s vision of a Center suite address the different needs of the array
complete Data Center Infrastructure Management of data center users including the Facilities teams, IT
(DCIM) system. The suite, as depicted in the above and Data Center Management, and other “C-Level”
figure, delineates functionality that is needed in a executives. Numerous portals allow the users to
typical datacenter and historically has been navigate through important data center operational
addressed through multiple disconnected and performance information through a preferred
applications. With the Schneider Electric interface, e.g. a facilities engineer through a building
StruxureWare for Data Centers suite, the integrated monitoring interface, an IT systems operator though
and holistic system is capable of managing data an IT room monitoring interface, and IT and facilities
centers across multiple domains to accommodate managers through an enterprise portal interface. In © 2013 Schneider Electric. All rights reserved.
the needs of each expert user within an environment addition DCIM is increasingly seen as C-level
that promotes collaboration. information tool, providing high-level management
information summaries, energy benchmarks and
other Data Center productivity related key
performance indicators (KPIs).). This perspective
emphasizes the need to deliver the right information
to the right users in real-time.
Structural View
The structural perspective, as illustrated below, This information can be used to assess the health and
represents the physical elements of the data center efficiency of power systems throughout the design.
architecture management. This view shows that the StruxureWare Data Center Expert collects information
devices in the IT, Mechanical and Electrical spaces from Data Center equipment and controllers as well as
are accessible to any of the StruxureWare for Data from meters located in the power systems. Cooling
Centers management software applications – Power Monitoring Expert gathers information from network
Monitoring Expert (ION Enterprise), Cooling controllers which monitor and control devices in the
© 2013 Schneider Electric. All rights reserved.
Monitoring Expert (Andover Continuum or TAC Heating Ventilation and Air Conditioning (HVAC)
Vista), StruxureWare Data Center Expert, system. Since all of the equipment and intelligent
StruxureWare Data Center Operation and devices are connected to the same TCP/IP network,
StruxureWare Resource Advisor. In addition, this data from any device is available to each of the
architecture highlights the freedom of management systems where relevant. Each server can
communication between the enterprise software then enable data viewing and manipulation through
systems for more efficient information exchange. their associated client applications, and data from all of
the systems can be aggregated into a site-level or
hosted dashboard perspective.
Schneider Electric’s 3 core monitoring and contol This information can be used to assess the health and
applications: Power Monitoring Expert (ION efficiency of power systems throughout the design.
Enterprise), Cooling Monitoring Expert (Andover StruxureWare Data Center Expert collects information
Continuum/TAC Vista), and StruxureWare Data from Data Center equipment and controllers as well as
Center Expert manage the data collection, from meters located in the power systems. Cooling
monitoring and automation type functions, while Monitoring Expert gathers information from network
StruxureWare Data Center Operation assists with controllers which monitor and control devices in the
the business process type functions like data center Heating Ventilation and Air Conditioning (HVAC)
asset management, operational analysis and capital system. Since all of the equipment and intelligent
© 2013 Schneider Electric. All rights reserved.
costs. These applications are hosted on servers, devices are connected to the same TCP/IP network,
with access to both the corporate network and the data from any device is available to each of the
DCIM network. The DCIM network is a generic management systems where relevant. Each server can
TCP/IP network with the sole focus of facilitating then enable data viewing and manipulation through
status and control communications between devices their associated client applications, and data from all of
and applications. This network is isolated from the the systems can be aggregated into a site-level or
corporate network to increase security and partition hosted dashboard perspective.
network traffic. Power Monitoring Expert primarily
communicates with meters and gateways in the
electrical space.
In the example provided of a StruxureWare for Data The large screens provide a view into the overall
Centers NOC, a NOC Client Virtual Machine Server status and key indicators of the data center
is configured to host the multiple sub-system client infrastructure. The dashboards allow the user to
application interfaces using multiple Virtual Machine follow the paths of cooling and power through the
images. Multiple displays are leveraged to enable data center rooms and understand the operating
interaction with each of the management software status of the equipment. In addition, the user would
systems from the central console. It should also be be able to “zoom” to look at quality, cost, and
noted that the management software client capacity information at the global, site, room, and
applications can simultaneously be accessed rack level.
through the network on alternate workstations and
laptops, or through the variety of mobile device Along the bottom row, moving from left to right, © 2013 Schneider Electric. All rights reserved.
applications that are available as extensions to the StruxureWare Cooling Monitoring Expert and Power
sub-system client tools. Monitoring Expert provide the details related to the
operation of the Electrical and Mechanical Space,
While the sequence of the actual displays is variable with StruxureWare Data Center Expert and
and depends on the preference of the users, in the StruxureWare Data Center Operation representing
example provided the screens have been arranged the specifics of the IT Space.
such that the large screens at the top display the
high level Global and Site -level dashboards with the
smaller screens at the bottom being leveraged for
the four sub-systems.
violated for its monitored devices. The monitored everything occurring on the network.
NetBotz Appliances each generate their own alert
notifications in response to alert threshold violations The integrations from StruxureWare Data Center
that occur at the devices they monitor. Expert to Microsoft System Center Operations
Manager and IBM Tivoli provide a tight integration
The Surveillance feature within StruxureWare Data between the IT systems and the physical
Center Expert is used to configure and view infrastructure that supports those systems. Events
surveillance data available to the StruxureWare Data from the physical infrastructure can be viewed side-
Center Expert server from the APC NetBotz line of by-side with the system events to which they may be
cameras. The user can filter and view a summary of related,
all captured surveillance event images from a
specified day or range of days.
MONITORED EQUIPMENT
In an IT block with twelve 8kW density (IT) racks and In this specific design, the RC units have been
two 1.5kW density (Networking), there are 8 InRow grouped together within the block. This achieved by
RC cooling units to provide N+1 cooling within the using a serial connection daisy-chained from one
block. Each of these units are able to operate RC to the next. When in this operating mode, the
independently, in an closed aisle mode such as this RCs gather all of the data from the temperature
one, by setting goal temperature set points for the sensors in the group and adjust all of the cooling
rack next to it. Each RC unit has a single external units based on the highest rack inlet temperature.
temperature sensor that is place in the rack adjacent Each RC will have the same control commands to
to it. Based on the temperature of the adjacent rack, increase decrease fan speed and chilled water flow
the RC adjusts its fan speed and chilled water flow. with their own internal valves.
MONITORED EQUIPMENT
heat created by the servers. into the real-time and historical data contained in the
servers.
IT equipment and to remove the heat created by the
servers. The client software can display the complete Due to the capabilities of customizable user
HVAC System monitoring including overall status of interfaces and wide data collection, the BMS can
individual coolers, chillers, towers and the associated also be configured to host the overall data center
pumps, fans, valves and other related devices. In status portals. From this view, the operators are able
addition, the BMS displays the physical plant status to aggregate data from the IT, Electrical and
and performance as well as real-time data through Mechanical Space and present it in raw or
open communication protocols such as BACNet, processed form in custom screens viewed in the
LonWorks and Modbus. workstation or on remote clients.
The central plant shall have the following distinct The secondary chilled water loop pump speed shall
operating modes: off, operate –with lead/lag plants, be regulated by a BMS PID loop using the secondary
operate- with concurrent plants, emergency cool chilled water loop pressure differential as the
(loss of chillers). process variable. To comply with the redundant
design each secondary chilled water pump will be
Off: assigned to a separate controller and will each have
The chillers, pumps and towers are off with all independent control points.
applicable valves closed. The cooling tower heaters
remain powered under separate thermostatic control. Plate Frame Heat Exchanger Economizer
Dry coolers remain monitored for freeze condition.
Note: At least one Chiller, heat exchanger and Each chilled water plant shall have an integrated
drycooler and associated pumps will always be water side economizer plat frame heat exchanger.
operational. The heat exchanger shall have a 3-way mixing valve
under proportion control of a BMS PID loop. During
Operate- Lead/Lag Plants: periods of active use the mixing valve shall be
Chilled water is being actively produced by one of modulated as needed to maintain desired setpoint of
the two plants. Rotation of lead plant is cycled at a the chilled water. To comply with the redundant
prescribed interval. Failure switch over is provided design each heat exchanger will be assigned to a
between plants in the event of a critical failure occurs separate controller and will each have independent
on the primary plant. control points.
Facility managers need to be able to analyze any Facilities want to know that they are being charged
event that resulted in downtime so that the root cause fairly by their utility and that meter-reading or
can be determined to prevent a similar event in the accounting errors are not made in the favor of the
future. By utilizing logs with time-stamped incidents, utility. Even small errors on a percentage basis can
the user can view the root causes of current and past mean a large cost to a facility because of the large
events. amount of electricity that is consumed.
It is important for facility managers to have information Facilities also want to know what they can do to
about the electrical system to understand what role the reduce the costs of the electrical bill. A power
electrical supply had in any event. Sometimes monitoring system is expected to provide information
reliability problems are blamed on the electrical supply that facility managers can use to help reduce these
when actually there were other causes involved. costs (eg. PUE trends). For example, facility
Conversely, reliability problems can sometimes be mangers need to be able to justify replacement of
blamed on equipment, operator error or from an equipment for more energy efficient models. They
unexplained source, when the source of the problem is need to be able to identify waste of energy, including
actually a disturbance in the electrical supply. incorrectly operated equipment or equipment that
needs maintenance. They may need to know
Data Center operators also want to be able to prove whether it is worth the investment ot install
when a disturbance has been caused by the electrical equipment to mitigate the conditions that result in
utility, so that the utility can be held accountable for Power Factor or other penalties, or just to justify an
© 2013 Schneider Electric. All rights reserved.
any damages. With Power monitoring Expert analysis investment in local generation equipment in order to
tools, the users can proactive assess current power reduce utility demand during peak billing rates or to
quality conditions and trends. avoid setting a new peak demand.
Energy cost is a smaller but increasingly important The power monitoring expert system allows
concern to data centers. Facility operators want to operators to report on environmental metrics. Usage
know more about the elements of their electrical bill data can be collected, aggregated, normalized and
and how those drive their electricity cost, and they summarized in to user created reports. The
want actionable information to be able to reduce those architecture described in this use case enables the
costs. applications as discussed above.
The power management offer is designed to Power Quality can be tracked in the Utility feeds,
uncover opportunities for safety, reliability, energy UPS input, Critical power distribution, and in Critical
performance and balanced power infrastructure Mechanical power distribution. Metering can be
utilization. It utilizes intelligent sensors, meters, data valuable at the generator output, UPS input, Critical
collection hardware and software to: provide the Mechanical power distribution, Mechanical
information required to monitor infrastructure in real- distribution, and for other building loads in order to
time; to understand and manage operations and measure usage and calculate PUE. In addition, the
risk; and provide the analytic tools necessary to plan ability to test with load banks connected to the UPS
for constant change and dynamic growth. output and generator switchgear will be important for
ongoing reliability.
With these devices in place we can conduct EPSS
tests, calculate PUE as well as show an online
dynamic display of circuit breaker status and
measurements, show power quality reports including
harmonics, power factor, maintenance reports,
energy dashboards, and alarming.
Under normal circumstances, this system connects The minimum requirement for this location is a
to the utility feed while the PM800 series meter on PM800 to the power consumed by the mechanical
the low voltage electrical bus captures advanced PQ load (for PUE calculations). It would be even more
data. Having a PQ meter like the PM 800 at the beneficial to have a basic PQ meter such as PM800
entrance of the UPS allows the operator to analyze to monitor any harmonics produced by the VFDs
events that may be specific to the UPS. It is also and Soft Starters in the event they malfunction.
useful if the utility breaker is open and the system is
fed off the generators.
Mechanical Load
Building Loads
Generator Switchgear
Load Bank
Key
A-link
Format for Additional T Temperature Sensor
Hub Sensor Pod Sensor Pod Sensor Pod Sensor Pod Camera
Electrical Space SP150 SP150 SP150 SP150
UPS
T/H Door Door T Door Door T/H Door Door T Door Door T/H Door Door T Door Door T/H Door Door T Door Door
USB
Mechanical Electrical
Space AHUs Space AHUs
Sensor Pod Sensor Pod
SP150 SP150
Beacon
T/H Door Door T Door Door T/H Door Door T Door Door
NetBotz Leak
A-link
T Door Door T/H Door Door
InRow RC
InRow RC
InRow RC
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
InRow RC
CRAH
CRAH
CRAH
CRAH
PDU
Corporate
Network
Ethernet
Switch
Core
Ethernet Switch
(Private Network)
Struxureware Ethernet
Central
© 2013 Schneider Electric. All rights reserved.
Switch
InRow RC
InRow RC
InRow RC
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
Rack PDU
InRow RC
CRAH
CRAH
CRAH
CRAH
PDU
Electrical Crisis
ECPR Prevention and Recovery
Communication Unit
O/C O/C O/C O/C O/C O/C O/C O/C
EGX100 Meter Meter Meter Meter Meter
PM5350 PM5350 PM5350 PM5350 PM5350
RS485: Modbus RTU
Ethernet: Modbus TCP ECPR
Meter Meter Meter ulogic ulogic ulogic ulogic
PM9C PM9C PM9C
Meter
Mechanical B Loads PM800
Corporate ulogic ulogic ulogic ulogic
Network
UPS B Output Board
Corporate
Network
StruxureWare
Cooling Monitoring
Notes:
1. Bus Communications are continuous daisy
chain as shown, order of unit may change with
Infrastructure approval of Schneider Electric and redline
documentation must follow installation.
Network 2. Schneider Electric Panels and 12
Controllers.