Summary of Bill of Quantities Guest House
Summary of Bill of Quantities Guest House
Guest House
A. SUB STRUCTURE
B. SUPER STRUCTURE
1 Concrete work..........................................................................
Birr 2,395,704.50
2 Block work................................................................................
Birr 1,330,919.80
3 Aluminum Work............................................................................
Birr 1,185,041.78
4 Plastering ................................................................................
Birr 1,203,764.72
5 Floor & Wall Finishing ...............................................................
Birr 1,690,641.39
6 Painting ...................................................................................
Birr 250,207.54
7 Electrical Installation,...............................................................
Birr 1,489,964.00
8 Sanitary Installation.....................................................................
Birr 777,525.00
Page 2
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
2.CONCRETE WORKS
Particular attention !!! must be given to the
following notes along with the Technical
Specification and Method of Measurement
prepared by BaTCoDA.
Constituents of concrete:
The quality of ingredients of concrete must fulfill
the requirements, concrete trial mixes shall be
done and certified & confirmed by laboratory
test results before casting of structural
elements & Cement shall be use OPC for
Structure above C-25 Mpa of Compresive
strength. During concrete casting samples
should be taken for laboratory tests.
Concrete :
The specified concrete strength must be
confirmed by laboratory test.
Reinforcement bar :
The specified yield strength and other related
properties of reinforcement bar must be
certified both in manufacturer's
catalogue/manual and by laboratory test.
Form Work
Formwork shall be constructed to the exact
sizes, shapes lines and dimensions shown and
as required to obtain accurate alignment,
location grade, level and plumb work in finished
structures. Provision shall be made for
openings, offset, sinking, keyways, recesses,
moldings, reglets, chamfers, blockings, screeds
bullheads, anchorages, inserts and other
features as required.
Page 3
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
2.4 Provide, cut and fix in position sawn seasoned
timber or wrought iron form work made up of
minimum 3mm thick sheet metal & folded
thickness of 50mm whichever is appropriate;
Contractor to submit formwork design;
Page 4
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
B. SUPER-STRUCTURE
1. CONCRETE WORK
Particular attention !!! must be given to the
following notes along with the Technical
Specification and Method of Measurement
prepared by BaTCoDA.
Constituents of concrete:
The quality of ingredients of concrete must fulfill
the requirements, concrete trial mixes shall be
done and certified & confirmed by laboratory
test results before casting of structural
elements & Cement shall be use OPC for
Structure above C-25 Mpa of Compresive
strength. During concrete casting samples
should be taken for laboratory tests.
Concrete :
The specified concrete strength must be
confirmed by laboratory test.
Reinforcement bar :
The specified yield strength and other related
properties of reinforcement bar must be
certified either by manufacturer's
catalogue/manual or/and by laboratory test.
Form Work
Formwork shall be constructed to the exact
sizes, shapes lines and dimensions shown and
as required to obtain accurate alignment,
location grade, level and plumb work in finished
structures. Provision shall be made for
openings, offset, sinking, keyways, recesses,
moldings, reglets, chamfers, blockings, screeds
bullheads, anchorages, inserts and other
features as required.
Page 5
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
1.4 Steel reinforcement for use in Super Structure
Concrete works with a minimum yield strength
Fyk of 300MPa for reinforcement bar of dia.
less than and equal to 10 mm & Fyk of 400MPa
for reinforcement bar of dia. greater than and
equal to 12 mm. Reinforcement shall be
according to Structural Drawings and Technical
Specifications. Price includes cutting bending,
placing in position and tying wires.
Page 6
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
3. ALUMINUM WORK
Supply and fix Doors & Windows made of
Aluminum tubular profile frames ALLCO-5 or
equivalent, 2mm thick average weight
1000gm/ml, door kick plate 1500gm/ml, partly
covered with aluminum sheet according to the
detail drawing and window door schedule .
Complete work includes all the necessary iron
mongery and ASSA or equivalent type of
cylindrical lock. All aluminum windows and
doors type shall be approved by the Engineer.
Price includes 4mm thick non - reflective tinted
clear glass.
3.1 Windows:
a) Type W1 ,150 x 150cm. No 40.00 8,005.77 320,230.80
b) Type W2 , 60 x150cm. No 36.00 3,202.31 115,283.09
c) Type TW1, 80 x 40cm. No 20.00 1,138.60 22,771.97
d) Type TW1, 40 x 40cm. No 25.00 569.30 14,232.48
3.2 Doors:
a)Type D-1', 135x 210cm. No 1.00 10,087.27 10,087.27
b)Type D-1, 135 x 210cm. No 16.00 10,087.27 161,396.32
c)Type D-2, 90 x 210cm. No 15.00 6,724.85 100,872.70
d)Type D-3, 80 x 210cm. No 36.00 5,977.64 215,195.10
e)Type D-4, 100 x 210cm. No 1.00 7,472.05 7,472.05
3.3 Staircase:
Aluminum hand rail & baluster consists of .
a)
Dia.50/3mm CHS Hand rail top Horizontal
baluster
ml 37.00 1,900.00 70,300.00
3.4 Glased Aluminum Wall
Supply and fix curtain wall made of concealed
Aluminum frames ( Two studded structurally
Glazed curtain wall) , glazing consists
externally 5mm thick non reflective
glass.Complete all works as per the drawing,
standard specification and as per the engineers
approval . Works shall include glazing, all
accessories including trims and flashings and
best quality iron mongery and supply and fixing
b)30x30x2mm
of the curtain wall which RHS to
shall be subject
Vertical baluster at c/c 100cm anchored
approval of shop drawings from the or fixed
to sides of steps Height = 90cm. Complete
manufacturer.
work all according to drawing and technical
specification m2 32.00 4,600.00 147,200.00
TOTAL CARRIED TO SUMMARY 1,185,041.78
4. PLASTERING & Pointing
Finishing work shall include all surface pre-
cleaning, preparation and application of
finishing and cleaning at the end of finishing
work
4.1 Apply two coats of plaster in cement sand
mortar mix [1:3] in Internal wall surfaces. m2 2,600.00 110.58 287,508.00
4.2 Ditto as item 7.1 but for all Internal structural
elements like soffits, beams & columns
surfaces. m2 1,984.97 179.55 356,401.36
4.3 Ditto as item 7.1 but for External wall surfaces. m2
650.00 110.58 71,877.00
4.4 Apply smooth and standard type of Gypsum as
third coat over the plastered internal wall
surfaces. m2 2,600.00 106.43 276,718.00
Page 7
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
4.5 Ditto as item 7.4 but for all Internal structural
elements like soffits, beams & columns
surfaces. m2 1,984.97 106.43 211,260.36
4.6 Apply pointing in cement mortar mix(1:2) to fine
massonery wall as where shown on the
Architectural drawing.Price shall include pre-
cleaning and preparation of the surface.
m2 220.00 44.22 9,728.40
TOTAL CARRIED TO SUMMARY 1,203,764.72
5. FLOOR & WALL FINISHING
5.1 Apply 48mm thick rough cement sand screed
on concrete slab in cement mortar. m2 889.00 158.99 141,342.11
5.2
10mm thickness Supply and fix
600mmx600mm non Slippery ceramic tile
flooring bedded in cement sand ratio (1:3)
including mortar bedding,Price shall include
30mm thick cement mortar bedding. Color and
pattern of tile shall be approved by the
engineer. m2 139.00 812.72 112,968.08
5.3 Supply and fix approved 200x300x6mm glazed
Ceramic wall tiles stuck to wall with cement
mortar mix (1:2) backing and 2 mm joints to be
grouted in white cement. m2 585.2 449.67 263,146.88
5.4 8mm thickness(600*600)mm. Porcelain Floor
Tile bedded on & including cement sand mortar
mix 1:3 and joints grouted in cement mortar.
Price shall include 30mm thick cement mortar
bedding.
m2 102.00 532.16 54,280.32
5.5 Supply and fix 100mm high 10mm thick
porcelain skirting to wall. ml 93.34 106.43 9,934.36
5.6 25mm thickness(500*500)mm. polished granite
Floor Tile bedded on & including cement sand
mortar mix 1:3 and joints grouted in cement
mortar. Price shall include 30mm thick cement
mortar bedding coloure shall be approve as per
the inspection of the engineer.
m2 106.00 4,580.00 485,480.00
5.7 Supply and apply approved type 3mm thick
Epoxy paint over leveled,cured and hardened
cement,sand & gravel screed with mix ratio of
(1:2:3). Price includes standard painting,
primer,cement-sand-gravel screed & polishing.
Application shall be as per the Manufacturer's
catalog & the Engineer's inspection.
m2 154.00 893.00 137,522.00
5.8 100mm high 2mm thick PVC skirting. Price
shall include adhesive or glue to fix with the
wall. ml 21.95 94.16 2,066.81
5.9 Supply and fix 2cm thick wooden parquet floor
finish. Complete all works as per AR drawing
and engineers approval. m2 374.00 449.67 168,176.58
5.10 Supply and fix white approved Marble bedded
& joined in cement and sand mortar mix
1:3.Price shall include cement sand mortar
bedding.
a) Marble Window sill 230mmx 20mm ml 113.65 560.05 63,649.68
thickness
b) Marble Treads 330mmx30mm thickness ml 96.00 1,204.50 115,632.00
c) Marble Risers 160mmx20mm thickness ml 108.00 389.60 42,076.80
d) Landing 30mm thickness m2 16.83 3,650.00 61,429.50
Page 8
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
5.11 Supply & fix 2cm thick White or Equivalent
marble bedded on and including 3cm thick
cement sand screed 1:3 ratio and joints grouted
in White or equivalent type of cement mortar
(1:2) ratio.all work prosidur shall inspect by the
engineer.
m2 14.00 2,352.59 32,936.26
TOTAL CARRIED TO SUMMARY 1,690,641.39
6. PAINTING
6.1 Apply two coats of plastic paint to plastered in
Internal wall surfaces. m2 2,600.00 45.23 117,598.00
6.2 Ditto as item 9.1 but for all Internal structural
elements like Soffits, beams & columns
surfaces. m2 1,984.97 48.60 96,469.54
6.3 Ditto as item 9.1 but for External wall surfaces. m2
650.00 55.60 36,140.00
TOTAL CARRIED TO SUMMARY 250,207.54
7.ELECTRICAL INSTALLATION
Supply and Install :-
7.1 Power & Tele Intakes
Manhole
7.1.1 Manhole in bricks and with concrete base
internally of 800x800x700mm including
concrete cover with lifting hole. No 1.00 5,500.00 5,500.00
Conduits & pipes
7.1.2 PVC conduit of 110mm diameter for main
power cable intake provision ml 10.00 155.00 1,550.00
7.1.3 PVC conduit of 50mm diameter for main Tel.
cable intake provision ml 20.00 120.00 2,400.00
7.2 Low Voltage System Earthing
7.2.1 20x3000mm earth rod No 1.00 1,000.00 1,000.00
7.2.2 Single core, 1x50 sq mm bare copper
earth/grounding conductor from MDB earth
terminal to earth rods in PVC pipe 25mm
diameter (measured elswhere). ml 13.00 310.00 4,030.00
7.3 Feeder Power Cables in Conduits
Multi-core power cable copper conductor,
insulated PVC sheathed, colour coded, type
SIEMENS NYM 0.3/0.5KV or equivalent, in
PVC conduits, connected and tested, including
mounting clips, all as specified and as shown
on drawings:-
7.3.1 Cables
7.3.1.1 5x2.5mm sq. from MDB to SDB-B ml 5.00 108.00 540.00
7.3.1.2 3x4mm sq. from MDB to SDB-G1 ml 17.00 95.00 1,615.00
7.3.1.3 3x4mm sq. from MDB to SDB-G2 ml 18.00 95.00 1,710.00
7.3.1.4 3x4mm sq. from MDB to SDB-G3 ml 15.00 95.00 1,425.00
7.3.1.5 5x4mm sq. from MDB to SDB-1A ml 21.00 138.00 2,898.00
7.3.1.6 5x4mm sq. from MDB to SDB-1B ml 21.00 138.00 2,898.00
7.3.1.7 5x4mm sq. from MDB to SDB-2A ml 26.00 138.00 3,588.00
7.3.1.8 5x4mm sq. from MDB to SDB-2B ml 26.00 138.00 3,588.00
7.3.1.9 5x10mm sq. from MDB to SDB-3A ml 32.00 315.00 10,080.00
7.3.1.10 5x10mm sq. from MDB to SDB-3B ml 30.00 315.00 9,450.00
7.3.1.11 5x10mm sq. from MDB to SDB-4A ml 37.00 315.00 11,655.00
7.3.1.12 5x10mm sq. from MDB to SDB-4B ml 35.00 315.00 11,025.00
7.3.1.13 3x95/50mm sq. from intake point to MDB ml 23.00 2,800.00 64,400.00
7.3.2 Conduits and Pipies
7.3.2.1 20mm diameter from MDB to SDB-B ml 5.00 26.00 130.00
7.3.2.2 25mm diameter from MDB to SDB-G1 ml 17.00 30.00 510.00
7.3.2.3 25mm diameter from MDB to SDB-G2 ml 18.00 30.00 540.00
Page 9
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
7.3.2.4 25mm diameter from MDB to SDB-G3 ml 15.00 30.00 450.00
7.3.2.5 25mm diameter from MDB to SDB-1A ml 21.00 30.00 630.00
7.3.2.6 25mm diameter from MDB to SDB-1B ml 21.00 30.00 630.00
7.3.2.7 25mm diameter from MDB to SDB-2A ml 26.00 30.00 780.00
7.3.2.8 25mm diameter from MDB to SDB-2B ml 26.00 30.00 780.00
7.3.2.9 32mm diameter from MDB to SDB-3A ml 32.00 65.00 2,080.00
7.3.2.10 32mm diameter from MDB to SDB-3B ml 30.00 65.00 1,950.00
7.3.2.11 32mm diameter from MDB to SDB-4A ml 37.00 65.00 2,405.00
7.3.2.12 32mm diameter from MDB to SDB-4B ml 35.00 65.00 2,275.00
7.3.2.13 110mm diameter from intake point to MDB ml 13.00 155.00 2,015.00
7.4 Distribution Boards
Page 10
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
7.5 Light Points
7.5.1 Flush mounted light points fed through PVC
insulated conductors of 3x2.5mm2 inside PVC
conduits of 16mm diameter, including junction
boxes with covers, screw type insulating caps,
all complete
No 250.00 309.00 77,250.00
7.6 Extra Over Light Points for Flush Mounted
Switches
Page 11
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
7.7.12 Type 14: Compact fluorescent ceiling fitting
suitable for outdoor area, with 1xCFL 18W
lamp No 54.00 950 51,300.00
7.7.13 Type 15
FLUORESCENT 2x18W LAMP, CEILING
FITTING EXIT LIGHT WITH PICTOGRAM,
Philips TCS 198 2x TL-D 18w , lamp socket
G13 with 2x18w flourescent lamp +3hrs
emergency kit
No 7.00 3800 26,600.00
7.7.14 Type 16
FLUORESCENT 2x18W LAMP, WALL
FITTING EXIT LIGHT WITH PICTOGRAM,
Philips TCS 198 2x TL-D 18w , lamp socket
G13 with 2x18w flourescent lamp +3hrs
emergency kit
No 7.00 3800 26,600.00
7.8 Flush Mounted Socket Outlet Points
7.8.1 10-16A/1P flush mounted socket outlet points
fed through PVC insulated conductors of
3x2.5mm2 inside PVC conduit of 16mm
diameter including junction boxes with covers,
screw type insulating caps and all complete.
No 193.00 370 71,410.00
7.8.3 25A/1P flush mounted socket outlet points fed
through PVC insulated conductors of 3x6 mm²
inside regid PVC conduits of 25mm diameter
including junction boxes with covers, and
insulating screw cap connectors all for flush
mounting
No 16.00 480 7,680.00
7.8.4 16A/3P flush mounted socket outlet points fed
through PVC insulated conductors of 5x2.5
mm² inside regid PVC conduits of 20mm
diameter including junction boxes with covers,
screw type insulating caps, and all complete.
No 2.00 610 1,220.00
7.9 Flush Mounted Socket Outlets with Earth
Contact
Type Legrand or Equivalent complete with
boxes, screw type plates and accessories.
7.9.1 Socket outlet of 10A/16A 1Phase No 157.00 110.00 17,270.00
7.9.2 Water Heater Socket outlet of 10A/16A 1Phase No 36.00 150.00 5,400.00
7.9.4 Socket outlet of 25A 1Phase No 16.00 190.00 3,040.00
7.9.5 Socket outlet of 16A/3P No 2.00 195.00 390.00
7.10 TV System
7.10.1 Supply and install sattelite dish 2.0m diameter
with universal LNB per sattelite station
including roof mounting bracket and SAT-IF
cable up to head end equipment.
No 1.00 3,000.00 3,000.00
7.10.2
TV point fed through RG6 75ohms broad band
Co-axial cable (47-2500MHz) suitable for
TV/FM/SAT signal distribution inside PVC
conduit of 20mm diameter, including junction
boxes with covers, insulating screw cap
connectors No 29.00 450.00 13,050.00
7.10.3 TV Terminal Box No 5.00 550.00 2,750.00
7.10.4 Flush mounting terminal SAT/TV/FM outlet. No 29.00 160.00 4,640.00
7.11 Telecom / Data
Page 12
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
7.11.1
Supply and install all server equipment such as
- switches, PABX, MDF, chords, cable
organizer, patch panels, UPS etc… inside rack
cabinate. Terminate incoming cables, test and
commission. Prepare shop drawings and agree
with the engineer before supply and install
products. Ls 5.00 16,294.00 81,470.00
7.11.2 Data/telephone points fed through 2x(twisted
pair category 6E UTP cable) inside PVC
conduit of 25mm diameter. No 36.00 380.00 13,680.00
7.11.3 Flush mounting RJ45 Data/telephone outlet
CAT5E type LEGRAND Suno, range with 8-
contacts complete with cover and clip on
support frame. No 36.00 182.00 6,552.00
7.12 Bell System
7.12.1 Suplly and install Bell call points fed through
PVC insulated conductor of 2 x 1.5mm2 inside
thermo plastic conduit of ø 16mm complete
with all connection and fixing accessories. No 8.00 295.00 2,360.00
7.12.2 Bell push button with bell sign for flush
mounting No 4.00 110.00 440.00
7.12.3 Bell/buzzer for bell call system No 4.00 450.00 1,800.00
7.13 Generator
7.13.1
Supply and install Generator that can operate
automatically (power/supply turned off),
Standby diesel generator: Smax=125kVA,
voltage=3 Phase, 380/220 Volt, 0.8 power
factor, 4 Wire + Earth, 50 Hz The generator
shall be equipped with: automatic voltage
regulator (AVR), automatic transfer switch
(ATS) No 1.00 437,500.00 437,500.00
TOTAL CARRIED TO SUMMARY 1,489,964.00
8.SANITARY INSTALLATION
All fixtures which specified below is subjected
to the consultant approval, based on
samples,catalogues and brochures presented
by the contractor.
8.1 Hand Wash Basin
Page 13
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
8.2 Water closet
Page 14
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
8.8 Shower Trey
Supply and fix Shower trays made from
vitreous enameled sheet steel, slip resistant
with adjustable shower head and all other
necessary accessories.The fixture shall
conform to BS6340-7:1983 or equivalent
institution. The waste fittings, connecting
pieces, fixing and supporting element shall
comply with the relevant clauses of BS
standards or equivalent institution.
Size:- 700 x 700
mm. No 20.00 2,300.00 46,000.00
8.9 Tower hanger
Supply and fix towel hanger 610 x 25 mm with
chrome plated tubular towel rail complete with
the necessary accessories. No 20.00 210.00 4,200.00
8.10 Kitchen Sink
Supply and fix double bowl stainless steel
kitchen sink with brass chrome plate trap. The
waste fittings, connecting pieces, fixing and
supporting element and otheraccessories which
complete the set sahll comply with BSEN
695;1997 or the relevant clauses of BS
standards or equivalent institution. The tap
ware shall comply to BS2878:1980
Size 1500 x 600
x 150mm (bowl depth) No 16.00 1,200.00 19,200.00
8.11 Eletric Water Heater
Page 15
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
8.12 PPR-Pipes
Page 16
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
Page 17
ITEM
DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
No.
Page 18
TAKE OFF SHEET
ST
Timizing Dimension Quantity Item Description
A.SUB-STRUCTURE
1.Excavation & earthwork
Site clearing
1 1 15.91
22.00 350.02 m²
350.02 m² total
Bulk excavation in ordinary soil to a depth not
exceeding 1500 mm from reduced level.
1 1 186.50
1.50 279.75 m³
279.75 m³ total
Bulk excavation in ordinary soil to a depth not
exceeding 3000 mm from reduced level.
1 1 186.50
1.50 279.75 m³
279.75 m³ total
Bulk excavation in ordinary soil to a depth not
exceeding 3000 mm from reduced level.
1 1 186.50
1.50 279.75 m³
279.75 m³ total
Pit excavation in ordinary soil to a depth not exceeding
1500 mm from reduced level.
1 6 2.20 F-1
2.20
1.50 43.56 m³
1 12 2.60 F-2
2.60
1.50 121.68 m³
1 2 2.90 F-3
2.90
1.50 25.23 m³
190.47 m³ Total
Pit excavation in ordinary soil to a depth not over 1500
mm but not exceeding 3000mm from reduced level.
1 6 2.20 F-1
2.20
1.50 43.56 m³
1 12 2.60 F-2
2.60
1.50 121.68 m³
1 2 2.90 F-3
2.90
1.50 25.23 m³
190.47 m³ Total
Trench to a depth not exceeding 1500mm.starting from
reduced ground level.
1 1 56.27
1.50
1.00 84.41 m³
84.41 m³ Total
19
Back fill around isolated footing foundation column,and
1.30 masonry wall with….
1 1 465.35
-74.20 391.15 m3
391.15 m3 Total
20
Ditto as item above , but under hard core
1 1 279.75 `
-65.28 214.48 m 3
214.48 m3 Total
Cart away surplus excaveted……
1,374.60
1,374.60 Total
1.37 25cm thick basaltic or equivalent stone hardcore
1 1 10.30
15.46 159.24
1 1 2.70
1.27 3.42
162.66 m total
5cm thick lean concrete class C-5, 150kg of cement
1.1 /m under:
3
a) Footing pads
1 6 1.80 F-1
1.80 19.44 m²
1 12 2.20 F-2
2.20 58.08 m²
1 2 2.50 F-3
2.50 12.50 m²
90.02 m² Total
b) Basement Floor Beam
1 1 10.52 BFB 3
0.40 4.21 m²
1 1 10.67 BFB 4
0.40 4.27 m²
1 1 10.87 BFB 5
0.40 4.35 m²
1 2 17.16 BFB 8
0.40 13.72 m²
26.55 m²
c) Stone masonary wall
1 1 56.27
0.60 33.76
33.76 Total
1.2 Reinforced concrete class C-25,360kg of cement
a) Footing pads
1 6 1.70 F-1
1.70
0.40 6.94 m³
1 12 2.10 F-2
2.10
0.50 26.46 m³
1 2 2.40 F-3
2.40
0.70 8.06 m³
41.46 m³ Total
b) Foundation column
1 14 2.15 C-1
0.30
0.30 2.71 m³
1 4 2.05 C-2
0.30
0.30 0.74 m³
21
1 2 1.85 C-3
0.40
0.40 0.59 m³
4.04 m³ Total
c) Basement Floor Beam
1 1 3.20 BFB 1
0.30
0.40 0.38 m³
1 1 10.32 BFB 2
0.30
0.40 1.24 m³
1 1 10.52 BFB 3
0.30
0.40 1.26 m³
1 1 10.67 BFB 4
0.30
0.40 1.28 m³
1 1 10.87 BFB 5
0.30
0.40 1.30 m³
1 1 11.10 BFB 6
0.30
0.40 1.33 m³
1 2 15.97 BFB 7
0.30
0.40 3.83 m³
1 2 17.43 BFB 8
0.30
0.40 4.18
14.80 m³
d) Retaining wall
1 1 48.47
0.20
1.90 18.42 m3
18.42 m3 total
e) Ground Floor Beam
1 1 3.72 GB 1
0.30
0.40 0.45 m³
1 1 3.70 GB 2
0.30
0.40 0.44 m³
1 1 10.52 GB 3
0.30
0.40 1.26 m³
1 1 10.67 GB 4
0.30
0.40 1.28 m³
1 1 10.87 GB 5
0.30
0.40 1.30 m³
1 1 11.10 GB 6
0.30
0.40 1.33 m³
1 4 15.97 GB 7
0.30
0.40 7.67 m³
13.73 m³
f) In 10cm thick Basement floor slab.
1 1 175.36
1.00 175.36
22
175.36 Total
e) In 15cm thick ground floor slab.
1 1 166.79
1.00 166.79
166.79 Total
f) enterance concrete steps
1 12 3.46 Steps Area=1/2*0.15*0.3 =0.0225
0.02 0.93
1 1 3.46 Soffit Area=2.3*0.15=0.615
0.615 2.13
3.06
Provide, cut and fix in position sawn wooden or steel
formwork which ever appropriate.
a) Footing pads
4 6 1.70 F-1
0.40 16.32 m²
4 12 2.10 F-2
0.50 50.40 m²
4 2 2.40 F-3
0.70 13.44 m²
80.16 m² Total
b) Foundation column
4 14 2.15 C-1
0.30 36.12 m²
4 4 2.05 C-2
0.30 9.84 m²
4 2 1.85 C-3
0.40 5.92 m²
51.88 m² Total
c) Basement Floor Beam
2 1 3.20 BFB 1
0.40 2.56 m²
2 1 10.32 BFB 2
0.40 8.26 m²
2 1 10.52 BFB 3
0.40 8.42 m²
2 1 10.67 BFB 4
0.40 8.54 m²
2 1 10.87 BFB 5
0.40 8.70 m²
2 1 11.10 BFB 6
0.40 8.88 m²
2 2 15.97 BFB 7
0.40 25.55 m²
2 2 17.43 BFB 8
0.40 27.89 m²
98.80 m²
d) Retaining wall
2 1 48.47
1.90 184.19
184.19 m2
e) Ground Floor Beam
2 1 3.72 GB 1
0.40
2.97 m²
2 1 3.70 GB 2
0.40
2.96 m²
2 1 10.52 GB 3
0.40
8.42 m²
23
2 1 GB 3
8.42 m²
2 1 10.67 GB 4
0.40
8.54 m²
2 1 10.87 GB 5
0.40
8.69 m²
2 1 11.10 GB 6
0.40
8.88 m²
2 4 15.97 GB 7
0.40
51.10 m²
91.56 m²
e) In 15cm thick ground floor slab.
1 1 166.79
1.00 166.79
166.79 Total
f) enterance concrete steps
1 12 3.46 Steps
0.30 12.46
1 13 3.46 Steps
0.15 6.75
1 1 3.46 soffit
4.10 14.19
33.40
MASONERY WALL
Below NGL
1 1 56.27
0.80
0.50 22.51 m3
22.51 m3 Total
Dito but above NGL
1 1 56.27
0.70
0.50 19.69 m3
19.69 m3 Total
B.SUPER-STRUCTURE
1.Concrete Works
1.1 Reinforced concrete work in c-25 with
a) Elevation Column
24
1 14 15.10 C-1
0.30
0.30 19.03 m³
1 4 16.90 C-2
0.30
0.30 6.08 m³
1 2 15.10 C-3
0.40
0.40 4.83 m³
29.94 m³ Total
b) floor Beam (1st - Roof)
4 1 3.72 FB-1
0.40
0.30 1.79 m³
4 1 3.70 FB-2
0.40
0.30 1.78 m³
4 1 10.52 FB-3
0.40
0.30 5.05 m³
4 1 10.67 FB-4
0.40
0.30 5.12 m³
4 1 10.86 FB-5
0.40
0.30 5.21 m³
4 1 11.10 FB-6
0.40
0.30 5.33 m³
4 4 15.96 FB-7
0.40
0.30 30.64 m³
54.92 m³ total
d) roof Beam
1 3 3.20 RB-1'
0.40
0.30 1.15 m³
1 2 5.71 RB-2'
0.40
0.30 1.37 m³
1 1 3.72 RB-1
0.40
0.30 0.45 m³
1 1 3.70 RB-2
0.40
0.30 0.44 m³
1 1 10.52 RB-3
0.40
0.30 1.26 m³
1 1 10.67 RB-4
0.40
0.30 1.28 m³
1 1 10.86 RB-5
0.40
0.30 1.30 m³
1 1 11.10 RB-6
0.40
0.30 1.33 m³
1 4 15.96 RB-7
0.40
0.30 7.66 m³
25
16.24 m³ total
e) Suspended Floor solid slab
1 4 187.35 1st - 4th floor slab
1.00 749.40 m²
749.40 m² total
f) Suspended roof solid slab
1 1 206.22 Roof slab
1.00 206.22 m²
206.22 m² total
g) Stair case-1
10 1 3.10 soffit
3.25
0.25 25.19 m³
5 1 3.25 landing
1.27
0.25 5.16 m³
5 18 1.20 Steps Area=1/2*0.15*0.3 =0.0255
0.03 2.75 m³
33.10 m³ total
Provide cut and Fix in position sawn zigba wood
formwork or equivalent.
a) Elevation Column
4 14 15.10 C-1
0.30
253.68 m³
4 4 16.90 C-2
0.30
81.12 m³
4 2 15.10 C-3
0.40
48.32 m³
383.12 m² Total
26
b) floor Beam (1st - 4th floor)
4 2 3.72 FB-1
0.40
11.90 m²
4 2 3.70 FB-2
0.40
11.84 m²
4 2 10.52 FB-3
0.40
33.66 m²
4 2 10.67 FB-4
0.40
34.14 m²
4 2 10.86 FB-5
0.40
34.75 m²
4 2 11.10 FB-6
0.40
35.52 m²
4 8 15.96 FB-7
0.40
204.29 m²
366.10 m2 total
d) roof Beam
2 3 3.20 RB-1'
0.40
7.68 m²
2 2 5.71 RB-2'
0.40
9.14 m²
2 1 3.72 RB-1
0.40
2.98 m²
2 1 3.70 RB-2
0.40
2.96 m²
2 1 10.52 RB-3
0.40
8.42 m²
2 1 10.67 RB-4
0.40
8.54 m²
2 1 10.86 RB-5
0.40
8.69 m²
2 1 11.10 RB-6
0.40
8.88 m²
2 4 15.96 RB-7
0.40
51.07 m²
108.36 m2 total
e) Suspended Floor solid slab
1 4 187.35 1st - 4th floor slab
1.00 749.40 m²
749.40 m² total
f) Suspended roof solid slab
1 1 206.22 Roof slab
1.00 206.22 m²
206.22 m² total
27
g) Stair case-1
10 1 3.10 soffit
3.25
100.75 m²
5 1 3.25 landing
1.27
20.62 m²
5 18 1.20 Steps
0.30 32.40 m²
5 20 1.20 Steps
0.15 18.00 m²
171.77 m² total
28
NO. OF
NO. OF TOTAL
DIA LENGTH BARS
LOCATION MEMBE NO . OF
(MM) (M) PER
R BARS 8.00 10.00 12.00 14.00 16.00 20.00 24.00
MEMBER
SUB STRUCTURE
Footing Pad
8 0.8 41 2 82 65.60
29
NO. OF
NO. OF TOTAL
DIA LENGTH BARS
LOCATION MEMBE NO . OF
(MM) (M) PER
R BARS 8.00 10.00 12.00 14.00 16.00 20.00 24.00
MEMBER
St-up 8 1.20 87 5 435 522.00
FB-4 16 11.27 6 5 30 338.10
16 1.68 1 5 0.00
16 2.23 1 5 0.00
16 2.23 1 5 0.00
16 1.68 1 5 0.00
St-up 8 1.20 90 5 450 540.00
FB-5 16 11.47 6 5 30 343.95
16 1.71 3 5 15 25.65
16 2.26 2 5 10 22.60
16 3.50 2 5 10 35.00
St-up 10 1.20 69 5 345 414.00
FB-6 16 11.70 6 5 30 351.00
16 1.75 2 5 10 17.50
16 2.30 2 5 10 23.00
St-up 8 1.20 86 5 430 516.00
FB-7 16 17.26 6 20 120 2071.20
16 6.48 1 20 20 129.60
16 4.98 2 20 40 199.20
St-up 8 1.20 61 20 1220 1464.00
10 1.20 56 20 1120 1344.00
1 Floor to Roof Slab
st
1 8 6.11 14 5 70 427.70
2 8 5.98 14 5 70 418.25
3 8 5.03 13 5 65 326.63
4 8 3.25 91 5 455 1478.75
5 8 5.04 13 5 65 327.60
6 8 4.47 5 5 25 111.63
7 8 4.28 12 5 60 256.80
8 8 4.48 5 5 25 112.00
30
NO. OF
NO. OF TOTAL
DIA LENGTH BARS
LOCATION MEMBE NO . OF
(MM) (M) PER
R BARS 8.00 10.00 12.00 14.00 16.00 20.00 24.00
MEMBER
9 8 4.28 12 5 60 256.80
10 8 5.22 26 5 130 678.60
11 8 5.23 26 5 130 679.90
12 8 5.38 33 5 165 887.70
13 8 5.38 33 5 165 887.70
14 8 5.49 23 5 115 630.78
15 8 5.05 19 5 95 479.28
16 8 5.00 23 5 115 574.43
17 8 3.25 24 5 120 390.00
18 8 4.25 69 5 345 1466.25
19 8 6.32 26 5 130 820.95
19' 8 5.72 30 5 150 857.25
20 8 5.48 19 5 95 520.13
21 10 2.30 30 5 150 345.00
22 10 2.30 43 5 215 494.50
23 8 2.30 19 5 95 218.50
24 8 2.30 19 5 95 218.50
25 8 2.30 28 5 140 322.00
26 8 2.30 28 5 140 322.00
27 10 2.34 23 5 115 268.53
28 10 3.03 24 5 120 363.60
29 8 2.34 74 5 370 863.95
30 8 2.89 75 5 375 1083.75
31 10 2.24 21 5 105 235.20
32 10 2.21 20 5 100 220.50
33 10 2.48 36 5 180 446.40
Water tanker slab
1 8 5.12 36 1 36 184.32
31
NO. OF
NO. OF TOTAL
DIA LENGTH BARS
LOCATION MEMBE NO . OF
(MM) (M) PER
R BARS 8.00 10.00 12.00 14.00 16.00 20.00 24.00
MEMBER
2 8 7.64 19 4 76 580.26
3 10 2.93 19 2 38 111.15
RB-1 16 3.85 6 2 12 46.20
st-up 16 1.43 2 2 4 5.70
8 1.20 24 2 48 57.60
16 6.37 6 2 12 76.38
RB-1 16 3.28 1 2 2 6.55
16 1.76 1 2 2 3.52
st-up 8 1.20 45 2 90 108.00
Staircase
14 5.64 12.00 5.00 60 338.40
14 1.85 12.00 5.00 60 110.70
14 1.72 12.00 5.00 60 103.20
14 2.18 12.00 5.00 60 130.50
14 2.24 12.00 5.00 60 134.10
8 1.55 35.00 5.00 175 271.25
8 1.55 35.00 5.00 175 271.25
8 1.23 100.00 5.00 500 615.00
14 4.13 12.00 5.00 60 247.80
14 1.88 12.00 5.00 60 112.50
14 1.63 12.00 5.00 60 97.80
14 2.36 12.00 5.00 60 141.30
8 1.55 31.00 5.00 155 240.25
8 1.55 31.00 5.00 155 240.25
8 1.23 100.00 5.00 500 615.00
14 1.96 24.00 1.00 24 46.92
14 6.03 24.00 1.00 24 144.72
10 0.896 264.00 1.00 264 236.54
10 2.22 24.00 1.00 24 53.28
8 3.66 22.00 1.00 22 80.41
Landing Beam-1 16 3.85 7.00 5.00 35 134.75
32
NO. OF
NO. OF TOTAL
DIA LENGTH BARS
LOCATION MEMBE NO . OF
(MM) (M) PER
R BARS 8.00 10.00 12.00 14.00 16.00 20.00 24.00
MEMBER
10 1.20 24.00 5.00 120 144.00
Landing Beam-2 16 4.38 3.00 5.00 15 65.70
8 1.20 5.00 5.00 25 30.00
TOTAL LENGTH, M 25,792.79 4,676.70 - 1,607.94 7,485.78 - -
UNIT WEIGHT , KG/ M 0.40 0.62 0.89 1.21 1.58 2.47 3.56
TOTAL WEIGHT,KG 10,188.15 2,885.52 - 1,944.00 11,820.04 - -
33
0.00
6.31
-
34