The document compares the costs of various items in the sanctioned estimate versus the actual working estimate for urgent road repairs between km 3/950 to 4/250 in Ananthapuramu district, Andhra Pradesh, India. Several items such as earthwork, concrete work, and road surfacing saw changes in quantities, rates, and costs between the estimates. The total estimated cost was Rs. 40,00,001 but the actual working estimate is Rs. 40,00,000.

Uploaded by

VannurSwamy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
19 views

CST

The document compares the costs of various items in the sanctioned estimate versus the actual working estimate for urgent road repairs between km 3/950 to 4/250 in Ananthapuramu district, Andhra Pradesh, India. Several items such as earthwork, concrete work, and road surfacing saw changes in quantities, rates, and costs between the estimates. The total estimated cost was Rs. 40,00,001 but the actual working estimate is Rs. 40,00,000.

Uploaded by

VannurSwamy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

CAMPARTIVE STATEMENT

NAME OF WORK;-Urgent Repairs to road in Km 3/950 to 4/250 of Bukkapatnam Nallamada Pulagampalli road in Ananthapuramu district.

S.NO Description As per sanctioned estimate As per working estimate More Less Remarks

qty rate Amount qty rate Amount

As per actual execution


Scarifying the BT surface to a deoth
1 1925 8.4 16170 1995.00 8.4 16758 588
of 50mm
As per actual execution
Forming embankment with side earth
2 500 154 77000 254.66 154 39217.64 37782.36
by mechanical means up to SDR
As per actual execution
Construction of Granular sub-base by
3 providing HBG material confirming to 195 1919 374205 222.94 1919 427821.86 53617
Grading - V

As per actual execution


Providing, Laying, Spreading and
compacting graded HBG crushed
4 43 2117 91031 0.00 2117 0 91031.00
stone aggregate to Wet Mix
macadem

As per actual execution

Providing and applying tack coat with


5 42 10 420 0.00 10 0 420.00
bitumen VG-10 (Bulk)

Providing Vibrated Cement Concrete As per actual execution


6 193.0 3696 713328 199.50 3696 737352 24024
(1:4:8)
Vibrated cement concrete M 35 As per actual execution
7 385.0 5434 2092090 399.00 5434 2168166 76076
grade concrete
Providing Uncoated Mild Steel bars As per actual execution
8 0.409 53519 21889 0.320 53519 17126 4763.19
(Fe-250)
As per actual execution
9 Providing 25.40 mm mastic pads 15.40 839 12921 8.40 839 7048 5873.00

As per actual execution

10 providing HYSD bars for tie bars 0.49 53781 26352.69 0.25 53781 13445.25 12907.44

As per actual execution


Providing 30 mm thick bituminous
11 1 8203 8203.00 0.00 8203 0 8203.00
concrete
As per actual execution
12 Contraction joint groove cutting 0 0 0 726.00 66.8 48496.8 48497

As per actual execution


13 treating pavement by VDF 0 0 0 1995.00 70 139650 139650

14 Provision for Seigniorage charges 117978.00 112553.00 5425.00

15 Provision for NAC 3434.00 3615.00 181

16 provision for GST 426603.00 426060.00 543.00

17 Provision for Avagahana Sadassu 2500.00 2500.00


18 Provision for unforeseen 15876 20944.00 5068

19 TP 0 -163995.23 163995.23

4000001 4000000 347701 330943