Doosan Power Systems India PVT Limited: Magnetic Particle Examination Report
Doosan Power Systems India PVT Limited: Magnetic Particle Examination Report
No :
MAGNETIC PARTICLE EXAMINATION REPORT DATE :
CUSTOMER : M/s BANDEL TPS EQUIPMENT : SIMS – YOKE
CUSTOMER P.O.No. : ------ DRAWING No. :
PROJECT : UNIT #5, 210MW PART No. :
: PART NAME :
QAP.No./FQP No : FQP WELD JOINT DETAIL :
DATE OF
QAP. STAGE No. : AFTER Stress Relieving :
EXAMINATION
PROCEDURE No : REV:
ACCEPTANCE STANDARD : ASME SEC VIII Div I
MATERIAL & THICKNESS :
LIGHTING
STAGE OF TEST : AFTER SR :
EQUIPMENT
EXTENT OF TEST : 100 %
SURFACE CONDITION : SMOOTH LIGHT INTENSITY : LUX
DISPOSITION :
EXAMINED BY
FORMAT No:QC/F/06