Property Survey Report For: Bamburi Cement LTD
Property Survey Report For: Bamburi Cement LTD
For
Bamburi Cement Ltd
Company
Andrew Coxon
AIG Engineer
Insurance Broker
"Our survey of our customer's operations is for underwriting/business partners' purposes and to assist our customers in
their loss control activities. However, no responsibility is assumed for the discovery and elimination of hazards, which
could possibly cause accidents or damage, nor do we certify to the adequacy of any water supply system or the proper
functioning or adequacy of any fire protection system at any facility that is inspected. Compliance with any submitted
recommendations in no way guarantees the fulfilment of obligations as may be required by any local, state or federal law."
Coats No. AIG SOUTH AFRICA LTD IS AN AUTHORISED FINANCIAL SERVICES PROVIDER LICENSED IN
SOUTH AFRICA FSP: 15805. REGISTERED ADDRESS, 77 DE KORTE ST, BRAAMFONTEIN,
JOHANNESBURG, SOUTH AFRICA
SCOPE
• A site tour to evaluate the layout of the factory, the associated hazard profile and
extent of protections to key exposures.
• A review of key management systems governing the prevention and mitigation of
loss.
• An exit interview to clarify progress on previous recommendations and the direction
of new risk management recommendations to further reduce the likelihood and
severity of losses.
Previous Recommendations
There was no formal record of receipt or explicit action of the first survey report’s
recommendations. The recommendations are repeated for action.
Additional Comments: One of the CO2 bottle banks, for the coal dust explosion
suppression system, was indicating 34Barg, well below the minimum allowable limit of
100Barg. This indicates an absence of an integral inspection and maintenance
programme for fire protection equipment, which compromises the integrity of the fire
protections and specifically impairs these critical protections. The recommendation is
repeated for the inclusion of this key protection item in the self-inspection programme.
The location of the HFO service tank beneath the kilns’ control room
represents a key fire exposure to this area. In the event of a tank fire
there is an obvious probability of escalation to the control room affecting
AIG SOUTH AFRICA IS AN AUTHORISED FINANCIAL SERVICES PROVIDER LICENSED IN SOUTH
AFRICA FSP: 15805. REGISTERED ADDRESS: 77 DE KORTE ST, BRAAMFONTEIN,
JOHANNESBURG, SOUTH AFRICA
The transformers are fouled with dust from the plant environment. The
fouling of this equipment reduces the efficiency of the oil cooling fins
resulting in increased oil temperatures. This accelerates the degradation
of the cooling oils, increasing the likelihood of breakdown and fire. To
manage the condition of transformer oils through more favourable
operating temperature windows, it is recommended that the frequency of
transformer cleaning be reviewed to prevent the extent of fouling
observed during the survey.
Additional Comments: During the survey hot work activities were in progress on
RM5 in the absence of a permit. This recommendation is repeated for reviewed
consideration and action.
New Recommendations
Previous Recommendations
There was no formal record of receipt or explicit action of the first survey report’s
recommendations. The recommendations are repeated for action.
Additional Comments: Although the condition of the coal mill area was in a much
improved state of housekeeping and the furnace coal pump’s area has been opened up
to remove confinement and provide natural ventilation, there is still an accumulation of
coal dust representing a secondary dust explosion risk. The recommendation is
repeated for formal feedback on the dust cleaning facilities and management systems
governing the maintenance practices of these hazardous dust locations.
The gravity tank fire water supply for the hydrants is inadequate. In the
absence of an adequate and reliable water supply, the fire fighting capability
of the site is compromised. This increases the probability of escalation and
interruption to business operations. To ensure adequate water resources for
manual and automatic fire fighting measures, it is recommended that an
adequate private water supply be provided in accordance with recognised
standards (eg. NFPA20/22, Installation of Fire Pumps and Water Tanks).
The water supply should be sized to deliver 2000-1800l/min at the most
remote hydrant point at a minimum of 300kPag pressure.
Additional Comments: The static pressure of the private water supply is about
350kPag and a hydrant test during the 2005 survey developed an estimated flow of
500l/min at 25kPag. This recommendation is repeated for reviewed consideration and
action.
99-11-10 Provision of Fire Protection Measures for the HFO Bulk Storage Facility
(Revised)
The HFO storage tanks are located adjacent to the Works/Control Room
building. In the event of a tank fire there is a likely conflagration exposure to
the critical Works/Control Room building, which will result in the interruption
to production operations. To manage the conflagration exposure in this
critical area it is recommended that a fire wall (2-hour fire rated) be erected
between the tanks and the building. In addition to this, a fire hydrant and
foam extinguishing equipment (eg. AF120 mobile unit) should be provided for
active protection.
New Recommendations
The presence of the RK2 transformer (oil filled) substation directly below the
Kiln 1/2 central electronic equipment room represents a key fire and
business interruption exposure. In the event of a transformer failure and fire
there is a likely conflagration exposure to the Kiln 1/2 electronic equipment
room, which will result in a critical business interruption loss. To manage
this critical fire and business interruption exposure, it is recommended that
the transformer be relocated to an area remote from the electronic
equipment room.
Alternatively, the substation enclosure should be fire proofed for 2hr fire
resistance, cable decking penetrations fire stopped (2hr fire rated), automatic
AIG SOUTH AFRICA IS AN AUTHORISED FINANCIAL SERVICES PROVIDER LICENSED IN SOUTH
AFRICA FSP: 15805. REGISTERED ADDRESS: 77 DE KORTE ST, BRAAMFONTEIN,
JOHANNESBURG, SOUTH AFRICA
sprinklers installed (10mm/min density) and bund walls provided for the
containment of oil and 30minutes of sprinkler flow volume (see FM5-4 –
Transformers, FM5-31 – Cables and Bus Bars, NFPA13 – Standard for the
Installation of Sprinkler Systems, NFPA221 – Standard for Fire
Walls/Barriers). The man-way opening to/from the cable tunnel should be
cut-off with 2hr rated fire-stops. The old cables and other combustible
storage should be removed and the enclosure maintained in a clean and
orderly condition (see Photograph). The cable reticulations should be
installed in properly secured rack arrangements in accordance with
recognized standards (see Recommendation 05-03-08).
There is no fixed, active fire protection installed in the cable tunnels. This
represents a critical fire and business interruption exposure. In the event of
a cable tunnel fire there is a likely conflagration exposure owing to the
presence of a grouped cable fire load and the general inaccessibility of the
area for manual intervention. To manage this critical fire and business
interruption exposure, it is recommended that automatic sprinkler protection
be provided for the cable tunnels (5mm/min design density over 216m2 or
30m linear distance, see FM5-31 Cables and Bus Bars). The sprinkler
protection should be designed and installed in accordance with a recognized
standard (eg. NFPA13 Standard for the Installation of Sprinkler Systems).
There are no automatic fire detection alarm systems installed in the critical
fire exposure areas (eg. Main Substation’s and other substations’ switch
panel rooms). In the absence of these protections the early warning of fire is
improbable, increasing the likelihood of conflagration and interruption to
business. To ensure early warning of fire in key areas it is recommended
that this protection be installed in these unprotected areas. The protection
should be provided in the sensitive administration areas, engineering
stores/offices, electrical substation/generator rooms and any other areas that
are not continuously occupied by personnel and where there is the
probability for the unacceptable spread of fire and disruption to business
operations. The alarms should be liked to a continuously occupied central
control station for monitoring and emergency response. See FM5-48
Standard on Automatic Fire Detection, NFPA72 National Fire Alarm Code.
SUMMARY
A survey of the Bamburi Cement Ltd manufacturing facility in Mombasa was carried out
on 24th March 2005 at the request of AIG Kenya. The objective of the survey was to
update underwriting information, review loss estimates, determine progress of previous
recommendations and provide direction on new risk management recommendations.
The survey was liaised through the Bamburi Cement Nairobi head office, however owing
to a communication breakdown, the Mombasa factory Management was not advised of
the visit, preventing Management planning and limiting the depth of the survey. This
was a second visit to the cement factory.
The Bamburi Cement facility in Mombasa is an established (1967, 1976) cement factory,
producing portland cement for the building construction industry (AIU Occupancy,
Cement, 3241, Hazard Grade 6 and Quarrying, 1422, Hazard Grade 1). The facility
produces about ??kt/annum of cement in a two-in-parallel kiln/mill (1200t/d, 1950t/d) line
operation. The cement is produced from on-site quarried deposits of coral stone, off-site
quarried (by contractor) deposits of shale and imported gypsum, bauxite and iron ore
from sources abroad.
The presence of large rotating equipment items (crushers, mills, rotary kilns) represents
an obvious exposure to machinery breakdowns. The arrangement, however, of the
production facility in two-in-parallel kiln/mill lines with spare redundant capacity in some
areas (eg. cement mills), represents a positive feature mitigating business interruption
exposures to machinery breakdowns. This is further managed through a preventative
maintenance philosophy incorporating time scheduled and predictive reliability centred
components using on/off-line condition monitoring. Infra-red imaging, vibration and oil
analyses are routinely programmed on electrical distribution equipment, bearings and
transformers. The maintenance programme is well managed and administrated through
a computerised system (MAXIMA) incorporating work order planning, documented work
instructions, history and other management reporting tools.
The key utility is electricity, which is purchased from a dual redundant Kenya Power and
Lighting Company (KPLC) 33kV supply. A critical business interruption exposure
associated with the supply is the presence of a single 23MVA, 33kV/11kV, KPLC power
transformer in the incoming switchyard. A service level agreement with KPLC specifies
the availability of a spare unit within a 7day lead time (?).
The Bamburi Cement facility is a multiple building complex, established on a very large
boundary plan. The main production buildings are lofty single and multiple storey
structures, constructed of concrete/steel frame, brick/steel sheeting walls, concrete deck
and concrete/steel sheeting roof (Construction Class AA/B). Internally the buildings
AIG SOUTH AFRICA IS AN AUTHORISED FINANCIAL SERVICES PROVIDER LICENSED IN SOUTH
AFRICA FSP: 15805. REGISTERED ADDRESS: 77 DE KORTE ST, BRAAMFONTEIN,
JOHANNESBURG, SOUTH AFRICA
communicate horizontally and vertically throughout, although there is generally a low fire
load and continuity of combustibles representing an improbable/negligible conflagration
exposure.
The primary hazards of the occupancy are those associated with the operation of heavy
production equipment, large HT electrical infrastructure, fired (pulverised coal) kilns and
the handling of combustible coal dusts. The fire/explosion hazards are considered
moderate in extent, which are restricted to localised areas, such as the kiln, electrostatic
precipitator/bag filters, electrical transformer/switch substations, cable tunnel areas,
conveyer belts, fuel storage and engineering stores. The combustible dust hazards and
explosion risks are managed through the provision of explosion venting and automatic
CO2 explosion suppression protection, although the integrity of these protections is
compromised by the absence of inspection, testing and maintenance programmes and
routine specialist hazard reviews. Peculiar business interruption exposures to fire are
the presence of an unprotected central electronic control equipment room, a
communicating oil filled transformer substation below this room and the absence of
recognised engineering standards governing the installation of grouped cables in the
cable tunnels and other substation areas.
The general fire protection is based on a manual philosophy incorporating hand fire
extinguishers for incipient stage fire defence and a hydrant main system for
secondary/developed fires. The hydrant main system is supplied from a private,
elevated tank, which head is inadequate for the hydrant demand and compromises the
integrity of this protection. The emergency management is developed under an
appointed command and fire response team structure, governed by documented
emergency procedures. Fire drills are exercised quarterly to test the co-ordination and
effectiveness of the emergency response. Public protection is provided by the Mombasa
fire brigade, a professional, full-time municipal service, located about 10-15minutes
away.
The kilns’ fines dust management has been upgraded through the installation of
electrostatic precipitators and bag filters, which has reduced general dust fouling of the
plant and the environment. A control system upgrade has centralised the electronic
control equipment in the old control room above and in direct communication with the
Kiln #2 transformer substation, representing a critical business interruption exposure to
fire.
LOSS HISTORY
GENERAL COMMENTS
PHOTOGRAPHS
View of new electrostatic precipitator and bag filters and good condition of facilities
Cable basement showing grouped cable arrangement and communication with cable
tunnel
View of ventilation screen opening from switch room showing communication with
transformer enclosure
View of unprotected cable tunnel opening and grouped cable installation features in RK2
transformer substation
SITE PLAN
SUPPORTING DOCUMENTS
Sketch/Drawing Yes No
Insured’s Brochure Yes No
Others (listed below) Yes No
• Site Plan
• Hot Work Permit & Procedure