DHPP Implementation Schedule

This document provides a schedule for the Dasu Hydel Power Project from 2015 to 2026. It outlines various project activities including construction of transmission lines from 2015 to 2021, access roads from 2015 to 2022, project colonies from 2019 to 2022, resettlement villages from 2019 to 2022, and the main dam works from 2017 to 2026. The schedule shows planned start and finish dates for over 30 different activities essential to the completion of the Dasu Hydel Power Project.

Uploaded by

Umer Bilal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
66 views

DHPP Implementation Schedule

This document provides a schedule for the Dasu Hydel Power Project from 2015 to 2026. It outlines various project activities including construction of transmission lines from 2015 to 2021, access roads from 2015 to 2022, project colonies from 2019 to 2022, resettlement villages from 2019 to 2022, and the main dam works from 2017 to 2026. The schedule shows planned start and finish dates for over 30 different activities essential to the completion of the Dasu Hydel Power Project.

Uploaded by

Umer Bilal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Dasu Hydel Power Project- 20210131 DHPP Implementation Schedule

Activity ID Activity Name Original Start Finish 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 027
Duration

3901 24-Aug-15 A 28-Apr-26 28-Apr-26, D


Dasu Hydel
Hyde Power Project- 20210131
230 02-Nov-15 A 25-Jul-21 25-Jul-21, 132 KV Transmission Line (TL-01)
132 KV Transmission
Tr Line (TL-01)
A1000 Line Work 227 02-Nov-15 A 14-Jul-21 Line Work
A1010 Grid Station Works 230 02-Nov-15 A 25-Jul-21 Grid Station Works
358 24-Aug-15 A 28-Feb-21 28-Feb-21, Right Access Bank Road-01 (RAR-01)
Right Access
Acc Bank Road-01 (RAR-01)
A1020 Preparation and Mobilization 87 24-Aug-15 A 06-Jan-21* Preparation and Mobilization
A1040 Road Construction 328 23-Sep-15 A 28-Feb-21 Road Construction
546 24-Aug-15 A 30-Apr-22 30-Apr-22, Relocation of Karakoram Highway-01 (KKH-01)
Relocation of Karakoram Highway-01 (KKH-01)
Relocatio
A1050 Preparation and Mobilization 90 24-Aug-15 A 09-Jan-21 Preparation and Mobilization
A1080 Road Construction 486 23-Oct-15 A 30-Apr-22 Road Construction
701 15-Jul-19 A 17-May-21 17-May-21, Project Colony-01 (PC-01)
Project Co
Colony-01 (PC-01)
A1090 Land Development including Internal Roads 340 15-Jul-19 A 14-Mar-21 Land Development including Internal Roads
A1100 Project Colony Buildings 610 25-Jan-20 A 27-Apr-21 Project Colony Buildings
A1110 Project Colony Utilities 385 02-Nov-20 A 17-May-21 Project Colony Utilities
363 01-Jul-21 28-Jun-22 28-Jun-22, Project Colony-02 (PCI-02)
Project Co
Colony-02 (PCI-02)
A1120 Land Development including Internal Roads 120 01-Jul-21* 28-Oct-21 Land Development including Internal Roads
A1130 Project Colony Buildings 244 28-Oct-21 28-Jun-22 Project Colony Buildings
A1140 Project Colony Utilities 121 28-Oct-21 25-Feb-22 Project Colony Utilities
2261 18-Jun-19 A 16-May-22 16-May-22, Choochang Resettlement of Village of Village Choochang and
Choochang Resettlement of Village of Village Choo
Choocha
A1160 Construction of Shatial Museum 486 18-Jun-19 A 12-Feb-21 Construction of Shatial Museum
A1170 Construction of Resettlement Villages 343 02-Sep-19 A 29-Apr-22 Construction of Resettlement Villages
A1175 Construction of Local Amenities and Utilities 370 29-Jul-20 A 16-May-22 Construction of Local Amenities and Utilities
364 01-Jul-21 29-Jun-22 29-Jun-22, Resettlement Villages (RVs)
Resettlement Villages (RVs)
Resettlem
A1180 Land Development 364 01-Jul-21* 29-Jun-22 Land Development
A1190 Access Roads 364 01-Jul-21 29-Jun-22 Access Roads
A1200 Utilities 93 30-Sep-21 31-Dec-21 Utilities
720 31-Dec-20 20-Dec-22 20-Dec-22, Right Access Bank Road-02 (RAR-02)
Right Access
Acc Bank Road-02 (RAR-02)
A1210 Preparation and Mobilization 90 31-Dec-20* 30-Mar-21 Preparation and Mobilization
A1220 Road Construction 660 01-Mar-21 20-Dec-22 Road Construction
720 01-Mar-21 A 20-Dec-22 20-Dec-22, Relocation of Karakoram Highway-02 (KKH-02)
Relocation of Karakoram Highway-02 (KKH-02)
Relocatio
A1250 Preparation and Mobilization 90 01-Jul-21 A 30-Mar-21
A1260 Road Construction 660 01-Mar-21 20-Dec-22 Road Construction
720 31-Dec-20 20-Dec-22 20-Dec-22, Right Access Bank Road-03 (RAR-03)
Right Access
Acc Bank Road-03 (RAR-03)
A1290 Preparation and Mobilization 90 31-Dec-20 30-Mar-21 Preparation and Mobilization
A1300 Road Construction 658 03-Mar-21 20-Dec-22 Road Construction
1945 23-Jun-17 A 28-Apr-26 28-Apr-26, M
Main Works-01
Wor :Dam,HSS (MW-01)
A1320 Preparatory Works 60 23-Jun-17 A 28-Feb-21 Preparatory Works
A1330 River Diversions, Tunnels & Coffer Dams 570 21-Oct-17 A 21-Sep-22 River Diversions, Tunnels & Coffer Dams
A1340 Dam Foundation Excavation Including Plunge Pool, etc. 785 20-Jan-21 15-Mar-23 Dam Foundation Excavation Including Plunge Pool, etc.
A1350 RCC Placement 900 22-Sep-22 09-Mar-25 RCC Placement
A1360 LLO Civil and Mechanical Works 710 15-Jul-23 23-Jun-25 LLO Civil and Mechanical
A1370 Design and Installation of HSS 1651 23-Jun-17 A 28-Mar-25 Design and Installation of HSS
A1380 Spill way Concrete and Installation #1 to #8 249 04-Feb-25 10-Oct-25 Spill way Concrete an
A1390 Flushing Tunnels 1445 01-Mar-21 12-Feb-25 Flushing Tunnels
A1400 Dam Control Building 365 02-Apr-23 31-Mar-24 Dam Control Building
A1410 Impounding 30 03-Apr-25 02-May-25 Impounding
A1420 Dewatering and Inspection 61 27-Feb-26 28-Apr-26 Dewatering a
3481 23-Jun-17 A 10-Feb-26 10-Feb-26, Main
Main Works-02:
Wor Power House)
Actual Level of Effort Remaining Work Milestone Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
Dasu Hydel Power Project- 20210131 DHPP Implementation Schedule
Activity ID Activity Name Original Start Finish 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 027
Duration

A1430 Preparatory Works 60 23-Jun-17 A 28-Feb-21 Preparatory Works


A1440 Intake Structure 960 13-May-20 A 16-Oct-23 Intake Structure
A1450 Power Tunnel 450 01-Mar-21 24-May-22 Power Tunnel
A1460 Power House Cavern 1500 28-May-18 A 07-Jun-25 Power House Cavern
A1470 Transformer Cavern 670 07-Mar-20 A 28-Feb-23 Transformer Cavern
A1480 Surge Chamber 1095 31-Dec-19 A 28-Apr-24 Surge Chamber
A1490 Tailrace Tunnel 1095 30-Apr-21 28-Apr-24 Tailrace Tunnel
A1500 Tailrace Outlet 365 01-Mar-21 28-Feb-22 Tailrace Outlet
A1510 GIL Tunnel 1200 01-Mar-21 12-Jun-24 GIL Tunnel
A1520 Switchyard and Control Building 395 01-Mar-21 30-Mar-22 Switchyard and Control Building
A1530 HSS Design Manufacturing, Testing, and Transportation 780 19-Jul-17 A 18-Feb-23 HSS Design Manufacturing, Testing, and Transportation
A1540 Installation of Intake Gate and Trashrack 1350 31-Dec-20 10-Sep-24 Installation of Intake Gate and Trashra
A1550 Installation of Gate for Surge Chamber 420 16-Nov-23 08-Jan-25 Installation of Gate for Surge Cha
A1560 Installation of Gate for Tailrace Outlet 210 02-Jul-23 27-Jan-24 Installation of Gate for Tailrace Outlet
A1570 Dewatering and Inspection 61 12-Dec-25 10-Feb-26 Dewatering and
1705 01-Feb-21 02-Oct-25 02-Oct-25, Main Work
Main Works
Wor Electro-Mechanical (EM-01)
A1580 Design, Manufacturing, Testing and Transportation 600 01-Feb-21* 23-Sep-22 Design, Manufacturing, Testing and Transportation
A1590 Draft Tube 365 21-Aug-22 20-Aug-23 Draft Tube
A1600 Spiral Casing 450 19-Dec-22 12-Mar-24 Spiral Casing
A1610 Turbine Equipment 450 18-Apr-23 10-Jul-24 Turbine Equipment
A1620 Installation of OHTC 120 16-Aug-23 13-Dec-23 Installation of OHTC
A1630 Generator Equipment 420 15-Oct-23 07-Dec-24 Generator Equipment
A1640 AIG/GIS Transformer 540 12-Feb-24 04-Aug-25 AIG/GIS Transformer
A1650 Commissioning 170 09-Apr-25 25-Sep-25 Commissioning
A1660 Various Tests During Operations 7 26-Sep-25 02-Oct-25 Various Tests During O

Actual Level of Effort Remaining Work Milestone Page 2 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation