04 - Sanjana Bhandiwad - Assignment 3 - Methods of Construction of Basement
04 - Sanjana Bhandiwad - Assignment 3 - Methods of Construction of Basement
• Construction of basement is difficult for it must be carried out below deep ground in adverse
condition such as existence of ground water, muddiness or limited working space.
• Besides, works are needed to be done amidst layers of props, struts, walling’s and shores, which
cannot be removed until the permanent works are completed and capable of carrying the final
loads.
• For each case of basement construction, the method of soil support, sub-soil condition, structure
of the basement as well as the layout requirement of the entire building must be taken into
consideration before designing the method of works.
• Transfer the vertical load on the existing wall down to the new lower foundation level, and,
• Hold back the horizontal load of the ground, hydrostatic pressure and any other surcharge loads
acting on the outside walls of the basement.
1. Foundation Benching
• Benching is a less costly and quicker way to create more space in your basement.
• It involves digging down to the depth you wish your new foundation floor to be and creating
new walls to extend from the new depth up to the existing.
• This new wall has to be reinforced and has a cap – which creates a bench-like structure around
your new foundation floor. You can use the new wall to create book cases, shelves or add
cupboards for storage.
• This method is good if what you need to do is create useable space to free up space elsewhere
in your home.
• However, benching may be the solution depending on the soil conditions around your home, the
nearness of your neighbour’s home, the sewage system your home uses, your budget or the
schedule in which you want to have the work completed.
2. Underpinning
Stage 1 – Excavation
Stage 2 – Reinforcement
Construction Sequence -
1. The sides of the excavation are sloped to provide stability, with possible slope protection to
maximise the angle of the slope.
2. Upon excavating to the required depth, the basement is constructed from bottom upwards.
3. After the completion of the basement, the remaining excavated areas between the basement
and the side slope are backfilled.
Construction -
• Rods are inserted into the soil alongside the slope, nets are cast over the slope and concrete are
sprayed onto them, to prevent the soil from eroding or sliding during rainy days.
• In some cases, pile sheeting may be provided to reduce differential settlement to the adjacent
buildings.
• In built-up urban areas, such a technique is often impractical in view of site constraints and the
need to restrict ground movements adjacent to the excavation.
• The main criteria to consider for an open cut technique is the geological condition of the site, as
this has a direct effect on the earth slope.
• The main limitation of this technique is that the site is exposed to the weather.
• Flooding usually occurs after a downpour.
• Provision of dewatering and temporary drainage system are necessary.
• When the trench is very deep and/or expensive backfill, materials are required, then a vertical
cut at the toe of the slope supported by shoring may be effective.
Advantages
Disadvantages
• The slope of the bank requires more excavation and backfill volume than the Other options.
• The only bank support is the strength of the soil. If drying, flooding, or change Of soil properties
weakens the soil, then sloughing and collapse can happen with Little or no warning.
• The sloped banks require a wider work area.
• The bank slopes may force the use of larger equipment because the distance.
• To reach into the trench is increased and a greater volume of soil must be Excavated and
backfilled.
• This technique is usually employed in constrained sites where ground movements to the adjacent
surrounding has to be kept to the minimum.
• Retaining walls are required to support the excavation with the provision of bracing as the
excavation proceeds downward until the deepest basement level.
• The basement is then constructed in the conventional way, bottom upwards in sequence with
removal of the temporary struts.
Construction –
• The figure shows the construction of a five storey basement with diaphragm wall around the
perimeter in a congested site.
• The diaphragm wall is supported with wall bracing and heavy strutting.
• A working stage is erected to provide access in and out the site, and to provide the platform for
mechanical plants to operate on.
• The excavation is carried out mainly by two large excavators with boom arms that can reach to
basement level 4.
• Excavated earth is carted away by Lorries. As the excavation proceeds to a deeper level, smaller
excavators are mobilised into the basement for excavation under the stage.
• The side of the excavation is supported using heavy lateral bracing (strutting), installed at various
depths with the subsequent progress of excavation, and the intermediate vertical king posts and
bracings.
• The stresses in the struts are monitored to ensure proper load transfer using jacks and adjustable
connectors.
• After the excavation, the basement floor slabs are constructed with connection to the starter
bars pre-formed with the reinforcement cage of the diaphragm wall.
• The struts are subsequently removed with the construction and gaining of strength of the floors.
Sequence of Excavation-
• In situations where a clear space may be needed for access, or the shape of the site makes
supporting by horizontal strutting not economical ground anchors/soil nails may be used.
• Ground anchors are small diameter bored piles drilled at any inclination for the purpose of
withstanding thrusts from soil of external loading.
• A ground anchor consists of a tendon, which is fixed to the retained structure at one end whilst
the other end is firmly anchored into the ground beyond the potential place of failure.
• The main disadvantages of a cut and cover construction are its disruptive effects in congested
urban environment.
• Cost of cut and cover construction increases sharply with increased depth.
3. Top-Down Method -
Design and construction principles for Top-down method primarily call for two major structural
elements -
(i) Columns with sufficient capacity must be pre-founded in form of Bored Piles or Barrettes to
sustain the construction load and to utilize as part of bracing system. Excavation for
basement must be carried out with the support of permanent retaining wall so that basement
floor slabs can be utilized as lateral bracing.
(ii) Diaphragm wall of 0.8m to 1.2m in thickness with sufficient embedment in firm soil layers is
commonly used as a retaining wall, whereas prefabricated structural steel columns, also
known as Stanchions, embedded in either large diameter deep-seated bored piles or
barrettes are utilized as compression members.
Sequence of Construction –
• In this method, basement concrete slabs act as lateral bracing for the perimeter wall system.
Ground level and first basement slabs are poured, with access holes left to allow excavation
beneath.
• As each subsequent subgrade level is completed, the floors act as lateral bracing for the
perimeter wall system.
• Similar to the cut and cover technique, permanent perimeter walls are first constructed.
• Pre-founded columns are then constructed, followed by the construction of the ground floor slab.
• Pre-founded columns are structural columns/piles formed before basement excavation.
• Boreholes are formed to the hard strata.
• Steel stanchion/H-sections are inserted, and concrete pumped in to slightly over the lowest
basement slab level. The holes are then backfilled with soil.
• This lower part of the stanchions embedded in concrete will later form the integral part of the
foundation for the structure.
• The upper part of the stanchions not embedded in concrete serves as the column supports for
the subsequent basement floors.
• Excavation then proceeds downward, and basement slabs are constructed while construction
of the superstructure proceeds simultaneously
• Temporary openings are provided at various strategic locations on the basement floors to
provide access for removal of excavated earth as well as delivery of excavation machinery and
materials for the construction of the substructure.
• Excavation proceeds without the need for strutting to support the excavation as the slabs act as
the permanent horizontal supports. When the formation level is reached, pile caps and ground
beams are constructed.
• Column installation method is usually selected by the piling contractor who takes into
consideration three main factors such as installation depth, size of column and size of bored or
barrette piles.
• Though installation details may be different from one contractor to another, column installation
can be categorized under two types, namely, Post-concreting or Plunging installation and Pre-
concreting installation or placing column prior to concreting.
• This operation required personnel to trim the pile, set pile caps or make in-situ bases for final
column installation at final basement level.
• In this method, column is installed immediately after completion of bored pile concreting process.
General construction sequence involved in this method is demonstrated in Fig. 3. Guide frame or
Jigs is used to install the column at the correct position.
• On several occasions in the old past, installation of steel columns on the wet concrete were
rejected because of the risk of inaccurate placing of columns.
• More recently in abroad, specialist firms have developed jigs to enable the steel plunge column
to be placed very accurately both in verticality and position within the unlined box supported by
bentonite slurry.
• The general accuracy of placing the plunged column into the wet concrete is of the same order
as bored pile construction (1:75); but with the refined site controls, accuracy even upto 1: 200 to
1:400 could be maintained.
• In this method, column is installed immediately after completion of drilling and reinforcement
lowering prior to concreting process.
• In some projects column is attached to the last section of reinforcement and installed.
Advantages
Disadvantages
• Problems of excavating in dark & dusty situation even with artificial lighting
• Limited head room & working area during casting of concrete slab, boring of holes and inserted
pre-founded column
• Cost of construction is high as it involves installation of more sophisticated temporary support such
as prefounded columns.
• Provision of mechanical ventilation and artificial lighting is necessary during construction.
• In cases where pre-founded columns are to be removed or enlarged, great care must be taken
to ensure effective load transfer.
• The constraints with headroom, access etc. can also make the removal of unwanted soil, e.g.
boulders, a tedious job as great care is required so as not to weaken the ‘pre-constructed’
surrounding structures.
Basement Foundations –
1. Slab Foundation –
Process –
• Pouring - Before pouring the concrete, all sewer and electrical lines are put in place.
• The pipes are embedded in the concrete.
• Below the concrete is a 6 inch pile of gravel covered by a plastic sheet to prevent excess moisture
from reaching the slab. The slab itself is usually 4-6 inches thick.
• Once the concrete is poured over the surface, a screed board is used to smooth out any
imperfections.
• A jitterbug tool is then used to
bring any sand, water and
cement to the surface.
• This ensures that the concrete
has a smooth, durable surface.
• This is especially important
because the slab will become
the basement floor. Any large
pieces of aggregate are
pushed as close to the earth as
possible.
Advantages
• Slab basements require little preparation and are suited for warm, level sites. Little labour is
necessary and only light formwork construction.
• The home is closer to the ground than in other designs, so fewer stairs are required during the rest
of construction.
• The slab prevents water and other gases, such as radon, from entering the home because there
is no space between the ground and the slab.
Disadvantages
2. Piled Foundations
• These can be defined as a series of columns constructed or inserted into the ground to transmit
the load(s) of a structure to a lower level of subsoil.
• Piled foundations can be used when suitable foundation conditions are not present at or near
ground level making the use of deep traditional foundations uneconomic.
• The lack of suitable foundation conditions may be caused by:
3. Presence of layers of highly compressible subsoils such as peat and recently placed filling
materials which have not sufficiently consolidated.
Pile cap
➢ A pile cap is defined as a concrete block cast
on the head of a group of piles, to transmit
the load from the structure to the group of
piles.
➢ To protect the top of pile from blow of
hammer on top, pile cap is provided.
➢ Generally, pile cap transfers the load form the
structures to a pile group, then the load
further transfers to firm soil.
➢ External pressures on a pile are likely to be
greatest near the ground surface. Ground
stability increases with depth and pressure.
➢ The top of the pile therefore, is more
vulnerable to movement and stress than the
base of the pile.
➢ Pile caps are thus incorporated in order to tie
the pile heads together so that individual pile
movement and settlement is greatly reduced.
➢ Thus stability of the pile group is greatly
increased