Vmware Conversion Process
Vmware Conversion Process
Mail:
Hi Virtualization team, you are authorized to convert
Lab11r22k8 machine .
Please Migrate it by end of this Month
Thanks,
Shankar
InfraStructure Director,
CloudSoft
2.VMware Virtualization team manager will assign this task to respective Engineer
(say : Amarnath)
3.VMware Engineer Will Maill all the stake holders about the conversion date and
time.
Mail
TO : Vmware team Members,
Team manager,
Lab11r22k8 Machine owner,
Sharepoint Application Owner,
Backup Administrators,
Security team,
Wintel Team.
Hi EveryOne,
Lab11r22k8 Machine which is running in Lab11 rack2 will be
Migrated to vcenter on Jan22,2012
You may experience downtime between 8PM to 6AM
Please plan accordingly,
Thanks and Regards,
Amarnath
Hi Team,
Mail
To : Security team,
CC : Team Manager,Team Lead
Hi Team,
Lab11r222k8 Machine will migrated to vcenter (P2V) on Jan22.
As a part of Migration process, Some of the Security Software
Services will be stopped.
Thanks,
Amarnath.
Mail
To : SharePoint Administrator,
CC : Team Manager,Team Lead
Hi Team,
FYI
Lab11r222k8 Machine will migrated to vcenter (P2V) on Jan22.
You may experience the downtime.
Please let me know if there is any business Impact
Thanks,
Amarnath
TO SharePoint Administrator
CC: Team manager, Team Lead
Hi ,
Labb11r22k8 machine is converted to VM.
Please Do the UAT and send me the observations
Details to connect:
vcenter Hostname:
Username:
ResourcePool:
Machine Name:
Thanks and Regards,
Amarnath
Hi Amarnath,
UAT is fine,
Please go ahead with the remaining process
Thanks,
Sharepoint Administrator
Hi EveryOne,
Forwarding the UAT result done by Application Owner,
Hence we confirm that, Migration process is successful.
Please let us know in case of any problems
Once the migration is successful, Physical machine will be kept powered off for a
week and after that the physcal machine can be reused.