Method Statement For Testing & Commissioning of Diesel Generator
Method Statement For Testing & Commissioning of Diesel Generator
4512
15
Share
The purpose of this procedure is to define the step by step method to implement the
correct practices for the testing, precommissioning & commissioning of “Diesel
Generator”through the guidelines contained herein so as to ensure that the job execution
complies with the project requirements and serves the intended function to satisfactory
level.
Required Equipments:
Electronic Governor
The low idle speed, rated speed, start fuel limit & ramp time shall be measured &
recorded against the setting value.
The actuator compensation, gain, reset, droop, load gain & over speed settings shall
be recorded against the setting value. All setting values shall be as per manufacturer’s
guidelines.
The system shall be filled with potable water with rust inhibitor & the air shall be
purged.
The water level shall be checked & any leakage in the system shall be checked.
The engine shall be run at no load & the cicuit shall be checked for any leakage.
The operation of the low coolant level sensor shall be checked as per manufacturer’s
guidelines.
The jacket water temperature high alarm & shut down simulation shall be checked as
per manufacturer’s guidelines.
Fuel oil system with fire valve, 2 port ,motorised valve, pressure switch & level
sensor shall be checked for proper installation with alignment.
The tank shall be filled & the system shall be checked for leakage.
Incase of a leak, the leak will be detected by a drip tray mounted float switch which
shall be connected to sound an alarm.
The engine shall be run at no load & the cicuit shall be checked for any leakage.
The fuel oil high level & low level alarm switch shall be checked.
The fuel oil high level & low level pump stop switch shall be checked.
The system shall be filled with the oil recommended by the manufacturer.
The oil level shall be checked & it shall be ensured that there are no leaks in sump &
drain.
The engine shall be started & the oil pressure shall be observed as
per manufacturer’s guidelines.
The engine shall be run at no load & the cicuit shall be checked for any leakage.
The engine shall be stopped & the oil level shall be checked again.
The lube oil high temperature alarm & shut down shall be checked as per
manufacturer’s guidelines.
The lube oil low pressure alarm & shut down shall be checked.
The load test on the generator shall be carried out increasing the load from 0% to
100% in steps of 25% using load bank.
At 0% the run time shall be 5 mins, for 25%- 10 mins, for 50-10 mins, for 75%- 3 Hrs
& for 100% – 3 Hrs.
The fuel consumption, actual KW, line voltage, line currect, oil pressure, coolant
temperature, RPM & battery voltage shall be recorded at agreed intervals of run time.
Check the voltage availability in the line side of the ATS. If the voltage is available,
the changeover switch remains unchanged.
When the voltage is not available in the line side, check for signal from the ATS to
the generator sensing panel to start generator.
Once the generator full voltage is available at the ATS emergency terminals, check
the ATS change over to generator supply.