0% found this document useful (0 votes)
338 views7 pages

Procedure For Backfilling

This document provides the procedure for backfilling a trench after laying a steel pipeline in Ballari-Gadag, India. It outlines that backfilling should only begin once at least 200mm of padding has been placed over the pipe. The backfill material should not damage the pipe or coating and must be well-consolidated in layers. Surplus backfill should form a crown over the trench to allow for future settling. In steep areas, breakers filled with sand and cement must be installed according to the consultant's directions.

Uploaded by

Ajit Kumar Rout
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
338 views7 pages

Procedure For Backfilling

This document provides the procedure for backfilling a trench after laying a steel pipeline in Ballari-Gadag, India. It outlines that backfilling should only begin once at least 200mm of padding has been placed over the pipe. The backfill material should not damage the pipe or coating and must be well-consolidated in layers. Surplus backfill should form a crown over the trench to allow for future settling. In steep areas, breakers filled with sand and cement must be installed according to the consultant's directions.

Uploaded by

Ajit Kumar Rout
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

PROCEDURE FOR

MAO BACKFILLING

MAS CONSTRUCTIONS
Doc No.: MAS-BGRL-TE-JP-A4-18 , TRACTCB€L/.+
Rev.-00 er\t(sl{?

LAYING OF 3 LPE COATED STEEL PIPELINE IN BALLARI-


PROJECT
GADAG
CLIENT M/s BHARAT GAS RESOURCES LIMITED

CONSTILTANT N{/s TRACTEBEL ENGINEERING

CONTRACTOR M/s MAS CONSTRUCTIONS

JOB PROCEDT]RE MAS-BGRL-TE-JP-A4- I 8, Rev.-00

JOB PROCEDURE FOR


BACKFILLTNG

FOR MAS CONSTRUCTIONS FOR BGRI/TRACTEBEL

PREPARE} CHECKEI) APPROYED

NAME:
G.s*d,r*@ MM-# t/]^/pil
a) /, rVl,
SIGNATIIRE:
A*ffi
,\\-
ffiu,r,1, l$)H L<-<-*
DATE: otloeho\1 Twta-lu*a

No. MAS-BGRL-TE-JP-A4- 1 8 - Rev.-00 1 of5


PROCEI}URS FOR
MAO
MAS CONSTRUCTIONS
BACIfi'ILLING

Dcc No.: MAS-BGRL-TE-JP-A4-18 , THACTEB€L,rar+


Rev.-00 er$6i€

INDEX

Topic No. Page


Items
No.

1.0 Purpose 3

2.A Scope of Work 3


{,.

Reference 3

_ 4.0 Machinery & Equipment 3

-s.o Methodologr 3

6.0 Ilealth Safety & Environment 5

7.4 Appendiccs / Format 6

(_

Nq }4AS-BGRL-TE-JP-A4- I I, Rev.-00 2 of5


. r;ilt,,
TIIOCEI}URS FOR
'i L*
BACKFILLING #
EiHAFTA'T
&*s st!*46-srees

MAS CONSTRUCTIONS
Doc No.: MAS-BGRL-TE-JP-A4-18 , TRACTEB€L -r*!
Rev"-00 {3FTGiE

1. Purpose:
The purpose of this Work procedure is to lay guidelines and requirements and to establish a method or a system to control
the Backfilling activrty and inspection to be used in the LAYING OF 3 LPE COATED STEEL PIPELINE
IN BAILARI-GADAG, by MAS for executingthe Project-
2. Scope of Work:
This covers the backfilling of trench with the excavated./ borrowed earth soil after providing soft
padding of select backfilling as per requirements stated in alignment sheet & specification and
uft"r rlop" breaker where shown in drawings for LAYING OF 3 LPE COATED STEEL
PIPELINE, IN BALARI-GADAG.
3. References:
I Folowing documents in totality or in part shall from the reference documents:
'*-.

4.: Machinery & Equipment:

5. Methodology:
Backfilling is to be commenced only after padding is done at least for 200mm covering above
the pipe. Backfilling shall not be done until the pipe and appurtenances have been properly
fitted and the pipe is according to the ditch profile at the required depth that will provide the
required and it does not rest upon any stone, hmd lumps etc., and has a bed which is
"or*i
frei of extraneous material which allows the pipe to rest smoothiy and evenly. De-watering if
required should be carried out; in general trench should be dry prior to padding. The last 3 or
4 prpe lengths shall not be backfilled at both ends to facilitate tie-ins of the lowered sections'

Backfilling shall be done with prior approval of BGRL/TRACTEBEL. Before start of


backfilling MAS shaltr ensure the provision of anti-buoyancy meas\Ires.
The backfill material shall be soil, sand, clay or other containing no materials which could
damage the pipe and/or coating or leave voids in the backf,lled trench. Each completed layer
of backfrlling shall be carefully deposited, watered where necessary and thoroughly
consolidated to the satisfaction of BGRL/TRACTEBEL. The surplus material shall be neatly
,., . ,.,,''crowned directly over the trench and the adjacent excavated areas on both sides of the trench
.,,t,:,lri::,"'i,,,jt6, such a height, which will, provide for firture settlement of the trench backfill during the
I
!
..i;,;p,;,,,rri,'-#aintenance period and thereafter. The crown sha1l be high enough to prevent the formation
depression in the soil when backfill has settled into its permanent position.
='".,_ _-'':dthe
:!j-.,.+-i.
fol
.,' */If depression occurs after backfill, MAS shall carryout the remedial work immediately'
Surplus material left from this operation shall be disposed off to the satisfaction of landowner
or authority having jurisdiction.

No. MAS-BGRL-TE-JP-A4-1 8, Rev.-00


PROCEDTTRE FOR .
"rir''

MA@ BACKFILLING
ETHAFTAT
*a*
'tJ
,;:;!iri

fac*rilEfedls
%

MAS CONSTRUCTIONS
Doc No.: MAS-BGRL-TE-JP-A4-18, THACT€B€t}*-
Rev.-00 {3t-*(Et€

Where rock, gravel, are encountered at the time of trench excavation, sufficient earth, select
backfill materials (like soil, sand, clay or earth containing no gravel), shall be placed around
and over the pipe to form a protective cushion extending at least to a height of 200 mm all
around the pipe. Loose rock/stone of size not more than 150 firm may be retumed to the trench
after the required selected backflll material has been placed,
When the trench has been dug through driveways or roads, all backfilling shall be executed
with sand or suitable materials (shall be approved by BGRL/TRACTEBEL) in suitable layers,
which will be thoroughly compacted. Compaction tests shall be carried out to ensure proper
compaction and avoid future settlement. At the end of each day's work, MAS shall maintain
the backfrll against washouts etc., until the completion and final acceptance of the work by
BGRL/TRACTEBEL.
Back filling in steep areas where slope is lAYo ormore shall be provided with breakers. These '\-
breakers will consists of grout bags filled with 4:1 sand: Portland cement as per directions of
BGRL/TRACTEBEL.
MAS shall arrange to take levels as soon as the lowering activity is completed in presence
r BGRL/TRACTEBEL to allow survey the centre line of the pipe and the level of pipeline in
: : the trench prior to backfitling. MAS shall replace the top soil wherever applicable, which was
stored separately during trenching slope & soil stabilization to be carried out as per relevant
'- specif,rcation& at locations shown in alignment sheets or identified by BGRL/TRACTEBEL.
For U/G pipeline crossings & overhead power line crossings concrete slab 100mm Thickness
6r piastic grating 6mm thickness to be provided as per standard.
MAS shall make arrangements for measuring the deviations of the plpe centerline a.fter
backfilling. If it is more than 300 mm, it shall be brought to the notice of
BGRL/TRACTEBEL. For underground pipeline crossings and overhead power line crossings,
concrete slab/plastic grating to be provided as per Standard with prior approval.
Warning mat shall be anti rodenttype width 500 mm & thickness I mm. size shall be laid over the
HDPE conduit. HDPE conduit shall be backfilled with soft soil or sand like pipeline as table givd.-
below:

6. Health, Safety & Environment:

execution.
It is to be noted that the special care to be adopted against snake / insects bite.
PPE is a rnust in this activity.
Only trained rigging personnel to be deployed for this activity.
All Measuring & Test Equiprnents used must be well maintained.
All lifting devices & Tools used shall be well maintained and approved by a competent
authority.
Availability of First Aid Box willbe ensured at site during the work execution.

)oc No. MAS-BGRL-TE-JP-A4-18 , Rev.-00 Page 4 of5


PROCEDTIRE FOR
BACKFILLING
MAS CONSTRUCTIONS
Doc No.: MAS-BGRL-TE-JP-A4-18 , TR,'*CreB€L
Rev.-00 {s}ffifig

7. Appendices lFormat:

Note: In of any conflict between the requirements of this procedure and


case
BGRLITRACTEBEL Specification the later shall govem, until & unless speciflcally meant.

FORMAS CONSTRUCTIONS FOR BGRL/TRACTEBEL

PREPARED C}TECKED APPROVED

NAME:
Q*g^y.ffi[XqnosrwWil
SIGNATTIRE:

DATE: orfrrlN{ %rp,1,,-


M
No. MAS-BGRL-TE-JP-A4- 1 I . Rev.-00 5 of5
PROJECT : LAYING OF 3 LPS COATDD STEET PTPELINE IN BALLARI-
GADAC
CLIENT : M/s BEAtrLdT GAS RDSOLTRCES LIMI"ED
CONSULTANT : M/S TRACTEBEL ENGINEERING

MAS CONTRACTOR: M/s MAS CONSTRUCTIONS i TR.ACT€E}€L


CONSTRUCTIONS Doe No. : MAS-FITP-A4-18, Rev.-$0 iG
I

INSPECTION TEST PLAN FOR BACKFILLING


-'--T'-'- Activities
'-'-'1------t"-.-#;"-"."i',1-*i--'-1---'
s.No I Re merks
I I MAS I BGRLITRACTEBEL I

Submission & approval ofwork procedure w R/A

2 Ilealth check of equipment w R

J Checking the cover at the top ofpipe w w

Padding/Anti botrncy, rock Shield/ Plastic


4 gr:af,nd Saddle wi./Slope breaker/Conc. w w
Coating/ C.P. points.

5 BackJilling/ Arable soil spreading w RW

6 Makiog crowr at top of the trench w RW

1 Center line/ kvel Check w RW

8 WamingTape w w
Compaction of Backlilling at road crossing
I etc,
w w

l0 HSE w RW

LEGENDS:

'.W,, : WITNESS POINT "HP": HOLDPOINT

rrRMrI: RANDOM
"WC" : 100% EXAMINATION BY CONTRACTOR

"R' : REVIEW OF DOCUMENTATION "AP" : APPROVAL

FORMAS CONSTRUCTIONS T F'ORBGRLITRACTEBEL

IIGN: SIGN:

YAlvrE: H,s6{N NAME:


6@tw;Et |\
DArE: OqYgW DATE:
PROJECT I LAYING OF3 LPE COATED STEEL PIPELINE IN
BALLARI-G{}AG
CLIEIW : Mls BI{ARAT GAS RESOURCES LIMITED
CONSLILTANT : MIs TRACTEBEL ENGINEERING

CONSTRUCTIONS CONTRAC:rCIR : M/s MAS CONSTRUCTI0NS


TRAC'EEI€L
Doc No. : MAS-BGRL-TE-IR-A+18, Rev.-{X} ffiE

INSPECTION REPORT FOR BACIGILLING


Chainage From: Report No:

3hainagc To: Dafe:

Ref. Chainage WeldNo.


Length(M) Descriplion ofgap Reilarks
From To Fnrn T*

1 1j,,
i
$

*) -{
\) \ '/

.1
,,
!
j

Today Progress

Previous Progress

Cummulative

Remmks:

CHECIGD & \TERIFIED BY


F'OR MAS CONSTRUCTIONS FOR BGRL/TRACTEBEL

'IGN' \_Q,ffi SIGN:

NAME,**wWil;A !-1,
NA}IE :

DA'E, 0f lrw DATE:

You might also like