ITP For Earthing
ITP For Earthing
Owner’s reply on
□Approved
□Approved with comments
□comments
Comments
D I STR I .
OWNER E
PM
CM/CE
BUSINESS
COST
R SCH
E
V PROCESS
I
EQIPMENT
S
I MACHINE
O A FURNACE
INST
PROJECT TEAM: GPUFP
Bangladesh Chemical Industries Corporation
CIVIL
APPROVED
CONST
CONTRACTOR
PROCURE
Mitsubishi Heavy Industries, Ltd
SECTION QA/QC Gr. SUBCONT
CHINA NATIONAL CHEMICAL ENGINEERING & CONSTRUCTION
APPROVED CORPORATION SEVEN, LTD
PROJECT
MHI E
Ghorasal Polash Urea Fertilizer Project SITE
6488C-AA70-EF1-00-00200 A
DRAWN DATE 13-Apr-2021 TOTAL
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project EL-ITP-001-01
Inspection and Testing Plan Rev. No. 00
for Earthing Rev. Date. 13.Apr.2021
REVIEW GRADE
A Accepted
Acceptance in any of these categories in no way relieves the Contractor/Supplier of its responsibility for
the due & proper performance of the Works in accordance with the Contract/Purchase Order
NAME DATE:
2. DEFINITIONS ................................................................................................... 1
3. REFERENCE ..................................................................................................... 1
5. RESPONSIBILITY ............................................................................................ 2
9. INSPECTION RECORD.................................................................................... 5
12.APPENDIX ....................................................................................................................... 7
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project EL-ITP-001-01
Inspection and Testing Plan Rev. No. 00
For Earthing Rev. Date. 13.04.2021
1. SCOPE
This procedure is provided for control of the construction of Field work inspection
and test (hereafter called 'Inspection') to verify that earthing works are being located,
and the earthing works must in compliance with the latest construction drawings,
instructions, procedures and other applicable documents for Ghorasal Polash Urea
Fertilizer project.
2. DEFINITIONS
3. REFERENCE
WORKS
1 / 15
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project EL-ITP-001-01
Inspection and Testing Plan Rev. No. 00
For Earthing Rev. Date. 13.04.2021
In order to ensure that the operation quality of all parts and all links of the project
management, the quality control points of GPUFP project are divided into five categories
including “R”, “I”, “SW”, “W” and “H” explained as below. Strict joint inspections
5. RESPONSIBILITY
5.1.3 Submitting the inspection records and results required to verify conformance to
specified requirements.
2 / 15
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project EL-ITP-001-01
Inspection and Testing Plan Rev. No. 00
For Earthing Rev. Date. 13.04.2021
5.1.5 Control of the inspection, measuring and test equipment used for inspection.
5.1.6 CC7 shall be responsible for supervision and management of Construction Teams.
among the MHI、BCIC and CC7 for control of witness inspection and for evaluating
The Quality Inspector of CC7 shall be responsible for carrying out all “I”
Inspector of CC7 shall be responsible for review of records and results to verify
6.1 CC7 shall establish the inspection plan, which must conform to requirements specified
in the Construction Quality Requirements and shall specify the inspection items
described in the list of Field inspection items into the quality plan depending on
6.2 CC7 shall submit the inspection plan to MHI&BCIC for review and formal approval
6.3 During the construction phase, additional plans may be made if necessary, CC7 and
MHI shall jointly review the additional submitted plans for new inspection item.
3 / 15
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project EL-ITP-001-01
Inspection and Testing Plan Rev. No. 00
For Earthing Rev. Date. 13.04.2021
6.4 The main activities for civil to be controlled on field are as follow:
*Earthing Installation
The purpose of each individual ITP is to define and specify the required level of
Quality Control for the involved work main steps and related involvement of
concerned parties, the above list may not be exhaustive and could be added to in
6.5 Any deviations or exceptions to any of the inspection and test points of the ITP
7. INSPECTION FLOW
4 / 15
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project EL-ITP-001-01
Inspection and Testing Plan Rev. No. 00
For Earthing Rev. Date. 13.04.2021
8.1 The QA/QC department will collect the RFI prepared by all engineers and send it to
8.2 Document no. of Request for Inspection (RFI) shall be controlled as following.
GPUFP-XX-XX-XXXX
① ② ③
① Area
Code Area Code Area
00 Common Area/System AM Ammonia Area/System
UR Urea Synthesis Area/System UG Urea Granulation Area/System
CO CO2 Recovery Area/System UT Utility Area/System
OF Offsite Area/System
② Work Code:
Code Description Code Description Code Description
CVS Civil Works BD Building IN Instrument
ME Mechanical EL Electric PA Painting
PI Piping IS Insulation FI Fire Proofing
TK Tank PR Pre-commissioning MI Miscellaneous
9. INSPECTION RECORD
inspector shall prepare and maintain the records of inspected items. Inspection records
* Date of inspection
5 / 15
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project EL-ITP-001-01
Inspection and Testing Plan Rev. No. 00
For Earthing Rev. Date. 13.04.2021
* Type of inspection
Professional engineer and quality inspector shall evaluate the inspection results
requirements, and sign and date on the records for an acceptable item. For an
unacceptable item, Subcontractor shall re-inspect after solving the causes of un-
acceptance.
10.1.1 Only for inspection items requiring document review, the QC inspector shall file
and store the inspection records within one working day after the inspection.
10.1.2 Qualified CC7's Inspector shall evaluate the inspection records and certificates
requirements.
6 / 15
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project EL-ITP-001-01
Inspection and Testing Plan Rev. No. 00
For Earthing Rev. Date. 13.04.2021
10.2.1 Professional engineer shall prepare the inspection report of each inspection and
10.2.2 Qualified CC7's Inspector shall file and maintain the approved inspection report.
11.1 QC inspector shall establish the control status of inspection and test with indicators
such as marking, stamps, tags, labels or records to the product of service that has
passed the required inspection and test, is released for next processing.
11.2 The procedure for identification established by Subcontractor should specify the
12. APPENDIX
7 / 15
REQUEST FOR INSPECTION
Inspection Date:
Precise Unit/Location:
Noted:
If it is related, the “√” will be marked.
No Item No./Description Insp. Scope Area/ Location Date, Start Time Duration
Attachment Required
Name
Position
Signature
Date
8 / 15
Civil/Structure
Mechanical/Rotating
SUMMARY OF FIELD INSPECTION (DAILY BASIS)
Piping
Instrument
Inspection Points
No. Items to Be Inspected Q’ty Area/Block Location Time Person in Charge Remarks
CC7 MHI BCIC 3rdP
Prepared by:
Date:
9 / 15
Inspection and Test Plan (ITP) Remarks
CC7-GF-QAC-EL-ITP-001-01
For Earthing
Reference Documents, Inspection Action
Inspection/Test Acceptance Verifying
No. Characteristic to be Verified Frequency Specs & Procedure Doc.
Stage Criteria CC7 MHI Owner Document
No.
1 Material
1. Electrostatic earth bunch 6488M-S711-000-00-
wire and connecting wire 00100 Material Control
appearance check. Procedure
Material Receiving Inspection
1.1
Inspection
2.Check properties of wires, 100% 6488M-E436-000-00- As requirements I SW R
Record
Cross sectional area, 00400
mechanical strength, Corrosion Earthing Resistance
Calculation
resistance, not easy to break
2 Under ground
Engineering Standard
Under ground for Electrical work 1. Normal
a. Earthing conductor laying 6488M-E711-000-00- Buried Depth
Electrostatic installation of earth grid. 00100 600mm
2.1 100% I SW SW FEL001
Earth Connection b. Connection to Earthing Standard Drawing for 2. Exothermic
Conductor. Electrical Works welding
c. Confirm the Earth Cable Size 6488M-E712-000-00- connections.
00100
3 Above ground
Main Earthing:
a. Pipeline system electrostatic earth
connection Engineering Standard
b. Mechanical electrostatic earth for Electrical work
connection 6488M-E711-000-00-
Bolt connection
Electrostatic c. Tank electrostatic earth 00100 FEL001
3.1 100% or exothermic I SW SW
Earth Connection connection Standard Drawing for FEL002
weld
d. Instrument earth connection Electrical Works
e. Electrical Panel Earth Connection 6488M-E712-000-00-
f. All Underground and 00100
Aboveground Connection
g. Building Earthing grid
10 / 15
Inspection and Test Plan (ITP) Remarks
CC7-GF-QAC-EL-ITP-001-01
For Earthing
Reference Documents, Inspection Action
Inspection/Test Acceptance Verifying
No. Characteristic to be Verified Frequency Specs & Procedure Doc.
Stage Criteria CC7 MHI Owner Document
No.
Engineering Standard
for Electrical work The maximum
a. Connecting joint type 6488M-E711-000-00- allowable
3.2
Final Inspection and b. Connecting wire specification,
100%
00100 earthing I SW SW FEL003
Test material Earthing Resistance resistance as
c. Earthing resistance Calculation design
6488M-E436-000-00- requirement
00400
Prepared by (CC7): Approved by (MHI): Approved by (OWNER): Rev. No.& Date: R: Review
I: Inspection
SW: Spot Witness (can be proceed
if given clearance)
W: Witness
H: Hold Point
11 / 15
Ghorasal Polash Urea Fertilizer Project (GPUFP)
Project GPUFP
12 / 15
QUALITY CONTROL FORM
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
13 / 15
QUALITY CONTROL FORM
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
14 / 15
QUALITY CONTROL FORM
Results:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
15 / 15