ITP For Civil
ITP For Civil
Owner’s reply on
□ Approved
□ Approved with comments
□ Comments
11, 20, 21, 22, 24,26/85 updated and QCF added or changed
according ot inspection stages
D I STR I .
OWNER E
PM
89 SHEETS WITH COVER
CM/CE
QA/QC
BUSINESS
COST
R SCH
E
V PROCESS
I C 03.06.2020
EQIPMENT
S
I B 28.08.2020
MACHINE
O
N A 10.04.2020 FURNACE
S On the Not on the APP’D APP’D
NO DATE DESCRIPTION REFERENCE NO. control control PIPING
list list SECTION PROJECT TEAM
ORDER NO. 563500 ELECT.
OWNER INST
PROJECT TEAM: GPUFP
CIVIL
APPROVED Bangladesh Chemical Industries Corporation
CONST
CONTRACTOR
PROCURE
Mitsubishi Heavy Industries, Ltd
SECTION QA/QC Gr. SUBCONT
CHINA NATIONAL CHEMICAL ENGINEERING & CONSTRUCTION
APPROVED
CORPORATION SEVEN, LTD
PROJECT
MHI E
SITE
Ghorasal Polash Urea Fertilizer Project
JAPAN EXPORT On the Not on the CONTRACTOR DWG. No. REV.
CONTROL Control List Control List SPARE
6488C AA80-000-00-00100 C
DRAWN DATE 06-June-2021 TOTAL
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project CVS-ITP-001-01
Inspection and Testing Plan Rev. No. 02
for Civil Works Rev. Date. 06.June.2021
REVIEW GRADE
A Accepted
Acceptance in any of these categories in no way relieves the Contractor/Supplier of its responsibility for
the due & proper performance of the Works in accordance with the Contract/Purchase Order
NAME DATE:
2. DEFINITIONS ................................................................................................... 1
3. REFERENCE ..................................................................................................... 1
5. RESPONSIBILITY ............................................................................................ 2
9. INSPECTION RECORD.................................................................................... 7
12.APPENDIX ....................................................................................................... 9
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project CVS-ITP-001-01
Inspection and Testing Plan Rev. No. 02
for Civil Works Rev. Date. 06.June.2021
1. SCOPE
This procedure is provided for control of the construction of Field work inspection
and test (hereafter called 'Inspection') to verify that civil works are being located, and
the civil works must in compliance with the latest construction drawings, instructions,
procedures and other applicable documents for Ghorasal Polash Urea Fertilizer project.
2. DEFINITIONS
3. REFERENCE
Chinese Standards
1 / 86
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project CVS-ITP-001-01
Inspection and Testing Plan Rev. No. 02
for Civil Works Rev. Date. 06.June.2021
5. RESPONSIBILITY
5.1.3 Submitting the inspection records and results required to verify conformance to
specified requirements.
2 / 86
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project CVS-ITP-001-01
Inspection and Testing Plan Rev. No. 02
for Civil Works Rev. Date. 06.June.2021
5.1.5 Control of the inspection, measuring and test equipment used for inspection.
5.1.6 CC7 shall be responsible for supervision and management of Construction Teams.
among the MHI、BCIC and CC7 for control of witness inspection and for evaluating
The Qualified Inspector of CC7 shall be responsible for witnessing the inspection
6.1 CC7 shall establish the inspection plan, which must conform to requirements specified
in the Construction Quality Requirements and shall specify the inspection items
described in the list of Field inspection items into the quality plan depending on
6.2 CC7 shall submit the inspection plan to MHI&BCIC for review and formal approval
6.3 During the construction phase, additional plans may be made if necessary, CC7 and
MHI shall jointly review the additional submitted plans for new inspection item.
6.4 The main activities for civil to be controlled on field are as follow:
3 / 86
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project CVS-ITP-001-01
Inspection and Testing Plan Rev. No. 02
for Civil Works Rev. Date. 06.June.2021
*Survey
*Piling
*Earth Work
*Rebar
*Form Work
*Drainage/Trench Work
*Fence Work
*Roof
*Plumbing
*HVAC
*HVAC Electrical
The purpose of each individual ITP is to define and specify the required level of
Quality Control for the involved work main steps and related involvement of
4 / 86
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project CVS-ITP-001-01
Inspection and Testing Plan Rev. No. 02
for Civil Works Rev. Date. 06.June.2021
concerned parties, the above list may not be exhaustive and could be added to in
6.5 Any deviations or exceptions to any of the inspection and test points of the ITP
5 / 86
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project CVS-ITP-001-01
Inspection and Testing Plan Rev. No. 02
for Civil Works Rev. Date. 06.June.2021
7. INSPECTION FLOW
Rejected
Received by MHI/Owner
8.1 The QA/QC department will collect the RFI prepared by all engineers and send it to
MHI and Owner. CC7 shall carry out inspection independently and close all punch
8.2 Document no. of Request for Inspection (RFI) shall be controlled as following.
GPUFP-XX-XX-XXXX
① ② ③
6 / 86
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project CVS-ITP-001-01
Inspection and Testing Plan Rev. No. 02
for Civil Works Rev. Date. 06.June.2021
① Area
Code Area Code Area
00 Common Area/System AM Ammonia Area/System
UR Urea Synthesis Area/System UG Urea Granulation Area/System
CO CO2 Recovery Area/System UT Utility Area/System
OF Offsite Area/System
② Work Code:
Code Description Code Description Code Description
CVS Civil Works BD Building IN Instrument
ME Mechanical EL Electric PA Painting
PI Piping IS Insulation FI Fire Proofing
TK Tank PR Pre-commissioning MI Miscellaneous
9. INSPECTION RECORD
inspector shall prepare and maintain the records of inspected items. Inspection records
* Date of inspection
* Type of inspection
7 / 86
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project CVS-ITP-001-01
Inspection and Testing Plan Rev. No. 02
for Civil Works Rev. Date. 06.June.2021
Professional engineer and quality inspector shall evaluate the inspection results
requirements, and sign and date on the records for an acceptable item. For an
unacceptable item, Subcontractor shall re-inspect after solving the causes of un-
acceptance.
prepare the inspection records within one working day after the inspection.
10.1.2 Qualified CC7's Inspector shall evaluate the inspection records and certificates
requirements.
10.2.1 Professional engineer shall prepare the inspection report of each inspection and
10.2.2 Qualified CC7's Inspector shall file and maintain the approved inspection report.
8 / 86
Ghorasal Polash Urea Fertilizer Doc. No.
CC7-GF-QAC-
Project CVS-ITP-001-01
Inspection and Testing Plan Rev. No. 02
for Civil Works Rev. Date. 06.June.2021
11.1 QC inspector shall establish the control status of inspection and test with indicators
such as marking, stamps, tags, labels or records to the product of service that has
passed the required inspection and test, is released for next processing.
11.2 The procedure for identification established by Subcontractor should specify the
12. APPENDIX
9 / 86
REQUEST FOR INSPECTION
Inspection Date:
Precise Unit/Location:
Noted:
If it is related, the “√”will be marked.
No Item No./Description Insp. Scope Area/ Location Date, Start Time Duration
Attachment Required
Name
Position
Signature
Date
10 / 86
Civil/Structure
Mechanical/Rotating
SUMMARY OF FIELD INSPECTION (DAILY BASIS)
Piping
Instrument
Inspection Points
No. Items to Be Inspected Q’ty Area/Block Location Time Person in Charge Remarks
CC7 MHI BCIC 3rdP
Prepared by:
Date:
11 / 86
Test & Witness Requirement
Tolerance or Check
No. Work Category Quality Control Item Inspection Frequency Report
Point
Method CC7 MHI Owner
Survey
1.
2. Piling
2.3 Pile Placing Tension Load As per Drawing All Test Pile As per Drawing ○ ○ △ FCV004
D/4 or 10 cm Whichever
Location Steel Tape All ○ ○ - FCV003
Smaller
Penetration Testing
2.4 (Check Pile Welding Crackle or defect PT 10% Pile connected ○ ○ - Test Report
Joint)
Dynamic Test Bearing Capacity and As per Method FCV006 PDA
2.5 5% of work pile As per Method Statement ○ ○ -
(PDA) integrity Statement Test Report
Static Load Test
Bearing Capacity and As per Method As per pile Dia /
2.6 (compression / As per Method Statement ○ ○ - Test Report
integrity Statement Tension pile
Tension)
FCV005 Pile
Pile final position / D/4 or 10cm whichever Head Cut-off Pile
2.7 Location / Elevation Scale All ○ △ -
Pile Head Cut-off small / ±2.5 cm FCV007 As-Built
Record
12 / 86
Test & Witness Requirement
Tolerance or Check
No. Work Category Quality Control Item Inspection Frequency Report
Point
Method CC7 MHI Owner
3. Earth Work
13 / 86
Test & Witness Requirement
Tolerance or Check
No. Work Category Quality Control Item Inspection Frequency Report
Point
Method CC7 MHI Owner
ASTM D1557, 1 Test per Cohesive Soil
4.2 Pipe Bed Material ○ △ R Test Report
6938 5000m3 L.L≦40%
ASTM D1557, 1 Test per
PI≦25% ○ △ R Test Report
6938 5000m3
FCV003 Field
Level of Pipe Bed As per Drawing Every 24m ≥ -2.5cm ≤ 0cm ○ △ R
Survey
Compaction
ASTM D1557, ≥ 90% Measured by RI FCV053
*Compact Every Every 100m ○ △ R
6938 (ASTM D6938) Compaction Test
150~300mm
ASTM D1557, Test Above Compact every FCV053
○ △ R
6938 Each Layer 150~300mm Compaction Test
ASTM D1557, 1 Test per Cohesive Soil
4.3 Back filling Material ○ ○ R Test Report
6938 5000m3 L.L≦40%
ASTM D1557, 1 Test per
PI≦25% ○ ○ R Test Report
6938 5000m3
ASTM D1557, ≥ 90% Measured by FCV053
Back filling Compaction Every 100m ○ △ R
6938 RI(ASTM D6938) Compaction Test
ASTM D1557, Test Above Compact Every FCV053
○ △ R
6938 Each Layer 150~300mm Compaction Test
5. Rebar
Mill Sheet or
5.1 Rebar Quality Every Lot As per Drawing ○ ○ △ FCV001
Tensile Test
Each Foundation
5.2 Rebar Assembly Dia, Spacing Visual, Scale As per Drawing ○ ○ △ FCV011
and Structure
Splice, Anchorage Scale As per Drawing ○ ○ △ FCV011
6. Form Work
Each Foundation
Contact Surface Visual As per Drawing ○ ○ - FCV011
and Structure
Each Foundation
Dimension Scale As per Drawing ○ ○ - FCV011
and Structure
14 / 86
Test & Witness Requirement
Tolerance or Check
No. Work Category Quality Control Item Inspection Frequency Report
Point
Method CC7 MHI Owner
15 / 86
Test & Witness Requirement
Tolerance or Check
No. Work Category Quality Control Item Inspection Frequency Report
Point
Method CC7 MHI Owner
FCV015Concrete
DFT: (to be verified with
Visual All As per Drawing ○ △ △ Protective
paint manufacture later)
Coating
9. Paving and Road
FCV003 Field
9.1 Subgrade Elevation Level Per 50m -5cm~+1cm ○ ○ ○
Survey
Transit, Steel FCV003 Field
Width Per 50m 0~5cm ○ ○ △
Tape Survey
ASTM D1557, ≧90% Measured by FCV053
Compaction Per 200 m3 ○ ○ ○
6938 RI(ASTM D6938) Compaction Test
ASTM D1557, Test Above Compact Every FCV053
○ ○ △
6938 Each Layer 150~300mm Compaction Test
ASTM D1883,
CBR / Plate Load Test ○ ○ △ Test Report
1196
Base Course and FCV003 Field
9.2 Elevation Level Per 50m -1.5cm~+1cm ○ ○ △
Sub-base Survey
Transit, Steel FCV003 Field
Width Per 50m 0~5cm ○ ○ △
Tape Survey
FCV003 Field
Thickness Level, Scale Per 50m 12mm~±0 ○ ○ ○
Survey
ASTM D1557, ≧95% Measured by FCV053
Compaction Per 200 m3 ○ ○ ○
6938 RI(ASTM D6938) Compaction Test
ASTM D1557, Test Above Compact every FCV053
○ ○ ○
6938 Each Layer 150~200mm Compaction Test
FCV003 Field
9.3 Surface Slope Level Per 25m ±5mm ○ ○ △
Survey
Transit, Steel FCV003 Field
Width Per 25m 0~5cm ○ ○ △
Tape Survey
FCV003 Field
Thickness Level, Scale Per 25m -5mm~±0 ○ ○ △
Survey
As Directed by
Material (Bitumen Type) As per Drawing Temp >500C, MC 70 ○ △ △ FCV001
MHI
9.4 Prime Coat
As Directed by
Application As per Drawing 0.8 to 1.2 Kg / m2 ○ △ ○ FCV016
MHI
16 / 86
Test & Witness Requirement
Tolerance or Check
No. Work Category Quality Control Item Inspection Frequency Report
Point
Method CC7 MHI Owner
Temp >1400C, Asphalt
Content -4.5% to 6.5%,
Material (Asphalt) As per Drawing Each Load ○ △ △ FCV001
Asphalt Wearing Asphalt Penetration
9.5
Course Grade- 60 - 100
96% of Marshal Density
Application As per Drawing Daily ○ △ ○ FCV016
Level Diff < 6mm
As Directed by
Material (Bitumen Type) As per Drawing Temp >750C, RC 250 ○ △ △ FCV001
MHI
9.6 Tack-Coat
As Directed by
Application As per Drawing 0.2 to 0.4 Kg / m2 ○ △ ○ FCV016
MHI
FCV017 Road
As Directed by Shoulder
9.7 Road Shoulder Material As per Drawing Max Size -75mm ○ △ -
MHI Inspection
Checklist
10. Drainage/Trench Work
Material Test Manufacturer's
10.1 Vendor Data Sheet Each Batch ○ △ - FCV001
Certificate Certificate
Survey and Setting Location of Point, FCV003 Field
10.2 Visual Each Location As per Drawing ○ △ -
Out Coord, Survey
FCV018 Drainage
Installation As Indicated in the Trench
10.3 Visual Each Location As per Drawing ○ △ -
Inspection Drawing installation
inspection
12.1 Materials Cement, Brick, etc. Document review Each Batch Certificate R R R FCV001
17 / 86
Test & Witness Requirement
Tolerance or Check
No. Work Category Quality Control Item Inspection Frequency Report
Point
Method CC7 MHI Owner
FCV024 Final
12.6 Final walk down Completeness Visual Package No Outstanding Items ○ ○ ○ Inspection Report
for the fence
13. Chemical Resistance Lining/Painting Work
As per Method
15.7 Grouting Statement ASTM All Non-shrink Grouting ○ △ - FCV032 Grouting
C109/C348/C940
FCV033
No Damage/≧
15.8 Paint to Structure Visual/DFT All ○ ○ △ Structural Steel
Spec.(Thickness)
Checklist
19 / 86
Test & Witness Requirement
Tolerance or Check
No. Work Category Quality Control Item Inspection Frequency Report
Point
Method CC7 MHI Owner
Manufacturer's
16.1 Material Fire-proofing Coating Every Lot Certificate △ △ △ FCV001
Certificate
FCV034
Visual/ No Damage/≧
16.2 Fireproof Concrete Appearance/DFT All ○ ○ ○ Fireproofing
Measurement Spec.(Thickness)
Check List
17. Plumbing
FCV035
Visual/water
17.1 Plumbing Installation and Flushing All No Leakage ○ ○ ○ Plumbing
flushing
Checklist
FCV036 Pressure
17.2 Utility Leakage Pressure Test All No Leakage ○ ○ ○
Test Report
FCV037
17.3 Drain Leakage Full Water Test All No Leakage ○ ○ ○ Plumbing/Piping
System Leak Test
18. HVAC
FCV038 HVAC
18.1 Temperature Performance Test Each Room ±2℃ ○ ○ ○ Functional
Testing Checklist
Air Volume Performance Test Each Room ≧Design Air Volume ○ ○ ○ FCV038
FCV039
Duct, Damper, Installation/Testin
18.2 Installation As per Drawing All Connection ○ △ -
Diffuser g of HVAC
Accessories
FCV040
Refrigerant
18.3 Refrigeration piping Installation As per Drawing All Pressure Test ○ △ - Piping Layout and
Support
Installation
FCV041 Indoor &
Indoor & Outdoor
18.4 Installation As per Drawing All Stability ○ △ - Outdoor Unit
Unit
installation
Visual Inspection/ FCV042 HVAC
18.5 Exposure Test Installation Insulation or All Leakage Property ○ △ - Duct work
Exposed Duct Testing
20 / 86
Test & Witness Requirement
Tolerance or Check
No. Work Category Quality Control Item Inspection Frequency Report
Point
Method CC7 MHI Owner
FCV043
18.6 Ventilation Installation As per Drawing All Stability ○ △ - Ventilation
Installation
FCV044
Insulation of
Insulation for
18.7 Installation As per Drawing All Defect & Gap Free ○ △ - HVAC Ducts
Ducting & Piping
Pipes and
Equipment
Testing & Air Balance & FCV045 HVAC
18.8 Operation As per Drawing All ○ △ -
Commissioning Performance Inspection Record
19. HVAC Electrical updated and QCF added accordingly
FCV048 Control
and Relay Panels
Inspection
HCP, HPDP
19.1 Installation As per Drawing All Performance ○ △ - Checklist
Installation Check
FCV049 Power
Panel Inspection
Checklist
FCV046 Cable
Cabling & Tray
19.2 Installation As per Drawing All Performance ○ △ - Installation
Installation Check
Checklist
FCV046 Cable
Cable Termination Arrangement, Wire
19.3 As per Drawing All Performance ○ △ - Installation
Inspection Marking & Termination
Checklist
FCV047
Insulation
Insulation
Resistance Test and
19.4 Resistance & Continuity As per Specified All Performance ○ △ - Resistance Test
Continuity
and Continuity
Inspection
Inspection
FCV056 Voltage
Voltage and Phase
19.5 Voltage & Phase As per Specified All Performance ○ △ - and Phase Check
Check
Record
FCV038 HVAC
19.6 Function Test Function As per Specified All Performance ○ △ - Functional Check
List
21 / 86
Test & Witness Requirement
Tolerance or Check
No. Work Category Quality Control Item Inspection Frequency Report
Point
Method CC7 MHI Owner
Prepared by (CC7): Approved by (MHI): Approved by (OWNER): Rev. No.& Date: R: Review
○: Every Time
△: Discretion
―: None
22 / 86
Ghorasal Polash Urea Fertilizer Project (GPUFP)
updated
Project GPUFP
32 FCV032 Grouting 0
24 / 86
GPUFP Material Receiving Report(MRR)
FCV001
PROJECT ◇PHOTOGRAPH◇
Material Condition:
[ü ] No Issue
[ ] Shortage
[ ] Over
[ ] Others
( )
Material Condition:
[ü ] No Issue
[ ] Shortage
[ ] Over
[ ] Others
( )
25 / 86
QUALITY CONTROL FORM
Inspection/Test Stage: Area/Location
Form No. FCV002 Rev.0
Survey Report RFI No.
(Benchmarks) Report No.
Report Date
Inspection Checklist, Specification, Or Drawing Used as Reference:
Results: Follow-up Required Satisfactory
Description of Item/Work Inspected/Observed:
Written Measured Calculated Identify Failures
FDN Typed Standard Value (A)
Value (B) Deviation (A-B) Results
Northing
Easting
Elevation
Northing
Easting
Elevation
Northing
Easting
Elevation
Northing
Easting
Elevation
Northing
Easting
Elevation
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
26 / 86
QUALITY CONTROL FORM
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
27 / 86
QUALITY CONTROL FORM
Inspection/Test Stage: Area/Location
Form No. FCV004 Rev.0
Pile Driving Inspection Record RFI No.
Report No.
Report Date
Pile Data Hammer Data Design data
Drawing No./Rev. Make Working Load
Pile No. Model Required Blows
Type of Pile Stroke Driving formulas
Dia.(Top) Type Drop Height
Pile
Dia.(Tip) Ram weight
Size
Length Rated Energy
Casting Date(Age) Action
Driving Record
Date & Time(Start) Grade(Elev) Cut-Off(Elev/Length)
Pile
Date & Time(Stop) Last 10 Blows(Actual)
Top(Elev)
Pile Tip Last 10 Blows(max as per
Weather Condition
(Elev) set calculation)
Depth Blows per Drop Depth Blows per Drop Depth Blows per Drop
(m) Meter Height (m) Meter Height (m) Meter Height
Splicing Data
Result
No. Inspection Item Specification Remarks
Accept Reject
1 Splice Joint Cleaning Piling specification Joint Type:
2 Welding Joint(Visual) AWS D1.1 Welder No:
3 Splice Painting/Coating Piling specification
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
28 / 86
QUALITY CONTROL FORM
Inspection/Test Stage: Area/Location
Form No. FCV005 Rev.0
RFIN No.
Pile Head Cut-Off Report No.
Report Date
Pile Data Hammer Data Design Data
Drawing No./Rev Make Working Load
Type of Pile Model Required Blows
Manufacturer Stroke Driving Formula
Driving Record
Point Cut-off
Last Blow
S/N Pile No. Size Date Driven Coordinates Elevatio Elevatio Remarks
Count
n n
signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
29 / 86
QUALITY CONTROL FORM
Remarks:
Pile length at
Pile number Pile length
measuring point
Height(m) Drop distance(m)
hammer
Area(m2) Material
Lifting mode Number of hits
Accelerometer1 Strain gauge1 Accelerometer2 Strain gauge2
Sensor number
Remarks:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
30 / 86
QUALITY CONTROL FORM
Inspection/Test Stage: Area/Location
Form No. FCV007 Rev.0.
Pile As-Built Record RFIN No.
Report No.
Report Date
Reference Document / Equipment
1 Drawing No. Rev. No.
2 Survey Instrument Model Serial No.
3 Calibration Validity Date
Coordinate
No. Pile No. Design(A) Actual(B) Difference Remarks
meter meter C=B-A mm
N
1
E
N
2
E
N
3
E
N
4
E
N
5
E
Remarks:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
31 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV008 Rev. 0
RFIN No.
Excavation Inspection Report
No.
Report
Date
Inspection ACC REJ Remarks
A. Preparation
1. Survey and marking completed?
2. No existing facility is anticipated on the area to be excavated.
Where such adjacent or interfering facility or UG exist, proper
measures are observed to carefully carry-out excavation works.
B. During Excavation
1. Excavation is clear of foreign and loose material?
2. Excavation conforms to Design Drawings (Dimension, grade, elevation, etc).
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
32 / 86
QUALITY CONTROL FORM
Inspection / Test Stage Area/Location
Form No. FCV009 Rev. 0
Soil Density Test Log RFIN No.
Report No.
Report Date
Test Results
Density Test No. Date Placement Represented
Result 1 ACC REJ Result 2 ACC REJ
33 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV010 Rev. 0
RFIN No.
Backfilling Inspection
Report No.
Report Date
Inspection ACC REJ Remarks
A. Preparation
1 Fill material is clean and conforms to requirement?
B. During Backfilling/Compaction
1. Moisture control is properly carried-out as per current weather
Condition (if any)?
2. Fill and backfill layer (lift thickness) are uniformly compacted?
Remarks:
Signature
Name
Dept.
Signature
Date
34 / 86
QUALITY CONTROL FORM
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
35 / 86
QUALITY CONTROL FORM
Comments:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
36 / 86
QUALITY CONTROL FORM
Inspection / Test Stage:
Area/Location
Report No.
Report Date
Location (coordinates):
Orientation:
Elevation:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
37 / 86
QUALITY CONTROL FORM
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
38 / 86
QUALITY CONTROL FORM
Note:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
39 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV016 Rev. 0
Asphalt Concrete Compaction RFIN No.
Report No.
Report Date
Reference Document
1 Drawing No. Rev. No
2 Location Road No.
Test Items
Date: Type Mixture:
Location of Sample: Sample # of Test:
Contractor: Sample # of Standard:
Required Compact: % SP gr of Standard:
Degree of Compaction = Pavement Sp gr × 100= % Compaction
Standard Specimen Sp gr
Remarks:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
40 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV017 Rev. 0
Road Shoulder Inspection RFIN No.
(Civil Works) Report No.
Report Date
Drawing No. Rev. No.
Inspection Items ACC REJ Remarks
1. Materials used for Miscellaneous work conform to specs
2. Compaction of grade prior to installation
3. Alignment/Levelness
4. Compaction of grade prior to installation
5. Alignment/Levelness (No Sagging)
6. Sloping followed as per drawing
7. Shoulder surface finished as per drawing
8. Marking carried-out as per related Drawing
9. Signs installed as per related Drawing
10. Drain installed as per related Drawing
11. Joints sealed as per requirement
Notes:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
41 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV018 Rev. 0
Drainage Trench Installation Inspection RFIN No.
Report No.
Report Date
Drawing No.
Line No.
No. Inspection Items ACC REJ Remarks
1 Sub-grade, compacted, Elevation is acceptable
2 Drainage/Trench slope & Top-Level checking As per Drawing is
done
3 Cleanliness in Drainage/trench- Cracked boulders debris removed
etc.
4 The catch pit already completed as per requirements.
Notes:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
42 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV019 Rev. 0
Gravity Leak Test RFIN No.
Report No.
Report Date
Drawing No.
Specification
Static Head Pressure: Holding Time:
Test Medium : Time Start: Time Finish:
Result
No. ISO No.
ACC REJ
Remarks:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
43 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV020 Rev. 0
Masonry Work RFIN No.
(Building Finishing) Report No.
Report Date
No. Item/Location Description Material Alignment Staggering Jointing Mortar Ratio
/Application ACC/REJ Remarks
A. Brick Work
1
2
3
4
5
B. Concrete Work
6
7
8
9
10
C. Other
11
12
Remarks:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
44 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV021 Rev. 0
Plastering Work RFIN No.
(Building Finishing)
Report No.
Report Date
No. Item/Location Description Surface Layer Interval Mortar Ratio Surface ACC/REJ Remarks
Preparation /Application Finish
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Remarks:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
45 / 86
QUALITY CONTROL FORM
Report No.
Report Date
Drawing No.
Line No.
4.
5.
Note:
Signature
Name
Dept.
Signature
Date
46 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV023 Rev. 0
Windows and Doors Work RFIN No.
(Building Finishing) Report No.
Report Date
No. Item/Location Description Installed to Product Surface Hardware Glazing ACC/REJ Remarks
Drawing Quality Finish
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Remarks:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
47 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV024 Rev.0
RFI No.
Final Inspection Report for The Fence
Report No.
Report Date
Drawing No.:
Item Inspection/Verification Checkpoints ACC REJ Remarks
1 Materials are in accordance with Design Documents.
2 All Non-conformance Reports are closed.
3 Walkdown is complete.
Remarks:
Signature
CC7 MHI OWNER
Name
Dept.
Signature
Date
Picture as evidence during inspection
48 / 86
QUALITY CONTROL FORM
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
49 / 86
QUALITY CONTROL FORM
Pipeline No./
Painting System
Mechanical No.
Paint Information
Painting Application
Remarks:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
50 / 86
QUALITY CONTROL FORM
Report No.
Report Date
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
51 / 86
QUALITY CONTROL FORM
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
52 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV029 Rev. 0
High Strength Bolt Tightening RFIN No.
Inspection Record
Report No.
Report Date
□ACC □REJ
Size of Bolts Grade of Bolts Normal Temperature (10~30℃) Abnormal Temperature (0~60℃)
Remarks:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
53 / 86
QUALITY CONTROL FORM
Comments:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
54 / 86
QUALITY CONTROL FORM
Inspection / Test Stage:
Area/Location
Report No.
Report Date
Remarks:
Signature
Name
Dept.
Signature
Date
55 / 86
QUALITY CONTROL FORM
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
Picture as evidence during inspection
Before Grouting After Grouting
56 / 86
QUALITY CONTROL FORM
Report No.
Report Date
3. All structural supports installed per design and all temporary aids/
brackets removed
Notes:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
57 / 86
QUALITY CONTROL FORM
Inspection / Test Stage:
Area/Location
Report No.
Report Date
Drawing No.
Remarks:
Signature
Name
Dept.
Signature
Date
58 / 86
QUALITY CONTROL FORM
RFIN No.
Plumbing Checklist
Report No.
Report Date
7. Piping
8. Joints
9. Valves
10.Fixtures
11.Hydrotesting
Notes:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
59 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV036 Rev. 0
Pressure Test Report RFIN No.
Report No.
Report Date
Test Package No.: Description:
P. &I.D. No.(s) R P. &I.D. No.(s) R P. &I.D. No.(s) R P. &I.D. No.(s) R
Test Condition
Test Medium Chlorine Content
Test Media/Metal Temp Min. Max. Actual
Ambient Temp. Min. Actual
Test Pressure Min. Max. Test Pressure Min. Max.
Holding Time: Min. Actual
Test Gage M.T.E. Date Last Test Gage Low High
Number: M.T.E. Calibrated: Range: Low High
CC7 MHI BCIC
Signature Date Signature Date Signature Date
Pre-Test Walkdown Complete:
NDE, PWHT, PMI (if required)
Complete/Accepted:
Verification of Satisfactory Test Results
Verification of Line Restoration
Picture as evidence during inspection
60 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV037 Rev. 0
Plumbing/Piping System Leak Test RFIN No.
(Building Works) Report No.
Report Date
Work Scope
□ Plumbing □ Down Pipe
□ Drainpipe □ Other
Test Method
Test Medium Test Pressure Duration Remarks
□ Leak Test
□ Full Water Test
□ Flow Test
□ Ball Test
□ Other
Check List
Inspection ACC REJ Remarks
B. Leak/Full Water Test
1.Joint sealing and other requirements completed.
2.Leak test carried-out as per above method and result is acceptable
3.Drain out completed as necessary.
4.Cleaning of internal is carried-out satisfactorily after test.
5.Protection/cover provided (temporary or permanent) as precaution.
(Check if cover may be required to be installed for open ends)
C. Flow or Ball Test
1.Sealing and other required works completed
2.Flow direction is as per requirement
3.No blockage observed along the flow path
4.Cleaning of internal is carried-out satisfactorily after test.
5. Protection/cover provided(temporary or permanent) as precaution.
(Check if cover may be required to be installed for open ends)
Remarks:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
61 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV038 Rev. 0
RFIN No.
HVAC Functional Test Checklist
Report No.
Report Date
No. Description ACC REJ Remarks
1 Specified equipment installed in accordance with
manufacturer’s drawings and specifications.
2 Blowers/Fan/Ventilators working properly
3 Electrical/Instruments
4 Filters are cleaned and free of damage
5 Heating/Cooling Temperature measured and tested
6 Dryers are working properly
7 Compressor functioning properly
8 Outdoor/Indoor unit operational
9 Thermostat functioning
10 Drain pan and connection
11 Dampers working properly
12 Duct supports installed per specifications.
13 Balancing and adjusting completed and controls systems
adjusted.
14 Ceiling diffusers checked.
15 Systems checked for completeness
16 Controls and switches in working condition
17 Unit vibration control
18 CFM of Unit maintained as per required capacity and space
19 Measured & record flow
20 Check proper operation of humidifier
21 All the connection to unit installed
22 Check full load appears (FLA) as per manufacture required.
Remarks:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
62 / 86
QUALITY CONTROL FORM
Inspection / Test Stage:
Area/Location
Report No.
Report Date
2 Check the support are properly fixed and level as per drawing
Remarks:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
63 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV040 Rev. 0
RFIN No.
Refrigerant Piping Layout and Support
Installation Report No.
Report Date
No. Description ACC REJ Remarks
1 All duct work completed &connections sealed properly
2 Check search light required powered (min 500 watts)
3 Light test should be done proper darkness
4 Duct entire surface free of debris and dust
5 Duct leak test method
6 Duct leak test conducted and find : Accepted/Rejected
7 Check smoke fan housing proper fixed.
8 Identify ductwork section to be tested.
Signature
Name
Dept.
Signature
Date
64 / 86
QUALITY CONTROL FORM
Report No.
Report Date
Signature
Name
Dept.
Signature
Date
65 / 86
QUALITY CONTROL FORM
Report No.
Report Date
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
66 / 86
QUALITY CONTROL FORM
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
67 / 86
QUALITY CONTROL FORM
Inspection / Test Stage:
Area/Location
Report Date
2
Ensure all material are free from damages, debris and
dust
3
Ensure all material is stored properly in dry condition and
dust free
4
Check the insulation is applied in accordance with the
approved MS and drawing details
5
Check the insulation is correctly aligned, lapped and
adequately bonded
6 Check the vapor sealing has been correctly applied
7 Check the vapor seal around the support and anchor
8 Check the field applied jacket is properly done
9 Duct joints shall be sealed prior to insulation.
Signature
Name
Dept.
Signature
68 / 86
Date
69 / 86
QUALITY CONTROL FORM
Inspection / Test Stage:
Area/Location
Report No.
Report Date
8 Walkdown is complete.
Remarks:
Signature
Name
Dept.
Signature
Date
70 / 86
QUALITY CONTROL FORM
Report No.
Report Date
Cable No.
Drawing No.
Comments:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
71 / 86
QUALITY CONTROL FORM
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
72 / 86
QUALITY CONTROL FORM
Comments:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
73 / 86
QUALITY CONTROL FORM
Inspection / Test Stage: Area/Location
Form No. FCV049 Rev. 0
Comments:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
74 / 86
QUALITY CONTROL FORM
Remarks: The above form column is filled out according to the actual situation, if not, draw "/"
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
75 / 86
QUALITY CONTROL FORM
Inspection / Test Stage Area/Location
Form No. FCV051 Rev. 0
Lateral Field Data Sheet RFIN No.
Report No.
Report Date
Pile ID: Regression Equation:
Testing Type: Lateral Load Test Test Method: Dial of Pile: Pile Type: Length:
Dial of Piston(cm): Area of Piston(cm2): Design Load(KN): Max Test Load(KN):
Test Starting date: Test Completion Date: Max Settlement(mm): Net Settlement(mm):
Casting Date: Date of Calibration: Dial Gauge(M1)= Dial Gauge(M2)=
Load Observed Actual Settlement
% of Design Load on Test Time Interval Cumulative Average of Actual
Date Application Pressure M1 M2 Remarks
Load Pile(KN) (Min) Time(Min) Settlement(mm)
Time (Mpa) (mm) (mm)
76 / 86
QUALITY CONTROL FORM
Report Date
Remarks:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
77 / 86
QUALITY CONTROL FORM
Inspection/Test Stage: Area/Location
Form No. FCV053 Rev. 0
Test Date
Compaction Test
RFI No.
Report No.
Report Date
Test method
Equipment
Wet Density Moisture Dry Density Max. Dry Density Compaction
No. Test Position
(g/cm3) Rate(%) (g/cm3) (g/cm3) (%)
Remarks:
78 / 86
QUALITY CONTROL FORM
Inspection/Test Stage: Area/Location
Form No. FCV054 Rev. 0
Test Date
Trial compaction
RFI No.
Report No.
Report Date
Test Qty. 1 2 3
h1
h2
Depth(mm)
(h1+h2)/2
Moisture Rate (%)
Test Item Design Value Actual Value
L.L
Critical Moisture Rate P.L.
P.I.
Max. Dry Density (g/cm3) —
Values
Optimum Moisture Rate (%) —
Remarks:
79 / 86
QUALITY CONTROL FORM
Report No.
Report Date
Location/Area
Component No.
3 Temperature of Friction Surface Shall be Less Than 60℃ □ACC □REJ □N/A
Note: In principle, no metallic luster shall be observed after one time application. If there is still metallic
luster on the sprayed surface, please spray the part once more.
Comments:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
80 / 86
QUALITY CONTROL FORM
No. Verify the following are acceptable in accordance with design documents: Result Remark
Front to Rear
Comments:
Signature
CC7 MHI BCIC
Name
Dept.
Signature
Date
81 / 86
QUALITY CONTROL FORM
Inspection/Test Stage: Area/Location
Form No. FCV057 Rev. 0
Functional Test Checklist RFI No.
Report No.
Report Date
Location Area System No.
82 / 86