Maintenance Report January-2021

This monthly maintenance report from Armour Polymer Limited describes maintenance activities from January 2-25, 2021. Key activities included addressing issues with generators, compressors, circuit breakers, wiring, and machines. Maintenance tasks involved parameter setting, cleaning, greasing, replacing parts, and addressing problems with the generator, substation, heating zone, and kneader machine. Maintenance was performed by assistant engineer Atikur Islam Alnoman and focused on ensuring proper operation and verification of equipment.

Uploaded by

kafi1234
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
120 views

Maintenance Report January-2021

This monthly maintenance report from Armour Polymer Limited describes maintenance activities from January 2-25, 2021. Key activities included addressing issues with generators, compressors, circuit breakers, wiring, and machines. Maintenance tasks involved parameter setting, cleaning, greasing, replacing parts, and addressing problems with the generator, substation, heating zone, and kneader machine. Maintenance was performed by assistant engineer Atikur Islam Alnoman and focused on ensuring proper operation and verification of equipment.

Uploaded by

kafi1234
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Armour Polymer Limited

Vangnahati, Sreepur , Gazipur.


Monthly Maintenance Report (January-2021)
Reported By: Atikur Islam Alnoman
Assistant Engineer
Maintenance and Utility Department.
Date Working Work Details Working
Unit Person
02-01-2021 Operation & First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
Reading. VFD Parameter Setting Problem, Re-Setting
Parameter & Switching Problem Solved.
03-01-2021 Generator First I Come To the Office and Observed the Generator, Atikur
Operation & Substation, Compressor, Db Board and Machine with REB
Verification Reading. Air Release Valve Problem & 2 times valve
repairing. REB Load Shedding, Generator Start at 10:10 AM
& Generator Stop at 10:40 AM, Total Gen Set Run 30
Minutes.
04-01-2021 Operation & First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
Reading. Extension Line Removed & New 220V Line Set up
from Sub-Station to Chemical Shed Line.
05-01-2021 Operation First I Come To the Office and Observed the Generator, Atikur
Verification, Substation, Compressor, Db Board and Machine with REB
Kneader Reading. Generator, Radiator & Filter, Substation Cleaning,
Machine and Color Master batches Project Line Extend from
Maintenance Substation.(Kinder Motor-02 Points, Kinder Gear Box
Bearing-04 Points, Extruder Motor-02 Points) All Machine
& Motor are Greasing & cleaning. Kneader Machine
Gearbox old Grease Remove & New Greasing, 3 Bolt Losing
& Perfect Setup &Work Is Done for Kneader Machine.7
KGS Grease uses for Kneader Machine.
06-01-2021 Operation, First I Come To the Office and Observed the Generator, Atikur
Verification, Substation, Compressor, Db Board and Machine with REB
Compressor Reading. Since the Compressor has a 63 A Breaker Problem,
Maintenance a 40 Amp Breaker is fitted. The Work of the Duck ting of the
Generator is Inspection.
07-01-2021 Operation, First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
Reading. New Lights are Added to the Compressor Side.
09-01-2021 Operation First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
Reading. Verification Generator Ducting Works.
10-01-2021 Operation & First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
Reading. Verification Generator Ducting Works. 6 New
Heaters were checked and received.
11-01-2021 Operation First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
& Reading. Morning 2 times valve problem & Solved. 2: Pm
Maintenance Conveyor Motor Trip & Reset Function, & Again 9:00 Pm
Conveyor Motor Trip & Reset Function & Problem Solved.
12:30 am Valve Repairing & Setting ok.
12-01-2021 Generator First I Come To the Office and Observed the Generator, Atikur
Operation Substation, Compressor, Db Board and Machine with REB
Verification Reading. REB Load Shedding, Generator Start at 8:20 AM &
& Heating Generator Stop at 8:50 AM, Total Gen Set Run 30 Minutes.
Zone Heater is checked due to heating Zone Problem & Three
Maintenance Heater Problem is found & replaced. Two sensor pins are
broken & new sensor is installed. Gang box Switching
Problem Solved at Chemical Room. JONATICS
PNEUMATIC VOLVE are Received and fitted to the
Kneader Silencer.
13-01-2021 Operation & First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
Reading. I Checked Extruder Gear Box, Feeder Gear Box,
Kneader Gear Box Oil Level Is Perfect for the machine. 1
Liter Coolant Filling for Generator. Dormitory room line
problem solved.
14-01-2021 Operation & First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
CC Camera Reading. Observing Extruder Motor. 6 CC Cameras of main
Wiring Gate are connected, Electrical line is connected, and wiring
of CC Camera is Done.
16-01-2021 Operation First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
& Wiring Reading. System Engineers fill Security rooms line, Remove
old wire & Replace New Wire.
17-01-2021 Generator I went home on vacation and kept observation all the time. Atikur
Operation & REB Load Shedding, Generator Start at 4:20 AM &
Verification Generator Stop at 4:35 AM, Total Gen Set Run 15 Minutes.
Cooling Tower Pump Controlling Problem & Solved.

18-01-2021 Generator I went home on vacation and kept observation all the time. Atikur
Operation REB Load Shedding, Generator Start at 3:15 AM &
Verification Generator Stop at 3:30 AM, Total Gen Set Run 15 Minutes.
Kneader Motor thermal Relay Rating up 115 A, Air Pressure
Up 13 Bar.
19-01-2021 Operation, First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
& Wiring Reading. A New wiring Socket has been installed from SDB
to Clean the Powder During Loading/Unloading, Which had
to be Hang Earlier.
20-01-2021 Operation, First I Come To the Office and Observed the Generator, Atikur
Verification, Substation, Compressor, Db Board and Machine with REB
Maintenance Reading. All CC Camera Lance Cleaning. Heating Zone 8
One Heater Problem Change Heater. Kneader Pinion
Greasing, Cutter motor Bearing Greasing & All Motor &
Machine Cleaning. Kneader Machine 630 A Breaker Trip &
Fault Problem. So We Change Breaker.
21-01-2021 Generator First I Come To the Office and Observed the Generator, Atikur
Operation, Substation, Compressor, Db Board and Machine with REB
Verification Reading. New 630 Amp ABB MCCB Circuit Breaker is
& Kneader Bigger than the Previous Circuit Breaker, So the Bus bar is
Panel Drilled & Installed, and the Phase point is matched by the
Maintenance broken point. The nut bolt of the breaker is tightened well &
Checked with connection. Relay 252-PAOG is Changed as it
cannot take lode. REB Load Shedding, Generator Start at
5:10 AM & Generator Stop at 5:25 AM, Total Gen Set Run
15 Minutes.
23-01-2021 Operation, First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
Reading. And Encourage them not to Turn on the Lights
Unnecessarily, The Compressor filter box is tightened, the
System Engineers Remove the 440 volt line, the Machine is
arranged like a Color Master Batch drawing.
24-01-2021 Generator First I Come To the Office and Observed the Generator, Atikur
Operation, Substation, Compressor, Db Board and Machine with REB
Verification, Reading. & the Machine is arranged like a Color Master
Batch drawing. REB Load Shedding, Generator Start at
11:30 AM & Generator Stop at 12:00 PM, Total Gen Set Run
30 Minutes.
25-01-2021 Operation, First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
Reading. The Color Master batch machine is Sorted. And
Some Connections are made.
26-01-2021 Operation, First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
& Sample Reading. It is observed that non return valves are fitted in the
Filler fire pump pipeline. A 2”valve 2 no’s available in the water
Machine tank and needs to be replaced. Checking the filler Sample
Maintenance machine found the controlling problem of the main motor,
and tried to solve it. As it was night, no more attempts were
made.
27-01-2021 Operation, First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
& Sample Reading. Filler Sample Machine Problem Solved. It’s Earth
Filler Problem & Controlling Switching Problem. Mixer Gearbox
Machine Greasing, Extruder Gearbox Greasing & LUBE Oil Filling
Maintenance The Oil Gear Box. Machine All Connection Checkup & The
Nut Bolt is Tightened.
28-01-2021 Operation & First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
Reading. At 5:30 Am REB Two Phase Drop out Fuse
followed by Phase link, I come to the Factory on Friday and
Complained to REB Office, They Lifted the Fuse Link at
11:30 am, but Complained again Because they did not get
full Voltage and Provided full Voltage at 12:30 Pm.
30-01-2021 Operation & First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Compressor, Db Board and Machine with REB
Reading. Official Work.
31-01-2021 Operation, First I Come To the Office and Observed the Generator, Atikur
Verification Substation, Cooling tower, Compressor, Db Board and
& Cooling Machine with REB Reading. The Compressor, MDB
Tower Substation room is cleaned, the cooling tower is cleaned, and
Maintenance the water fan of the cooling tower was opened and
connected. January Month Pic Time Energy Consumption
11112.4986 kwh, off Pic Time Energy Consumption
26458.33 kwh, &Total 24 Hours Energy Consumption for
the month of December 37570.36 kwh. & Total REB Bill
Around 450,000+_ tk. Generator Fuel Consumption 90 Liter.
Diesel Gen Energy Consumption 96.7 KWH.

THANK YOU SO MUCH FOR GREAT SUPPORT ON BEHALF OF THE


MAINTENANCE & UTILITY DEPARTMENT

Prepared By: Asst. Engineer Assistant Head of Project Head of Operation