Structural Steel
LEARNING OBJECTIVES:
•MATERIALS
•WORKING DRAWINGS:
• Shop Drawing Submission
• Shop Drawing Review
• Contractor’s Responsibility
•FABRICATION PROCEDURE
• Workmanship, Finish, Fabrication and Welds
• Straightening and Curving
• Camber Procedures
• Bolt Holes
6
Structural Steel
LEARNING OBJECTIVES:
•HANDLING, STORING and SHIPPING MATERIALS:
• Marking & Shipping according to Erection Diagram
• Delivery Inspection and Checklist
•ERECTION PROCEDURE
• Structural Connections
• Bolt Tension
• Falsework
• Finishing and Protective Coating
3
7
Shopdrawings
LEARNING OBJECTIVES:
•STRUCTURAL PLANS & SHOPDRAWINGS:
• Framing Plans
• Typical Transverse Section
• Permissible Field Splice
•STAY IN PLACE FORM
• Recommended SIP Detail (s)
• Applicable Plan Notes
REFERENCE SPECIFICATIONS:
•Section 101
DEFINITIONS OF ABBREVIATIONS, ACRONYMS and TERMS
•Section 105.10
PLANS and WORKING DRAWINGS
•Section 107.17
CONSTRUCTION SAFETY and HEALTH STANDARD
•Section 226
STRUCTURAL STEEL
•Section 233
GALVANIZING
•Section 228
STEEL PILES
•Section 407
STEEL and OTHER STRUCTURES
•Section 411
PROTECTIVE COATING OF METAL IN STRUCTURES
4
Structural Steel
Material - Section 407.02
Structural Steel
Shapes
•Section 226 / pp:230
•ASTM A709 (Grade 36
or Grade 50W )
Unpainted.
Structural Steel
Structural Steel Shapes Bf
W Shape Wide Flange Beam
Web
W 36 x 135
D
Flange
Weight = 135 lbs / LF
Depth = 36”
Rolled Beam
5
Structural Steel
S Shape Standard Beam 7/8”
7B f
S 24 x 106
D
Weight = 106 lbs. / LF
Depth = 24”
Bf = Flange Width = 7 7/8”
Structural Steel
C 15 x 33.9
Weight = 33.9 lbs./ LF
Depth = 15”
6
Structural Steel
Angle Shape t
L 5 x 3 x 3/8”
Leg Dimension = 5” & 3”
Structural Steel
Girder
Jacking
Stiffener
Sole Plate
7
Structural Steel
HP Shape H-Pile
Section 228 W
HP 10 x 42
D
Weight = 42 lbs / LF
Depth = 10” = Width
Structural Steel
8
Structural Steel
Structural Steel
Fabrication:
Welds- Section 407.04 (a)
•Only welding or tack weld noted on the
plans shall be performed Welds
• Partial penetration weld shall not be
allowed.
• Electro-slag and Electro-gas welding
shall be pre-approval in writing
• “Structural units shall not be used
as worktable. Welding on other
work shall be completed before
parts are installed on units”
•Weld Checks :
Field Weld Other side of joint
• Non-conforming welds determined by Notes
Weld all around joint
visual inspection or NDT
Arrow side of joint
• Shall be repaired if not possible shall Weld size
be removed, replaced and re-
inspected.
•Groove Weld shallbe Ground Flush. Fillet Weld
9
Structural Steel
Welds
•Certification :
• Certificate of qualification shall be
for each welder, welding operator
of tacker
• Certificate of qualification shall not
exceed more that 3 months without
performing satisfactory welding
process.
• Qualification shall state Name /
Name and tittle who conducted the
examination and result of test.
• Other applicable AWS codes:
• AWS D1.4 = welds for
rebars, include tack welds
• AWS D1.2 = Welding for
Aluminum
• AWS D1.1 = Welding for
Tubular Structures
Weld Symbols
Structural
Structural SteelSteel
Types of Structural Welds
10
Structural
Structural SteelSteel
Types of Structural Welds
Structural Steel
Shop Full Penetration Weld:
11
Structural
Structural SteelSteel
Non-Conforming Weld
Structural Steel
Damages cause by faulty field Welds
12
Structural Steel
Shop Or Working Drawings Sections 407.03 & 105.10 (c)
• Contractor’s Responsibility
• Shall Submit the Engineering Working Drawing for Engineer’s
Review :
• Shop Drawing Items for Review:
• Structural Steel (Framing Plan, Camber etc.)
• Bridge Stakeout
• Anchor Device
• Bearing Assemblies
• Deck Drain Assembly
• Railing Assemblies
• Tooth Expansion Joints
• Stay-in-Place Forms
• Falsework
• Signal Poles
• Miscellaneous Shop drawings (i.e. Temporary Shoring)
Structural Steel
• Contractor’s Responsibility
• Stamped by an Engineer license to practice in Virginia.
• Provide 30 days from receipt turn around time for review.
• 45 Days if Rail Road, municipality or other entities are
involved.
• Section 105.10 - Contractor may authorize the Fabricator to act
on the Contractor’s behalf.
• Shall be Submitted to the District ACE
• Shop plans will be stamped reviewed with appropriate
comments.
• Hard copies shall furnish 9 sets with detail required unless
indicated in the contract.
• Staunton District S&B allows electronic file submission.
13
Structural Steel
FRAMING PLAN
•Labeling of Beams / Girders
•Horizontal Dimension
•Location of Permissible Field Splices
•Assembly of Structural Connection using H.S. Bolts
•Types of Structural Steel Beams
Structural Steel
Framing Plan
14
Structural Steel
Transverse Section
30
Structural Steel
Upstation Horizontal Dimensions
Girder 1
Girder 2
Permissible Field Splice
Girder 3
Girder 4
Girder 5
Girder 6
Girder 7
Framing Plan
15
31
Structural Steel
Looking Up-station
Beam Labeling
Structural Steel
16
Structural Steel
Structural Steel
17
Structural Steel
Cross Frames
36
Structural Steel
Stiffeners and Connectors
Bearing
Stiffener /
Connector
Plate
18
Structural Steel
Structural Steel
Flange Detail
19
Structural Steel
Structural Steel
Splice & Bolt Detail :
•Bolt layout
•Uniform / Staggered
Bolt Spacing
Field Splice
20
41
Structural Steel
42
Structural Steel
21
Structural Steel
Bolt / Nuts / Washer / DTI :
Structural Steel
Stay In Place Forms Shopdrawings
Field Splice
22
Structural
Structural
SteelSteel
Section 407.04 (a)
“Structural units shall not be used as a worktable.
Welding on other work shall be completed
before parts are installed on units”
Structural Steel
Bridge Survey Stakeout
Field Splice
23
Structural Steel
Temporary Shoring
Structural Steel
Temporary Shoring
Steel Piles
• Section 228
• H-Piles
• Shell Piles
• Sheet Piles
24
49
Structural Steel
Temporary Shoring
Slope
Failure
Structural Steel
Shopdrawings
25
51
Structural Steel
FABRICATION:
Structural Steel
FABRICATION:
Structural Steel Fabrication and
Camber Section 407.04 (a)
Figure 2
Fabricated Beam Shape
and Final Erected Position
26
Structural Steel
FABRICATION:
Structural Steel
Steel Fabrication
Camber Diagram
27
Structural Steel
FABRICATION:
Before
After
Structural Steel
FABRICATION:
28
Structural Steel
FABRICATION:
Structural Steel
FABRICATION:
29
Structural Steel
Jacking Stiffeners
Field Splice
Structural Steel
Jacking Stiffeners
30
Structural Steel
Jacking Stiffeners
Structural Steel
FABRICATION:
Bolt Holes – Section 407.04 (d)
•Shall be punched, drilled, or reamed as specified, but not flame or electrode cut
•Finished holes shall be 1/16 inch larger than the nominal bolt size.
•Oversized holes needs permission from the Engineer or in accordance with Section
407.06(b).
•Tolerance for finished holes is 1/16th inch:
• Plan gage and match mating holes shall not exceed tolerance.
• Offset not > the above tolerance.
•Burrs shall be removed from holes.
•Punched holes:
• Not on Carbon Steel with Fy < 36 ksi or thicker that ¾”.
• Not on HS-Steel with Fy > 36 ksi. Or thicker that 5/8”.
•Full size holes punched in structural members identified in Section 407.04 (k) or in the
Plans, SP or any primary members is not permitted.
31
Structural Steel
FABRICATION:
•Reamed and drilled holes:
•Cut Edges of Plates and Shapes:
•Facing of Bearing Surfaces:
•Bend Plates:
•Annealing and Stress Relieving:
•Stud Shear Connectors:
Structural Steel
32
Structural Steel
FABRICATION:
•Shop Assembly:
• Holes for field connections and field splices in the following main
units shall be drilled.
• Girders and Rolled Beams
• Trusses, Arches and Towers
• Bent and Rigid Frames
• Diaphragm, Cross-Frames
• Members designate and
• Main (primary) Members identified in the Plans, SP or Contract.
• Holes for floor-beam and stringer-end
• Surfaces of metal in contact
• Drift Pins.
• Connecting parts assembled in the shop
• Inspection:
Structural Steel
Handling, Storing and Shipping Section 407.05
• Material Storage:
• Placed 4” above ground
• Properly Supported
• Original Containers / Protective Storage
• Protected from other material contamination
• Contractor Responsibility
• Shall be responsible for loss and damage after shipment.
• Shall check materials delivery against shipping list.
33
Structural Steel
68
Structural Steel
Handling, Storing and Shipping
34
69
Structural Steel
Handling, Storing and Shipping
Structural Steel
Handling, Storing and Shipping
35
71
Structural Steel
Handling, Storing and Shipping
Structural Steel
Handling, Storing and Shipping
Field Splice
36
Structural Steel
Handling, Storing and Shipping
Field Splice
74
Structural Steel
Handling, Storing and Shipping
37
Structural Steel
76
Structural Steel
ERECTION PLAN:
Checklist:
1. Check feasibility or conflicts of staging plan
2. Check procedure, sequence and method of setting:
• Bracing Methods.
• Procedure and sequence of diaphragm installation.
• Staging for truck delivery
• Crane locations (check for distances vs. crane radius)
• Temporary support tower.
3. For single traffic lanes during construction, make sure that the flow of traffic is not
heavily impeded by sequencing the traffic flow with delivery of girders.
4. Check compression flanges against allowable.
5. Check beam against allowable deflection.
6. Bending Stresses
7. Bending at flanges due to clamps
8. Possibility of sliding if spreaders are not used.
9. Check cable capacity.
38
77
Structural Steel
ERECTION PLAN:
Checklist:
10. Check crane specifications:
• Crane Radius
• Check Counter weights used.
78
Structural Steel
Erection
39
Structural Steel
Erection
Field Splice
Structural Steel
Erection
40
Structural Steel
Erection
Structural Steel
Erection Procedure Section 407.06
•Assembly of Structural Connections Using High-Strength Bolts:
• Bolts, nuts and washer
• Bolted Parts
• Installation Method of High Strength Bolts
•Inspection: The Engineer will observe the installation and tightening of
bolts.
• Alignment at Bearings and Transverse Connections:
•Falsework:
•Straightening Material in the Field:
•Assembling Steel
•Finishing
•Protective Coating
41
83
Structural Steel
Erection Procedure Section
Structural Steel
42
Structural Steel
SAFETY
CONTRACTOR IS REQUIRED TO PROVIDE AND USE FALL
PROTECTION.
• 407.04 (j)
• Section 107.17 – Const. Safety and Health Std.
• IIM-CD-2013-01.01
• 29 CFR 1926.501(b)(2) - Each worker constructing a leading
edge 6 feet or more above a lower level must be protected.
– Guardrail System
– Safety Net System
– Personal Fall arrest System
Structural Steel
SAFETY