Ascon Design Department: Comparision Based On Value Engineered Option

The document compares the costs of using a conventional reinforced concrete (RCC) flat slab system versus a post-tensioned (PT) flat slab system for the typical floors of a residential development. It finds that using a PT system results in savings of approximately ₹89 per square meter in material costs due to reduced concrete and steel usage. However, there are also approximately ₹60 per square meter in additional expenses associated with PT. Therefore, the net savings per floor from using a PT system instead of RCC is estimated to be around ₹87,420.

Uploaded by

Ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
72 views

Ascon Design Department: Comparision Based On Value Engineered Option

The document compares the costs of using a conventional reinforced concrete (RCC) flat slab system versus a post-tensioned (PT) flat slab system for the typical floors of a residential development. It finds that using a PT system results in savings of approximately ₹89 per square meter in material costs due to reduced concrete and steel usage. However, there are also approximately ₹60 per square meter in additional expenses associated with PT. Therefore, the net savings per floor from using a PT system instead of RCC is estimated to be around ₹87,420.

Uploaded by

Ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

ASCON DESIGN DEPARTMENT

Project: 2B+G+3+Duplex Residential Development / CENTRE COURT Prepared by Sheik Mohamed Date 18-08-09 Rev 0

Part: Cost comparison between conventional RCC Flat Slab System & Post Tensioned Flat Slab System

Floor: Typical Floor


Comparision Based On Value Engineered Option Expenses incurred at Site due to PT
Assumption
2
Manpower to support PT related activities = 6.25 Dhs / m
2
Purpose Residential Grouting Tendons = 2.25 Dhs / m
2 2
Imposed Load 9 kN/m Pour strip concrete works = 1.5 Dhs / m
Span 7.8 m Edge shuttering & other miscell works
2
Total 10 Dhs / m
Slab Thickness
SAVINGS
PT Slab (Value Engineered Slab 210 mm
3 2
Thickness) Savings in Concrete = 0.05 m / m

RCC Flat Slab 260 mm


Concrete @ 350 Dhs / m3 = 17.5 Dhs / m
2

Untensioned Reinforcement

2
PT Slab Savings in Steel = 24 kg/m
3
Basic Mesh at bottom 35 kg/m
Slab edge reinforcement 7 kg/m3 Savings in Steel = 72 Dhs/m
2

Pour strip reinforcement 3 kg/m3 (Steel Price including cut, bend & fix @ 3000 dhs /Tons)
3
Reinforcement over pier 14 kg/m
3 2
Reinforcement around anchorages 7 kg/m Total Savings = 89 Dhs/m
Reinforcement for earth quake forces 6 kg/m3
EXPENSES
3
Total 72 kg/m
2 2
For an average slab thickness of 210mm = 15.12 kg/m PT Service charge = 50 Dhs/m

2
RCC Slab Expenses incurred at site due to = 10 Dhs/m
PT Works
3
Reinforcement 150 kg/m
(Steel in RCC slab varies between 140 - 160 kg /m3 ) Total PT Related Expenses = 60 Dhs/m
2

2 2
For an average slab thickness of 260mm = 39 kg/m Net Savings = 29 Dhs/m
2
Assuming an average Floor area = 3000 m
Net Savings per floor = 87,420.00 Dhs
ASCON DESIGN DEPARTMENT
Project: 2B+G+3+Duplex Residential Development / CENTRE COURT Prepared by Sheik Mohamed Date 18-08-09 Rev 0

Part: Cost comparison between conventional RCC Flat Slab System & Post Tensioned Flat Slab System

Floor: Typical Floors (First - Roof)

Comparision Based on Existing Detail Expenses incurred at Site due to PT

Assumption
2
Manpower to support PT related activities = 6.25 Dhs / m
2
Purpose Residential Grouting Tendons = 2.25 Dhs / m
Imposed Load 14 kN/m2 Pour strip concrete works = 1.5 Dhs / m
2

Span 7.8 m Edge shuttering & other miscell works


2
Total 10.00 Dhs / m
Slab Thickness
SAVINGS
PT Slab (Thickness Proposed by 250 mm
3 2
Project Consultant) Savings in Concrete = 0.01 m / m

RCC Flat Slab 260 mm

Concrete @ 350 Dhs / m 3 = 3.5 Dhs / m


2

PT Slab

2
Untensioned Reinforcement Savings in Steel = 22 kg/m
Basic Mesh at bottom & Top (Incl temperature effects) 35 kg/m 3
Slab edge reinforcement 7 kg/m 3 Savings in Steel = 67 Dhs/m
2

Pour strip reinforcement 3 kg/m 3 (Steel Price including Material, cut, bend & fix @ 3000 dhs /Tons)
Reinforcement over pier 14 kg/m 3
Reinforcement around anchorages 7 kg/m 3 Total Savings = 70.40 Dhs/m
2

Reinforcement for earth quake forces 6 kg/m 3


EXPENSES
3
Total 72 kg/m
2 2
For The Slab thickness of 250mm = 18 kg/m PT Service charge = 50 Dhs/m

2
RCC Slab Expenses incurred at site due to = 10 Dhs/m
PT Works
3
Reinforcement 155 kg/m
(Steel in RCC slab varies between 140 - 160 kg /m 3 ) Total PT Related Expenses = 60 Dhs/m
2

2 2
For the slab thickness of 260mm = 40.3 kg/m Net Savings = 10.40 Dhs/m

2
Assuming average Floor area = 3000 m

Net Savings per floor = 31,200.00 Dhs


Span To Depth Ratio For

PT Slab = 38
RCC Slab = 33
ASCON DESIGN DEPARTMENT
Project: Value Analysis Exercise Prepared by Sheik Mohamed Date 9/3/2009 Rev 0

Part: Cost comparision between conventional RCC Flat Slab system & Post Tensioned Flat Slab System

Floor: Mechanical Floor


Expenses incurred at Site due to PT
Assumption
2
Manpower to support PT related activities = 6.25 Dhs / m
2
Purpose Mechanical Floor Grouting Tendons = 2.25 Dhs / m
2 2
Imposed Load 14 kN/m Pour strip concrete works = 1.5 Dhs / m
Span 8.5 - 9 m Edge shuttering & other miscell works
2
Total 10 Dhs / m
Slab Thickness
SAVINGS
PT Slab 250 mm
3 2
Savings in Concrete = 0.05 m / m
RCC Flat Slab 300 mm (Assuming average PT slab thickness as 230mm against RCC slab of 310mm thick)

Concrete @ 350 Dhs / m3


2
= 17.5 Dhs / m
Untensioned Reinforcement

2
PT Slab Savings in Steel = 29 kg/m
Basic Mesh at bottom & Top (Incl temperature effects) 35 kg/m3
Slab edge reinforcement 7 kg/m3 Savings in Steel = 71 Dhs/m
2

Pour strip reinforcement 3 kg/m3 (Steel Price including cut, bend & fix @ 2500 dhs /Tons)
Reinforcement over pier 14 kg/m3
Reinforcement around anchorages 7 kg/m3 Total Savings = 89 Dhs/m
2

Reinforcement for earth quake forces 6 kg/m3


EXPENSES
3
Total 72 kg/m
2 2
For an average slab thickness of 250mm = 18 kg/m PT Service charge = 60 Dhs/m

2
RCC Slab Expenses incurred at site due to = 10 Dhs/m
PT Works
3
Reinforcement 155 kg/m
(Steel in RCC slab varies between 140 - 160 kg /m3 )
2
Total PT Related Expenses = 70 Dhs/m

2 2
For an average slab thickness of 300mm = 46.5 kg/m Net Savings = 19 Dhs/m

2
Assuming average Floor area = 2500 m

Net Savings per floor = 46,875.00 Dhs