Keterangan Zona: Pasongsongan Kota Sumenep Giligenting Ra'As Sapeken
Keterangan Zona: Pasongsongan Kota Sumenep Giligenting Ra'As Sapeken
MINGGU KE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
PERIODE HARI KALENDER
Bobot 12 16 23 30 1 8 15 22 29 6
NO JENIS PEKERJAAN Cost Pekerjaan 6 Sept. 13 Sept. 20 Sept. 27 Sept. 4 Okto. 11 Okto. 18 Okto. 25 Okto, BOBOT (%)
Agust. Agust. Agust. Agust. Novem. Novem. Novem. Novem. Novem. Desem.
(%)
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
15 22 29 7 14 21 28 5 12
5 Sept. 12 Sept. 19 Sept. 26 Sept. 3 Okto. 10 Okto. 17 Okto. 24 Okto. 31 Okto,
Agust. Agust. Agust. Novem. Novem. Novem. Novem. Desem. Desem.
1 2 3 5 6 7
500,008,900.20
JUMLAH BOBOT 100.00
RENCANA BOBOT MINGGUAN 0.29 1.29 4.66 6.81 7.10 8.09 8.38 8.09 8.38 8.09 8.38 8.09 8.38 6.80 4.01 1.28 1.58 0.29
KUMULATIF RENCANA BOBOT MINGGUAN 0 0.29 1.58 6.24 13.05 20.15 28.24 36.62 44.71 53.09 61.18 69.56 77.65 86.03 92.83 96.85 98.13 99.71 100.00
REALISASI BOBOT MINGGUAN - -
KUMULATIF REALISASI BOBOT MINGGUAN 0 0
DEVIASI (+/-) %
Dibulatkan 106,568,000.00 378,823,000.00 - 500,008,000.00 0.00 0.00 0.00 0.00 500,008,000.00 ###
Jumlah 106,568,000.00 378,823,000.00 - 500,008,000.00
Total Kontribusi 0% - -
1 Pembersihan Lapangan /1 M2
0.0600 Pekerja @ 70,000.00 = 4,200.00
0.0060 Mandor @ - = -
4,200.00
Tiap 1 M2 = 1/1 x 4,200.00 = 4,200.00
1 Pekerjaan Beton Fc. 7.4 Mpa atau K. 90 Kg/Cm2 Anal. A.4.1.1.4 /M3
1.2000 Pekerja @ 70,000.00 = 84,000.00
0.0830 Mandor @ - = -
0.2000 Tukang Batu @ 85,000.00 = 17,000.00
0.0280 Kepala Tukang @ - = -
0.7607 M3 Kerikil @ 255,000.00 = 193,988.89
0.6379 M3 Pasir Beton @ 220,000.00 = 140,328.57
230.0000 Kg Semen @ 1,060.00 = 243,800.00
200.0000 Ltr Air @ - = -
101,000.00 578,117.46 = 679,117.46
2 Pekerjaan Beton Fc. 14.5 Mpa atau K. 175 Kg/Cm2 Anal. A.4.1.1.5 /M3
1.4500 Pekerja @ 70,000.00 = 101,500.00
0.0830 Mandor @ - = -
0.2750 Tukang Batu @ 85,000.00 = 23,375.00
0.0280 Kepala Tukang @ - = -
0.7622 M3 Kerikil @ 255,000.00 = 194,361.00
0.5429 M3 Pasir Beton @ 220,000.00 = 119,438.00
326.0000 Kg Semen @ 1,060.00 = 345,560.00
215.0000 Ltr Air @ - = -
124,875.00 659,359.00 = 784,234.00
7 Pekerjaan Beton Fc. 7.4 Mpa atau K. 90 Kg/Cm2 Anal. A.4.1.1.4 /M3
1.0000 M3 Analisa Stamp Beton = 679,117.46 = 679,117.46
1.0000 Kg Analisa Pekerjaan Besi Beton = 11,325.00 = 11,325.00
1.0000 M2 Analisa Cetakan Beton = 86,220.00 = 86,220.00
= 776,662.46
8 Pekerjaan Beton Kolom, Sloof dan Ring Balk
1.0000 M3 Analisa Stamp Beton = 784,234.00 = 784,234.00 124,875.00
1.0000 Kg Analisa Pekerjaan Besi Beton = 12,410.00 = 12,410.00 1,085.00
1.0000 M2 Analisa Cetakan Beton 2 x pakai = 86,220.00 = 86,220.00 29,250.00
= 882,864.00 155,210.00
9 Pembongkaran Bekisting
0.0018 Pekerja @ 70,000.00 = 126.00
126.00 - = 126.00
1 Mencat Dengan Cat Minyak (1 plamuur, 1 cat dasar, 3 cat penutup) Anal. A.4.7.1.5/M2
0.0700 Pekerja @ 70,000.00 = 4,900.00
0.0030 Mandor @ - = -
0.1050 Tukang Cat @ 85,000.00 = 8,925.00
0.0040 Kepala Tukang @ - = -
0.2000 Kg Cat Menie @ 20,000.00 = 4,000.00
0.1500 Kg Plamuur @ 45,000.00 = 6,750.00
0.3500 Kg Cat Penutup @ 54,000.00 = 18,900.00
0.0300 Kg Pengencer @ 38,000.00 = 1,140.00
0.2000 Lbr Amplas @ 8,600.00 = 1,720.00
13,825.00 32,510.00 = 46,335.00
KEPALA TUKANG TUKANG BATU TUKANG KAYU TUKANG BESI TUKANG CAT PEKERJA MANDOR
NO URAIAN PEKERJAAN SAT VOLUME KET
INDEK JUMLAH INDEK JUMLAH INDEK JUMLAH INDEK JUMLAH INDEK JUMLAH INDEK JUMLAH INDEK JUMLAH
I PEKERJAAN PONDASI DAN BETON
1 Galian Tanah Biasa Sedalam 1 m m3 22.82 - - - - 0.45 10.27 -
2 Pasangan Pondasi Batu kali 1 Pc : 8 Ps m3 37.08 - 0.75 27.81 - - 1.50 55.61 -
3 Pasangan Pondasi Rollage 1 Pc : 6 Ps m2 22.43 - 0.10 2.24 0.30 6.73
4 Kolom Praktis 10/10
a. Pembesian kg 1,094.36 0.01 7.66 0.01 7.66
b. Beton Mutu K 175 m3 3.86 - 0.28 1.06 - - - 1.45 5.60 -
5 Ringbalk 10/10 - - - - -
a. Pembesian kg 554.55 0.01 3.88 0.01 3.88
b. Beton Mutu K 175 m3 2.85 0.28 0.78 1.45 4.14
6 Sloof 10/15
a. Pembesian kg 586.20 - - - 0.01 4.10 - 0.01 4.10 -
b. Beton Mutu K 175 m3 4.28 - 0.28 1.18 - - - 1.45 6.20 -
7 Bekisting Kolom Praktis 10/10 (2x pakai) m2 38.64 - - 0.13 5.02 - - 0.26 10.05 -
8 Bekisting Ringbalk 10/10 (2x pakai) m2 28.52 - - 0.13 3.71 - - 0.26 7.42 -
9 Bekisting Sloof 10/15 (1x pakai) m2 85.56 - - 0.13 11.12 - - 0.26 22.25 -
Jumlah - 33.07 19.85 15.65 - 143.90 - 15,901,857.73
II PEKERJAAN PASANGAN DINDING
1 Pasangan Bata 1pc : 4 ps m2 490.36 - 0.10 49.04 - - - 0.30 147.11 -
2 Plesteran Biasa 1pc : 4 ps tb. 15 mm m2 250.70 - 0.02 3.76 - - - 0.30 75.21 -
3 Acian m2 1,005.52 0.10 100.55 - - 0.15 150.83
4 Roster Batapres 20x20cm bh 288.00 0.00 0.72 - - 0.01 2.16
Jumlah 154.07 - - - 375.31 - 39,367,242.50
III PEKERJAAN ATAP, LISTRIK, LANTAI DAN PENGECATAN - - - - - - -
1 Pasang Rangka Atap Baja Ringan C. 75 - 0,75 m2 268.80 - 0.05 12.10 - - - 0.02 5.38 -
2 Pasang Penutup Atap Galvalum 0.25 mm m2 268.80 - 0.06 16.13 - - - 0.08 21.50 -
3 Lantai Keramik 20 x 20 cm m2 107.52 - 0.35 37.63 - - - 0.70 75.26 -
4 Rabat Beton Bawah Keramik m3 5.38 - 0.20 1.08 - - - 1.20 6.45 -
5 Fitting Lampu bh - - - - - - - -
6 Lampu 5 watt bh - - - - - - - -
7 Kabel NYM 2x1,5mm m - - -
8 Sakelar Tunggal bh - -
9 Pengecatan Tembok m2 1,005.52 0.06 63.35 0.02 20.11
Jumlah 66.93 63.35 128.71 20,083,103.6
C PEKERJAAN SEPTICTANK DAN RESAPAN - - - - - - -
I PEKERJAAN PIPA DAN ACCESORIS - - - - - - -
1 Pintu Aluminium Kamar Mandi unit 48.00 - 0.05 2.40 0.05 2.40
2 Floor Drain bh 48.00 0.10 0.01
3 Media Filter unit 48.00 - - - - - 2.56 122.88 -
4 Manhole Dia. 30 cm unit 96.00 - - - - - - -
5 Kloset Jongkok bh 48.00 - 0.35 16.80 - - - 0.05 2.59 -
6 Pasang Grease Trap Precast Dia. 30 cm unit 48.00 0.0844 4.0499 - - 0.3787 18.1797
7 Kran Air bh 48.00
8 Tee PVC AW Ø 1" bh 48.00
9 Elbow PVC AW Ø 2" bh 144.00
10 Tee PVC AW Ø 2" bh 48.00 - - - - - - -
11 Tee PVC AW Ø 3" bh 48.00 - - - - - - -
12 Pipa PVC AW Ø 1/2" m' 96.00 - - - - - - -
13 Pipa PVC AW Ø 2" m' 384.00 - - - - - - -
14 Pipa PVC AW Ø 3" m' 384.00 - - - - - - -
Jumlah 20.85 2.40 - - 146.05
II PEKERJAAN SEPTICTANK TYPE 1 (1-5 Jiwa) - - - - - - -
1 Galian Tanah Biasa m3 103.68 - - - - - 0.45 46.66 -
2 Plat Tutup Beton ( tb. 10 cm ) - - - - - - -
a. Pembesian kg 304.92 - - - - - - -
b. Beton Mutu K 175 m3 6.91 - 0.28 1.90 - - - 1.45 10.02 -
3 Bekisting Plat Tutup Beton ( tb. 10 cm ) (2x pakai) m2 47.04 0.13 6.12 - 0.26 12.23
4 Tangki Septik Beton ( tb. 10 cm ) - -
a. Pembesian kg 2,679.58 - - - - - - -
b. Beton Mutu K 175 m3 40.14 - 0.28 11.04 - - - 1.45 58.20 -
5 Bekisting Tangki Septik Beton ( tb. 10 cm ) (2x pakai) m2 199.25 - - 0.13 25.90 - - 0.26 51.81 -
6 Pipa Ventilasi Udara GIP dia 1" m' 96.00 - - - - - - -
Jumlah 12.94 32.02 - - 178.91
III PEKERJAAN SEPTICTANK TYPE 2 (6-10 Jiwa)
1 Galian Tanah Biasa m3 - - - - - - - -
2 Plat Tutup Beton ( tb. 10 cm ) - - -
a. Pembesian kg - - - -
b. Beton Mutu K 175 m3 -
3 Bekisting Plat Tutup Beton ( tb. 10 cm ) (2x pakai) m2 - - -
4 Tangki Septik Beton ( tb. 10 cm ) - - -
a. Pembesian kg - -
b. Beton Mutu K 175 m3 -
5 Bekisting Tangki Septik Beton ( tb. 10 cm ) (1x pakai) m2 -
Jumlah - - - - -
IV PEKERJAAN RESAPAN
1 Galian Tanah Biasa m3 56.52 0.45 25.43
2 Pas. Batu Bata (tanpa plester) m2 -
3 Pas. Buis Beton dia 80 bh 144.00
4 Plat Beton ( tb. 10 cm ) -
a. Pembesian kg 241.47 - - - -
b. Beton Mutu K 175 m3 3.77 0.28 1.04 - - - 1.45 5.46
7 Bekisting Plat m2 18.84 0.13 2.45 0.26 4.90
Jumlah 1.04 2.45 - - 35.80
TOTAL HOK - 288.90 56.72 15.65 63.35 1,002.68 -
STANDAR HARGA SATUAN UPAH TENAGA KERJA DAN BAHAN
TAHUN ANGGARAN 2021
KEGIATAN : SANITASI PERDESAAN PADAT KARYA ( PEN ) 2021
PEKERJAAN : PEMBANGUNAN TOILET INDIVIDU
TAHUN ANGGARAN : 2021
JUMLAH BANGUNAN : 48 UNIT
HARGA SATUAN
NO NAMA BAHAN DAN UPAH TENAGA KERJA SATUAN
HARGA TOKO ONGKOS
TOTAL (Rp)
(Rp) ANGKUT (Rp)
A UPAH TENAGA KERJA
1 Mandor org/hari - - -
2 Kepala Tukang org/hari - - -
3 Tukang Batu org/hari 85,000.00 - 85,000.00
4 Tukang Besi org/hari 85,000.00 - 85,000.00
5 Tukang Cat org/hari 85,000.00 - 85,000.00
6 Tukang Kayu org/hari 85,000.00 - 85,000.00
7 Pekerja org/hari 70,000.00 - 70,000.00
Jumlah
Total
NO. URAIAN PEKERJAAN. SAT Panjang Lebar Tinggi Jumlah Bang. : 46
Volume
Unit
4 Acian m2 1,005.52
5 Roster Batapres 20x20cm bh 6.00 48.00 288.00
Jumlah
Total
NO. URAIAN PEKERJAAN. SAT Panjang Lebar Tinggi Jumlah Bang. : 46
Volume
Unit
III PEKERJAAN ATAP, LISTRIK, LANTAI DAN PENGECATAN
1 Pasang Rangka Atap Baja Ringan C. 75 - 0,75 m2 2.80 2.00 5.60 48.00 268.80
3 Lantai Keramik 20 x 20 cm m2 48.00 107.52
Lantai 1.60 1.40 2.24
Dinding 0.00 0.00 0.00
Faktor Pengurangan Bak 0.00 0.00 0.00
4 Rabat Beton Bawah Keramik m3 1.60 1.40 0.05 48.00 5.38
5 Fitting Lampu bh 1.00 48.00 48.00
6 Lampu 5 watt bh 1.00 48.00 48.00
7 Kabel NYM 2x1,5mm m 3.00 48.00 144.00
8 Sakelar Tunggal bh 1.00 48.00 48.00
9 Pengecatan Tembok m2 1,005.52
A BAHAN MATERIAL
1 Pasir 116.00 m3 220,000 25,520,000
2 Batu Kali 53.00 m3 230,000 12,190,000
3 Batu bata 35,895.00 bh 700 25,126,500
4 Split/Kerikil 2/3 cm 52.00 m3 255,000 13,260,000
5 Usuk Kayu 5/7 5.00 m3 2,280,000 11,400,000
6 Paku 48.00 kg 15,000 720,000
7 Buis Beton Dia. 80 cm 145.00 bh 170,000 24,650,000
8 Semen Portland (PC) 842.00 zak 53,000 44,626,000
9 Besi Dia. 10 351.00 btg 80,000 28,080,000
10 Besi Dia. 8 189.00 btg 53,000 10,017,000
11 Besi Dia. 6 232.00 btg 32,000 7,424,000
12 Bendrat 82.00 kg 20,000 1,640,000
13 Papan Begisting 5.00 m3 2,280,000 11,400,000
14 Roster 288.00 bh 15,000 4,320,000
15 Baja Ringan C.75.75 861.00 m3 16,000 13,776,000
16 Dinabolt 269.00 bh 2,500 672,500
17 Galvalum 0,25 mm 358.00 m3 50,000 17,900,000
18 Baut Roofing 2,688.00 bh 100 268,800
19 Semen Warna 54.00 kg 15,000 810,000
20 Keramik 113.00 dos 65,000 7,345,000
21 Cat dasar 362.00 kg 30,000 10,860,000
22 Pintu Aluminium 48.00 bh 300,000 14,400,000
23 Floor Drain 48.00 bh 30,000 1,440,000
24 Media Filter 48.00 unit 432,000 20,736,000
25 Manhole Dia. 30 cm 96.00 bh 80,000 7,680,000
26 Kloset Jongkok 48.00 bh 180,000 8,640,000
27 Grastrap 48.00 bh 225,000 10,800,000
28 Kran Air 48.00 bh 30,000 1,440,000
29 Sealtape 2.00 bh 8,000 16,000
30 Tee PVC AW Ø 1" 48.00 bh 6,000 288,000
31 Elbow PVC AW Ø 2" 144.00 bh 9,000 1,296,000
32 Tee PVC AW Ø 2" 48.00 bh 12,000 576,000
33 Tee PVC AW Ø 3" 48.00 bh 15,000 720,000
34 Pipa PVC AW Ø 1/2" 96.00 m 7,000 672,000
35 Pipa PVC AW Ø 2" 385.00 m 26,000 10,010,000
36 Pipa PVC AW Ø 3" 384.00 m 41,000 15,744,000
37 Tripleks 9 mm 42.00 lbr 95,000 3,990,000
38 Ijuk 290.00 kg 10,000 2,900,000
39 Pipa GI 1" 96.00 m 57,000 5,472,000
378,825,800.00 75.76
B TENAGA KERJA
1 Tukang 426.00 HOK 85,000.00 36,210,000.00
2 Pekerja 1,005.00 HOK 70,000.00 70,350,000.00
106,560,000.00 21.31
C BIAYA OPERASIONAL PEKERJAAN (BOP)
I ALAT TULIS KANTOR (ATK) TERMASUK MATERAI :
1 Alat Tulis Kantor (ATK) 1.00 Ls 300,000.00 300,000
2 Materai 75.00 Lembar 11,000.00 825,000
PEMAKETAN -1
5 Buis Beton Dia. 80 cm 177.00 bh 170,000 30,090,000 Droping per titik lokasi
JUMLAH 111,226,000
PEMAKETAN -2
JUMLAH 165,500,000
PEMAKETAN -3
1 Media Filter 59.00 unit 432,000 25,488,000 Sarang Tawon Droping beberapa titik
JUMLAH 25,488,000
PEMAKETAN -4
JUMLAH 22,715,000
1 PEMAKETAN -1 : 111,226,000.00
2 PEMAKETAN -2 : 165,500,000.00
3 PEMAKETAN -3 : 25,488,000.00
4 PEMAKETAN -4 : 22,715,000.00
381,964,500
SELISIH (3,138,700.00)
RENCANA PENGGUNAAN DANA TERMIN I
A BAHAN MATERIAL
1 Pasir 116.00 81.00 81.00 m3 220,000 17,820,000
2 Batu Kali 53.00 37.00 37.00 m3 230,000 8,510,000
3 Batu bata 35,895.00 15,000.00 15,000.00 bh 700 10,500,000
4 Split/Kerikil 2/3 cm 52.00 36.00 36.00 m3 255,000 9,180,000
5 Usuk Kayu 5/7 5.00 4.00 4.00 m3 2,280,000 9,120,000
6 Paku 48.00 34.00 34.00 kg 15,000 510,000
7 Buis Beton Dia. 80 cm 145.00 90.00 90.00 bh 170,000 15,300,000
8 Semen Portland (PC) 842.00 500.00 500.00 zak 53,000 26,500,000
9 Besi Dia. 10 351.00 245.00 245.00 btg 80,000 19,600,000
10 Besi Dia. 8 189.00 130.00 130.00 btg 53,000 6,890,000
11 Besi Dia. 6 232.00 160.00 160.00 btg 32,000 5,120,000
12 Bendrat 82.00 57.00 57.00 kg 20,000 1,140,000
13 Papan Begisting 5.00 4.00 4.00 m3 2,280,000 9,120,000
14 Roster 288.00 202.00 202.00 bh 15,000 3,030,000
15 Baja Ringan C.75.75 861.00 603.00 603.00 m3 16,000 9,648,000
16 Dinabolt 269.00 188.00 188.00 bh 2,500 470,000
17 Galvalum 0,25 mm 358.00 247.00 247.00 m3 50,000 12,350,000
18 Baut Roofing 2,688.00 1,870.00 1,870.00 bh 100 187,000
19 Semen Warna 54.00 38.00 38.00 kg 15,000 570,000
20 Keramik 113.00 79.00 79.00 dos 65,000 5,135,000
21 Cat dasar 362.00 253.00 253.00 kg 30,000 7,590,000
22 Pintu Aluminium 48.00 33.00 33.00 bh 300,000 9,900,000
23 Floor Drain 48.00 34.00 34.00 bh 30,000 1,020,000
24 Media Filter 48.00 48.00 48.00 unit 432,000 20,736,000
25 Manhole Dia. 30 cm 96.00 96.00 96.00 bh 80,000 7,680,000
26 Kloset Jongkok 48.00 34.00 34.00 bh 180,000 6,120,000
27 Grastrap 48.00 48.00 48.00 bh 225,000 10,800,000
28 Kran Air 48.00 34.00 34.00 bh 30,000 1,020,000
29 Sealtape 2.00 1.00 1.00 bh 8,000 8,000
30 Tee PVC AW Ø 1" 48.00 34.00 34.00 bh 6,000 204,000
31 Elbow PVC AW Ø 2" 144.00 101.00 101.00 bh 9,000 909,000
32 Tee PVC AW Ø 2" 48.00 34.00 34.00 bh 12,000 408,000
33 Tee PVC AW Ø 3" 48.00 34.00 34.00 bh 15,000 510,000
34 Pipa PVC AW Ø 1/2" 96.00 66.00 66.00 m 7,000 462,000
35 Pipa PVC AW Ø 2" 385.00 270.00 270.00 m 26,000 7,020,000
36 Pipa PVC AW Ø 3" 384.00 269.00 269.00 m 41,000 11,029,000
37 Tripleks 9 mm 42.00 29.00 29.00 lbr 95,000 2,755,000
38 Ijuk 290.00 203.00 203.00 kg 10,000 2,030,000
39 Pipa GI 1" 96.00 67.00 67.00 m 57,000 3,819,000
264,720,000.00
B TENAGA KERJA
1 Tukang 426.00 298.00 298.00 HOK 85,000.00 25,330,000
2 Pekerja 1,005.00 704.00 704.00 HOK 70,000.00 49,280,000
74,610,000.00
C BIAYA OPERASIONAL PEKERJAAN (BOP)
I ALAT TULIS KANTOR (ATK) TERMASUK MATERAI :
1 Alat Tulis Kantor (ATK) 1.00 1.00 1.00 Ls 300,000.00 300,000.00
2 Materai 75.00 20.00 20.00 Lembar 11,000.00 220,000.00
IV KAMPANYE PHBS
1 Transport Sanitarian 3 kali untuk 2 orang 6.00 2.00 2.00 Org/Kali 50,000.00 100,000.00
2 Konsumsi Peserta 60.00 20.00 20.00 Org/Kali 14,000.00 280,000.00
3 Media PHBS (3 kali) 3.00 2.00 2.00 ls 300,000.00 600,000.00
A BAHAN MATERIAL
1 Pasir 116.00 81.00 35.00 116.00 m3 220,000 7,700,000
2 Batu Kali 53.00 37.00 16.00 53.00 m3 230,000 3,680,000
3 Batu bata 35,895.00 15,000.00 20,895.00 35,895.00 bh 700 14,626,500
4 Split/Kerikil 2/3 cm 52.00 36.00 16.00 52.00 m3 255,000 4,080,000
5 Usuk Kayu 5/7 5.00 4.00 1.00 5.00 m3 2,280,000 2,280,000
6 Paku 48.00 34.00 14.00 48.00 kg 15,000 210,000
7 Buis Beton Dia. 80 cm 145.00 90.00 55.00 145.00 bh 170,000 9,350,000
8 Semen Portland (PC) 842.00 500.00 342.00 842.00 zak 53,000 18,126,000
9 Besi Dia. 10 351.00 245.00 106.00 351.00 btg 80,000 8,480,000
10 Besi Dia. 8 189.00 130.00 59.00 189.00 btg 53,000 3,127,000
11 Besi Dia. 6 232.00 160.00 72.00 232.00 btg 32,000 2,304,000
12 Bendrat 82.00 57.00 25.00 82.00 kg 20,000 500,000
13 Papan Begisting 5.00 4.00 1.00 5.00 m3 2,280,000 2,280,000
14 Roster 288.00 202.00 86.00 288.00 bh 15,000 1,290,000
15 Baja Ringan C.75.75 861.00 603.00 258.00 861.00 m3 16,000 4,128,000
16 Dinabolt 269.00 188.00 81.00 269.00 bh 2,500 202,500
17 Galvalum 0,25 mm 358.00 247.00 111.00 358.00 m3 50,000 5,550,000
18 Baut Roofing 2,688.00 1,870.00 818.00 2,688.00 bh 100 81,800
19 Semen Warna 54.00 38.00 16.00 54.00 kg 15,000 240,000
20 Keramik 113.00 79.00 34.00 113.00 dos 65,000 2,210,000
21 Cat dasar 362.00 253.00 109.00 362.00 kg 30,000 3,270,000
22 Pintu Aluminium 48.00 33.00 15.00 48.00 bh 300,000 4,500,000
23 Floor Drain 48.00 34.00 14.00 48.00 bh 30,000 420,000
24 Media Filter 48.00 48.00 - 48.00 unit 432,000 -
25 Manhole Dia. 30 cm 96.00 96.00 - 96.00 bh 80,000 -
26 Kloset Jongkok 48.00 34.00 14.00 48.00 bh 180,000 2,520,000
27 Grastrap 48.00 48.00 - 48.00 bh 225,000 -
28 Kran Air 48.00 34.00 14.00 48.00 bh 30,000 420,000
29 Sealtape 2.00 1.00 1.00 2.00 bh 8,000 8,000
30 Tee PVC AW Ø 1" 48.00 34.00 14.00 48.00 bh 6,000 84,000
31 Elbow PVC AW Ø 2" 144.00 101.00 43.00 144.00 bh 9,000 387,000
32 Tee PVC AW Ø 2" 48.00 34.00 14.00 48.00 bh 12,000 168,000
33 Tee PVC AW Ø 3" 48.00 34.00 14.00 48.00 bh 15,000 210,000
34 Pipa PVC AW Ø 1/2" 96.00 66.00 30.00 96.00 m 7,000 210,000
35 Pipa PVC AW Ø 2" 385.00 270.00 115.00 385.00 m 26,000 2,990,000
36 Pipa PVC AW Ø 3" 384.00 269.00 115.00 384.00 m 41,000 4,715,000
37 Tripleks 9 mm 42.00 29.00 13.00 42.00 lbr 95,000 1,235,000
38 Ijuk 290.00 203.00 87.00 290.00 kg 10,000 870,000
39 Pipa GI 1" 96.00 67.00 29.00 96.00 m 57,000 1,653,000
114,105,800.00
B TENAGA KERJA
1 Tukang 426.00 298.00 128.00 426.00 HOK 85,000.00 10,880,000
2 Pekerja 1,005.00 704.00 301.00 1,005.00 HOK 70,000.00 21,070,000
31,950,000.00
C BIAYA OPERASIONAL PEKERJAAN (BOP)
I ALAT TULIS KANTOR (ATK) TERMASUK MATERAI :
1 Alat Tulis Kantor (ATK) 1.00 1.00 - 1.00 Ls 300,000.00 -
2 Materai 75.00 20.00 55.00 75.00 Lembar 11,000.00 605,000
- - -
II PEMBUATAN DOKUMEN LPJ KSM (Cetak, Foto Copy - - -
1 Cetak, Foto Copy dan Penggandaan LPJ Tahap I 5.00 5.00 - 5.00 Buku 200,000.00 -
2 Cetak, Foto Copy dan Penggandaan LPJ Akhir 5.00 - 5.00 5.00 Buku 250,000.00 1,250,000
- - -
III ALAT PELINDUNG DIRI DAN KESELAMATAN KERJ - - -
1 Helm Pengaman Kerja 12.00 12.00 - 12.00 Pcs 35,000.00 -
2 Sarung Tangan 12.00 12.00 - 12.00 Pasang 10,000.00 -
3 Sepatu Boods Panjang 12.00 12.00 - 12.00 Pasang 110,000.00 -
4 Rompi Pekerja 12.00 12.00 - 12.00 Pcs 25,000.00 -
5 Obat-obatan P3K 1.00 1.00 - 1.00 Set 150,000.00 -
6 Alat Pelindung Diri (APD) - - -
a. Masker 7.00 7.00 - 7.00 Kotak 30,000.00 -
b. Hand Sanitaizer 10.00 10.00 - 10.00 botol 15,000.00 -
- - -
IV KAMPANYE PHBS - - -
1 Transport Sanitarian 3 kali untuk 2 orang 6.00 2.00 4.00 6.00 Org/Kali 50,000.00 200,000
2 Konsumsi Peserta 60.00 20.00 40.00 60.00 Org/Kali 14,000.00 560,000
3 Media PHBS (3 kali) 3.00 2.00 1.00 3.00 ls 300,000.00 300,000
- - -
V KEGIATAN REMBUK WARGA - - -
1 Konsumsi untuk Rembuk Warga 1.00 1.00 - 1.00 ls 150,000.00 -
- - -
VI MEDIA INFORMASI PELAKSANAAN KEGIATAN - - -
1 Papan Informasi Pelaksanaan Kegiatan 1.00 1.00 - 1.00 ls 100,000.00 -
2 Sticker 48.00 - 48.00 48.00 lbr 9,000.00 432,000
3 Biaya Komunikasi 3.00 - 3.00 3.00 bln 100,000.00 300,000
4 Prasasti uk, 20 x 30 cm 48.00 48.00 - 48.00 unit 100,000.00 -
- - -
VII TRANSPORT KSM - - -
1 Transport ke Bank 5 kali untuk 3 orang 15.00 9.00 6.00 15.00 Org/Kali 50,000.00 300,000
3,947,000.00
JUMLAH TOTAL (A+B+C) 150,002,800.00
DIBULATKAN 150,000,000.00
A BAHAN MATERIAL
1 Pasir 116.00 21.00 21.00 m3 220,000 4,620,000
2 Batu Kali 53.00 14.00 14.00 m3 230,000 3,220,000
3 Batu bata 35,895.00 6,000.00 6,000.00 bh 700 4,200,000
4 Split/Kerikil 2/3 cm 52.00 14.00 14.00 m3 255,000 3,570,000
5 Usuk Kayu 5/7 5.00 2.50 2.50 m3 2,280,000 5,700,000
6 Paku 48.00 8.50 8.50 kg 15,000 127,500
7 Buis Beton Dia. 80 cm 145.00 36.00 36.00 bh 170,000 6,120,000
12 Bendrat 82.00 2.50 2.50 kg 20,000 50,000
13 Papan Begisting 5.00 24.00 24.00 m3 2,280,000 54,720,000
14 Roster 288.00 120.00 120.00 bh 15,000 1,800,000
15 Baja Ringan C.75.75 861.00 40.00 40.00 m3 16,000 640,000
16 Dinabolt 269.00 50.00 50.00 m 2,500 125,000
17 Galvalum 0,25 mm 358.00 400.00 400.00 m3 50,000 20,000,000
18 Baut Roofing 2,688.00 13.00 13.00 bh 100 1,300
19 Semen Warna 54.00 28.00 28.00 kg 15,000 420,000
20 Keramik 113.00 64.00 64.00 dos 65,000 4,160,000
21 Cat dasar 362.00 12.00 12.00 kg 30,000 360,000
22 Pintu Aluminium 48.00 12.00 12.00 bh 300,000 3,600,000
23 Floor Drain 48.00 30.00 30.00 bh 30,000 900,000
24 Media Filter 48.00 60.00 60.00 unit 432,000 25,920,000
25 Manhole Dia. 30 cm 96.00 12.00 12.00 bh 80,000 960,000
26 Kloset Jongkok 48.00 30.00 30.00 bh 180,000 5,400,000
27 Grastrap 48.00 12.00 12.00 bh 225,000 2,700,000
28 Kran Air 48.00 2.00 2.00 bh 30,000 60,000
29 Sealtape 2.00 12.00 12.00 bh 8,000 96,000
30 Tee PVC AW Ø 1" 48.00 36.00 36.00 bh 6,000 216,000
31 Elbow PVC AW Ø 2" 144.00 12.00 12.00 bh 9,000 108,000
32 Tee PVC AW Ø 2" 48.00 12.00 12.00 bh 12,000 144,000
33 Tee PVC AW Ø 3" 48.00 24.00 24.00 bh 15,000 360,000
34 Pipa PVC AW Ø 1/2" 96.00 96.00 96.00 m 7,000 672,000
35 Pipa PVC AW Ø 2" 385.00 96.00 96.00 m 26,000 2,496,000
36 Pipa PVC AW Ø 3" 384.00 38.00 38.00 m 41,000 1,558,000
37 Tripleks 9 mm 42.00 72.00 72.00 lbr 95,000 6,840,000
38 Ijuk 290.00 24.00 24.00 kg 10,000 240,000
162,103,800.00
B TENAGA KERJA
1 Tukang 426.00 73.00 73.00 HOK 85,000.00 6,205,000
2 Pekerja 1,005.00 200.00 200.00 HOK 70,000.00 14,000,000
20,205,000.00
C BIAYA OPERASIONAL PEKERJAAN (BOP)
I ALAT TULIS KANTOR (ATK) TERMASUK MATERAI :
1 Alat Tulis Kantor (ATK) 1.00 1.00 1.00 Ls 300,000.00 300,000.00
2 Materai 75.00 75.00 40.00 Lembar 11,000.00 440,000.00
IV KAMPANYE PHBS
1 Transport Sanitarian 3 kali untuk 2 orang 6.00 2.00 2.00 Org/Kali 50,000.00 100,000.00
2 Konsumsi Peserta 60.00 20.00 20.00 Org/Kali 14,000.00 280,000.00
3 Media PHBS (3 kali) 3.00 1.00 1.00 ls 300,000.00 300,000.00
HARGA
NO MINGGU (Periode) URAIAN
SATUAN (Rp.)
JUMLAH KESELURUHAN
CANA HOK
6 0 -
6 0 - -
3 5 15 1,275,000.00
9 5 45 3,150,000.00 4,425,000.00
4 6 24 2,040,000.00
12 6 72 5,040,000.00 7,080,000.00 Total HOK
4 6 24 2,040,000.00 tukang 75
12 6 72 5,040,000.00 7,080,000.00 pekerja 225
4 3 12 1,020,000.00
12 3 36 2,520,000.00 3,540,000.00 Jumlah 300
4 2 8 680,000.00
12 2 24 1,680,000.00 2,360,000.00 jumlah hari
6 6 36 3,060,000.00
18 6 108 7,560,000.00 10,620,000.00 jumlah tenaga kerja per hari
6 6 36 3,060,000.00
18 6 108 7,560,000.00 10,620,000.00
6 6 36 3,060,000.00
18 6 108 7,560,000.00 10,620,000.00
6 6 36 3,060,000.00
18 6 108 7,560,000.00 10,620,000.00
6 6 36 3,060,000.00
18 6 108 7,560,000.00 10,620,000.00
6 6 36 3,060,000.00
18 6 108 7,560,000.00 10,620,000.00
6 6 36 3,060,000.00
18 6 108 7,560,000.00 10,620,000.00
1 0 -
1 0 - -
CEK 98,825,000.00
x 85,000.00 = 6,375,000.00
x 70,000.00 = 15,750,000.00
22,125,000.00
= 20 hari kerja
Volume
NO URAIAN PEKERJAAN
Kebutuhan RPD 1
A BAHAN MATERIAL
1 Pasir 116.00 21.00
2 Batu Kali 53.00 14.00
3 Batu bata 35,895.00 6,000.00
4 Split/Kerikil 2/3 cm 52.00 14.00
5 Usuk Kayu 5/7 5.00 2.50
6 Paku 48.00 8.50
7 Buis Beton Dia. 80 cm 145.00 36.00
8 Semen Portland (PC) 842.00 -
9 Besi Dia. 10 351.00 -
10 Besi Dia. 6 232.00 -
11 Bendrat 82.00 -
12 Papan Begisting 5.00 2.50
13 Roster 288.00 24.00
14 Baja Ringan C.75.75 861.00 120.00
15 Dinabolt 269.00 40.00
16 Galvalum 0,25 mm 358.00 50.00
17 Baut Roofing 2,688.00 400.00
18 Semen Warna 54.00 13.00
19 Keramik 113.00 28.00
20 Cat dasar 362.00 65.00
21 Pintu Aluminium 48.00 12.00
22 Floor Drain 48.00 12.00
23 Media Filter 48.00 30.00
24 Manhole Dia. 30 cm 96.00 60.00
25 Kloset Jongkok 48.00 12.00
26 Grastrap 48.00 30.00
27 Kran Air 48.00 12.00
28 Sealtape 2.00 2.00
29 Tee PVC AW Ø 1" 48.00 12.00
30 Elbow PVC AW Ø 2" 144.00 36.00
31 Tee PVC AW Ø 2" 48.00 12.00
32 Tee PVC AW Ø 3" 48.00 12.00
33 Pipa PVC AW Ø 1/2" 96.00 24.00
34 Pipa PVC AW Ø 2" 385.00 96.00
35 Pipa PVC AW Ø 3" 384.00 96.00
36 Tripleks 9 mm 42.00 38.00
37 Ijuk 290.00 72.00
38 Pipa GI 1" 96.00 24.00
B TENAGA KERJA
1 Tukang 426.00 73.00
2 Pekerja 1,005.00 200.00
IV KAMPANYE PHBS
1 Transport Sanitarian 3 kali untuk 2 orang 6.00 2.00
2 Konsumsi Peserta 60.00 20.00
3 Media PHBS (3 kali) 3.00 1.00
RPD 2 RPD 3
300,000.00 - - - -
825,000.00 - - - -
- - -
- - -
- - 5.00 1,000,000.00
- - -
- - -
- - -
420,000.00 - -
120,000.00 - -
1,320,000.00 - -
300,000.00 - -
150,000.00 - -
- - -
150,000.00 - 2.00 60,000.00
45,000.00 - 7.00 105,000.00
- - -
- - -
100,000.00 - -
280,000.00 - -
300,000.00 - 1.00 300,000.00
- - -
- - -
150,000.00 - -
- - -
- - -
100,000.00 - -
- - -
- - -
1,200,000.00 12.00 1,200,000.00 29.00 2,900,000.00
- - -
- - -
150,000.00 3.00 150,000.00 3.00 150,000.00
5,910,000.00 1,350,000.00 4,515,000.00
346,181,000.00 636,250,500.00
Jumlah Jumlah Komulatif
RPD 5
Komulatif (Rp.)
volume biaya
257,250,000.00