S6 - Request For Stripping Formworks, Scaffolds and Supports

The documents are work inspection requests from SOGECOA Philippines International Construction and Trading Company regarding construction projects at the Banhao Tower site. The requests include inspections of the installation of bare copper wire for grounding, reinstallation of ground rods and exothermic welding connections, and inspection of rebars. The documents include details of the requests such as submittal descriptions, dates, locations within the building, and sign off sections for project management teams.

Uploaded by

ADEN LIU
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
70 views

S6 - Request For Stripping Formworks, Scaffolds and Supports

The documents are work inspection requests from SOGECOA Philippines International Construction and Trading Company regarding construction projects at the Banhao Tower site. The requests include inspections of the installation of bare copper wire for grounding, reinstallation of ground rods and exothermic welding connections, and inspection of rebars. The documents include details of the requests such as submittal descriptions, dates, locations within the building, and sign off sections for project management teams.

Uploaded by

ADEN LIU
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 129

SOGECOA Philippines International Construction

ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST

Installation of Bare Copper Wire(BCW) for Grounding System @


SUBMITTAL DESCRIPTION SUBMITTAL NO.-REV. #
Segment 1

SUBMITTED DATE & TIME Saturday, November 18, 2017 1:00:00 AM

REQUESTED DATE & TIME Saturday, November 18, 2017 10:00:00 AM SOG-BH-ELEC-WIR-002

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS SHOWN IN DRAWING
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER


ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA
WORK INSPECTION REQUEST
Re-Installation of Ground Rods and Exothermic Welding
SUBMITTAL DESCRIPTION SUBMITTAL NO.-REV. #
Connection for Grounding System @ Segment 1
SUBMITTED DATE & TIME Wednesday, January 24, 2018 1:00:00 PM
REQUESTED DATE & TIME Wednesday, January 24, 2018 10:00:00 AM SOG-BH-ELEC-WIR-003
ACTUAL DATE & TIME

ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________


DEPARTMENT

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS SHOWN IN DRAWING
SEGMENT 1
CONTRACTOR'S REPRESENTATIVE
MR. LIU GEN BAO
PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC


DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY
PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)


NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disappro E Noted
Received by SOGECOA: Received by ALC :
Signature : Signature :

Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST

SUBMITTAL DESCRIPTION SUBMITTAL NO.-REV. #

SUBMITTED DATE & TIME

REQUESTED DATE & TIME

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS____________

DRAWING NO.

FLOOR LEVEL
LOCATION AS SHOWN IN DRAWING
SEGMENT

CONTRACTOR'S REPRESENTATIVE

Mr. Sun Zhi Gui


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTIO
INSPECTION OF REBARS(EL.)@BP FR
SUBMITTAL DESCRIPTION
(1.54MIN TO 1.75MAX)

SUBMITTED DATE & TIME Friday, August 11, 2017 8:

REQUESTED DATE & TIME

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRI

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA


DEPARTMENTS SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM

PROJECT MANAGEMENT TEAM


NAME :

POSITION :

APPROVAL STATUS
A Approved B Approved with comment

Received by SOGECOA:

Signature :

Date :
SOGECOA Philippines International Construction
and Trading Company, Inc

RK INSPECTION REQUEST
ARS(EL.)@BP FROM
SUBMITTAL NO.-REV. #
O 1.75MAX)

8:00AM

SOG-BH-STR-0001-FND-0

L ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

AS SHOWN IN DRAWING

PRE-INSPECTION CHECKLIST BY ALC


SIGNATURE SIGNATURE

NAGEMENT TEAM RECOMMENDATION (ALC)

ANAGEMENT TEAM REPRESENTATIVE (ALC)


SIGNATURE :

DATE :

oved with comments C Resubmit D Disapproved E

Received by ALC :

Signature :

Date :
l Construction

-REV. #

01-FND-0

OTHERS_ ___________

RAWING

BY ALC
SIGNATURE
Noted
SOGECOA Philippines Inte
ALC - MANAGEMENT and Trading Compa

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


BORED PILE-HACKING ELEVATION
SUBMITTAL DESCRIPTION SU
BP# 45, 46 & 47

SUBMITTED DATE & TIME Friday, August 11, 2017 8:00AM

REQUESTED DATE & TIME SOG-BH


ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL S

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION

DEPARTMENTS SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)


PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
Philippines International Construction
rading Company, Inc

SUBMITTAL NO.-REV. #

SOG-BH-STR-0001-FND-0 A

CAL SURVEY OTHERS_ ___________

AS SHOWN IN DRAWING

PRE-INSPECTION CHECKLIST BY ALC

SIGNATURE

LC)
C)

D Disapproved E Noted
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTIO
BORED PILE-HACKING ELEVATION
SUBMITTAL DESCRIPTION
BP# 41,42, 43 & 44

SUBMITTED DATE & TIME Thursday, August 24, 2017 8:30

REQUESTED DATE & TIME

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICA

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA


DEPARTMENTS SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM R

PROJECT MANAGEMENT TEAM R


NAME :

POSITION :

APPROVAL STATUS
A Approved B Approved with comments

Received by SOGECOA:

Signature :

Date :
SOGECOA Philippines International Construction
and Trading Company, Inc

RK INSPECTION REQUEST
KING ELEVATION
SUBMITTAL NO.-REV. #
2, 43 & 44

8:30AM

SOG-BH-STR-0001-FND-0 B

L ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

AS SHOWN IN DRAWING

PRE-INSPECTION CHECKLIST BY ALC


SIGNATURE SIGNATURE

ANAGEMENT TEAM RECOMMENDATION (ALC)

MANAGEMENT TEAM REPRESENTATIVE (ALC)


SIGNATURE :

DATE :

oved with comments C Resubmit D Disapproved E

Received by ALC :

Signature :

Date :
l Construction

-REV. #

FND-0 B

OTHERS_ ___________

RAWING

BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTIO
TESTING OF REBAR 16MM DIA G-60
SUBMITTAL DESCRIPTION
[6.0, 10.5 & 12METER]

SUBMITTED DATE & TIME Monday, September 04, 2017 15:30

REQUESTED DATE & TIME

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICA

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA


DEPARTMENTS SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM R

PROJECT MANAGEMENT TEAM R


NAME :

POSITION :

APPROVAL STATUS
A Approved B Approved with comments

Received by SOGECOA:

Signature :

Date :
SOGECOA Philippines International Construction
and Trading Company, Inc

RK INSPECTION REQUEST
R 16MM DIA G-60
SUBMITTAL NO.-REV. #
12METER]

15:30PM

SOG-BH-STR-0001-FND-0 C

L ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

AS SHOWN IN DRAWING

PRE-INSPECTION CHECKLIST BY ALC


SIGNATURE SIGNATURE

ANAGEMENT TEAM RECOMMENDATION (ALC)

MANAGEMENT TEAM REPRESENTATIVE (ALC)


SIGNATURE :

DATE :

oved with comments C Resubmit D Disapproved E

Received by ALC :

Signature :

Date :
l Construction

-REV. #

FND-0 C

OTHERS_ ___________

RAWING

BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTIO
BORED PILE-HACKING ELEVATION
SUBMITTAL DESCRIPTION
BP# 37,38, 39 & 40

SUBMITTED DATE & TIME Friday, September 08, 2017 17:00

REQUESTED DATE & TIME

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICA

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA


DEPARTMENTS SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM R

PROJECT MANAGEMENT TEAM R


NAME :

POSITION :

APPROVAL STATUS
A Approved B Approved with comments

Received by SOGECOA:

Signature :

Date :
SOGECOA Philippines International Construction
and Trading Company, Inc

RK INSPECTION REQUEST
KING ELEVATION
SUBMITTAL NO.-REV. #
8, 39 & 40

17:00PM

SOG-BH-STR-0001-FND-0 D

L ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

AS SHOWN IN DRAWING

PRE-INSPECTION CHECKLIST BY ALC


SIGNATURE SIGNATURE

ANAGEMENT TEAM RECOMMENDATION (ALC)

MANAGEMENT TEAM REPRESENTATIVE (ALC)


SIGNATURE :

DATE :

oved with comments C Resubmit D Disapproved E

Received by ALC :

Signature :

Date :
l Construction

-REV. #

-FND-0 D

OTHERS_ ___________

RAWING

BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTIO
BORED PILE-HACKING ELEVATION
SUBMITTAL DESCRIPTION
BP# 29,30,31,32,33,34,35 & 36

SUBMITTED DATE & TIME Thursday, September 28, 2017 13:30

REQUESTED DATE & TIME

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICA

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA


DEPARTMENTS SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM R

PROJECT MANAGEMENT TEAM R


NAME :

POSITION :

APPROVAL STATUS
A Approved B Approved with comments

Received by SOGECOA:

Signature :

Date :
SOGECOA Philippines International Construction
and Trading Company, Inc

RK INSPECTION REQUEST
KING ELEVATION
SUBMITTAL NO.-REV. #
2,33,34,35 & 36

13:30PM

SOG-BH-STR-0004-FND-0

L ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

AS SHOWN IN DRAWING

PRE-INSPECTION CHECKLIST BY ALC


SIGNATURE SIGNATURE

ANAGEMENT TEAM RECOMMENDATION (ALC)

MANAGEMENT TEAM REPRESENTATIVE (ALC)


SIGNATURE :

DATE :

oved with comments C Resubmit D Disapproved E

Received by ALC :

Signature :

Date :
l Construction

-REV. #

4-FND-0

OTHERS_ ___________

RAWING

BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTIO
TESTING OF REBAR 28MM DIA G-75
SUBMITTAL DESCRIPTION & 16MM DIA G-60
[SEE ATTACHED MILL CERTIFICATE]
SUBMITTED DATE & TIME Saturday, September 30, 2017 9:00

REQUESTED DATE & TIME

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICA

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA


DEPARTMENTS SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM R

PROJECT MANAGEMENT TEAM R


NAME :

POSITION :

APPROVAL STATUS
A Approved B Approved with comments

Received by SOGECOA:

Signature :

Date :
SOGECOA Philippines International Construction
and Trading Company, Inc

RK INSPECTION REQUEST
AR 28MM DIA G-75
DIA G-60 SUBMITTAL NO.-REV. #
ILL CERTIFICATE]
9:00AM

SOG-BH-STR-0005-FND-0

L ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

AS SHOWN IN DRAWING

PRE-INSPECTION CHECKLIST BY ALC


SIGNATURE SIGNATURE

ANAGEMENT TEAM RECOMMENDATION (ALC)

MANAGEMENT TEAM REPRESENTATIVE (ALC)


SIGNATURE :

DATE :

oved with comments C Resubmit D Disapproved E

Received by ALC :

Signature :

Date :
l Construction

-REV. #

05-FND-0

OTHERS_ ___________

RAWING

BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTIO
HANDLING OVER OF SEGMENT 1
SUBMITTAL DESCRIPTION
PRIOR FOR LEAN CONCRETE PILE CAP

SUBMITTED DATE & TIME Tuesday, October 03, 2017 9:00

REQUESTED DATE & TIME

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICA

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA


DEPARTMENTS SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM R

PROJECT MANAGEMENT TEAM R


NAME :

POSITION :

APPROVAL STATUS
A Approved B Approved with comments

Received by SOGECOA:

Signature :

Date :
SOGECOA Philippines International Construction
and Trading Company, Inc

RK INSPECTION REQUEST
R OF SEGMENT 1
SUBMITTAL NO.-REV. #
ONCRETE PILE CAP

9:00AM

SOG-BH-STR-0005-FND-0 A

L ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

AS SHOWN IN DRAWING

PRE-INSPECTION CHECKLIST BY ALC


SIGNATURE SIGNATURE

ANAGEMENT TEAM RECOMMENDATION (ALC)

MANAGEMENT TEAM REPRESENTATIVE (ALC)


SIGNATURE :

DATE :

oved with comments C Resubmit D Disapproved E

Received by ALC :

Signature :

Date :
l Construction

-REV. #

-FND-0 A

OTHERS_ ___________

RAWING

BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTIO
REQUEST FOR INSPECTION OF SOIL POISONING AP
SUBMITTAL DESCRIPTION
MAT FOUNDATION PRIOR FOR LEAN CONCRETE @

SUBMITTED DATE & TIME Saturday, October 07, 2017 11:00

REQUESTED DATE & TIME

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICA

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA


DEPARTMENTS SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM R

PROJECT MANAGEMENT TEAM R


NAME :

POSITION :

APPROVAL STATUS
A Approved B Approved with comments

Received by SOGECOA:

Signature :

Date :
SOGECOA Philippines International Construction
and Trading Company, Inc

RK INSPECTION REQUEST
OIL POISONING APPLICATION AT
SUBMITTAL NO.-REV. #
LEAN CONCRETE @SEGMENT 1

11:00AM

SOG-BH-STR-0005-FND-0 B

L ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

AS SHOWN IN DRAWING

PRE-INSPECTION CHECKLIST BY ALC


SIGNATURE SIGNATURE

ANAGEMENT TEAM RECOMMENDATION (ALC)

MANAGEMENT TEAM REPRESENTATIVE (ALC)


SIGNATURE :

DATE :

oved with comments C Resubmit D Disapproved E

Received by ALC :

Signature :

Date :
l Construction

-REV. #

-FND-0 B

OTHERS_ ___________

RAWING

BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTIO
REQUEST INSPECTION FOR SURVEY LAYOUT/ GR
SUBMITTAL DESCRIPTION
SEGMENT 1 PRIOR FOR INSTALLATION OF REBARS

SUBMITTED DATE & TIME Wednesday, October 11, 2017 11:00

REQUESTED DATE & TIME

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICA

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA


DEPARTMENTS SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM R

PROJECT MANAGEMENT TEAM R


NAME :

POSITION :

APPROVAL STATUS
A Approved B Approved with comments

Received by SOGECOA:

Signature :

Date :
SOGECOA Philippines International Construction
and Trading Company, Inc

RK INSPECTION REQUEST
RVEY LAYOUT/ GRIDLINES AT
SUBMITTAL NO.-REV. #
ATION OF REBARS AT PILE CAP

11:00AM

SOG-BH-STR-0006-FND-0

L ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

AS SHOWN IN DRAWING

PRE-INSPECTION CHECKLIST BY ALC


SIGNATURE SIGNATURE

ANAGEMENT TEAM RECOMMENDATION (ALC)

MANAGEMENT TEAM REPRESENTATIVE (ALC)


SIGNATURE :

DATE :

oved with comments C Resubmit D Disapproved E

Received by ALC :

Signature :

Date :
l Construction

-REV. #

06-FND-0

OTHERS_ ___________

RAWING

BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTIO
REQUEST INSPECTION FOR COLUMN LAYOUT AT
SUBMITTAL DESCRIPTION
PRIOR FOR INSTALLATION OF REBARS AT PI

SUBMITTED DATE & TIME Thursday, October 12, 2017 11:00

REQUESTED DATE & TIME

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICA

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA


DEPARTMENTS SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM R

PROJECT MANAGEMENT TEAM R


NAME :

POSITION :

APPROVAL STATUS
A Approved B Approved with comments

Received by SOGECOA:

Signature :

Date :
SOGECOA Philippines International Construction
and Trading Company, Inc

RK INSPECTION REQUEST
LUMN LAYOUT AT SEGMENT 1
SUBMITTAL NO.-REV. #
OF REBARS AT PILE CAP

11:00AM

SOG-BH-STR-0007-FND-0

L ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

AS SHOWN IN DRAWING

PRE-INSPECTION CHECKLIST BY ALC


SIGNATURE SIGNATURE

ANAGEMENT TEAM RECOMMENDATION (ALC)

MANAGEMENT TEAM REPRESENTATIVE (ALC)


SIGNATURE :

DATE :

oved with comments C Resubmit D Disapproved E

Received by ALC :

Signature :

Date :
l Construction

-REV. #

07-FND-0

OTHERS_ ___________

RAWING

BY ALC
SIGNATURE
Noted
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST

SUBMITTAL DESCRIPTION REQUEST FOR INSPECTION FOR BOTTOM BARS AND 6 COLUMNS SUBMITTAL NO.-REV. #

SUBMITTED DATE & TIME Thursday, October 19, 2017 1:00PM

REQUESTED DATE & TIME Thursday, October 19, 2017 SOG-BH-STR-0008-FND-0008

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS SHOWN IN DRAWING
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION FOR SURVEY AND LAYOUT OF STP
SUBMITTAL DESCRIPTION SUBMITTAL NO.-REV. #
PRIOR FOR REBAR INSTALLATION

SUBMITTED DATE & TIME Monday, October 23, 2017 9:00am

REQUESTED DATE & TIME Monday, October 23, 2017 SOG-BH-STR-0008-FND-0009

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS SHOWN IN DRAWING
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION OF REBAR INSTALLATION
SUBMITTAL DESCRIPTION SUBMITTAL NO.-REV. #
INCLUDING PVC WATER STOP@STP IN SEGMENT 1

SUBMITTED DATE & TIME Wednesday, October 25, 2017 10:00am

REQUESTED DATE & TIME Wednesday, October 25, 2017 SOG-BH-STR-0010

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS SHOWN IN DRAWING
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION OF REBAR INSTALLATION
SUBMITTAL DESCRIPTION SUBMITTAL NO.-REV. #
(TOP BARS) @FOUNDATION SEGMENT 1

SUBMITTED DATE & TIME Wednesday, October 25, 2017 10:00am

REQUESTED DATE & TIME Wednesday, October 25, 2017 SOG-BH-STR-0011

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS SHOWN IN DRAWING
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION OF FORMWORKS AT MAT
SUBMITTAL DESCRIPTION SUBMITTAL NO.-REV. #
FOUNDATION INCLUDING PVC WATER STOP IN SEGMENT 1

SUBMITTED DATE & TIME Wednesday, October 25, 2017 10:00am

REQUESTED DATE & TIME Wednesday, October 25, 2017 SOG-BH-STR-0012

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS SHOWN IN DRAWING
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION FOR
GRIDLINE-5 COLUMN C2, C4 & C2A
SUBMITTAL DESCRIPTION SUBMITTAL NO.-REV. #
GRIDLINE-6 COLUMN C1(2) & C2
- Installation of Rebars prior for Formworks @ SEGMENT 1

SUBMITTED DATE & TIME Monday, November 06, 2017 13:00pm

REQUESTED DATE & TIME Monday, November 06, 2017 14:00:00 PM SOG-BH-STR-COL-0013

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS SHOWN IN DRAWING
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST

Request for Rebars inspection of 16mm and 20mm prior for


SUBMITTAL DESCRIPTION SUBMITTAL NO.-REV. #
Laboratory testing

SUBMITTED DATE & TIME Wednesday, November 08, 2017 8:00:00 AM

REQUESTED DATE & TIME Wednesday, November 08, 2017 10:00:00 AM SOG-BH-STR-0014

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS SHOWN IN DRAWING
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST

Request for Inspection of Rebars ( Horizontal and Vertical Bars ) of


SUBMITTAL DESCRIPTION SUBMITTAL NO.-REV. #
STP in Segment 1 prior for Formworks Activity

SUBMITTED DATE & TIME

REQUESTED DATE & TIME SOG-BH-STR-0015

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS SHOWN IN DRAWING
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


Request for Inspection of Formworks and Survey Points for
SUBMITTAL DESCRIPTION Columns ( 4 numbers ) along Gridlines A and Gridline 6 = C1(2) & C2 SUBMITTAL NO.-REV. #
and along Gridline 5 and Gridline A = C2

SUBMITTED DATE & TIME

REQUESTED DATE & TIME SOG-BH-STR-0016

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS SHOWN IN DRAWING
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


Request for Inspection of Formworks and Survey Points for
SUBMITTAL DESCRIPTION Columns ( 2 numbers ) along Gridlines B and Gridline 5= C4 and SUBMITTAL NO.-REV. #
along Gridline 5 and Gridline D = C2A and STP At Segment 1

SUBMITTED DATE & TIME

REQUESTED DATE & TIME SOG-BH-STR-0017

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS SHOWN IN DRAWING
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST

Installation of Bare Copper Wire(BCW) for Grounding System @


SUBMITTAL DESCRIPTION SUBMITTAL NO.-REV. #
Segment 1

SUBMITTED DATE & TIME Saturday, November 18, 2017 1:00:00 AM

REQUESTED DATE & TIME Saturday, November 18, 2017 10:00:00 AM SOG-BH-ELEC-WIR-002

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL FOUNDATION


LOCATION AS SHOWN IN DRAWING
SEGMENT 1

CONTRACTOR'S REPRESENTATIVE

MR. LIU GEN BAO


PM- SOGECOA

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ELECTRICAL

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION OF 4TH FLOOR POWER LAY-OUT, 3RD FLR.
SUBMITTAL DESCRIPTION LIGHTING AND 3RD FLR. AUXILLARY LAY-OUT @ 4TH FLOOR UPPER LEVEL SUBMITTAL NO.-REV. #

SUBMITTED DATE & TIME MONDAY, SEPTEMBER 10,2018 3:00:00 PM

REQUESTED DATE & TIME MONDAY, SEPTEMBER 10,2018 4:30:00 PM WIR-ELEC-0021

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

1 3 3
DRAWING NO.
E-12 E-15 E-19

FLOOR LEVEL FOURTH


LOCATION AS SHOWN IN DRAWING
SEGMENT 1&2

CONTRACTOR'S REPRESENTATIVE

Mr. Liu Gen Bao


PM- JQCIC

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ENGR.MARK JOEL I. RAZOS-JQICI


ELECTRICAL
ENGR. EDWARD CRUZ- VYC

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION OF LOWER 5TH FLOOR POWER LAY-OUT, LOWER
SUBMITTAL DESCRIPTION 4TH FLR. LIGHTING AND LOWER 4TH FLR. AUXILLARY LAY-OUT @ 5TH FLOOR SUBMITTAL NO.-REV. #
LOWER LEVEL

SUBMITTED DATE & TIME WEDNESDAY, SEPTEMBER 19,2018 3:00:00 PM

REQUESTED DATE & TIME THURSDAY, SEPTEMBER 20,2018 4:30:00 PM WIR-ELEC-0022

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

1 3 3
DRAWING NO.
E-12 E-16 E-20

FLOOR LEVEL FIFTH


LOCATION AS SHOWN IN DRAWING
SEGMENT 3

CONTRACTOR'S REPRESENTATIVE

Mr. Liu Gen Bao


PM- JQCIC

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ENGR.MARK JOEL I. RAZOS-JQICI


ELECTRICAL
ENGR. EDWARD CRUZ- VYC

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION OF UPPER 5TH FLOOR POWER LAY-OUT, UPPER
SUBMITTAL DESCRIPTION 4TH FLR. LIGHTING AND UPPER 4TH FLR. AUXILLARY LAY-OUT @ 5TH FLOOR SUBMITTAL NO.-REV. #
UPPER LEVEL

SUBMITTED DATE & TIME MONDAY, OCTOBER 08,2018 11:00:00 AM

REQUESTED DATE & TIME TUESDAY, OCTOBER 09,2018 3:00:00 PM WIR-ELEC-0023

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

1 3 3
DRAWING NO.
E-12 E-16 E-20

FLOOR LEVEL FIFTH


LOCATION AS SHOWN IN DRAWING
SEGMENT 1&2

CONTRACTOR'S REPRESENTATIVE

Mr. Liu Gen Bao


PM- JQICI

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ENGR.MARK JOEL I. RAZOS-JQICI


ELECTRICAL
ENGR. EDWARD CRUZ- VYC

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION OF LOWER 6TH FLOOR POWER LAY-OUT, LOWER
SUBMITTAL DESCRIPTION 5TH FLR. LIGHTING AND LOWER 5TH FLR. AUXILLARY LAY-OUT @ 6TH FLOOR SUBMITTAL NO.-REV. #
LOWER LEVEL

SUBMITTED DATE & TIME MONDAY, OCTOBER 15,2018 3:00:00 PM

REQUESTED DATE & TIME THURSDAY, OCTOBER 18 ,2018 10:00:00 AM WIR-ELEC-0024

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

1 3 3
DRAWING NO.
E-12 E-16 E-20

FLOOR LEVEL FIFTH


LOCATION AS SHOWN IN DRAWING
SEGMENT 3

CONTRACTOR'S REPRESENTATIVE

Mr. Liu Gen Bao


PM- JQICI

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ENGR.MARK JOEL I. RAZOS-JQICI


ELECTRICAL
ENGR. EDWARD CRUZ- VYC

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION OF RAMP 7 LIGHTING LAY OUT AND AUXILLARY
SUBMITTAL DESCRIPTION LAY-OUT SUBMITTAL NO.-REV. #

SUBMITTED DATE & TIME SATURDAY, OCTOBER 27,2018 3:00:00 PM

REQUESTED DATE & TIME MONDAY, OCTOBER 29 ,2018 3:00:00 PM WIR-ELEC-0026

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

3 3
DRAWING NO.
E-15 E-19

FLOOR LEVEL FIFTH


LOCATION AS SHOWN IN DRAWING
SEGMENT 3

CONTRACTOR'S REPRESENTATIVE

Mr. Liu Gen Bao


PM- JQICI

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ENGR.MARK JOEL I. RAZOS-JQICI


ELECTRICAL
ENGR. EDWARD CRUZ- VYC

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION OF LOWER 7TH FLOOR POWER LAY-OUT, LOWER
SUBMITTAL DESCRIPTION 6TH FLR. LIGHTING AND LOWER 6TH FLR. AUXILLARY LAY-OUT @ 7TH FLOOR SUBMITTAL NO.-REV. #
LOWER LEVEL

SUBMITTED DATE & TIME SATURDAY, NOVEMBER 03,2018 3:00:00 PM

REQUESTED DATE & TIME MONDAY, NOVEMBER 06 ,2018 10:00:00 AM WIR-ELEC-0027

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

2 1 1
DRAWING NO.
E-12 E-16 E- 20

FLOOR LEVEL FIFTH


LOCATION AS SHOWN IN DRAWING
SEGMENT 3

CONTRACTOR'S REPRESENTATIVE

Mr. Liu Gen Bao


PM- JQICI

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ENGR.MARK JOEL I. RAZOS-JQICI


ELECTRICAL
ENGR. EDWARD CRUZ- VYC

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION OF LOWER 7TH FLOOR FOR PLUMBING PIPE
SUBMITTAL DESCRIPTION SLEEVE AND FIRE PROTECTION PIPE SLEEVE @ 7TH FLOOR SUBMITTAL NO.-REV. #

SUBMITTED DATE & TIME TUESDAY, NOVEMBER 06,2018 10:00:00 AM

REQUESTED DATE & TIME TUESDAY, NOVEMBER 06,2018 3:00:00 PM JQ-WIR-MPFS-011

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL PLUMBING SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL FIFTH


LOCATION AS SHOWN IN DRAWING
SEGMENT 3

CONTRACTOR'S REPRESENTATIVE

Mr. Liu Gen Bao


PM- JQICI

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ENGR.MARK JOEL I. RAZOS-JQICI


ELECTRICAL
ENGR. EDWARD CRUZ- VYC

FIRE PROTECTION ENGR. NOEL CALDOZA

MECHANICAL ENGR. NOEL CALDOZA

PLUMBING ENGR. NOEL CALDOZA

SANITARY ENGR. NOEL CALDOZA

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST INSPECTION @ 5TH FLOOR UPPER AND SIXTH FLOOR LOWER FOR
SUBMITTAL DESCRIPTION LIGHTING LAY OUT,POWER LAY OUT AND AUXILLIARY LAY OUT. SUBMITTAL NO.-REV. #

SUBMITTED DATE & TIME SATURDAY, NOVEMBER 10,2018 11:00:00 AM

REQUESTED DATE & TIME MONDAY, NOVEMBER 12 ,2018 10:00:00 AM WIR-ELEC-0029

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MECHANICAL SURVEY OTHERS_ ___________

2 1 1
DRAWING NO.
E-12 E-16 E- 20

FLOOR LEVEL FIFTH


LOCATION AS SHOWN IN DRAWING
SEGMENT

CONTRACTOR'S REPRESENTATIVE

Mr. Liu Gen Bao


PM- JQICI

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ENGR.MARK JOEL I. RAZOS-JQICI


ELECTRICAL
ENGR. EDWARD CRUZ- VYC

FIRE PROTECTION

MECHANICAL

PLUMBING

SANITARY

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION OF LOWER 7TH FLOOR FOR PLUMBING PIPE
SUBMITTAL DESCRIPTION SLEEVE AND FIRE PROTECTION PIPE SLEEVE SUBMITTAL NO.-REV. #

SUBMITTED DATE & TIME TUESDAY, NOVEMBER 05,2018 2:00:00 PM

REQUESTED DATE & TIME WEDNESDAY, NOVEMBER 06,2018 10:00:00 AM JQ-WIR-MPFS-012

ACTUAL DATE & TIME

DEPARTMENT ARCHITECTURAL STRUCTURAL ELECTRICAL MPFS SURVEY OTHERS_ ___________

DRAWING NO.

FLOOR LEVEL 5&6


LOCATION AS SHOWN IN DRAWING
SEGMENT

CONTRACTOR'S REPRESENTATIVE

Mr. Liu Gen Bao


PM- JQICI

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ENGR.MARK JOEL I. RAZOS-JQICI


ELECTRICAL
ENGR. EDWARD CRUZ- VYC

FIRE PROTECTION AFUENTES/ MJRAZOS

MECHANICAL AFUENTES/ MJRAZOS

PLUMBING AFUENTES/ MJRAZOS

SANITARY AFUENTES/ MJRAZOS

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT

PROJECT :BANHAO TOWER

ADDRESS :SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA

WORK INSPECTION REQUEST


REQUEST FOR INSPECTION OF LOWER 9TH FLOOR FOR PLUMBING PIPE
SUBMITTAL DESCRIPTION SLEEVE,FIRE PROTECTION PIPE SLEEVE AND BLOCKOUTS. SUBMITTAL NO.-REV. #

SUBMITTED DATE & TIME WEDNESDAY, DECEMBER 5,2018 3:00:00 PM

REQUESTED DATE & TIME THURSDAY, DECEMBER 6,2018 8:30:00 AM JQ-WIR-MPFS-013

ACTUAL DATE & TIME

DEPARTMENT

DRAWING NO.

FLOOR LEVEL LOWER 9TH


LOCATION AS SHOWN IN DRAWING
SEGMENT

CONTRACTOR'S REPRESENTATIVE

Mr. Liu Gen Bao


PM- JQICI

PRE-INSPECTION CHECKLIST BY SOGECOA PRE-INSPECTION CHECKLIST BY ALC

DEPARTMENTS SIGNATURE SIGNATURE

SURVEYOR

ARCHITECTURAL

STRUCTURAL

ENGR.MARK JOEL I. RAZOS-JQICI


ELECTRICAL
ENGR. EDWARD CRUZ- VYC

FIRE PROTECTION N.CADALZO/ MJRAZOS

MECHANICAL N.CADALZO/ MJRAZOS

PLUMBING N.CADALZO/ MJRAZOS

SANITARY N.CADALZO/ MJRAZOS

SAFETY

PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)

PROJECT MANAGEMENT TEAM REPRESENTATIVE (ALC)

NAME : SIGNATURE :

POSITION : DATE :

APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted

Received by SOGECOA: Received by ALC :

Signature : Signature :

Date : Date :
JQ INTERNATIONAL CONSTRUCTION INC.

WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS

ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : Aug. 29, 2019

Work Item : Stripping of forms at 3rd Floor RC wall Requested by : Engr. Ron Jason

Contractor : JQ INTERNATIONAL CONSTRUCTION INC.

Date of Work Aug. 29, 2019

Contractor's Representative Project Management Inspector/s


Item # Checklist
Name/Initial Signature Name/Initial Signature

1 Line & Grade

2 Forms

3 Rebars, Dowel

4 Electrical

5 Sanitary

6 Plumbing

7 Structural

8 Mechanical

9 Architectural

10 Waterproofing

11 Equipment, Tools

12 QA/QC

13 Materials Approval

Notes:

Noted by : Mr. Liu Genbao Aug. 29, 2019


Project Manager-Chinese Date

Received by :
ALC Management Date

Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to
review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of
its obligations under contract.
JQ INTERNATIONAL CONSTRUCTION INC.

WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS

ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 10/7/2019

Work Item : Stripping of forms at 26th Floor Slabs and Beams @ GL A-E/1-6 Requested by : Engr. Ron Jason

Contractor : JQ INTERNATIONAL CONSTRUCTION INC.

Date of Work 10/7/2019

Contractor's Representative Project Management Inspector/s


Item # Checklist
Name/Initial Signature Name/Initial Signature

1 Line & Grade

2 Forms

3 Rebars, Dowel

4 Electrical

5 Sanitary

6 Plumbing

7 Structural

8 Mechanical

9 Architectural

10 Waterproofing

11 Equipment, Tools

12 QA/QC

13 Materials Approval

Notes:

Noted by : Mr. Liu Genbao 7-Oct-19


Project Manager-Chinese Date

Received by :
ALC Management Date

Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to
review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of
its obligations under contract.
JQ INTERNATIONAL CONSTRUCTION INC.

WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS

ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 10/18/2019

Work Item : Stripping of forms at 27th Floor Slabs and Beams @ GL A-E/1-6 Requested by : Engr. Ron Jason

Contractor : JQ INTERNATIONAL CONSTRUCTION INC.

Date of Work 10/18/2019

Contractor's Representative Project Management Inspector/s


Item # Checklist
Name/Initial Signature Name/Initial Signature

1 Line & Grade

2 Forms

3 Rebars, Dowel

4 Electrical

5 Sanitary

6 Plumbing

7 Structural

8 Mechanical

9 Architectural

10 Waterproofing

11 Equipment, Tools

12 QA/QC

13 Materials Approval

Notes:

Noted by : Mr. Liu Genbao 18-Oct-19


Project Manager-Chinese Date

Received by :
ALC Management Date

Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to
review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of
its obligations under contract.
JQ INTERNATIONAL CONSTRUCTION INC.

WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS

ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 11/21/2019

Work Item : Stripping of forms at 29th Floor Slabs and Beams @ GL A-E/1-6 Requested by : Engr. Ron

Contractor : JQ INTERNATIONAL CONSTRUCTION INC.

Date of Work 11/21/2019

Contractor's Representative Project Management Inspector/s


Item # Checklist
Name/Initial Signature Name/Initial Signature

1 Line & Grade

2 Forms

3 Rebars, Dowel

4 Electrical

5 Sanitary

6 Plumbing

7 Structural

8 Mechanical

9 Architectural

10 Waterproofing

11 Equipment, Tools

12 QA/QC

13 Materials Approval

Notes:

Noted by : Mr. Liu Genbao 21-Nov-19


Project Manager-Chinese Date

Received by :
ALC Management Date

Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to
review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of
its obligations under contract.
JQ INTERNATIONAL CONSTRUCTION INC.

WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS

ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 12/5/2019

Work Item : Stripping of forms at 30th Floor Slabs and Beams @ GL A-E/1-6 Requested by : Engr. Ron

Contractor : JQ INTERNATIONAL CONSTRUCTION INC.

Date of Work 12/5/2019

Contractor's Representative Project Management Inspector/s


Item # Checklist
Name/Initial Signature Name/Initial Signature

1 Line & Grade

2 Forms

3 Rebars, Dowel

4 Electrical

5 Sanitary

6 Plumbing

7 Structural

8 Mechanical

9 Architectural

10 Waterproofing

11 Equipment, Tools

12 QA/QC

13 Materials Approval

Notes:

Noted by : Mr. Liu Genbao 5-Dec-19


Project Manager-Chinese Date

Received by :
ALC Management Date

Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to
review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of
its obligations under contract.
JQ INTERNATIONAL CONSTRUCTION INC.

WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS

ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 9/19/2020

Work Item : Stripping of forms at 39TH (U) - 40TH (L)Floor Slabs and Beams @ GL A-E/3-6' Requested by : Engr. Ron

Contractor : JQ INTERNATIONAL CONSTRUCTION INC.

Date of Work 9/19/2020

Contractor's Representative Project Management Inspector/s


Item # Checklist
Name/Initial Signature Name/Initial Signature

1 Line & Grade

2 Forms

3 Rebars, Dowel

4 Electrical

5 Sanitary

6 Plumbing

7 Structural

8 Mechanical

9 Architectural

10 Waterproofing

11 Equipment, Tools

12 QA/QC

13 Materials Approval

Notes:

Noted by : Mr. Liu Genbao 19-Sep-20


Project Manager-Chinese Date

Received by :
ALC Management Date

Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to
review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of its
obligations under contract.
JQ INTERNATIONAL CONSTRUCTION INC.

WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS

ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 10/17/2020

Work Item : Stripping of forms at 40TH (U) - Roof Deck Floor Slabs and Beams @ GL A-E/1-6' Requested by : Engr. Ron

Contractor : JQ INTERNATIONAL CONSTRUCTION INC.

Date of Work 10/17/2020

Contractor's Representative Project Management Inspector/s


Item # Checklist
Name/Initial Signature Name/Initial Signature

1 Line & Grade

2 Forms

3 Rebars, Dowel

4 Electrical

5 Sanitary

6 Plumbing

7 Structural

8 Mechanical

9 Architectural

10 Waterproofing

11 Equipment, Tools

12 QA/QC

13 Materials Approval

Notes:

Noted by : Mr. Liu Genbao 17-Oct-20


Project Manager-Chinese Date

Received by :
ALC Management Date

Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to review
for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of its obligations
under contract.
JQ INTERNATIONAL CONSTRUCTION INC.

WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS

ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 11/5/2020

Work Item : Stripping of forms at 40TH (U) - Roof Deck Floor Slabs and Beams @ GL B-D/4-6' Requested by : Engr. Ron

Contractor : JQ INTERNATIONAL CONSTRUCTION INC.

Date of Work 11/5/2020

Contractor's Representative Project Management Inspector/s


Item # Checklist
Name/Initial Signature Name/Initial Signature

1 Line & Grade

2 Forms

3 Rebars, Dowel

4 Electrical

5 Sanitary

6 Plumbing

7 Structural

8 Mechanical

9 Architectural

10 Waterproofing

11 Equipment, Tools

12 QA/QC

13 Materials Approval

Notes:

Noted by : Mr. Liu Genbao 5-Nov-20


Project Manager-Chinese Date

Received by :
ALC Management Date

Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to review
for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of its obligations
under contract.
JQ INTERNATIONAL CONSTRUCTION INC.

WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS

ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 1/5/2021

: Stripping of forms at Roof deck columns, water tank saddle, Helipad and roof over
Work Item Requested by : Engr. Ron
stair columns, beams and slabs (See attached files)

Contractor : JQ INTERNATIONAL CONSTRUCTION INC.

Date of Work 1/5/2021

Contractor's Representative Project Management Inspector/s


Item # Checklist
Name/Initial Signature Name/Initial Signature

1 Line & Grade

2 Forms

3 Rebars, Dowel

4 Electrical

5 Sanitary

6 Plumbing

7 Structural

8 Mechanical

9 Architectural

10 Waterproofing

11 Equipment, Tools

12 QA/QC

13 Materials Approval

Notes:

Noted by : Mr. Liu Genbao 5-Jan-21


Project Manager-Chinese Date

Received by :
ALC Management Date

Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to review
for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of its obligations
under contract.
JQ INTERNATIONAL CONSTRUCTION INC.

REQUEST FOR STRIPPING FORMWORKS, SCAFFOLDS AND SUPPORTS

PROJECT : BANHAO TOWER SIWR : JQ-RFS-FORMS

ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested :

Work Item : Requested by :

Contractor : JQ INTERNATIONAL CONSTRUCTION INC.

Date of Work

Contractor's Representative Project Management Inspector/s


Item # Checklist
Name/Initial Signature Name/Initial Signature

1 Line & Grade

2 Forms

3 Rebars, Dowel

4 Electrical

5 Sanitary

6 Plumbing

7 Structural

8 Mechanical

9 Architectural

10 Waterproofing

11 Equipment, Tools

12 QA/QC

13 Materials Approval

Notes:

Noted by : Mr. Liu Aden


Project Manager-Chinese Date

Received by :
Management Date

Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to review
for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of its obligations
under contract.