S6 - Request For Stripping Formworks, Scaffolds and Supports
S6 - Request For Stripping Formworks, Scaffolds and Supports
REQUESTED DATE & TIME Saturday, November 18, 2017 10:00:00 AM SOG-BH-ELEC-WIR-002
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc
DRAWING NO.
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
PROJECT MANAGEMENT TEAM RECOMMENDATION (ALC)
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disappro E Noted
Received by SOGECOA: Received by ALC :
Signature : Signature :
Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc
DRAWING NO.
FLOOR LEVEL
LOCATION AS SHOWN IN DRAWING
SEGMENT
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
ALC - MANAGEMENT
WORK INSPECTIO
INSPECTION OF REBARS(EL.)@BP FR
SUBMITTAL DESCRIPTION
(1.54MIN TO 1.75MAX)
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
POSITION :
APPROVAL STATUS
A Approved B Approved with comment
Received by SOGECOA:
Signature :
Date :
SOGECOA Philippines International Construction
and Trading Company, Inc
RK INSPECTION REQUEST
ARS(EL.)@BP FROM
SUBMITTAL NO.-REV. #
O 1.75MAX)
8:00AM
SOG-BH-STR-0001-FND-0
AS SHOWN IN DRAWING
DATE :
Received by ALC :
Signature :
Date :
l Construction
-REV. #
01-FND-0
OTHERS_ ___________
RAWING
BY ALC
SIGNATURE
Noted
SOGECOA Philippines Inte
ALC - MANAGEMENT and Trading Compa
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
DEPARTMENTS SIGNATURE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit
Signature : Signature :
Date : Date :
Philippines International Construction
rading Company, Inc
SUBMITTAL NO.-REV. #
SOG-BH-STR-0001-FND-0 A
AS SHOWN IN DRAWING
SIGNATURE
LC)
C)
D Disapproved E Noted
ALC - MANAGEMENT
WORK INSPECTIO
BORED PILE-HACKING ELEVATION
SUBMITTAL DESCRIPTION
BP# 41,42, 43 & 44
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
POSITION :
APPROVAL STATUS
A Approved B Approved with comments
Received by SOGECOA:
Signature :
Date :
SOGECOA Philippines International Construction
and Trading Company, Inc
RK INSPECTION REQUEST
KING ELEVATION
SUBMITTAL NO.-REV. #
2, 43 & 44
8:30AM
SOG-BH-STR-0001-FND-0 B
AS SHOWN IN DRAWING
DATE :
Received by ALC :
Signature :
Date :
l Construction
-REV. #
FND-0 B
OTHERS_ ___________
RAWING
BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT
WORK INSPECTIO
TESTING OF REBAR 16MM DIA G-60
SUBMITTAL DESCRIPTION
[6.0, 10.5 & 12METER]
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
POSITION :
APPROVAL STATUS
A Approved B Approved with comments
Received by SOGECOA:
Signature :
Date :
SOGECOA Philippines International Construction
and Trading Company, Inc
RK INSPECTION REQUEST
R 16MM DIA G-60
SUBMITTAL NO.-REV. #
12METER]
15:30PM
SOG-BH-STR-0001-FND-0 C
AS SHOWN IN DRAWING
DATE :
Received by ALC :
Signature :
Date :
l Construction
-REV. #
FND-0 C
OTHERS_ ___________
RAWING
BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT
WORK INSPECTIO
BORED PILE-HACKING ELEVATION
SUBMITTAL DESCRIPTION
BP# 37,38, 39 & 40
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
POSITION :
APPROVAL STATUS
A Approved B Approved with comments
Received by SOGECOA:
Signature :
Date :
SOGECOA Philippines International Construction
and Trading Company, Inc
RK INSPECTION REQUEST
KING ELEVATION
SUBMITTAL NO.-REV. #
8, 39 & 40
17:00PM
SOG-BH-STR-0001-FND-0 D
AS SHOWN IN DRAWING
DATE :
Received by ALC :
Signature :
Date :
l Construction
-REV. #
-FND-0 D
OTHERS_ ___________
RAWING
BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT
WORK INSPECTIO
BORED PILE-HACKING ELEVATION
SUBMITTAL DESCRIPTION
BP# 29,30,31,32,33,34,35 & 36
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
POSITION :
APPROVAL STATUS
A Approved B Approved with comments
Received by SOGECOA:
Signature :
Date :
SOGECOA Philippines International Construction
and Trading Company, Inc
RK INSPECTION REQUEST
KING ELEVATION
SUBMITTAL NO.-REV. #
2,33,34,35 & 36
13:30PM
SOG-BH-STR-0004-FND-0
AS SHOWN IN DRAWING
DATE :
Received by ALC :
Signature :
Date :
l Construction
-REV. #
4-FND-0
OTHERS_ ___________
RAWING
BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT
WORK INSPECTIO
TESTING OF REBAR 28MM DIA G-75
SUBMITTAL DESCRIPTION & 16MM DIA G-60
[SEE ATTACHED MILL CERTIFICATE]
SUBMITTED DATE & TIME Saturday, September 30, 2017 9:00
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
POSITION :
APPROVAL STATUS
A Approved B Approved with comments
Received by SOGECOA:
Signature :
Date :
SOGECOA Philippines International Construction
and Trading Company, Inc
RK INSPECTION REQUEST
AR 28MM DIA G-75
DIA G-60 SUBMITTAL NO.-REV. #
ILL CERTIFICATE]
9:00AM
SOG-BH-STR-0005-FND-0
AS SHOWN IN DRAWING
DATE :
Received by ALC :
Signature :
Date :
l Construction
-REV. #
05-FND-0
OTHERS_ ___________
RAWING
BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT
WORK INSPECTIO
HANDLING OVER OF SEGMENT 1
SUBMITTAL DESCRIPTION
PRIOR FOR LEAN CONCRETE PILE CAP
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
POSITION :
APPROVAL STATUS
A Approved B Approved with comments
Received by SOGECOA:
Signature :
Date :
SOGECOA Philippines International Construction
and Trading Company, Inc
RK INSPECTION REQUEST
R OF SEGMENT 1
SUBMITTAL NO.-REV. #
ONCRETE PILE CAP
9:00AM
SOG-BH-STR-0005-FND-0 A
AS SHOWN IN DRAWING
DATE :
Received by ALC :
Signature :
Date :
l Construction
-REV. #
-FND-0 A
OTHERS_ ___________
RAWING
BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT
WORK INSPECTIO
REQUEST FOR INSPECTION OF SOIL POISONING AP
SUBMITTAL DESCRIPTION
MAT FOUNDATION PRIOR FOR LEAN CONCRETE @
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
POSITION :
APPROVAL STATUS
A Approved B Approved with comments
Received by SOGECOA:
Signature :
Date :
SOGECOA Philippines International Construction
and Trading Company, Inc
RK INSPECTION REQUEST
OIL POISONING APPLICATION AT
SUBMITTAL NO.-REV. #
LEAN CONCRETE @SEGMENT 1
11:00AM
SOG-BH-STR-0005-FND-0 B
AS SHOWN IN DRAWING
DATE :
Received by ALC :
Signature :
Date :
l Construction
-REV. #
-FND-0 B
OTHERS_ ___________
RAWING
BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT
WORK INSPECTIO
REQUEST INSPECTION FOR SURVEY LAYOUT/ GR
SUBMITTAL DESCRIPTION
SEGMENT 1 PRIOR FOR INSTALLATION OF REBARS
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
POSITION :
APPROVAL STATUS
A Approved B Approved with comments
Received by SOGECOA:
Signature :
Date :
SOGECOA Philippines International Construction
and Trading Company, Inc
RK INSPECTION REQUEST
RVEY LAYOUT/ GRIDLINES AT
SUBMITTAL NO.-REV. #
ATION OF REBARS AT PILE CAP
11:00AM
SOG-BH-STR-0006-FND-0
AS SHOWN IN DRAWING
DATE :
Received by ALC :
Signature :
Date :
l Construction
-REV. #
06-FND-0
OTHERS_ ___________
RAWING
BY ALC
SIGNATURE
Noted
ALC - MANAGEMENT
WORK INSPECTIO
REQUEST INSPECTION FOR COLUMN LAYOUT AT
SUBMITTAL DESCRIPTION
PRIOR FOR INSTALLATION OF REBARS AT PI
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
POSITION :
APPROVAL STATUS
A Approved B Approved with comments
Received by SOGECOA:
Signature :
Date :
SOGECOA Philippines International Construction
and Trading Company, Inc
RK INSPECTION REQUEST
LUMN LAYOUT AT SEGMENT 1
SUBMITTAL NO.-REV. #
OF REBARS AT PILE CAP
11:00AM
SOG-BH-STR-0007-FND-0
AS SHOWN IN DRAWING
DATE :
Received by ALC :
Signature :
Date :
l Construction
-REV. #
07-FND-0
OTHERS_ ___________
RAWING
BY ALC
SIGNATURE
Noted
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc
SUBMITTAL DESCRIPTION REQUEST FOR INSPECTION FOR BOTTOM BARS AND 6 COLUMNS SUBMITTAL NO.-REV. #
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc
REQUESTED DATE & TIME Monday, November 06, 2017 14:00:00 PM SOG-BH-STR-COL-0013
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc
REQUESTED DATE & TIME Wednesday, November 08, 2017 10:00:00 AM SOG-BH-STR-0014
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
SOGECOA Philippines International Construction
ALC - MANAGEMENT and Trading Company, Inc
REQUESTED DATE & TIME Saturday, November 18, 2017 10:00:00 AM SOG-BH-ELEC-WIR-002
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
ELECTRICAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT
1 3 3
DRAWING NO.
E-12 E-15 E-19
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT
1 3 3
DRAWING NO.
E-12 E-16 E-20
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT
1 3 3
DRAWING NO.
E-12 E-16 E-20
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT
1 3 3
DRAWING NO.
E-12 E-16 E-20
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT
3 3
DRAWING NO.
E-15 E-19
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT
2 1 1
DRAWING NO.
E-12 E-16 E- 20
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT
2 1 1
DRAWING NO.
E-12 E-16 E- 20
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
FIRE PROTECTION
MECHANICAL
PLUMBING
SANITARY
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
JQ International Construction Inc.
ALC - MANAGEMENT
DEPARTMENT
DRAWING NO.
CONTRACTOR'S REPRESENTATIVE
SURVEYOR
ARCHITECTURAL
STRUCTURAL
SAFETY
NAME : SIGNATURE :
POSITION : DATE :
APPROVAL STATUS
A Approved B Approved with comments C Resubmit D Disapproved E Noted
Signature : Signature :
Date : Date :
JQ INTERNATIONAL CONSTRUCTION INC.
WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS
ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : Aug. 29, 2019
Work Item : Stripping of forms at 3rd Floor RC wall Requested by : Engr. Ron Jason
2 Forms
3 Rebars, Dowel
4 Electrical
5 Sanitary
6 Plumbing
7 Structural
8 Mechanical
9 Architectural
10 Waterproofing
11 Equipment, Tools
12 QA/QC
13 Materials Approval
Notes:
Received by :
ALC Management Date
Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to
review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of
its obligations under contract.
JQ INTERNATIONAL CONSTRUCTION INC.
WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS
ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 10/7/2019
Work Item : Stripping of forms at 26th Floor Slabs and Beams @ GL A-E/1-6 Requested by : Engr. Ron Jason
2 Forms
3 Rebars, Dowel
4 Electrical
5 Sanitary
6 Plumbing
7 Structural
8 Mechanical
9 Architectural
10 Waterproofing
11 Equipment, Tools
12 QA/QC
13 Materials Approval
Notes:
Received by :
ALC Management Date
Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to
review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of
its obligations under contract.
JQ INTERNATIONAL CONSTRUCTION INC.
WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS
ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 10/18/2019
Work Item : Stripping of forms at 27th Floor Slabs and Beams @ GL A-E/1-6 Requested by : Engr. Ron Jason
2 Forms
3 Rebars, Dowel
4 Electrical
5 Sanitary
6 Plumbing
7 Structural
8 Mechanical
9 Architectural
10 Waterproofing
11 Equipment, Tools
12 QA/QC
13 Materials Approval
Notes:
Received by :
ALC Management Date
Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to
review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of
its obligations under contract.
JQ INTERNATIONAL CONSTRUCTION INC.
WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS
ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 11/21/2019
Work Item : Stripping of forms at 29th Floor Slabs and Beams @ GL A-E/1-6 Requested by : Engr. Ron
2 Forms
3 Rebars, Dowel
4 Electrical
5 Sanitary
6 Plumbing
7 Structural
8 Mechanical
9 Architectural
10 Waterproofing
11 Equipment, Tools
12 QA/QC
13 Materials Approval
Notes:
Received by :
ALC Management Date
Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to
review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of
its obligations under contract.
JQ INTERNATIONAL CONSTRUCTION INC.
WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS
ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 12/5/2019
Work Item : Stripping of forms at 30th Floor Slabs and Beams @ GL A-E/1-6 Requested by : Engr. Ron
2 Forms
3 Rebars, Dowel
4 Electrical
5 Sanitary
6 Plumbing
7 Structural
8 Mechanical
9 Architectural
10 Waterproofing
11 Equipment, Tools
12 QA/QC
13 Materials Approval
Notes:
Received by :
ALC Management Date
Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to
review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of
its obligations under contract.
JQ INTERNATIONAL CONSTRUCTION INC.
WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS
ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 9/19/2020
Work Item : Stripping of forms at 39TH (U) - 40TH (L)Floor Slabs and Beams @ GL A-E/3-6' Requested by : Engr. Ron
2 Forms
3 Rebars, Dowel
4 Electrical
5 Sanitary
6 Plumbing
7 Structural
8 Mechanical
9 Architectural
10 Waterproofing
11 Equipment, Tools
12 QA/QC
13 Materials Approval
Notes:
Received by :
ALC Management Date
Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to
review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of its
obligations under contract.
JQ INTERNATIONAL CONSTRUCTION INC.
WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS
ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 10/17/2020
Work Item : Stripping of forms at 40TH (U) - Roof Deck Floor Slabs and Beams @ GL A-E/1-6' Requested by : Engr. Ron
2 Forms
3 Rebars, Dowel
4 Electrical
5 Sanitary
6 Plumbing
7 Structural
8 Mechanical
9 Architectural
10 Waterproofing
11 Equipment, Tools
12 QA/QC
13 Materials Approval
Notes:
Received by :
ALC Management Date
Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to review
for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of its obligations
under contract.
JQ INTERNATIONAL CONSTRUCTION INC.
WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS
ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 11/5/2020
Work Item : Stripping of forms at 40TH (U) - Roof Deck Floor Slabs and Beams @ GL B-D/4-6' Requested by : Engr. Ron
2 Forms
3 Rebars, Dowel
4 Electrical
5 Sanitary
6 Plumbing
7 Structural
8 Mechanical
9 Architectural
10 Waterproofing
11 Equipment, Tools
12 QA/QC
13 Materials Approval
Notes:
Received by :
ALC Management Date
Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to review
for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of its obligations
under contract.
JQ INTERNATIONAL CONSTRUCTION INC.
WORK REQUEST
PROJECT : BANHAO TOWER SIWR : JQ-WR-FORMS
ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested : 1/5/2021
: Stripping of forms at Roof deck columns, water tank saddle, Helipad and roof over
Work Item Requested by : Engr. Ron
stair columns, beams and slabs (See attached files)
2 Forms
3 Rebars, Dowel
4 Electrical
5 Sanitary
6 Plumbing
7 Structural
8 Mechanical
9 Architectural
10 Waterproofing
11 Equipment, Tools
12 QA/QC
13 Materials Approval
Notes:
Received by :
ALC Management Date
Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to review
for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of its obligations
under contract.
JQ INTERNATIONAL CONSTRUCTION INC.
ADDRESS : SAN FERNANDO ST. CORNER MADRID ST. BINONDO MANILA Date Requested :
Date of Work
2 Forms
3 Rebars, Dowel
4 Electrical
5 Sanitary
6 Plumbing
7 Structural
8 Mechanical
9 Architectural
10 Waterproofing
11 Equipment, Tools
12 QA/QC
13 Materials Approval
Notes:
Received by :
Management Date
Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades tasked to review
for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve the contractor of its obligations
under contract.