Design Summary Table
Design Summary Table
Date: 16 / 9 / 2020
3113ENG –Civil Engineering Design Project
Contents
Design
SummaryTable......................................................................................................1
Task1: ......................................................................................................................2
Task 2: .....................................................................................................................4
Task 3: .....................................................................................................................5
Task 4: ......................................................................................................................7
3113ENG –Civil Engineering Design Project
Task 2
Q y b d Fr
n Side slope
(m3/s) (mm) (mm) (mm)
0.17 0.016 290 240 1:1 590 0.77
Task 3
Q y b d Fr Vmax AEP
n Side slope
(m3/s) (mm) (mm) (mm) (m/s) (%)
17 0.065 800 1965 1:4 1100 0.34 0.93 10
Task 4
Number / size HW inlet HW outlet Inlet or outlet d50 L t
A (m2)
of Culvert (s) (mm) (mm) control (mm) (mm) (mm)
10.8 2/1500×3600 1.26 1.22 Inlet control 300 7.5 600
1
3113ENG –Civil Engineering Design Project
Task 1:
Design a concrete pipe to drain the major road shown in Figure 1. Assume a design
discharge of 170 L/s and longitudinal slope of 0.4%. How much is the capacity of the
pipe? How much should be the selected AEP?
Solution:
1: DetermineQ,s,n.
Q =0.17m3/s S =0.4%
Use Table 2.1 (concrete pipe):n=0.013
2.Determine the D
Use Chart A1-2 (S=0.004, Q=0.17m3/s)
450 > D >375=> select D=450 mm
2
3113ENG –Civil Engineering Design Project
2 2
3
3113ENG –Civil Engineering Design Project
Task 2:
Design a rough bituminous channel to carry the same discharge. Discuss the
pros and cons of channel and pipe and draw the cross section of both.
Solution:
1: Determine Q, S, n, X
2
1 nQ 2 y 3
1 AR y2 2 1 x 2 - x
2 1
AR 3 S 2 3
Q= n ⇒S
2
2
Rearranging⇒
3 3
Q 0.17
V 1.1m/s
A 0.154
3: calculate B
B 0.82
Fr Q 0.17 0.77 0.9
gA 3
9.8 0.1543
5:Determine freeboard:
V2
freeboard: 2g =1.21/2×9.8=0.062 0.2y=0.2×0.29=0.058
4
3113ENG –Civil Engineering Design Project
Task 3:
Design an earthen channel to carry a flow of 17 m 3/s just before the crossing of the
abovementioned channel and major road (Figure 2). Assume a non-maintained
trapezoidal section, a side slope of 1V:4H in an easily erodible, 27% vegetated soil
with clean bottom and brush on sides. Discuss the pros and cons of the earthen
channel compared to the concrete one. How much should be the selected AEP?
5
3113ENG –Civil Engineering Design Project
122.85
S 0 125 0.006
360
From table 8.8.1.3, use So=0.006 and
stable surface fraction =0.25,
We can get
1.28 - 0.58
Vmax 0.25 - 0 0.58 0.93m/s
0.5 - 0
Q
2:Use to determine required A
V max
Q 17
A 18.28m 3
Vmax 0.93
6
3113ENG –Civil Engineering Design Project
y1 5.35m b1 -17.94m
y 2 0.8m b 2 19.65m
We get that y 0.8m
B= b+2Xy=19.65+2×4×0.8=26.05m
B 26.05
Fr Q 17 0.34 0.9
gA 3
9.8 18.283
7:Determine freeboard:
AEP:it can be regarded as kerb and channel flow of major road according to table
7.3.1, thus the ARI is 10, while the AEP is 10%.
Task 4 (~50%):
At the intersection of the above-mentioned road and the channel, a culvert system
(longitudinally shown in Figure 3) is required. Design the configuration of the
required standard box culvert(s) and provide the drawings 2 based on the information
given below. As a summary of your calculation steps, fill the relevant parts of the
attached design calculation form and insert in after the last calculation in this part.
The road width is 11 m, its crown elevation is 125.65 m and its cross fall (cross road
7
3113ENG –Civil Engineering Design Project
slope) is 3.5%. The Allowable Headwater (AHW) is 17 cm below the shoulder height
to avoid any potential damage. The inlet invert height is 122.85 m. Downstream of the
culvert, maximum allowable velocity is 1.7 m/s. The culvert is 27 m long and needs to
be made of reinforced concrete with a height limit of 1.7 m. The culvert entrance type
is square edged with 70o wingwall flare and there is no chance of blockage. What do
you recommend for the downstream protection? Provide the details if a protection is
required. Furthermore, check your design for an extreme event (AEP=1%) with 10%
more discharge. Pros and cons of the design option need to be discussed.
Inlet height=122.85m
AHW=125.35-122.85-0.17=2.33m
2: Selecting culvert size
Q 17
A 10m 3
VMAX 1.7
Required area
Try 2 square culverts with D=1.5m , B=3.6, (Table2)
8
3113ENG –Civil Engineering Design Project
3
A=2×1.5××3.6=10.8> 10 m
The culvert entrance type is square edged with 70o wingwall flar
HW
D 0.84 (See the table below)
9
3113ENG –Civil Engineering Design Project
HWi=0.84×D=0.84×1.5=1.26m < 2.33m(AHW)
A by xy 2 19.65y 4y 2
P b 2y 1 x 2 19.65 2 17y
y Tw 0.65<D 1.5
Q=17×1.1=18.7m3/s
∴TW=0.68< D=1.5 OK
D d c
h 0 max TW ,
Because 2
10
3113ENG –Civil Engineering Design Project
q 2 3 2.36 2
dc 3 0.83
g 9.8
Q 17 A
V 1.57m 3 /s R
A 10.8 n=0.012 L=27m P 0.38m
V 2 n2 1.57 2 0.012 2
hL 4 L 4 25 0.031m
R3 0.38 3
From table .2, reinforced concrete box, wingwall at 30o -75o to cell, crown
Edge square, ke=0.4
K e V 2
he
2g 0.05m
V 2 K e V 2 V 2 n 2
H 4 L 0.12 0.05 0.031 0.2m
2g 2g R3
6: Design protection
∵inlet control
Because it is inlet control, thus we need to calculate A0 ,and we need to find TW
1 2 1
Q AR 3 S 2
using the Manning formula n
11
3113ENG –Civil Engineering Design Project
Fr Q B/(gA3) 3.59
L=4D=4×1.5=6m
because it is designed for multiple cells, so it is recommended extending the
protection length by 25%. Thus L=1.25×6=7.5m. The expansion rate is 5:1. To
conclude, for rock apron,d50 =300mm, thickness of apron
t =1.5×400=600mm, the plan view is shown as followed.
12
3113ENG –Civil Engineering Design Project
Designer :
PROJECT : 3113ENG Checker / Reviewer:
Date:
Hydrological and Channel Information
Outlet
DESCRIPTIO Q D
Inlet Control Outlet Control: HW=H+h0-L.S0
N (Entrance Per
Type) cell
y Velocit
-
Q/B
3113ENG –Civil Engineering Design Project
Controlling HW