0% found this document useful (0 votes)
181 views

Design Summary Table

The document contains a drainage design report with 4 tasks: 1. Design of a concrete pipe to drain a major road, with a capacity of 0.177 m3/s. 2. Design of a rough bituminous channel to carry the same discharge of 0.17 m3/s. 3. Design of an earthen channel to carry a larger discharge of 17 m3/s. 4. Design of a culvert system with two 1.5m x 3.6m box culverts under the road, with a capacity of 10.8 m3 and a maximum headwater depth of 1.26m.

Uploaded by

周星星
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
181 views

Design Summary Table

The document contains a drainage design report with 4 tasks: 1. Design of a concrete pipe to drain a major road, with a capacity of 0.177 m3/s. 2. Design of a rough bituminous channel to carry the same discharge of 0.17 m3/s. 3. Design of an earthen channel to carry a larger discharge of 17 m3/s. 4. Design of a culvert system with two 1.5m x 3.6m box culverts under the road, with a capacity of 10.8 m3 and a maximum headwater depth of 1.26m.

Uploaded by

周星星
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 16

3113 ENG -Civil Engineer Design Project

Drainage Design Report

Name: Tianyou Miao

Student no: s204377

Date: 16 / 9 / 2020
3113ENG –Civil Engineering Design Project

Contents

Design
SummaryTable......................................................................................................1
Task1: ......................................................................................................................2
Task 2: .....................................................................................................................4
Task 3: .....................................................................................................................5
Task 4: ......................................................................................................................7
3113ENG –Civil Engineering Design Project

Design Summary Table


Task 1
Q(m3/s) AEP(%) n D (mm) V (m/s) Capacity (m3/s)
0.17 10 0.013 525 0.817 0.177

Task 2
Q y b d Fr
n Side slope
(m3/s) (mm) (mm) (mm)
0.17 0.016 290 240 1:1 590 0.77

Task 3
Q y b d Fr Vmax AEP
n Side slope
(m3/s) (mm) (mm) (mm) (m/s) (%)
17 0.065 800 1965 1:4 1100 0.34 0.93 10

Task 4
Number / size HW inlet HW outlet Inlet or outlet d50 L t
A (m2)
of Culvert (s) (mm) (mm) control (mm) (mm) (mm)
10.8 2/1500×3600 1.26 1.22 Inlet control 300 7.5 600

1
3113ENG –Civil Engineering Design Project

Task 1:
Design a concrete pipe to drain the major road shown in Figure 1. Assume a design
discharge of 170 L/s and longitudinal slope of 0.4%. How much is the capacity of the
pipe? How much should be the selected AEP?

Solution:
1: DetermineQ,s,n.
Q =0.17m3/s S =0.4%
Use Table 2.1 (concrete pipe):n=0.013
2.Determine the D
Use Chart A1-2 (S=0.004, Q=0.17m3/s)
450 > D >375=> select D=450 mm

2
3113ENG –Civil Engineering Design Project

2 2

(  0.45 )( 0.45 ) 3  0.004 2  0.106  0.15


1 2 1 1 2 1
AR 3 S 2
Q= n = 0.013 4 4

Thus select D=525m ,if use D=525m


1 2 1
Q  AR 3 S 2  0.176  0.15  D  525m
N
3. Determine the V and the Capacity
1 2 1
V R 3 S 2  76.92  0.168  0.0632  0.817 m/s
0.013
C  V  A  0.817  0.216  0.177 m 3 /s

4. Determine the AEP


AEP:Because it is a longitudinal drainage channel alongside a major road, thus it can
be regarded as kerb and channel flow of major road according to table 7.3.1, thus the
ARI is 10, while the AEP is 10%.

3
3113ENG –Civil Engineering Design Project

Task 2:
Design a rough bituminous channel to carry the same discharge. Discuss the
pros and cons of channel and pipe and draw the cross section of both.

Solution:
1: Determine Q, S, n, X

Q =0.17m3/s S =0.4% X=1


Use Table 2.1 (concrete pipe):n=0.016
2:Best hydraulic section method:
Y
R
2 A  by  xy 2 b  2y( 1  x 2  x)

 
2

1 nQ 2  y 3
1  AR  y2 2 1 x 2 - x  
2 1
AR 3 S 2 3

Q= n ⇒S
2
2

Rearranging⇒
3 3

 1.59Qn  8  1.59  0.17  0.016  8


y 1
   

 S 2 2 1  x 2  x   0.004 2 2 1  12  1 
1 
 =0.29
m
 
b  2y( 1  x 2  x)  2  0.29  1  12 - 1  0.24m

A  by  xy 2  0.24  0.29  1 0.29 2  0.154m 2

Q 0.17
V   1.1m/s
A 0.154

3: calculate B

B  b  2xy  0.24  2 1 0.29  0.82m

4:Calculate Froude Number (Fr) :

B 0.82
Fr  Q  0.17  0.77  0.9
gA 3
9.8  0.1543

5:Determine freeboard:
V2
freeboard: 2g =1.21/2×9.8=0.062 0.2y=0.2×0.29=0.058

4
3113ENG –Civil Engineering Design Project

freeboard =max {0.3,0.058,0.062}=0.3m

Depth d=y+ freeboard = 0.29+0.3=0.59m

Task 3:

Design an earthen channel to carry a flow of 17 m 3/s just before the crossing of the
abovementioned channel and major road (Figure 2). Assume a non-maintained
trapezoidal section, a side slope of 1V:4H in an easily erodible, 27% vegetated soil
with clean bottom and brush on sides. Discuss the pros and cons of the earthen
channel compared to the concrete one. How much should be the selected AEP?

5
3113ENG –Civil Engineering Design Project

1: Determine Q, So , n, X and Vmax

We know that X=4 and Q =17m3 /s

From table 8.4.3(a), we can know that n=


0.05+0.08
=0.065
2

122.85
S 0  125   0.006
360
From table 8.8.1.3, use So=0.006 and
stable surface fraction =0.25,
We can get
1.28 - 0.58
Vmax   0.25 - 0  0.58  0.93m/s
0.5 - 0
Q
2:Use to determine required A
V max
Q 17
A   18.28m 3
Vmax 0.93

3 :Calculate P using equation


5 1 5 1
A 3 S 2 12 18.28 3 0.006 2 12
P( ) ( )  26.11
Qn 17  0.065

6
3113ENG –Civil Engineering Design Project

4: Calculate y using equation

y1  5.35m  b1  -17.94m 
y 2  0.8m  b 2  19.65m   
We get that  y  0.8m

5: calculate B (surface width):

B= b+2Xy=19.65+2×4×0.8=26.05m

6:Calculate Froude Number (Fr) and check if it is acceptable:

B 26.05
Fr  Q  17   0.34  0.9
gA 3
9.8 18.283

7:Determine freeboard:

freeboard: V2/2g=0.932/2×9.8=0.044m 0.2y=0.2×0.8=0.16m


freeboard =max {0.3,0.044,0.16}=0.3m
Depth d=y+freeboard=0.8+0.3=1.1m
8:Determine the AEP

AEP:it can be regarded as kerb and channel flow of major road according to table
7.3.1, thus the ARI is 10, while the AEP is 10%.
Task 4 (~50%):

At the intersection of the above-mentioned road and the channel, a culvert system
(longitudinally shown in Figure 3) is required. Design the configuration of the
required standard box culvert(s) and provide the drawings 2 based on the information
given below. As a summary of your calculation steps, fill the relevant parts of the
attached design calculation form and insert in after the last calculation in this part.
The road width is 11 m, its crown elevation is 125.65 m and its cross fall (cross road

7
3113ENG –Civil Engineering Design Project

slope) is 3.5%. The Allowable Headwater (AHW) is 17 cm below the shoulder height
to avoid any potential damage. The inlet invert height is 122.85 m. Downstream of the
culvert, maximum allowable velocity is 1.7 m/s. The culvert is 27 m long and needs to
be made of reinforced concrete with a height limit of 1.7 m. The culvert entrance type
is square edged with 70o wingwall flare and there is no chance of blockage. What do
you recommend for the downstream protection? Provide the details if a protection is
required. Furthermore, check your design for an extreme event (AEP=1%) with 10%
more discharge. Pros and cons of the design option need to be discussed.

1: Determine allowable head water depth (AHW)

AHW=shoulder height-inlet height - free board(100mm)


0.035
- 17 
125.65 ( ) 125.35m
Shoulder Height= 2

Inlet height=122.85m
AHW=125.35-122.85-0.17=2.33m
2: Selecting culvert size

Q 17
A   10m 3
VMAX 1.7
Required area
Try 2 square culverts with D=1.5m , B=3.6, (Table2)

8
3113ENG –Civil Engineering Design Project

3
A=2×1.5××3.6=10.8> 10 m

 D  1.5m B  3.6m 1.5m<1.7m

3: Check for inlet control HW depth


D=1.5m B=3.6m
Q 17
QPercell    8.5m 3 /s
N 2
Q 8.5
q   2.36m 3 /s
B 3.6

 The culvert entrance type is square edged with 70o wingwall flar

HW

D 0.84 (See the table below)

9
3113ENG –Civil Engineering Design Project

HWi=0.84×D=0.84×1.5=1.26m < 2.33m(AHW)

4: Check for outlet control HW depth


3
X= 4 Q= 17 m / s n=0.012

To find h0 , we must find TW using manning’s equation


1
Q= AR2/3S1/2
N

A  by  xy 2  19.65y  4y 2
P  b  2y 1  x 2  19.65  2 17y

y  Tw  0.65<D  1.5

check your design for an extreme event (AEP=1%)


with 10% more discharge

Q=17×1.1=18.7m3/s

∴TW=0.68< D=1.5 OK

  D  d c 
h 0  max TW ,  
Because   2 

10
3113ENG –Civil Engineering Design Project

Therefore,we should find d c

q 2 3 2.36 2
dc  3   0.83
g 9.8

Then(D+dc)/2=1.165m Therefore h 0 =max(0.65,1.165)=1.165m

Then, use equation to get h L

Q 17 A
V   1.57m 3 /s R 
A 10.8 n=0.012 L=27m P 0.38m

V 2  n2 1.57 2  0.012 2
hL  4 L  4  25  0.031m
R3 0.38 3

From table .2, reinforced concrete box, wingwall at 30o -75o to cell, crown
Edge square, ke=0.4
K e V 2
he  
2g 0.05m

V 2 K e V 2 V 2  n 2
H   4  L  0.12  0.05  0.031  0.2m
2g 2g R3

HW0  h 0  H - S 0  L  1.165  0.2  0.15  1.22<2.33


(AHW)

5: Determine the control head water:


HW  max  HW0, HWi   max1.22,
1.26  1.2
Thus, inlet control.

6: Design protection

∵inlet control
Because it is inlet control, thus we need to calculate A0 ,and we need to find TW

1 2 1
Q AR 3 S 2
using the Manning formula n

A0  3.6×0.65=2.34 m 2 B = width of flow at surface=3.6×2=7.2m

11
3113ENG –Civil Engineering Design Project

Fr  Q B/(gA3) 3.59

L=4D=4×1.5=6m
because it is designed for multiple cells, so it is recommended extending the
protection length by 25%. Thus L=1.25×6=7.5m. The expansion rate is 5:1. To
conclude, for rock apron,d50 =300mm, thickness of apron
t =1.5×400=600mm, the plan view is shown as followed.

12
3113ENG –Civil Engineering Design Project

Designer :
PROJECT : 3113ENG Checker / Reviewer:
Date:
Hydrological and Channel Information

Q1 = 7m3/s AEP 2 % TW1 = 0.32 m


1.2
3
Q2 = 17m /s AEP 2 % TW2 = 0.65 m

Q3= 18.7m3/s AEP 1 % TW3= 0.68 m 0.65


3.5%

Q1 : low flow condition (~40% design condition)


Q2 : deign condition
Q3 : extreme condition (check)
Maximum Allowable Stream Velocity= 1.7m/s

CULVERT Size Headwater Computation Comments

Outlet
DESCRIPTIO Q D
Inlet Control Outlet Control: HW=H+h0-L.S0
N (Entrance Per
Type) cell

y Velocit
-
Q/B
3113ENG –Civil Engineering Design Project

Controlling HW

HWi/D HW Ke H dc (dc+D)/2 TW h0 L.S0 HWo


quare edged
0. 0.
with 70o 8.5 3.6×1.5 0.84 1.2 0.83 1.165 0.65 1.165 Inlet control
4 2
wingwall flare
Summary and Recommendations:

You might also like