0% found this document useful (0 votes)
37 views1 page

Request For Inspection: RTCC Material Storage / Ware House

RFI-PLB-048

Uploaded by

Joni Carino Suni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
37 views1 page

Request For Inspection: RTCC Material Storage / Ware House

RFI-PLB-048

Uploaded by

Joni Carino Suni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

REQUEST FOR INSPECTION

Saudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. RFI-PLB-48

BI: 10-09003-0006 JO: Phase Construction Title Industrial Support Facilities (ISF) Package 13

To : Project Inspection Unit/ Mr. Julius I Balanlay Civil Mech. Plumb. Comms. Elect. Others

Inspection/monitoring is required on (date) 06-Oct -2020 (time) 09:00 A.M prior to

for the following location/equipment RTCC MATERIAL STORAGE / WARE HOUSE

Work Permit Required: Yes No Inspection Level: RH Review/Approval of Documents Hold points Witness Point

SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected is
inspection and conforms to the project requirements complete and in compliance with the following specifications:

SAPMT Name ABDULLAH A ALWASEL SAES/SAMSS/Others# SATIP-S-070-03/SACI-S-4057


Signature Date 05-Oct-20 Contractor/Company RTCC
Telephone Fax QA/QC Name Syed Khaffoor
QA/QC Signature Date 05-Oct-20

This form received by the undersigned Inspection Department employee:

Name JULIUS I BALANLAY Signature Date Time

Work Description: Installation of 2 inch potable water entrance Inspection at admin building
Mechanical room GR-139,Gr-168 and GR-109 toilets:
Drawing reference :RTCC-SD-538155-001-01

NOTE: Inspector's signature is for receiving this request only and not for approval or disapproval of the work or facility inspected.

Distribution:
A. Original – Inspection Unit B. 1st Copy – RPO Proponent C. 2nd Copy – ID Coordinator D. 3rd Copy – Construction Contractor