0% found this document useful (0 votes)
222 views

Daily Report Sample

This daily project report summarizes progress on the Interim Road Improvement Doha South - Phase 02 project in Qatar over the last day. Major achievements included general safety arrangements and housekeeping, steel fabrication for precast concrete works, excavation works, and pipe laying. The report lists the contractor and GEIC staff on site and their roles. Weather was reported as sunny with temperatures between 34-43 degrees Celsius. No safety or environmental incidents were reported.

Uploaded by

Ahamed Ziyath
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
222 views

Daily Report Sample

This daily project report summarizes progress on the Interim Road Improvement Doha South - Phase 02 project in Qatar over the last day. Major achievements included general safety arrangements and housekeeping, steel fabrication for precast concrete works, excavation works, and pipe laying. The report lists the contractor and GEIC staff on site and their roles. Weather was reported as sunny with temperatures between 34-43 degrees Celsius. No safety or environmental incidents were reported.

Uploaded by

Ahamed Ziyath
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Client: GEC Main Contractor Contract Start Date 26-Apr-20 HSE QUALITY

Project Daily Report 1095 Safety Incidents:


Testing and any other details:
Project Duration (days)
PWA-RPD-CON-FM-1507 ROADS PROJECTS DEPARTMENT Project Completion Date 25-Apr-23 Manhours without fatality:
Rev. : 2 Date : Jan. 2019 Project Days Elapsed 436 Environmental Incidents:

PROJECT TITLE: Approved New Contract Completion Weather Report Humidity: Temperature (oC)
INTERIM ROAD IMPROVEMENT DOHA SOUTH - PHASE 02 5-Jul-21 DATE with extension Sunny Cloudy Rain Sandstorm Windy Max. Min.
(if applicable) :
Report No.
Project No. SA032 SDR_PH02_322 Contract Code: C2020/33 43 C 34 C

DAY SHIFT WORKING HOURS : NIGHT SHIFT WORKING HOUR: No Night Shift
MAJOR Achievements: MAJOR Achievements: DESCRIPTION Day Night DESCRIPTION Day Night
Work Order - 06: Al Wukair Road Upgrading Zone 90 Work Order - 07: Fifa Training Site Contractor Staff GEIC Staff
General Safety Arrangement and House Keeping General Safety Arrangement and House Keeping Project Director 1 Chief Engineer 1
General Steel Fabrication for Precast Foundation Concrete Works General Steel Fabrication for Precast Foundation Concrete Works Project Manager 1 Resident Engineer 1
Works Housekeeping | Safety |Security | Maintenance of Storage | Dewatering Works Housekeeping | Safety |Security | Maintenance of Storage | Dewatering Technical Manager 1 Planning Engineer 1
Removal & Shifting of Excavated Material to Stockpile Area Removal & Shifting of Excavated Material to Stockpile Area Deputy Technical Manager 1 Senior Works Inspector 2
Trench Exccavation | Pipe Laying | Surrounding | Backfilling Project Engineer 1 Sinior quantity surveyor 1
Phase -01 SWD MH Exca | Base | Wall | Foam Concrete | Concrete Cover Slab | Bacfilling Sr. Planning Engineer 1 Senior QA/QC Engineer 1
TSE Granular Surround | Backfilling Gully Exca | Connection and Concreting Planning Engineer 1 Environmental Specialist 1
Road Excavation | Formation TSE TSE trench; Excavation, Pipe Laying, Surrounding & Backfilling Commercial / Contracts Manager 1 CAD Technician 1
Road Road Kerbs |Aggregate Road Base | Sub-Grade | Asphalt Road Base Sr.Quantity Surveyor 1 Senior Works Inspector 3
Duct Excavation | Pipe Laying | Backfilling Quantity Surveyor 2 Quantity Surveyor 1
ITS Excavation | Concrete work for ITS Chambers QA/QC Engineer 2 Stakeholder Management Engineer 1
QA/QC Inspector 1 Site Engineer 3
Phase -02 Work Order - 08: Katara Signalized Pedestrian Crossing Senior Material Engineer 1 Publicity Officer 1
SWD Gully Excavation |Manhole Excavation | Connection and Concreting General Safety Arrangement and House Keeping Environmental Officer 1 Material Engineer 1
TSE Trench Excavation | Pipe Laying | Surrounding | Backfilling LV: Backfilling Traffic Engineer 1 Land Surveyor 1
HSE Engineer
Duct Excavation | Pipe Laying | Backfilling Road Kerb and Interlock Paving HSE Engineer 2 1
Work Order - 10: Ministry of Education & Higher Education HSE Officer 4 Senior Works Inspector 1
General Safety Arrangement and House Keeping Senior Draftsman 2 Admin Staff 1
SWD Grating Channel: Concrete Cover Slab | Precast Works | Tie-in Work Land Surveyor 2
Site Engineer 4
PRO/PRR 1
Secretary 1
Document Controller 1
Foreman 4
Store Keeper 2

Night Shift - No Work

WO-07: SWD Trench pipe surrounding


WO-06: Phase-01:Excavation for road
aggregates
WO-07: TSE Pipe laying WO-07: Concreting kerb foundation Sub Total 40 23

MATERIALS DELIVERED TO SITE PLANT & MACHINERIES ON SITE Manpower at Site


Day Shift Night Shift Charge Hand 12
SI No. Material Description Unit Quantity DESCRIPTION On Site
Work Idle Work Idle Unskilled Labor 85
1 HDPE LINER WITH RUBBER RINGS SET 24 1 Excavator: Hammer 16 16 Carpenter 14
2 ROAD GULLY – H-1100MM DIA PCS 60 2 Excavator: Bucket 8 8 Steel Fixer 18
3 KERBSTONE PCS 2040 3 Shovel 966 3 3 Mason 20
4 SINGLE SIZE GABBRO AGGREGATES TON 1069 4 Grader 2 2 Pipe Fitter 20
5 LOCAL LIMESTONE BACKFILL MATERIALS TON 53 5 JCB 6 6 Electrician 4
6 Roller Compactor: 2Ton 10 10 Painter 2
7 Roller Compactor: 10Ton 5 5 Operator 62
8 PTR Roller 4 4 Light Driver 2
9 Asphalt Paver 2 2 Heavy Driver 22
10 Asphalt Milling Machine 1 1
11 Boom Truck 4 4
12 Bobcat 10 6 4
13 Borehole Machine -
14 Mobile Crane 3 2 1
15 Tipper 6 Wheel Truck 15 15
16 Water Tanker 4 4
17 Plate Compactor 10 10
18 Bus 3 3 Sub Total 261 0 0 0
19 Pick up 2 2 Today's TOTAL 301
PREV. Day's Cumulative 47,250
Today's Cumulative 47,551
Today's GRAND TOTAL 301
PREV. Day's GRAND TOTAL 47,250
TOTAL TOTAL 108 96 12 - - CUMULATIVE TOTAL 47,551

Areas Of Concern
01. Aditional works by QNBN for the ITS & QNBN works. 09. Claim against Engineer's Instruction to provide additional Engineer's site offices and offices equipment.
WO-06
02. Renewal of RO for phase 01. 10. Claim against Engineer's instruction to procure backfilling, subgrade, subbase from QPMC exclusively.
03. SWD Trench collapsed due to unstable soil condition interrupting the flow of work progress leading for delay. 11. ESD recommendations for new rates did not consider for the allocation of the items in bill wise.
WO-07
04. Delay in obtaining RO has negative impact to whole WO-07 by time and cost.
05. Change request for completion date: waiting response.
WO-08
06.Waiting for electrical shutdown to energized pedestrian crossing light.
07. Unreasonable recommendations by GEIC/ESD for new rates.
08. The new rates submitted by MRTC for dewatering works in WO-#6&7, GEIC/ESD state the rate is included item in bill 1. The cost environmental
controls cannot be included for dewatering.
Checked by GEC SRE/RE (Verify information) For RPD : Review & Final acceptance
Prepared by MRTC - Contractor
Signature: Signature: Signature:
Name: ENGR. KHALED SHOEIB Name: ENGR. JACOB MATHEWS Name:
Designation: Project Manager Designation: Resident Engineer Designation:
Guidance Note:
1) Project Daily Report to be completed accurately and on daily basis by GEC
2) All applicable sections to be completed by GEC
Client: GEC Main Contractor Contract Start Date 26-Apr-20 HSE QUALITY
Project Daily Report Safety Incidents:
Testing and any other details:
Project Duration (days) 1095
PWA-RPD-CON-FM-1507 ROADS PROJECTS DEPARTMENT Project Completion Date 25-Apr-23 Manhours without fatality:
Rev. : 2 Date : Jan. 2019 Project Days Elapsed 436 Environmental Incidents:

PROJECT TITLE: Approved New Contract Completion Weather Report Humidity: Temperature (oC)
INTERIM ROAD IMPROVEMENT DOHA SOUTH - PHASE 02 5-Jul-21 DATE with extension Sunny Cloudy Rain Sandstorm Windy Max. Min.
(if applicable) :
Report No.
Project No. SA032 SDR_PH02_322 Contract Code: C2020/33 43 C 34 C
3) Completed Project Daily Report to be verified by GEC project specific SRE/RE
4) Completed Project Daily Report to be submitted Daily by GEC to RPD

You might also like