Daily Report Sample
Daily Report Sample
PROJECT TITLE: Approved New Contract Completion Weather Report Humidity: Temperature (oC)
INTERIM ROAD IMPROVEMENT DOHA SOUTH - PHASE 02 5-Jul-21 DATE with extension Sunny Cloudy Rain Sandstorm Windy Max. Min.
(if applicable) :
Report No.
Project No. SA032 SDR_PH02_322 Contract Code: C2020/33 43 C 34 C
DAY SHIFT WORKING HOURS : NIGHT SHIFT WORKING HOUR: No Night Shift
MAJOR Achievements: MAJOR Achievements: DESCRIPTION Day Night DESCRIPTION Day Night
Work Order - 06: Al Wukair Road Upgrading Zone 90 Work Order - 07: Fifa Training Site Contractor Staff GEIC Staff
General Safety Arrangement and House Keeping General Safety Arrangement and House Keeping Project Director 1 Chief Engineer 1
General Steel Fabrication for Precast Foundation Concrete Works General Steel Fabrication for Precast Foundation Concrete Works Project Manager 1 Resident Engineer 1
Works Housekeeping | Safety |Security | Maintenance of Storage | Dewatering Works Housekeeping | Safety |Security | Maintenance of Storage | Dewatering Technical Manager 1 Planning Engineer 1
Removal & Shifting of Excavated Material to Stockpile Area Removal & Shifting of Excavated Material to Stockpile Area Deputy Technical Manager 1 Senior Works Inspector 2
Trench Exccavation | Pipe Laying | Surrounding | Backfilling Project Engineer 1 Sinior quantity surveyor 1
Phase -01 SWD MH Exca | Base | Wall | Foam Concrete | Concrete Cover Slab | Bacfilling Sr. Planning Engineer 1 Senior QA/QC Engineer 1
TSE Granular Surround | Backfilling Gully Exca | Connection and Concreting Planning Engineer 1 Environmental Specialist 1
Road Excavation | Formation TSE TSE trench; Excavation, Pipe Laying, Surrounding & Backfilling Commercial / Contracts Manager 1 CAD Technician 1
Road Road Kerbs |Aggregate Road Base | Sub-Grade | Asphalt Road Base Sr.Quantity Surveyor 1 Senior Works Inspector 3
Duct Excavation | Pipe Laying | Backfilling Quantity Surveyor 2 Quantity Surveyor 1
ITS Excavation | Concrete work for ITS Chambers QA/QC Engineer 2 Stakeholder Management Engineer 1
QA/QC Inspector 1 Site Engineer 3
Phase -02 Work Order - 08: Katara Signalized Pedestrian Crossing Senior Material Engineer 1 Publicity Officer 1
SWD Gully Excavation |Manhole Excavation | Connection and Concreting General Safety Arrangement and House Keeping Environmental Officer 1 Material Engineer 1
TSE Trench Excavation | Pipe Laying | Surrounding | Backfilling LV: Backfilling Traffic Engineer 1 Land Surveyor 1
HSE Engineer
Duct Excavation | Pipe Laying | Backfilling Road Kerb and Interlock Paving HSE Engineer 2 1
Work Order - 10: Ministry of Education & Higher Education HSE Officer 4 Senior Works Inspector 1
General Safety Arrangement and House Keeping Senior Draftsman 2 Admin Staff 1
SWD Grating Channel: Concrete Cover Slab | Precast Works | Tie-in Work Land Surveyor 2
Site Engineer 4
PRO/PRR 1
Secretary 1
Document Controller 1
Foreman 4
Store Keeper 2
Areas Of Concern
01. Aditional works by QNBN for the ITS & QNBN works. 09. Claim against Engineer's Instruction to provide additional Engineer's site offices and offices equipment.
WO-06
02. Renewal of RO for phase 01. 10. Claim against Engineer's instruction to procure backfilling, subgrade, subbase from QPMC exclusively.
03. SWD Trench collapsed due to unstable soil condition interrupting the flow of work progress leading for delay. 11. ESD recommendations for new rates did not consider for the allocation of the items in bill wise.
WO-07
04. Delay in obtaining RO has negative impact to whole WO-07 by time and cost.
05. Change request for completion date: waiting response.
WO-08
06.Waiting for electrical shutdown to energized pedestrian crossing light.
07. Unreasonable recommendations by GEIC/ESD for new rates.
08. The new rates submitted by MRTC for dewatering works in WO-#6&7, GEIC/ESD state the rate is included item in bill 1. The cost environmental
controls cannot be included for dewatering.
Checked by GEC SRE/RE (Verify information) For RPD : Review & Final acceptance
Prepared by MRTC - Contractor
Signature: Signature: Signature:
Name: ENGR. KHALED SHOEIB Name: ENGR. JACOB MATHEWS Name:
Designation: Project Manager Designation: Resident Engineer Designation:
Guidance Note:
1) Project Daily Report to be completed accurately and on daily basis by GEC
2) All applicable sections to be completed by GEC
Client: GEC Main Contractor Contract Start Date 26-Apr-20 HSE QUALITY
Project Daily Report Safety Incidents:
Testing and any other details:
Project Duration (days) 1095
PWA-RPD-CON-FM-1507 ROADS PROJECTS DEPARTMENT Project Completion Date 25-Apr-23 Manhours without fatality:
Rev. : 2 Date : Jan. 2019 Project Days Elapsed 436 Environmental Incidents:
PROJECT TITLE: Approved New Contract Completion Weather Report Humidity: Temperature (oC)
INTERIM ROAD IMPROVEMENT DOHA SOUTH - PHASE 02 5-Jul-21 DATE with extension Sunny Cloudy Rain Sandstorm Windy Max. Min.
(if applicable) :
Report No.
Project No. SA032 SDR_PH02_322 Contract Code: C2020/33 43 C 34 C
3) Completed Project Daily Report to be verified by GEC project specific SRE/RE
4) Completed Project Daily Report to be submitted Daily by GEC to RPD