N7 Tools
N7 Tools
New 7
Quality
Control
Tools
N7 Quality Tools
(Planning & Management Tools)
Matrix Data
Analysis Chart
Gathers large amounts of language data into a logical
way making them into systematic order to help you plan
Affinity Diagrams actions
• Sift through large volumes of data
When to Use It? • Encourage new patterns of thinking
Step 1 – Generate ideas
Step 2 – Display ideas
Step 3 – Sort ideas into groups
Step 4 – Create header cards
Step 5 – Draw finished diagram
Step 5 –
Draw finished
diagram
Affinity Diagram
Applications
Develop next generation camera
by organizing customer
complaints and requirements
using Affinity Diagram.
Have a large view
finder screen
Zoom lens
Take pictures inside &
at night
Next Generation Camera
Affinity Diagram
Applications
Lack of skills of Affinity Diagram
employees
Applications
Caffera House formed a quality
circle to find out causes of
defective incoming materials.
Solution
Interrelationship
Digraph
Constructing
Interrelationship
Digraph (Relations
Diagram)
Constructing
Interrelationship
Digraph (Relations
Diagram)
Potential causes of poor quality
1/1 1/1
0/1
1/1
0/1
4/1 2/2
3/0
0/1
In/Out 5/0
1/1
1/4
1/1 0/1
0/1
1/1
Source: Nayatani, Y., The Seven New QC Tools (Tokyo, Japan, 3A Corporation, 1984)
Tree Diagrams
•
When to use TD?
• Issue is known
• Developing actions
• Analyzing processes in detail
• Probing for the root cause of
a problem
• Evaluating implementation
issues for several potential
solutions
• After an affinity diagram or
interrelationship diagram has
uncovered key issues
Constructing a Tree Diagram
Matrix Diagrams
idea/issue in one or more other groups of items.
a table that allows sets of data to be compared in order
to make better decisions
Matrix Diagrams – cont.
• Displays the existence and
strength of relationship
between pairs of items of two
or more sets.
• Can be used as part of other
decision-making tools (e.g. CED
and QFD)
13
12
2
13
3
12 2 10 15 4
Analysis???
Matrix Diagrams Examples
Procedure
Construct • Construct a two-dimensional table.
Work through
• Work through the matrix and discuss the
relationships between every pair of items.
Procedure – cont.
Place the appropriate Give weighted scores to
symbol at the intersecting show relative importance of
cell of the matrix. items.
1
Matrix Diagram Growth Mindset Challenge:
A restaurant manager wants to improve customer’s dining
experience!
Matrix Diagram Challenge cont.
How would you fill in the matrix?
Improve customer's dining experience
FACTORS TOTAL
Food
Staff
Atmosphere
Increase Budget
Improve Quality
Improve Quality
Decrease Menu
for Decorations
Increase Menu
of Service
Add Staff
OPTIONS
Choices
of Food
Prices
+ High (5)
= Medium (3)
- Low (1)
shows the connection (or
correlation) between each
idea/issue in one or more other
organizes a large number of ideas groups of items
into their natural relationships.
Arrow Diagrams
Used to plan the most appropriate schedule for any complex task and
all of its related subtasks.
Arrow Diagrams – cont.
Task 1 Task 2
Determine Task
times and Critical 2 days 3 days
4 days
Task 4 Task 5
1 day 2 days
Activity Duration
Earliest start (ES) = earliest time at which an
activity can start, assuming all
predecessors have been
completed
Earliest finish (EF) = earliest time at which an
Perform a Critical activity can be finished
Path Analysis
Latest start (LS) = latest time at which an activity
can start so as to not delay the
completion time of the entire
project
Latest finish (LF) = latest time by which an activity
has to be finished so as to not
delay the completion time of the
entire project
Earliest Start Time Rule:
EF = ES + Activity time
Example
ES EF = ES + Activity time
Start
0 0
0
EF of A =
ES ES of A + 2
of A
A
Start 0 2
0 0
2
A
0 2
2 EF of B =
ES ES of B + 3
0
Start
0 of B
B
0 0 3
3
A C
0 2 2 4
2 2
Start
0 0
= Max (2, 3) D
0
3 7
B
0 3
3
4
A C
0 2 2 4
2 2
Start
0 0
B D
0 3 3 7
3 4
Activity Name
or Symbol
Calculate forward Earliest
A Earliest
pass (ES & EF) as Start
ES EF Finish
well as backward
pass (LS & LF) for LS LF
Latest Latest
each task. Start 2 Finish
Activity Duration
Latest Finish Time Rule:
If an activity is an immediate predecessor
for just a single activity, its LF equals the
LS of the activity that immediately follows
Backward Pass it
If an activity is an immediate predecessor
to more than one activity, its LF is the
minimum of all LS values of all activities
that immediately follow it
LS = LF – Activity time
LS/LF Times Example
A C F
0 2 2 4 4 7
2 2 3
Start E H
0 0 4 8 13 15
13 15
0 4 2
B D – Activity time
LS = LF G
0 3 3 7 8 13
3 4 5 LF = EF
of Project
LS/LF Times
LS/LF Example
Times Example
A C F
0 2 2 4 4 7
10 13
2 2 3
Start E H
0 0
LF =4 Min(LS
8 of 13 15
following activity) 13 15
0 4 2
B D G
0 3 3 7 8 13
3 4 5
LF = Min(4, 10)
A C F
0 2 2 4 4 7
2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
8 13
3 4 5
A C F
0 2 2 4 4 7
0 2 2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
Slack: the length of time an activity
can be delayed without delaying the
Calculate the entire project
slack time for
each activity
Slack = LS – ES or Slack = LF – EF
Arrow Diagram Example
Flawless Paper Products Manufacturing, Inc.
(FPPMI) located in Pasig City has long been
trying to avoid the expense of installing air
pollution control equipment in its facility.
The DENR has recently given the
manufacturer 16 weeks to install a complex
air filter system. FPPMI has been warned
that it may force to close the facility unless
the devise in installed in the allotted period.
Kristoffer Cruz, the plant manager, wants to
make sure that installation of the filtering
system progresses smoothly and on time.
Immediate
Activity Description Predecessors
A Build internal components —
B Modify roof and floor —
Activities and
C Construct collection stack A
D Pour concrete and install A, B
Predecessors frame
E Build high-temperature C
burner
F Install pollution control C
system
G Install air pollution device D, E
H Inspect and test F, G
FPPMI’s Activities with Task Time
Activity A
A (Build Internal Components)
Start
Activity B
Start B (Modify Roof and Floor)
Activity
PROJECT’S PRECEDENCE DIAGRAM
A C
Start
B D
Activities A and B
Precede Activity D
PROJECT’S PRECEDENCE DIAGRAM
F
A C
E
Start H
B D G
A C F
0 2 2 4 4 7
0 2 2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
Computing Slack Time
Earliest Earliest Latest Latest On
Start Finish Start Finish Slack Critical
Activity ES EF LS LF LS – ES Path
A 0 2 0 2 0 Yes
B 0 3 1 4 1 No
C 2 4 2 4 0 Yes
D 3 7 4 8 1 No
E 4 8 4 8 0 Yes
F 4 7 10 13 6 No
G 8 13 8 13 0 Yes
H 13 15 13 15 0 Yes
Slack = LS – ES or Slack = LF – EF
Arrow Network Growth Mindset Challenge
A network consists of the following list. Times are given in weeks.
Process
Decisions
Program
Charts
Process
Decisions
Program
Charts
Used to plan various contingencies
Process
Steers events in required direction if
Decisions
unanticipated problems occur
Program Charts
Finds feasible counter measures to
For producing the overcome problems
desired result from
many possible
outcomes
PDPC Growth Mindset Challenge
1 2 3
A structural engineering project A kitchen hygiene improvement A mailroom project to improve
manager uses it to help find team uses PDPC to check for delivery times uses it to help check
problems in a plan for constructing possible areas where infection the proposed solution, checking in
a road bridge. could come into contact with particular that it will not have any
consumable foodstuffs. An side-effects that might upset other
individual sub-project is then processes.
spawned for all identified danger
areas.
N7 Q.C. Tools
Matrix Data Analysis
Non- Partially
STEP 3: DRAW A CHART
AND PUT ALL THE DATA
STEP 4: ANALYZE THE
GRAPH BASED ON THE
Desirable Desirable
IN X AND Y GRAPH QUADRANT.
Score
Dishes Visual Score
MDAC Example Attractiveness Taste
Visual
Analysis???
Macaroni (8,8)
Papdi (8,7)
Visual
Different Dishes
Macaroni (8,8)
Desirable
Analysis??? Dishes
Papdi (8,7)