Steel Frame 3
Steel Frame 3
A MAIN SUMMARY
Contingency 5%
GRAND TOTAL
Rate Amount
Item Description Qty Unit
A Bill No : 01 - PRELIMINARIES
A.1
The contractor shall provide and maintain temporary sheds for the
storage of materials, tools, and tackle and the use of all persons
employed on the Site. Those used for the storage of cement and other
perishable materials and the like are to be weatherproofed at all times 1 Item
A.4 Allow for provision of water for the works including drinking water,
and paying all charges and other expenses in connection with the
supply from water mains or any other alternative method of water
supply, storage and distribution. It is the sole responsibility of the
contractor to ensure steady, uninterrupted adequate supply of water
required for main contract and nominated sub contract work.
1 Item
A.5 Allow for providing and maintenance of name board and advertising
board to the specifications and as directed by the Engineer.
1 Item
A.7 Allow for any other item necessary for the proper execution of the
works and not listed in the items above ( Please Provide a detailed
List below) 1 Item
CONTENTS
C Concrete Work
D Masonry Work
H Metal Work
L Painting Work
M Electrical Installation
N Provisional Sums
SUMMARY
Bill No. 02
C Concrete Work
D Masonry Work
K Painting Work
M Electrical Installation
N Provisional Sums
C CONCRETE WORKS
In Situ Concrete
Formwork as specified : to
Reinforcement
Lintel
COLLECTION
Page -2
Page-3
D MASONRY WORKS
Masonry Work
Up to DPC level
D.3a Ditto: 150mm Thick walls for toiltets and work top 11 m²
F STRUCTURAL METALWORKS
Definitions
a.01 All, rivets, nails, clips, strips and delivering and fixing in
position. Note
a.02 All timber shall apply Priming backs & applying two
coats of an approved wood preservative before fixing.
Note
Roof Covering
Ridges
G.6 Supplying & fixing of 110 dia PVC rain water down
pipes with metal straps to concrete block work at
1000mm centres vertically 220 m
c.02 Brass Nails, Brass screws, glue, rawl plugs etc,. Note
c.07 Rate shall include for 5mm thick clear float glass/ wired
glass /tinted glass /translucent glass as appropriate to suit
the respective doors and windows as shown in the
drawings. Note
c.08 Rate shall include for ply wood sheets of approved colour
with melamine coat on both sides where necessary.
Note
c.09 Rates shall include for fixing timber frame, door sash /
window casement brass fixing screws, lock sets with 3
keys manufactured in Europe to be used on all doors.
f Preservative Treatment
g Sizes
h Ironmongery
Timber Doors
H.1 32mm thick wood work double leaf door set, type D3, of
size 900x2500mm high overall, comprising of timber
door frame & timber ledged, braced & battened door
sash : include for all necessary door locks, iron mongery,
final finish, & fixing to concrete or blockwork
21 Nos.
H.2 32mm thick wood work single sash door set, type D4, of
size 800x2250mm high overall, comprising of timber
door frame & timber ledged, braced & battened door
sash : include for all necessary door locks, iron mongery,
final finish, & fixing to concrete or blockwork
5 Nos.
Metal doors
COLLECTION
Page -9
Page -10
Wall Finishes
J.1 20mm thick cement & sand (1:5) plaster finished semi
rough with wood float on external faces, on blockwalls
or concrete surfaces 614 m²
Floor finishes
J.3 20mm. thick cement and sand 1:3 screed finished smooth
with coloured cement floating. 290 m²
J.3a 500mm x 500mm porcelain floor tiles for toillet ,
Laboratory and work tops inclusive skirting 320 m²
J.3b 200mm x 300mm ceramic floor and wall tiles for toillet ,
Laboratory and work tops 20 m²
Plinth Plaster
J.4 20mm. thick cement and sand 1:3 plinth plaster finished
smooth with coloured cement floating. 190 m²
Ceiling Finishes
K PAINTING
Walls
K.1 Prepare and apply one coat of primer and two coats of
weather shield paint of approved colour and quality to
external faces of walls 614 m²
K.2 Prepare and apply one coat of primer and two coats of
vinyly silk paint of approved colour and quality to
internal faces of walls 1225 m²
K Painting To Summary
Plumber
d.02 Cutting and waste of pipes etc., and joining pipes. Note
d.05 Casing to brick walls etc. and making good all works
disturbed. Note
L.10 Excavation and back fill to pipe trench for normal pipe
laying areas, depth not exceeding 1.0m deep as per detail
drawing. (Rate shall include for screed concrete work)
100 m
Sanitary Fittings
L.11 Supplying & fixing of squatting pan with 'S' or 'P' trap
outlet approved colour, complete with and fittings , drop
pipe, flexible connections and necessary water
connection etc. 4 Nos.
L.11a Supplying & fixing of Wash hand basins with 'S' or 'P'
trap outlet approved colour, complete with and fittings ,
drop pipe, flexible connections and necessary water
connection etc. 12 Nos.
L.11b Supplying & fixing of Dobby Sink sixe 550mm x
350mm with 'S' or 'P' trap outlet approved colour,
complete with and fittings , drop pipe, flexible
connections and necessary water connection etc. 4 Nos.
L.11c Supplying & fixing of Shower with 'S' or 'P' trap outlet
approved colour, complete with and fittings , drop pipe,
flexible connections and necessary water connection etc.
2 Nos.
COLLECTION
Page - 14
Page- 15
M ELECTRICAL INSTALLATIONS
13ASocket Outlet
Light Fittings
Earthing Arrangement
COLLECTION
Page - 13
Page- 14
N PROVISIONAL SUMS
CONTENTS
C Concrete Work
D Masonry Work
J Finishes
K Painting
M Electrical Installation
N Provisional Sums
Lot 3:Bill 3-Bill of Quantities for Construction of Toilets in Blood Bank in Malakal Hospital
Upper Nile
CONTENTS
C Concrete Work
D Masonry Work
J Finishes
K Painting
M Electrical Installation
N Provisional Sums
Rate Amount
Item Description Qty Unit
Bulk excavations
B.2 Excavation for pits not exceeding 1.5m deep from the stripped
level in any material except rock : include removal of excavated
material and depositing where directed: approximately 100m
away 14 m³
B.3 Ditto: over 1.50metres deep but not exceeding 3.0metres deep
from the stripped level 19 m³
B.4 Ditto: over 3.00metres deep but not exceeding 4.50metres deep
from the stripped level 19 m³
B.5 Ditto: over 4.50metres deep but not exceeding 6.00metres deep
from the stripped level 19 m³
B.6 Ditto: over 6.00metres deep but not exceeding 7.50metres deep
from the stripped level 1 m³
Water disposal
B.8 Allow for keeping all excavations from all types of water
including rain and spring water by pumping or through any
method 1 item
C CONCRETE WORKS
In Situ Concrete
Formwork
C.10 Lintel size 200 x 150 mm in cross section :including 4No. T10
bars and R 6 links at 100mm centres, complete with all formwork:
as per Drawing 126-ST 009 A 5 m
D MASONRY WORK
a Rate shall include for lifting, handling, weighting all rough and
fair cutting, plumbing angles, normal straight cutting, forming
rebated reveals and raking out joints for plastering.
Note
Up to DPC level-Substructure
D.1 225 mm Thick solid concrete block walls: bedded and jointed in
cement and sand (1:4 ) mortar to steps 5 m²
F STRUCTURAL METALWORK
Definitions
b.2] All welds are 6mm thick fillet weld & allowance for rolling
margin. Note
b.5] Cutting to size and shape and joints in the running length. Note
b.7] Machine drilled bolt, holes, bolts, nuts and washers, cleats,
shoe and gusset plates and all other connections. Note
b.8] After fabrication wire brushed to clean the all steel surfaces
and spray painted with two coats of quick drying metal primer
zinc phosphate & two coats of matt anti corrosive with necessary
accessories. Note
Roof structures
F.1 Roof truss spanning 1500mm wide; tappered all as per Drawing
126-WS 401 3 No
Purlins
F.3 Allow sum for any other item required for the construction and
completion of the roof framework, which are not covered under
the above items ( The items will have to be approved and paid
accordingly ) 1 Item
a.01 All, rivets, nails, clips, strips and delivering and fixing in position.
Note
a.02 All timber shall apply Priming backs & applying two coats of an
approved wood preservative before fixing. Note
a.03 All timber shall have final finish; Two coat of wood preservative,
two coats of primer, two coats of wood sheen spray paint.
Note
Roof Covering
Roof drainage
G.3 Supplying & fixing of PVC eave gutters of cross section 200mm
x 200mm ( 680mm girth (average) : bolted to valance board:
internal support brackets 6 m
G.4 Supplying & fixing of 110 dia PVC rain water down pipes:
fixed to concrete block work with metal straps at 1000mm centres
vertically 7 m
b.01 Outer frame & Inner frame - 75mm x 100mm minimum - Finish
Size, unless otherwise stated. Note
b.02 The contractor shall submit shop drawings for the approval of the
Architect & Engineer, prior to fabrication. Note
b.05 Where swing doors has been specified prices shall include for
provisions of floor hinges. Note
c.01 Hoisting and fixing in position, drilling and making good. Note
c.02 Brass nails, brass screws, glue, rawl plugs etc,. Note
c.03 Framing together all work in accordance with the best practices. Note
c.05 Final Finish; Two coat of wood preservative, two coats of primer,
two coats of wood sheen spray paint. Note
c.06 Rate to include for providing sundry items related to the door &
windows like glass blocks etc.. where necessary as a
Architectural feature to the door or window. Note
c.07 Rate shall include for 5mm thick clear float glass/ wired glass
/tinted glass /translucent glass as appropriate to suit the respective
doors and windows as shown in the drawings. Note
c.08 Rate shall include for ply wood sheets of approved colour with
melamine coat on both sides where necessary. Note
c.09 Rates shall include for fixing timber frame, door sash / window
casement brass fixing screws, lock sets with 3 keys
manufactured in Europe to be used on all doors.
f Preservative Treatment
f.02 Preservative treatment for back of door & door frame in contact
with masonry or concrete. Note
g Sizes
g.01 The sizes given in the drawings and description of Bill of
Quantities are finished sizes and subject to same permitted in
the specifications. Note
g.02 The contractor shall check the measurement of openings
physically at the site before fabricating the doors & windows.
Note
J FINISHES
b The rate shall include for all temporary rules, screeds, grounds
etc. for raking out joints of new brick work or hacking new
concrete for key, internal & curved angles, joints between
different surfaces arises quirks, inter sections between curved or
irregular surfaces, etc. and all making good around pipes, sanitary
fittings & the like. Note
0 Wall Finishes
J.2 12mm thick cement lime sand (1:1:5) plaster finished smooth
with lime putty or concrete or blockwork: to surfaces of internal
walls 57 m²
Floor finishes
J.3 50mm Thick cement and sand (1:3) screed : steel trowelled hard
and smooth to internal floors 12 m²
Plinth Plaster
J.4 20mm Thick cement and sand (1:3) render : wood floated hard
and smooth to plinths: externally 4 m²
J Finishes To Summary
K PAINTING
Wall Painting
K.1 Prepare and apply one coat of primer and two coats of exterior
quality weather shield paint of approved colour and quality to
rendered external surfaces of walls and concrete.
36 m²
K.3 Prepare and apply one coat of primer and two coats of interior
quality emulsion paint of approved colour and quality to
plastered internal faces of walls and concrete. 57 m²
K Painting To Summary
d.02 Cutting and waste of pipes etc., and joining pipes. Note
d.03 All specials such as elbows, bends, tees, junctions, plugs, reducers
and similar pipe fittings except for valves which will be measured
separately. Note
d.05 Casing to brick walls etc. and making good all works disturbed.
Note
e.01 Fittings such as taps, waste water outlet, internal overflows etc.
and supporting brackets, incidental materials for fixing, unless
otherwise measured separately. Note
f.03 All pipe specials such as bends, junctions, elbows, tees etc.
Note
f.06 Giving notices, obtaining permits, paying fees, fixing, testing and
commissioning etc. Note
Bib Tap
Angle valve
Isolating valves
Vent Pipes
L.9 Excavation and back fill to pipe trench for normal pipe laying
areas, depth not exceeding 1.0m deep as per detail drawing. (Rate
shall include for screed concrete work) 24 m
M ELECTRICAL INSTALLATIONS
Rates for final circuit wiring shall include all necessary switches,
sockets, materials Cables, conduits, PVC sunk box, & junction
boxes, draw wires, etc. and labour required to complete the
electrical installation to good working order.
N PROVISIONAL SUMS
Site Works
Page Total
Carried to
Collection
B.15 Allow for water recharge testing for bore hole yield
for at least 36 hours including records of the yields
at one hour intervals ( The contractor is to provide
for power for this process)
1 item
Page Total
Carried to
Collection
D.2 Allow the P.C Sum for the Supply & installation of
Water supply pump set, one duty & one stand by
capacity 2 kw including valves & pipes as
manufactured in either Denmark, UK, USA , Japan
or approved by the Engineer.
1 item
E WATER TANK
F PROVISIONAL SUMS