This document provides a progress report for the second billing period of the construction of a general hospital's diagnostic building in San Pedro, Cabusao, Camarines Sur. It details the percentage of work completed and corresponding costs for 17 items. To date, 75.1034% of the work has been completed, with 35.0339% finished in the previous period and 40.0696% in the current period. The total value of work accomplished so far is PHP14,237,155.58 out of the PHP18,956,727.52 project budget.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
48 views

Accomplishment Report

This document provides a progress report for the second billing period of the construction of a general hospital's diagnostic building in San Pedro, Cabusao, Camarines Sur. It details the percentage of work completed and corresponding costs for 17 items. To date, 75.1034% of the work has been completed, with 35.0339% finished in the previous period and 40.0696% in the current period. The total value of work accomplished so far is PHP14,237,155.58 out of the PHP18,956,727.52 project budget.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Project Title : CONSTRUCTION OF GENERAL HOSPITAL PHASE 1- DIAGNOSTIC BUILDING

Location : San Pedro, Cabusao, Camarines Sur


STATEMENT OF WORK ACCOMPLISHMENT (2ND PROGRESS BILLING)

No. Description Total Cost Rel. Wt Relative Wt. Accomplishment % Work Accomplishment Value of Accomplishment

Previous This Period To Date Previous This Period To Date Previous This Period To Date

I GENERAL REQUIREMENTS 105,052.50 0.5542% 0.2771% 0.2771% 0.5542% 50.00% 50.00% 100.00% 52,526.25 52,526.25 105,052.50

II SITEWORKS 542,272.11 2.8606% 2.4378% 0.4228% 2.8606% 85.22% 14.78% 100.00% 462,120.05 80,152.06 542,272.11

III STRUCTURAL STEEL WORKS 1,608,704.53 8.4862% 8.4180% 0.0682% 8.4862% 99.20% 0.80% 100.00% 1,595,773.98 12,930.55 1,608,704.53

IV CONCRETE WORKS 1,621,666.22 8.5546% 8.0378% 0.5168% 8.5546% 93.96% 6.04% 100.00% 1,523,696.56 97,969.66 1,621,666.22

V MASONRY WORKS 1,749,510.93 9.2290% 8.5293% 0.6996% 9.2290% 92.42% 7.58% 100.00% 1,616,883.27 132,627.66 1,749,510.93

VI ROOF AND ROOF FRAMING WORKS 2,043,869.54 10.7818% 6.0284% 4.4590% 10.4874% 55.91% 41.36% 97.27% 1,142,785.45 845,289.64 1,988,075.09

VII CEILING WORKS 1,184,409.72 6.2480% 0.0000% 6.1291% 6.1291% 0.00% 98.10% 98.10% - 1,161,877.32 1,161,877.32

VIII DOORS AND WINDOWS 1,566,589.33 8.2640% 0.0000% 2.1497% 2.1497% 0.00% 26.01% 26.01% - 407,510.67 407,510.67

IX TILE WORKS 3,124,177.06 16.4806% 0.0000% 16.3313% 16.3313% 0.00% 99.09% 99.09% - 3,095,879.32 3,095,879.32

X PAINTING WORKS 386,499.75 2.0389% 0.0000% 1.2953% 1.2953% 0.00% 63.53% 63.53% - 245,539.85 245,539.85

XI ELECTRICAL WORKS 1,548,260.08 8.1673% 0.0000% 0.5580% 0.5580% 0.00% 6.83% 6.83% - 105,778.86 105,778.86

XII PLUMBING/SANITARY WORKS 1,619,498.40 8.5431% 0.0000% 6.1122% 6.1122% 0.00% 71.54% 71.54% - 1,158,667.86 1,158,667.86

XIII CARPENTTRY WORKS 289,884.66 1.5292% 0.0000% 0.0000% 0.0000% 0.00% 0.00% 0.00% - - -

XIV RAILINGS/HANDRAIL 36,120.44 0.1905% 0.0000% 0.0000% 0.0000% 0.00% 0.00% 0.00% - - -

XV MECHANICAL WORKS 1,066,973.79 5.6285% 0.0000% 0.0000% 0.0000% 0.00% 0.00% 0.00% - - -

XVI LANDSCAPING WORKS 153,880.11 0.8117% 0.0000% 0.7241% 0.7241% 0.00% 89.20% 89.20% - 137,261.97 137,261.97
XVII FORMS AND SCAFFOLDINGS 309,358.35 1.6319% 1.3055% 0.3264% 1.6319% 80.00% 20.00% 100.00% 247,486.68 61,871.67 309,358.35

TOTAL 18,956,727.52 100.0000% 35.0339% 40.0696% 75.1034% 35.03% 40.07% 75.10% 6,641,272.24 7,595,883.34 14,237,155.58

Prepared by :

MACARIO P. APIN II
MJ Apin Builders-Manager