Introduction To Pile Foundations 01
Introduction To Pile Foundations 01
PILE FOUNDATIONS
by
Dr. L. I. N. de Silva
Module Outline
3
Types of foundations
Df
B Soft soil
Df < B
(Terzaghi)
Hard soil
4
Pile foundations
Piles are used when the soils close to the surface are too weak or too
compressible to allow for shallow foundation
Piles are used to carry either,
High vertical downward loads High uplifting loads High lateral loads
P P
P
Skin Friction, Qs
Skin Friction, Qs
resistance
The movement required
Passive
to mobilize the ultimate
shaft friction is in the
order of 0.3% to 1% of
the pile diameter.
End Bearing, Qb
Relative magnitudes of Qs and Qb depend on the
The movement required to mobilize soil condition and depth
the ultimate base resistance of the If Qb is dominant, the pile is known as end bearing
pile is in the range of 10% to 20% of pile and if Qs is dominant it is known as friction pile
the base diameter 6
Types of deep foundations
There are number of classifications available for different types of pile
foundations
8
Types of deep foundations
2. Based on the effect it has on ground
q They are preformed at the surface and driven into the ground. These
piles are made of timber, concrete or steel.
q Pile toe and head should be protected during driving by appropriate shoe
and helmet, respectively.
q In Sri Lanka, Hora, Rubber and Coconut tree trunks are widely used as
timber piles
Displacement piles
Preformed piles
1.1 Timber piles and accessories
Displacement piles
Preformed piles
1.1 Timber piles and accessories
Displacement piles
Preformed piles
1.1 Timber piles and
accessories
Displacement piles
Preformed piles
2. Concrete piles
q There are two types of concrete piles namely, reinforced concrete piles and
prestressed concrete piles. They are usually of square, triangular, circular
or octagonal section
q Prestressed concrete piles are ideal for corrosive and marine environments
q Steel piles are available in various cross sections such as, box piles, tube
piles, H piles and screw piles
q Steel has the advantage of being robust, easy to handle, and strong in
bending, tension and compression. Therefore, it is capable of withstanding
hard driving conditions.
q Corrosion is the biggest problem in steel piling. Therefore, the pile should
be protected against corrosion or a large section should be selected to
allow for corrosion during the service life.
Displacement piles
Preformed piles
3.1 Steel H piles and accessories
Driving the
tube open Clean Fill with
ended inside by Finish
concrete
augur
Displacement piles
Preformed piles
3.3 Screw piles
q Screw piles have large diameter helical screws at the lower end. Piles are
screwed in to the ground using a capstan. Then soil inside is removed and
filled with concrete.
Hammer Parts:
1 - crab
2 - piston
3 - fuel pump
4 - inlet
5 - cylinder
6 - anvil
Stages in Cycle:
I - ram up (start), scavenging
II - termination of scavenging, fuel feed
III - termination of compression stroke,
blow delivered on anvil block, fuel
combustion
IV - termination of fuel combustion,
exhaust, beginning of scavenging
Displacement piles
Pile driving equipment
Vibratory hammers
Hydraulic Jacks
Displacement piles
Pile driving equipment
Types of deep foundations
Displacement piles
Partially preformed piles
q Tube piles and screw piles which were discussed before are also partially
preformed piles.
Hammer blows
Displacement piles
Driving head
Partially preformed piles connected to
mandrel
Example -1
q Number of precast concrete shells are joined
with the help of an internal mandrel and a Precast
concrete shoe is attached at the bottom concrete
shells
q The above system is driven in to ground by Internal steel
giving hammer blows to the driving head mandrel
attached to the internal mandrel
Steel bands
q Once the required depth is reached the with bitumen
seals
mandrel is removed and the reinforcement
cage is inserted
A. A plug of sand / stone is placed in the piling tube and compacted with a
hammer
B. The tube is driven by applying blows of the internal drop hammer to the plug
which arches in the tube and draws the tube into the ground. Internal drop
hammer gives less vibration
C. On reaching the founding level the tube is held by the extracting gear while
the plug is expelled using blows of the hammer.
D. Measured quantities of relatively dry concrete are expelled from the toe of
the tube thus forming an enlarged base.
E. The reinforcing cage is placed in the tube which is then filled with high slump
concrete.
F. The tube is extracted by means of the extraction gear. On deeper piles the
concrete level may have to be topped up during extraction.
Displacement piles
Partially preformed piles
Animation of the
construction of steel
s h e l l a n d c a st i n s i t u
concrete piles
Displacement piles
Partially preformed piles, Some examples
( e g : 2 b ) – S te e l s h e l l a n d ca st I n s i t u
Concrete Piles when the casings are made
of corrugated steel plates
Steel
expandable
A steel expanding mandrel should be mandrel
used to su p p o r t t h e t h i n wa l l e d
corrugated casing.
Steel
corrugated
Then the mandrel and casing is driven
pile
together to the required depth
Disadvantages
q Cannot directly inspect the completed pile. Dynamic testing can be used for
this purpose
q First a hole is created in the ground either by using a continuous flight augur
or a bucket augur/short flight augur connected to a kelly bar
q In most of the cases where bucket or short flight augur is used, a side
support system is required to prevent collapsing of soil in to the hole
q Once the hole is drilled up to the required depth, the base is cleaned
q Then the reinforcement cage is inserted and high slump concrete is placed in
the hole.
q Due to the difficulty in withdrawing casings, sometimes casings are only used
in the upper levels
Non displacement piles
Rotary Bored Piles - equipment
Continuous
flight augur
Kelly bar
Bucket
augur
Short flight
augur
Non displacement piles
Rotary Bored Piles
The percussion tool, consisting of the tripod or shear leg, a winch and the cutter,
are set up. A starter hole is then made by dropping the cutter from the raised
position.
Non displacement piles
Large diameter Bored Piles
Non displacement piles
Rotary Bored Plies- Construction sequence
1. Centering
2. Starting drilling
3. Inserting casing
4. Continue drilling and feeding bentonite
5. Drilling till the specified depth
6. Insert the undereaming tool
7. Undereamin bore hole bottom
8. Measuring depth
9. Setting up iron-reinforcement cage
10. Inserting tremie tube
11. Cleaning the pile bottom by an air-lift
12. Concreting
13. Removal of temporary casing
14.Completing cast-in-place concrete underremed pile
Underreaming Tools
Concreting shall not proceed if the bentonite density at the bottom of the borehole
exceeds 1250 kg/m3.
Specifications for bentonite slurry
Concreting cast in situ bored piles
The time interval between the final cleaning-up and placing concrete should not exceed 6
hours. If there is any delay the depth of the pile bottom should be checked against the
measured drilled depth before placing the concrete to ensure that no soil has fallen into the
hole.
The internal diameter of tremie must be 6 times the maximum size of the aggregate or 150
mm whichever is the greater. The maximum outside diameter of the pipe including joints
should be less than 0.35 times the pile diameter or inner diameter of the casing.
During concreting, the tremie tip must always be immersed 1.50 m below concrete surface
for piles less than 1200 mm diameter and 2.50 m for piles greater than 1200 mm.
The concreting of pile is to be done up to minimum of 300 mm above the cut off level
(overcast) to get good and sound concrete at cut off level.
Concrete casting tolerances above cut-off levels for specified conditions