Project Management: Assignment
Project Management: Assignment
ASSIGNMENT
PROJECT – CONSTRUCTION OF 351 FEET LORD
SHIVA STATUE & ALLIED WORKS IN 16 ACRE LAND
AT NATHDWARA, UDAIPUR, RAJASTHAN.
Submitted By
DRISYA K
Roll No 27
MBA
PROJECT INTRODUCTION
Name of project 351 Feet High Lord Shiva Statue
Objective of project To bring and highlight name of nathdwara on the world
map, to increase tourism
Type of project A mix of infrastructure, bridge, roads, buildings & allied
works
client Tadpadam upwan (Miraj Developers Ltd)
Contractor Shapoorji Pallonji and company
Architect Placekinesis associate
Structural consultant Skeleton consultant pvt. Ltd
MEP consultant Transenergy, Ahmedabad
• Project description – A unique 351 feet high shiva statue in a
very pleasing appearance on an artificial hillock at Nathdwara,
Rajasthan under charitable flagship of Miraj Group.
• It has staircases, elevators and slabs for movement inside the statue.
• The statue has been designed to have all the details, expressions, features and emotions of shiva in
shell concrete itself.
• Single use innovative FRP molds were specially designed & prepared to obtain required features in
the statue.
• Strength testing– Structural stability is checked for earthquake resistance and also for heavy winds
upto 250kmph by wind tunnel analysis at Sydney- Australia
Stages of construction
STAGES OF PROJECT
SANCTION STAGE
PROJECT
BUILDING PERMIT STAGE
CONSTRUCTION STAGE
OCCUPANCY CERTIFICATION
STAGE
PROJECT FEASIBILITY STAGE
• APPROVALS FROM UIT
• *Land Use Plan Approval : For the plot is required from Udaipur Development Authority (UIT) and the Ministry of UD , when the
land is shown s Govt. land in the Mater plan of Udaipur. The land use plan for land area is to be notified by the ministry of UD after
the same is approved by UITs.
• *Approval For Change In Land Use : Approval for change in land use of the plot is required from UIA and the Ministry of UD, when
the land shown in zonal plan (where the plot is located)/ Land allotment letter to be changed. The land use *plan for land area is to be
notified by the Ministry of UD after the same is approved by UIA.
• *NOC For Construction / Augmentation : Of any departmental residential pool accommodation by a Ministry / Department is required
from the Directorate of Estate , Ministry of UD.
PROJECT FEASIBILITY STAGE
• No Objection Certificate : Is required for height clearance of Buildings / Structures / Masts from the Directorate of
Air Traffic Management , Airport Authority of India (AAI), when the project lies within 20 kms . Radius of Air
strips/funnel.
• *No Objection Certificate From L&DO : When the land is lease-hold; owned by L&DO and no construction was
undertaken within the time limit stipulated in the allotment letter.
SANCTION STAGE
• Local Body Approvals : Is required from the local authority ( UIA and Local body) under the provisions of Udaipur Buildings
Byelaws, Master plan of Udaipur and Local Body Acts.
• *Approval From National Monument Authority : No Objection Certificate required from the National Monument Authority ( NMA)
/ Archeological Survey of India (ASI), When the entire project site or part/s of it is within 300meter radius from the declared
boundary of any monument protected under Ancient Monument Act and is under the control of ASI.
• *Approval From Forest Department : Is required from the Forest Department, GNCTD when there is a proposal for tree
cutting/felling and transplantation at the site.
• *Approval From Heritage Conservation committee : Is required from the Heritage Conservation Committee (HCC) when the project
has any link/ relation from the Heritage building and precincts and within their compound.
SANCTION STAGE
• Approval From Road Owning Agency : NOC is required from the Road Owning Agency when cutting of footpath or road or service
lane or Right of way (ROW) is involved.
• Approval From Traffic Police : NOC is required from the Udaipur Traffic Police when the proposal involves disruption of general
traffic movement/ circulation pattern temporarily or permanently during and after the construction of the project.
• Approval From Chief Fire Officer : Approval /Fire Safety Certificate is required from Chief Fire Officer (CFO) / Director, Udaipur Fire
Services for the proposals at layout plan stage as stipulated in the Udaipur building byelaws and National Building Code ( NBC).
• Environment Clearance Is Required From Ministry Of Environment And Forests ( MEF) : State level expert committee for all building
/ construction projects having built up area more than 20000 square meters and area development projects / townships covering am
area more than 50 hectare or built up area more than 1,50,000 square meters.
BUILDING PERMIT STAGE
• Approval/noc/assurance from water supply agency is required for uninterrupted water supply,
drainage and sewage connections.
CONSTRUCTION STAGE
• Permission is required from central ground water authority to abstract ground water.
• Intimation to the local authority : the owner/applicant who has been granted building permit shall
intimate the local authority in writing before 7 days of starting construction.
• Completion cum occupancy certificate from local body before occupation of the building
• Approval from the lift inspector : Noc from lift inspector before granting completion cum
occupancy certificate when lifts are installed in the building.