Achieving The Benefits and Requirements of Integrated Project Delivery Method Using BIM
Achieving The Benefits and Requirements of Integrated Project Delivery Method Using BIM
To cite this article: Mahdi S. Salim and Ahmed Mohammed Raoof Mahjoob 2020 IOP Conf. Ser.:
Mater. Sci. Eng. 901 012033
Abstract. Through the last decade, Integrated Project Delivery (IPD) methodology considers
one of the new contractual relations that are also on the way to further integrate the process of
combining design and instruction. On the other hand, Building Information Modeling (BIM)
made significant advancements in coordinating the planning and construction processes. It is
being used more often in conjunction with traditional delivery methods. In this paper, the
researcher will present the achievement of IPD methodology by using BIM through applying
on the design of the financial commission building in Mayssan Oil Company in Iraq. The
building has not been constructed yet and it was designed by using 2D CAD drawings. The
researcher will redesign the project by using BIM to eliciting the abilities that are consistent
with the requirements and benefits of integrated project delivery (IPD). The results show that
BIM is an appropriate technology that can be used with the IPD method because it has
achieved most of the requirements and benefits of IPD.
1. Introduction
Integrated Project Delivery (IPD) is a new approach, its main requirements is the involvement of the
major project participants from initial phases of the project, and that can be achieved by using BIM.
BIM is a tool that recently adopted by architecture, engineering, and construction industries in the
world. BIM technology provides a precise digital virtual model of building without conflicts or
clashes. It promotes design during all its phases, enabling better control and analysis when the model
completed, it become a curate digital model contains all data that support the construction and other
phases of the project. Using the IPD method with BIM relatively is a new approach to the design and
construction phases of the project [1].
through to deliver the project [4]. The main emphasis in delivering the integrated project is the final
value that has been formed for the structure and the owner, instead of focusing each participant
exclusively on their share of the building without considering the implications of the entire project
process. This IPD system will bring the whole participants together early with cooperative incentives
to maximize the value of the project to the customer. This integrated system will allow participants to
make decisions in early project designing so they can prepare most of the costs. Close teamwork can
get clear of a large waste trade in the scheme, and permit data to be shared simultaneously between the
planning and construction team, which removes a large obstacles to increasing project productivity
[4].
2
International Conference on Geotechnical Engineering-Iraq IOP Publishing
IOP Conf. Series: Materials Science and Engineering 901 (2020) 012033 doi:10.1088/1757-899X/901/1/012033
IPD is the catalyst that allows parties to easily exchange ideas, information, and intellectual
property, and this along with BIM, creates efficiencies throughout the project life. This methodology
also removes the " us vs them " attitude because participants must share protected intellectual property
in another way to achieve project outcomes.
Figure 2. Architectural drawing for the ground floor of the financial commission building.
3
International Conference on Geotechnical Engineering-Iraq IOP Publishing
IOP Conf. Series: Materials Science and Engineering 901 (2020) 012033 doi:10.1088/1757-899X/901/1/012033
and obtain the approval for the budget to prepare the contract documents for bidding. Fig. 3
summarized the current workflow of the designing phase in the department of design.
In general, there is no single model that combines all the components of the building design to
detect conflicts that cause delays in the construction phase. Also, the steps followed in the design stage
suffer from fragmentation and were not characterized by cooperation where each division design their
part and prepare the related bill of quantities without reference to other components of the building
design. This may cause many inconsistencies and errors during the construction phase that result in a
delay in the implementation time and increasing the construction cost of the project due to rework.
Also, the majority of these activities in the design phase were made by correspondence between
departments and between designers while the face-to-face communication may be nonexistent.
Yes
Manually create bill of quantity Manually create bill of quantity for Manually create bill of quantity
for civil works electrical works for mechanical works
Yes
Tendering/Bidding
Figure 3. the current design flow chart for the case study during the design phase.
4
International Conference on Geotechnical Engineering-Iraq IOP Publishing
IOP Conf. Series: Materials Science and Engineering 901 (2020) 012033 doi:10.1088/1757-899X/901/1/012033
7. Application of BIM
The main goal was to fulfill these requirements so that they construct one building collecting all the
departments of the financial commitment to facilitate the communication between them and decrease
the time consumed to perform the transaction. Meeting with most of the stakeholders of the project to
identify the requirements of the building before starting the design process, means involve the
participation of all parties concerned from the early stages of the project. This step will achieve one of
the most important principles of the IPD method (Early Involvement of Key Participants), which
enhances the ability to define the project goals (Early Goal Definition). Thus, creating a long list of
requirements are achieved, and then shorten this list to the requirements only to being creating a
schematic design and produce it to the owner or the requesting body for approval. Then starting the 2D
architectural plan. To redesign the building using BIM methodology, the architectural model will be
allocated after conversion from 2D to 3D as a central file to be imported to create local files to
complete the other components of the building (Structural and MEP design). The design in each local
file will be synchronized to the central file to show all the updates in the central file and show the
work of each other local files in this local file and vice versa. The researcher will apply the flowchart
diagram that illustrated in Fig. 4 to redesign the building using BIM methodology.
5
International Conference on Geotechnical Engineering-Iraq IOP Publishing
IOP Conf. Series: Materials Science and Engineering 901 (2020) 012033 doi:10.1088/1757-899X/901/1/012033
BIM coordinator
Borrower
Synchronize each Synchronize each
local file local file
6
International Conference on Geotechnical Engineering-Iraq IOP Publishing
IOP Conf. Series: Materials Science and Engineering 901 (2020) 012033 doi:10.1088/1757-899X/901/1/012033
file to merge the structural and architectural design in one model. Fig. 6 shows the structural model for
the building.
7
International Conference on Geotechnical Engineering-Iraq IOP Publishing
IOP Conf. Series: Materials Science and Engineering 901 (2020) 012033 doi:10.1088/1757-899X/901/1/012033
The fire alarm system was also represented in the 3D model based on the 2D CAD and the items
description in the bill of quantity. Smoke detectors have represented in the ceiling for each story and
linking them to the 4-zone panel of fire alarm. The electrical and telephone cables will be represented
by draw conduits and marking each conduit to represent a specific cable. The cables included in the
building consist of the cables from the main boards to the sub-panels on each floor, in addition to the
interconnecting cables between the mainboards, as well as the interconnecting cables between the
main boards and the main feeders of the building. The specification of each cable was fixed in the
properties as shown in Fig. 8.
This teamwork in the design phase was done through the work-sharing feature in Revit 2019 that
allowed all team members to communicate and collaborate by exchanging information and
8
International Conference on Geotechnical Engineering-Iraq IOP Publishing
IOP Conf. Series: Materials Science and Engineering 901 (2020) 012033 doi:10.1088/1757-899X/901/1/012033
synchronizing each work to the central model. Therefore, the communication was open between all
parties and mutual trust in addition to mutual understanding and a high degree of coordination
between them that led to the completion of the design of the building in all its domains. This means
that several IPD requirements have been achieved, which are (Collaboration during all phases of the
project, Mutual understanding concerning each other’s objectives, Open communication among
parties, Mutual trust among the parties).
9
International Conference on Geotechnical Engineering-Iraq IOP Publishing
IOP Conf. Series: Materials Science and Engineering 901 (2020) 012033 doi:10.1088/1757-899X/901/1/012033
Figure 11. The view of a clash for pipes and walls clashes detection.
Using BIM methodology in the design phase has immediate and clear benefits. This methodology
requires the collaboration to obtain the benefits of this technique for all participants, which enhances
mutual trust, exchanging of information and open communication. Therefore, most of the
requirements and principles of IPD method have been achieved, so BIM technology can be considered
as the appropriate technology because it catalyzes the processes of the IPD method, and thus fulfills
one of the principles and requirements of IPD method ( appropriate technology).
10
International Conference on Geotechnical Engineering-Iraq IOP Publishing
IOP Conf. Series: Materials Science and Engineering 901 (2020) 012033 doi:10.1088/1757-899X/901/1/012033
the performance of construction projects. Adopting the use of IPD method in the public sector (as a
philosophy), which means adopting this method through its principles because of the difficulty of
creating a contract among all parties, will help in providing better and faster building in the future. As
well as encourage using the IPD method with BIM to obtain the greatest benefit for BIM and helps to
providing faster and excellent buildings.
References
[1] J. Neil, The use of an Integrated Project Delivery Approach in conjunction with BIM, M.Sc.
MSc Building Information Modelling and Integrated Design, University of Salford, 2015.
[2] A.I.A. Guide, Integrated project delivery: A guide. American Institute of Architects, California
(2007).
[3] B.M. Perlberg, Contracting for Integrated Project Delivery: Consensus Docs, The 48th Annual
Meeting of Invited Attorneys, Victor O. Schinnerer & Company, Inc., 2009.
[4] R. Anderson, An Introduction to the IPD Workflow for Vectorworks BIM Users, Nemetschek,
Vectorworks, 2010.
[5] S.A. Rahim, M.N. Mohd Nawi, and F.A.A. Nifa, Integrated project delivery (IPD): A
collaborative approach to improve the construction industry, Adv. Sci. Lett., 22(5–6) 2016
1331–1335.
[6] B. McNamara, BIM: What Can It Do For Me?/Bentley Building Solutions, presented to the
CADD/GIS Center Symposium.
https://tsc.wes.army.mil/symposium/2006/Thursday%5CMcNamara.pdf,” 2006.
[7] A. Mahjoob and M.M. Abed, Assessing BIM Integration with Sustainable Requirement for
Buildings Construction, International Journal of Science and Research (IJSR), 6 2017 2258-
2265.
11