Alarm Verification FOR Incubators (Microbiology, Q-Block)
Alarm Verification FOR Incubators (Microbiology, Q-Block)
:
PURE & CURE ALARM VERIFICATION REPORT
H/GNP/0119
HEALTHCARE FOR REVISION NO.: 00
PVT. LTD., INCUBATORS REPORT No.:
H/GNR/0119
HARIDWAR (MICROBIOLOGY, Q-BLOCK) REVISION NO.: 00
PAGE No.: 1 of 13
ALARM VERIFICATION
REPORT
FOR
INCUBATORS
(MICROBIOLOGY, Q-BLOCK)
1. PRE APPROVAL 3
2. OBJECTIVE 4
3. SCOPE 4
4. RESPONSIBILITY 4
6. SITE OF STUDY 5
7. EQUIPMENTS DETAILS 5
8. SYSTEM DESCRIPTION 5
9. PRE-QUALIFICATION REQUIREMENTS 6
17. CONCLUSION 11
18. RECOMMENDATION 11
19. ABBREVIATIONS 12
PREPARED BY:
OFFICER/EXECUTIVE
(QUALITY ASSURANCE)
REVIEWED BY:
APPROVED BY:
4.0 RESPONSIBILITY:
The verification study group, comprising of a representative from each of the following departments,
shall be responsible for the overall compliance of this report:
DEPARTMENTS RESPONSIBILITIES
Preparation, Review, Approval and Compilation of the
Verification Report.
Co-ordination with Engineering and Production to carryout
Quality Assurance
Verification Activity.
Monitoring of Verification Activity.
Post approval of Activity after execution.
Review of Verification Report.
Microbiology To Execute Verification Activity.
Post review of Verification Report report after execution.
Reviewing of Verification Report for correctness,
completeness and technical excellence.
Responsible for trouble shooting (if occurred during
Engineering
execution).
Maintenance & preventive maintenance as per schedule.
Post review of Verification Report after execution.
2. PC/INS/S-39/02 35-39°C
3. PC/INS/S-39/03 42-44°C
4. PC/INS/S-39/04 55-60°C
5. PC/INS/S-39/05 20-25°C
6. PC/INS/S-39/06 30-35°C
7. PC/INS/S-39/07 20-25°C
8. PC/INS/S-39/08 30-35°C
9. PC/INS/S-39/09 35-39°C
Temperature Sensors
*Training Evaluation
Trainee
S. No Name of Trainee Designation (Satisfactory / Not
(Sign. / Date)
Satisfactory)
Inference:
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
Reviewed By: ______________
Manager QA
Sign/Date
Inference:
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
Inference:
Alarm Verification
Inference:
…………………………………………………………………………………………………………..
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
……
7.0 CONCLUSION:
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
FORMAT NO.: QAH-093/F07-02
PROTOCOL No.:
PURE & CURE ALARM VERIFICATION REPORT
H/GNP/0119
HEALTHCARE FOR REVISION NO.: 00
PVT. LTD., INCUBATORS REPORT No.:
H/GNR/0119
HARIDWAR (MICROBIOLOGY, Q-BLOCK) REVISION NO.: 00
PAGE No.: 12 of 13
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
8.0 RECOMMENDATION:
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
9.0 ABBREVIATIONS:
o
C : Degree centigrade
GNP : General Protocol
GNR : General Report
CC : Change Control
QC : Quality Control
QA : Quality assurance
SOP : Standard operating procedure
ID. : Identification Number
INS : Instrument
Ltd. : Limited
No. : Number
QB : Q- Block
PREPARED BY:
OFFICER/EXECUTIVE
(QUALITY ASSURANCE)
REVIEWED BY:
OPERATING MANAGER
(QUALITY ASSURANCE)
HEAD
(QUALITY CONTROL
/ MICROBIOLOGY)
HEAD
(ENGINEERING)
APPROVED BY:
HEAD
(QUALITY ASSURANCE)