100% found this document useful (3 votes)
1K views

Checklist For Reinforcement:: Doc. No.: QA/CL-REN/: Project Location: Project Client

This document is a checklist for reinforcing a structural project. It contains 15 items to check including verifying bar sizes and placements match plans, lap lengths are correct, chairs and cover blocks are provided, reinforcement is properly cleaned and bound, and test reports have been approved. Upon completion, the quality assurance engineer signs off after inspecting and any remarks are noted.

Uploaded by

CSEC Uganda Ltd.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
1K views

Checklist For Reinforcement:: Doc. No.: QA/CL-REN/: Project Location: Project Client

This document is a checklist for reinforcing a structural project. It contains 15 items to check including verifying bar sizes and placements match plans, lap lengths are correct, chairs and cover blocks are provided, reinforcement is properly cleaned and bound, and test reports have been approved. Upon completion, the quality assurance engineer signs off after inspecting and any remarks are noted.

Uploaded by

CSEC Uganda Ltd.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Checklist for Reinforcement

Project : Doc. No. : QA/CL-REN/


Client : Project Location :

SITE LOCATION DATE

YES NO NA

1 Structural Drg. No. and date as per which reinforcement checked.


Bar Bending Schedule Prepared?

2 Connecting of bars to existing dowels to be checked for alignment. OK?

3 Placing of Bar diameter, number, spacing match with the Construction Schedule?

4 Lap Length, Position of lap, OK?

5 Cleanliness of shuttering and Bars OK?

6 Chairs provided?

7 Cover for reinforcement ok?

8 Provision of cover blocks/ preparation of cover blocks

9 Maintaining records and getting approval for additional reinforcement not shown

10 To check the construction joint for proper concrete bonding before placing
reinforcement
11 Laying of bars of required dia. As per requirement

12 Check for Test Reports for steel and approved brand or not

13 Check colour coding for identification

14 Check for proper binding (double strand/quality of binding wire of 18 SWG)

15 Check for any rework or alteration

Remarks of Quality Assurance Engineer: