0% found this document useful (0 votes)
125 views

Quantity Check

This document is a detailed estimate from the Government of Nepal's Ministry of Urban Development for the construction of a compound wall at the Civil Service Hospital in Kathmandu. It provides itemized estimates for 22 line items related to the excavation, construction materials, reinforcement, and finishing work required. The total estimated cost for the project is NPR 4,556,030.85.

Uploaded by

Rajib Maharjan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
125 views

Quantity Check

This document is a detailed estimate from the Government of Nepal's Ministry of Urban Development for the construction of a compound wall at the Civil Service Hospital in Kathmandu. It provides itemized estimates for 22 line items related to the excavation, construction materials, reinforcement, and finishing work required. The total estimated cost for the project is NPR 4,556,030.85.

Uploaded by

Rajib Maharjan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 222

Government of Nepal

Ministry of Urban development


Department of Urban Development & Building Construction
BABAR MAHAL, KATHMANDU, NEPAL

DETAILED ESTIMATE
F/Y: 2072/073

Project : Construction of Compound wall


Site : Civil service hospital Minbhawan, KTM

Weigh
Length Breadth Height
S.N. Description of Work No. t Kg / Quantity Unit Remarks
m m m
m Code
1 Dismantling of Dismentled
brickwork in cement mortar
including disposal of the debris
out of site .
North side 1 175.0 0.35 3.0 183.75

Total 183.75 cum

2 Earthwork in excavation in
hard/boulder mix soils in
foundation including 10m
hauling distance and 1.5 m. lift
all complete.
Foundation footing 77 1.2 1.20 1.125 124.74
In Fill wall 1 82.6 0.23 0.60 11.39

Total 136.13 cum

3 Local flat brick soiling work with


sand filling.
Foundation footing 77 1.2 1.20 110.88
In Fill wall 1 82.6 0.23 18.99

Total 129.87 sqm

4 Plain cement Concrete (PCC) in


1:3:6 ratio for foundations,
flooring and walls with approved
quality of cement and sand and
crushed stone aggregate
including mixing, laying, curing
etc all complete in approval of
site engineer.

North side 77 1.2 1.20 0.075 8.31


1 82.6 0.23 0.075 1.42

Total 9.73 cum


5 Good quality local chimney
made Brickwork in 1:6 C/S
mortar up to ground floor in
perfect line level finishe
including wetting the bricks,
racking the joints and curing the
work for at least 7 days all
complete.
North side In Foundation 1 157.29 0.23 1.515 54.80

Total 54.80 cum

6 Plain cement Concrete (PCC)


for RCC works (1:2:4) for
slab/lintels with approved quality
of cement and sand and
crushed stone aggregate
including mixing, laying, curing
etc all complete in approval of
site engineer.
Footing 77 1.20 1.20 0.20 22.17
Trapizide 77 0.63 0.20 9.70
Col 77 0.23 0.23 2.10 8.55
FoundationTie 1 157.29 0.23 0.23 8.32
Top Tie 1 157.29 0.23 0.23 8.32

Total 57.06 cum

7 Tor steel reinforcement bar of fe


415/500 grade including
straightening, cleaning, cutting,
binding & fixing in position with
annealed tying binding wire as
per drawing, design &
instruction all complete.

Footing 12mm dia 150 c/c both w 1386 1.500 0.888 1846.15
Col 12mm dia 308 3.100 0.888 847.86
8mm dia sti 1386 0.870 0.395 476.29
FoundationTie 6 187.240 0.888 997.61
8mm dia sti 1176 0.870 0.395 404.13
Top Tie 6 162.240 0.888 864.41
8mm dia sti 1176 0.870 0.395 404.13

Total 5840.58 Kg

8 Formwork, shuttering, centering


with 19mm thick waterproof ply
board and steel post for all
works necessary propping,
scaffolding, staging, supporting
inclusive of wedging and cutting
holes for utilization till the
support if fully unyielding nett.

Footing 77 4.80 0.2 73.92


Col 77 0.92 2.1 148.76
FoundationTie 2 157.29 0.23 72.35
Top Tie 2 157.29 0.23 72.35

Total 367.38 sqm


9 12.5mm thick cement sand
plaster in (1:4) ratio on wall of
good finish including racking the
joint, wetting of surfaces &
curing the work all complete.
Wall in side 1 175.0 1.88 329.00
Col 77 0.23 1.88 33.29

Total 362.29 sqm


10 Fencing with 62mm X 62mm
size mesh made up of 7mm Ø
rods framed on 25X25X4 mm
angles and 50mm Ø M.S.
blackpipe post in 2m interval
including jointting , fixing,
erection and primer painting with
all necessary M.S. grills and
plates as per drawing and inst
(USEING OLD EXISTING
MESH ) About 70.0 Sqm

1 1.00

Total 1.00 job


11 Fencing with 62mm X 62mm
size mesh made up of 7mm Ø
rods framed on 25X25X4 mm
angles and 50mm Ø M.S.
blackpipe post in 2m interval
including jointting , fixing,
erection and primer painting with
all necessary M.S. grills and
plates as per drawing and inst
(USEING NEW MESH )
Same as plaster 1 101.50 1 101.50

Total 101.50 sqm

12 Colouring with 2 coats


waterproof cement paint of
approved colour to give uniform
colouring after rendering the
surface all complete.
Same as plaster 1 362.29 362.29

Total 362.29 sqm


13 2 coats of ready made enamel
paint of approved colour over 1
coats of primer Painting over
porperly sanded wooden
surface all complete
2 175.00 1.05 367.50

Total 367.50 sqm

14 Site clearence work Before and


after work,all complete
1 1.00

Total 1.00 Job

15

Total 0.00

16

Total 0.00

17

Total 0.00

18

Total 0.00

19
Total 0.00

20

Total 0.00

21

Total 0.00

22

Total 0.00

23

Total 0.00

24

Total 0.00

25

Total 0.00

26
Total 0.00

27

Total 0.00

28

Total 0.00

29

Total 0.00

30

Total 0.00

31

Total 0.00

32
Total 0.00

33

Total 0.00

34

Total 0.00

35

Total 0.00

36

Total 0.00

37

Total 0.00

38

Total 0.00

39
Total 0.00

40

Total 0.00

41

Total 0.00

42

Total 0.00

43

Total 0.00

44

Total 0.00

45
Total 0.00

46

Total 0.00

47

Total 0.00

48

Total 0.00

49

Total 0.00

50

Total 0.00

51

Total 0.00

52
Total 0.00

53

Total 0.00

54

Total 0.00
of] kmfOn original file xf] . s[kof tkfO{sf] sfd o;
kmfO{ndf save gug'{ xf]nf . File save_as u/L cs}
. { gfddf save ug'{ xf]nf
x/]s cfO6dsf] hDdf nfO{ Name Box df uO{ gfd lbg'
xf]nf . Gffd lb+bf qt_(Code Number) u/L lbg'
. xf]nf
Abstract df Estimate sf] sequence df code
number lbg' xf]nf . Quantity sell df "=qt_(Code
. Number)" lbg' xf]nf
olb s'g} cfO6d ln:6 eGbf aflx/sf] lbg k/]df sf]8df *
lbg'xf]nf / Description, Unit / Unit rate df ;DjlGwt
. 8f6f lbg'xf]nf

0.485
476.29

404.13

404.13
1284.55
4556.03
49 1.500 1.00 73.50
Page 14 of 222

Government of Nepal
Ministry of Urban development
Department of Urban Development & Building Construction
BABAR MAHAL, KATHMANDU, NEPAL

REVISED DETAILED ESTIMATE


F/Y: 2072/073

Weigh
Length Breadth Height
Description of Work No. t Kg / Quantity Unit Remarks
m m m
m Code
Dismantling of Dismentled
brickwork in cement mortar
including disposal of the debris
1 out of site .
North side 1 159.0 0.35 3.0 166.95

Total 166.95 cum

Earthwork in excavation in
hard/boulder mix soils in
foundation including 10m
hauling distance and 1.5 m. lift
all complete.
2
Foundation footing 48 1.2 1.20 1.125 77.76
In Fill wall 1 58.4 0.23 0.60 8.05 158-42-48*1.2=58.4
1 43.25 0.8 0.8 27.68 42+1.25=43.25
Total 113.49 cum

Local flat brick soiling work with


3 sand filling.
Foundation footing 48 1.2 1.20 69.12
In Fill wall 1 58.4 0.23 13.43

Total 82.55 sqm


4 Pumping out of water from
foundation or pit. 3 43.25 0.8 0.3 31.14 cu.m.
Total 31.14 cu.m.
5 Dry rubble masonry work in
perfect line level finish all
complete.
In Fill wall 1 43.25 0.8 0.3 10.38 cu.m.
Total 10.38 cu.m.
6 Rubble masonry in 1:4 C/S
mortar in perfect line level finish
including, racking the joints and
curing the work for at least 7
days all complete.
In Fill wall 1 43.25 0.7 0.43 12.86 cu.m.

`
Page 15 of 222

Plain cement Concrete (PCC) in


1:3:6 ratio for foundations,
flooring and walls with approved
quality of cement and sand and
crushed stone aggregate
including mixing, laying, curing
etc all complete in approval of
site engineer.
7
North side 48 1.2 1.20 0.075 5.18
1 101.4 0.23 0.075 1.74

Total 6.92 cum

Good quality local chimney


made Brickwork in 1:6 C/S
mortar up to ground floor in
perfect line level finishe
including wetting the bricks,
racking the joints and curing the
work for at least 7 days all
8 complete.
North side In Foundation 1 104.96 0.23 1.67 40.31
1 43.25 0.23 1.195 11.88
Total 52.19 cum

Plain cement Concrete (PCC)


for RCC works (1:2:4) for
slab/lintels with approved quality
of cement and sand and
crushed stone aggregate
including mixing, laying, curing
etc all complete in approval of
9 site engineer.
Footing 48 1.20 1.20 0.20 13.82
Trapizide 48 0.63 0.20 6.04
Col 48 0.23 0.23 2.10 5.33
FoundationTie 2 104.96 0.23 0.23 11.10
1 43.25 0.23 0.23 2.28
Top Tie 1 159.00 0.23 0.08 2.74

Total 41.31 cum

Tor steel reinforcement bar of fe


415/500 grade including
straightening, cleaning, cutting,
binding & fixing in position with
annealed tying binding wire as
per drawing, design &
instruction all complete.
10
a Footing 12mm dia 150 c/c both w 864 1.500 0.888 1150.84
b Col 12mm dia 192 3.100 0.888 528.53
8mm dia sti 864 0.870 0.395 296.91
c FoundationTie 8 128.240 0.888 911.01
8mm dia sti 1176 0.870 0.395 404.13
d Top Tie 2 128.240 0.888 227.75
8mm dia sti 1000 0.100 0.395 39.50

Total 3558.67 Kg
Page 16 of 222

Formwork, shuttering, centering


with 19mm thick waterproof ply
board and steel post for all
works necessary propping,
scaffolding, staging, supporting
inclusive of wedging and cutting
holes for utilization till the
support if fully unyielding nett.
11
Footing 48 4.80 0.2 46.08
Col 48 0.92 2.1 92.73
FoundationTie 4 116.00 0.23 106.72
2 43.25 0.23 19.89
Top Tie 2 159.00 0.08 23.85
Total 289.27 sqm

12.5mm thick cement sand


plaster in (1:4) ratio on wall of
good finish including racking the
joint, wetting of surfaces &
curing the work all complete.
12
Wall 2 159.0 1.88 597.84

Total 597.84 sqm


Fencing with 62mm X 62mm
size mesh made up of 7mm Ø
rods framed on 25X25X4 mm
angles and 50mm Ø M.S.
blackpipe post in 2m interval
including jointting , fixing,
erection and primer painting with
all necessary M.S. grills and
plates as per drawing and inst
(USEING OLD EXISTING
MESH ) About 70.0 Sqm
13
1 1.00 1.00

Total 1.00 job


Fencing with 62mm X 62mm
size mesh made up of 7mm Ø
rods framed on 25X25X4 mm
angles and 50mm Ø M.S.
blackpipe post in 2m interval
including jointting , fixing,
erection and primer painting with
all necessary M.S. grills and
plates as per drawing and inst
14 (USEING NEW MESH )
1 159.00 159.00

Total 159.00 sqm


Colouring with 2 coats
waterproof cement paint of
approved colour to give uniform
colouring after rendering the
surface all complete.
15
Same as plaster 2 159.00 1.88 597.84

sqm
Page 17 of 222

Total 597.84 sqm

2 coats of ready made enamel


paint of approved colour over 1
coats of primer Painting over
porperly sanded wooden
surface all complete
16
2 159.00 1.05 333.90

Total 333.90 sqm

Site clearence work Before and


17 after work,all complete
1 1.00

Total 1.00 Job

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00
Page 18 of 222

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00
Page 19 of 222

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00
Page 20 of 222

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00
Page 21 of 222

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00
Page 22 of 222

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00

Total 0.00
Page 23 of 222

of] kmfOn original file xf] . s[kof tkfO{sf] sfd o;


kmfO{ndf save gug'{ xf]nf . File save_as u/L cs}
. { gfddf save ug'{ xf]nf
x/]s cfO6dsf] hDdf nfO{ Name Box df uO{ gfd lbg'
xf]nf . Gffd lb+bf qt_(Code Number) u/L lbg'
. xf]nf
Abstract df Estimate sf] sequence df code
number lbg' xf]nf . Quantity sell df "=qt_(Code
. Number)" lbg' xf]nf
olb s'g} cfO6d ln:6 eGbf aflx/sf] lbg k/]df sf]8df *
lbg'xf]nf / Description, Unit / Unit rate df ;DjlGwt
. 8f6f lbg'xf]nf
45+70.7+42+1.25=158.95

158-42-48*1.2=58.4 0.485

175-60*12-42=61
Page 24 of 222

175-60*1.2=103

175-60*.23-42=119.20

158-42=116

296.91
17*.72+175-42=145.24
404.13

39.50
740.54 158-48*.23=(146.96)/.15 c/c=980 ~1000
2818.13
Page 25 of 222

49 1.500 1.00 73.50


zx/L ljsf; tyf ejg lgdf{0f ljefu, l8lehg sfof{no, ;'v]{t

lansf] s|d ;+VofM– ;ftf}+ /lgË lan


7]Ssf ;DalGw aLn sfof{De cfb]z ldltM– )^$.)^.@&
of]hgfsf] gfdM– %) z}of c:ktfn ejg lgdf{0f sfo{ , ;'v]{t ;Dem\of}tf ldltM– @)^$.)^.!*
7]s]bf/sf] gfd M– /lagf , cflzif k|lti7f , g]kfn k|utL h]=eL= z}a' , sf7df08f}+ . sfd ;DkGg ug'{ kg]{ ldltM– @)^^.)@.!&-;Dem\of}tfsf] @) dlxgf _yk @)^^.)*.!& ;Dd
7]Ssf k6[fsf] ;+VofM– !) - @)^#÷)^$ _ sfd ;DkGg ePsf] ldltM– rfn'''''''
cl3Nnf] e"QmfgL lansf] s|d;+VofM– gjf} /lgË lan e"QmfgL efpr/ g+=–
cl3Nnf] e"QmfgL ef=g+=M– e"QmfgL ldltM–
gfkL lstfa g+= sf] k[i7 g+=M– b]lv ;Dd
,@= e]l/Pzg kl5sf] Oi6Ld]6
!= ;'?sf] Oi6Ld]6 cg'zf/sf] sfd ,@= sf]
cg'zf/sf] sfd cBfjlw ePsf] sfd
Oi6Ld]6 hDdf jfls
s||=;+= sfdsf] laj/0f PsfO{ jfls sfo{ s}lkmot
kl/df0f b/ hDdf d"No kl/df0f b/ hDdf d"No kl/df0f b/ hDdf d"No cg'zf/ d"No
jfls kl/df0f
A CIVIL WORKS

1 Site Development work


Dismantling of Dismentled brickwork in
1 cement mortar including disposal of the m3 183.75 1158.05 212791.69 166.95 1158.05 193336.45 3799.23 100.00 379922.50 -3632.28 -363227.50
debris out of site .
Earthwork in excavation in hard/boulder mix
2 soils in foundation including 10m hauling m3 2131.88 393.84 839619.62 113.49 393.84 44696.90 2561.44 200.00 512287.80 -2447.95 -489589.80
distance and 1.5 m. lift all complete.

3 Local flat brick soiling work with sand filling. m3 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 3185.34 60.00 191120.22 Err:509 Err:509
4 Pumping out of water from foundation or pit. m3 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 620.11 2500.00 1550270.00 Err:509 Err:509
Dry rubble masonry work in perfect line level
5 finish all complete. ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 106.35 4500.00 478575.00 Err:509 Err:509

Rubble masonry in 1:4 C/S mortar in perfect


6 line level finish including, racking the joints ### 9.73 11262.55 109584.61 0.00 11262.55 0.00 200.77 5655.13 1135403.07 -200.77 -1135403.07
and curing the work for at least 7 days all
Plain cement Concrete (PCC) in 1:3:6 ratio
complete.
for foundations, flooring and walls with
7 approved quality of cement and sand and ### 54.80 10836.94 593864.31 0.00 10836.94 0.00 1008.69 4576.61 4616394.47 -1008.69 -4616394.47
crushed stone aggregate including mixing,
laying, curing etc all complete in approval of
site engineer.
Good quality local chimney made Brickwork
in 1:6 C/S mortar up to ground floor in
8 perfect line level finishe including wetting the
bricks, racking the joints and curing the work
for at least 7 days all complete.
Plain cement Concrete (PCC) for RCC works
(1:2:4) for slab/lintels with approved quality
9 of cement and sand and crushed stone ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 1374.68 6529.70 8976228.40 Err:509 Err:509
aggregate including mixing, laying, curing etc
all complete in approval of site engineer.
Tor steel reinforcement bar of fe 415/500
grade including straightening, cleaning,
10 cutting, binding & fixing in position with ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 618.65 8547.38 5287859.39 Err:509 Err:509
annealed tying binding wire as per drawing,
design & instruction all complete.
Formwork, shuttering, centering with 19mm
thick waterproof ply board and steel post for
all works necessary propping, scaffolding,
11 staging, supporting inclusive of wedging and ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 309496.12 60.51 18727610.22 Err:509 Err:509
cutting holes for utilization till the support if
fully unyielding nett.
12.5mm thick cement sand plaster in (1:4)
ratio on wall of good finish including racking
12 the joint, wetting of surfaces & curing the m2 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 10075.11 313.00 3153509.43 Err:509 Err:509
work all complete.
Fencing with 62mm X 62mm size mesh
made up of 7mm Ø rods framed on 25X25X4
mm angles and 50mm Ø M.S. blackpipe post
in 2m interval including jointting , fixing,
13 erection and primer painting with all
necessary M.S. grills and plates as per
drawing and inst (USEING OLD EXISTING
MESH ) About 70.0 Sqm

Fencing with 62mm X 62mm size mesh


14 made up of 7mm Ø rods framed on 25X25X4 m2 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
mm angles and 50mm Ø M.S. blackpipe post
in 2m interval
Colouring with 2including jointting , cement
coats waterproof fixing,
15 erection and primer
paint of approved painting
colour to give with
uniformall m2 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
necessary M.S. rendering
colouring after grills and the
plates as per
surface all
drawing
complete.and inst (USEING NEW MESH )
2 coats of ready made enamel paint of
approved colour over 1 coats of primer
16 Painting over porperly sanded wooden m2 5840.58 119.29 696722.79 0.00 119.29 0.00 7341.88 120.00 881025.60 -7341.88 -881025.60
surface all complete
Site clearence work Before and after work,all
17 m2 362.29 138.20 50068.48 0.00 138.20 0.00 3118.47 140.00 436585.80 -3118.47 -436585.80
complete
Government of Nepal

Ministry of Physical Planning & works


Department of Urban Development & Building Construction
VARIATION CHART
Project :- 50 Bed Regional Hospital Construction,

Site:-Civil Hospital-Meenbhawan KTM Contract effective date: 2064-6-27 Completed date:

Financed by : Completion date:

Contract No. : - New completion date after this variation:.

Name of Contractor : Sailendra and sons construction Increase or decrease:.Estimate wrt Originnal cost in NRs: NRs. -2841352.33

Name of Consultant/ Office :DUDBC,Head Office, Kathmandu Percentage Increase or Decrease in Estimate: -92.270 % (+)

Original Cost Estimate in NRs. : 3079385.68 Increase or decrease in contract amount in NRs. : (+) NRs. 0.00

Original Contract Amount in NRs. : 0.00 Percentage of Increase or Decrease wrt Original Contract Amount : (+) #DIV/0!

Revised Cost Estimate in NRs. : 238033.35 Percentage Increase or Decrease in new contract amount wrt Original Estimated Amount :(+) -100.000

Revised Contract Amount in NRs. : 0.00 Budget Sanction for increased works (Govt/Foreign) :

S.N. Item Unit Original Cost Estimate in NRs. Revised Cost Estimate(till date) in %age Original Contract Amount New Contract Amount % Change in % Change in Remarks
NRs. Change of in NRs. after this Variation in Original Original
work NRs. Contract Estimated
Quantity Amount & Amount &
new contract revised estimated
amount after amount after this
this Variation Variation n NRs.
in NRs.

Unit Quantity Rate Amount Quantity Rate Amount Rate Amount Rate Amount
A CIVIL WORKS
1 Site Development work

1 Dismentalling of dismentalled brick work


m3 183.75 1158.05 212791.69 166.95 1158.05 193336.45
2 Earthwork in Excavation in foundation
m3 2131.88 393.84 839619.62 113.49 393.84 44696.90
3 Local flat brick soiling with sand filling
m2 129.87 745.09 96764.84 745.09 0.00
4 Pumping out of water from foundation or pit
hr 0.00 0.00 0.00 0.00 0.00
5 Dry rubble masonry work in perfect line level
m3 0.00 0.00 0.00 0.00 0.00
6 Rubble masonry in 1:4 C/S mortar in perfect line level
m3 0.00 0.00 0.00 0.00 0.00
7 PCC (1:3:6)
m3 9.73 11262.55 109584.61 11262.55 0.00
8 Brick Masonry Work in 1:6 c/s mortar
m3 54.80 10836.94 593864.31 10836.94 0.00
9 PCC for RCC Work (1:2:4)
m3 57.06 0.00 0.00
10 Reinforcement work ( Fe 415/500)
kg 5840.58 119.29 696722.79 119.29 0.00
11 Formwork
m2 367.38 0.00 0.00
12 12.5mm Thick Ceiling plaster in 1:4 cement sand mortar
m2 362.29 138.20 50068.48 138.20 0.00
13 Fencing with 62mm * 62mm size mesh (Using Old
Existing Mesh)
job 1.00 24500.00 24500.00 24500.00 0.00
14 Fencing with 62mm * 62mm size mesh (Using New Mesh)
m2 101.50 3075.91 312204.87 3075.91 0.00
15 Colouring with 2 coats water proof cement paint
m2 362.29 100.94 36569.55 100.94 0.00
16 2 coats of readymade enamel paints
m2 367.50 249.51 91694.93 249.51 0.00
17 Site clearance work before and after work all complete
job 1.00 15000.00 15000.00 15000.00 0.00

SUB TOTAL 3079385.68 238033.35 0.00 0.00

Contingency 5% NRs. 153969.28 NRs. 11901.67 NRs. 0.00 NRs. 0.00

TOTAL AMOUNT WITHOUT VAT 3233354.96 249935.02 0.00 0.00

VAT 13 % NRs. 400320.14 NRs. 30944.34 NRs. 0.00 NRs. 0.00

NET TOTAL AMOUNT WITH VAT NRs. 3633675.10 NRs. 280879.36 NRs. 0.00 NRs. 0.00

Prepared By: Checked By: Certified & Recommended By: Approved By:

Name: Name: Name: Name:

Designation: Designation: Designation: Designation:

Signature: Signature: Signature: Signature:

Date: Date: Date: Date:

a9L ePdf -±_ 36L ePdf -–_ lrGx clÍt ug]{


Oli6d]6eGbf a9L vr{ ePsf] d"Vo sf/0f M–
:jLs[t l8hfO{g :k]l;lkms]zg adf]lhd sfd ePsf] egL k|dfl0ft ug]{ M–
zx/L ljsf; tyf ejg lgdf{0f ljefu, l8lehg sfof{no, ;'v]{t d=n]=k=kmf=g+= !^*

lansf] s|d ;+VofM– ;ftf}+ /lgË lan


7]Ssf ;DalGw aLn sfof{De cfb]z ldltM– )^$.)^.@&
of]hgfsf] gfdM– %) z}of c:ktfn ejg lgdf{0f sfo{ , ;'v]{t ;Dem\of}tf ldltM– @)^$.)^.!*
7]s]bf/sf] gfd M– /lagf , cflzif k|lti7f , g]kfn k|utL h]=eL= z}a' , sf7df08f}+ . sfd ;DkGg ug'{ kg]{ ldltM– @)^^.)@.!&-;Dem\of}tfsf] @) dlxgf _yk @)^^.)*.!& ;Dd
7]Ssf k6[fsf] ;+VofM– !) - @)^#÷)^$ _ sfd ;DkGg ePsf] ldltM– rfn'''''''
cl3Nnf] e"QmfgL lansf] s|d;+VofM– gjf} /lgË lan e"QmfgL efpr/ g+=–
cl3Nnf] e"QmfgL ef=g+=M– e"QmfgL ldltM–
gfkL lstfa g+= sf] k[i7 g+=M– b]lv ;Dd
cfO{ cBfjlw sfd ePsf] cl3Nnf] landf r9]sf] xfn ePsf] sfd
s||=;+ 6d sfdsf] laj/0f PsfO{ s}lkmot
g+== kl/df0f b/ hDdf d"No kl/df0f hDdf d"No kl/df0f hDdf d"No
A CIVIL WORKS
1 1.2 Earth work in Excavation in site Development m3 3799.23 100.00 379922.50 3799.23 379922.50 0.00 0.00
2 2 Earth work excavation in BM Soil on Foundation m3 2561.44 200.00 512287.80 2533.71 506741.40 27.73 5546.40
3 3 Earth filling Work m3 3185.34 60.00 191120.22 3185.34 191120.22 0.00 0.00
4 4 150 mm thick stone soling with sand m3 620.11 2500.00 1550270.00 516.92 1292300.00 103.19 257970.00
5 5 75mm thick lean concrete (1:3:6) in foundation m3 106.35 4500.00 478575.00 104.04 468184.50 2.31 10390.50
6 6 P.C.C. (1:2:4) Work m3 200.77 5655.13 1135403.07 155.54 879598.92 45.23 255804.15
7 7 Brick Masonary work ( 1:6 ) m3 1008.69 4576.61 4616394.47 885.30 4051668.25 123.39 564726.22
8 Extra Brick Masonary work With ( 1:4 ) Cement mortar m3 100.27 6778.67 679704.01 85.35 578532.36 14.93 101171.65
9 8 R.C.C. Works
10 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 1374.68 6529.70 8976228.40 1331.55 8694641.62 43.12 281586.78
11 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 618.65 8547.38 5287859.39 618.65 5287859.39 0.00 0.00
12 8.3 Reinforcements works kg 309496.12 60.51 18727610.22 302507.13 18304706.43 6988.99 422903.79
13 8.4 Form work m2 10075.11 313.00 3153509.43 9547.64 2988411.32 527.47 165098.11
14 10 12.5 mm Thick Wall Plaster in 1:4 m2 7341.88 120.00 881025.60 3798.63 455835.60 3543.25 425190.00
15 11 12.5 mm Thick Ceiling Plaster in 1:3 Plaster m2 3118.47 140.00 436585.80 1884.13 263778.20 1234.34 172807.60
16 16.1 Sand Filling Work m3 334.94 1300.00 435422.00 244.47 317811.00 90.47 117611.00
17 17 Moisac flooring m2 1320.33 900.00 1188297.00 0.00 0.00 1320.33 1188297.00
18 18 Kota stone flooring m2 559.62 1200.00 671544.00 0.00 0.00 559.62 671544.00
19 19 Marble flooring m2 28.84 2000.00 57680.00 0.00 0.00 28.84 57680.00

TOTAL AMOUNT (without VAT) Rs. 49,359,438.91 Rs ### Rs. 4,698,327.20

pko'{Qm adf]lhd 7Ls 5 egL k|dfl0ft ug]{sf] ;xLM–


==================================== ===================
;j OlGhlgo/ O{lGhgLo/ 7]s]bf/sf] ;xL
of] lansf] hDdf -Eof6 afx]]s_ ?= 49359438.91
cl3Nnf] e"QmfgL lanaf6 e"QmfgL ePsf] - 44661111.71
afFsL lbg' kg]{ -Eof6 afx]s_ 4698327.20
d"No clea[l4 s/ !# Ü n] ?= 610782.54
hDdf lbg' kg]{ Eof6 ;lxt ? 5309109.74
s6[L ug'{ kg]{ ?=M–
s_ k]ZsL– 1327277.434
v_ dfn;dfgsf] df]nM–
u_ d]zLg cf}hf/ axfnM–
3_ cfos/ !=%Ü M– 70474.9079999998
ª_ w/f}6L %Ü M– 234916.36
r_ cGo M– 4698.32719999999
hDdf s§L ? 1637367.03
v"b lbg' kg]{ -Eof6 ;d]t_ ?=M–3671742.71
k]z ug]{sf] ;xLM– hfFr ug]{sf] ;xLM– :jLs[t ug]{sf] ;xLM–
hDdf ?= cIf]?kLM– sf] r]s g+= af6 k|fKt ePsf] egL ;xL ug]{ 7]s]bf/sf] ;xLM–
Department of Urban Development & Building Construction
Birendranagar , Surkhet
Name of work :- 50 Bed Hospital Construction Work F/Y-066 - 067
Place :- Birendranagar - 3 , Kalagaon , Surkhet

DETAILS OF MEASUREMENT ( 9th. Bill )

Ite
S.N. m Items No. Length T.Length Breadth Height Quantity Unit
(A) No. CIVIL WORKS
1 Site Development work
Earth work in Excavation in site
1 1.2 Same as 8th previous bill running Bill 3799.225 m3
Development
Earth work excavation in BM Soil on
2 2 Foundation Same as 8th previous bill running Bill 2533.707 m3

Side of ramp landing (way to 5th block) 1 1.78 1.77 0.60 0.90 0.96
1 2.38 2.37 0.60 0.90 1.28
Entrance Ramp
first step long wall 2 21.00 42.00 0.60 0.90 22.68
short wall 1 5.22 5.22 0.60 0.90 2.82
Total 2561.439 m3

3 3 Earth filling Work Same as 8th previous bill running Bill 3185.337 m3

4 4 150 mm thick stone soling in sand Same as 8th previous bill running Bill 516.920 m3
on block 5
upper level
room 4 6.85 27.40 6.85 0.15 28.15
passage 1 16.86 16.85 2.50 0.15 6.32
down level
room 6 6.85 41.10 6.85 0.15 42.23
passage 1 23.03 23.02 2.50 0.15 8.63
passage 1 13.70 13.70 2.50 0.15 5.14
wall 1 1.78 1.77 0.60 0.15 0.16
Entrance ramp
first step long wall 2 21.00 42.00 0.60 0.15 3.78
short wall 1 5.22 5.22 0.60 0.15 0.47
Waiting to lift zone 1 14.40 14.40 2.57 0.15 5.54
Ramp (Way to 5th block upper level) 1 7.20 7.20 2.57 0.15 2.77
Total 620.108 m3

5 5 Lean Concrete Base (1:3:6) Same as 8th previous bill running Bill 104.041 m3
Side of ramp landing (way to 5th block) 1 1.78 1.77 0.60 0.075 0.08
1 2.38 2.37 0.60 0.075 0.11
Entrance ramp
first step long wall 2 21.00 42.00 0.60 0.075 1.89
short wall 1 5.22 5.22 0.60 0.075 0.23
Total 106.350 m3

6 6 P.C.C. (1:2:4) Work Same as 8th previous bill running Bill 155.54 m3
Block 5
room 4 6.85 27.40 6.85 0.075 14.08
passage 1 16.86 16.85 2.50 0.075 3.16
down level
room 6 6.85 41.10 6.85 0.075 21.12
passage 1 23.03 23.02 2.50 0.075 4.32
passage 1 13.70 13.70 2.50 0.075 2.57
Block 1 & 3
Room 10 6.85 68.5 6.85 0.075
Passage 5 6.85 34.25 2.5 0.075
Room 6 6.85 41.1 6.85 0.075
Passage 3 6.85 20.55 2.5 0.075
block 4 1 24.86 24.86 16.12 0.075
block 2 1 19.53 19.52 15.10 0.075
1 24.86 24.86 15.89 0.075
1 6.33 6.32 6.85 0.075
1 19.45 19.45 2.70 0.075
ramp 1 1 14.40 14.40 2.57 0.15
ramp 2 1 7.20 7.20 2.57 0.15
Total 200.77 m3

6 7 Brick Masonary work ( 1:6 ) Same as 8th previous bill running Bill 885.30 m3
Block 5
Down level
pantry room 2 1.29 2.58 0.23 3.26 1.94
1 3.02 3.02 0.23 3.00 2.08
toilet 1 3.08 3.08 0.23 3.53 2.50
1 1.10 1.10 0.23 3.53 0.89
wall 8 6.61 52.84 0.23 2.95 35.85
4 6.61 26.42 0.23 3.53 21.42
1 4.57 4.57 0.23 3.53 3.71
4 6.61 26.44 0.23 2.95 17.94
2 6.61 13.22 0.23 3.53 10.72
1 9.98 9.98 0.23 3.53 8.09
1 4.52 4.52 0.23 2.95 3.07
2 1.67 3.33 0.23 3.53 2.70
1 4.41 4.40 0.23 2.95 2.99
2 2.99 5.98 0.23 3.53 4.85
1 4.77 4.77 0.23 3.53 3.87
1 4.55 4.55 0.23 3.53 3.69
1 2.38 2.37 0.23 3.53 1.92
brick pillar 5 0.46 2.30 0.46 2.95 3.12
5 0.23 1.15 0.23 3.53 0.93
window wall w1 5 2.00 10.00 0.23 0.90 2.07
w2 3 2.00 6.00 0.23 1.80 2.48
v 1 2.00 2.00 0.23 1.80 0.83
w4 1 0.60 0.60 0.23 0.90 0.12
lift area 2 3.37 6.74 0.23 3.53 5.46
2 2.20 4.40 0.23 3.53 3.57
stair 2 6.61 13.22 0.23 2.20 6.69
stair 1 6.61 6.61 0.10 0.90 0.59
future expantion wall
first step 1 1.78 1.77 0.60 0.25 0.27
1 2.38 2.37 0.60 0.25 0.36
second step 1 1.93 1.92 0.45 0.25 0.22
1 2.38 2.38 0.45 0.25 0.27
third step up to sill level 1 2.15 2.14 0.23 1.90 0.94
1 2.38 2.38 0.23 1.90 1.04
Deduction
D9 6 0.80 4.80 -0.23 2.95 -3.26
D5 5 1.20 6.00 -0.23 2.95 -4.07
D1 3 2.00 6.00 -0.23 2.95 -4.07
D4 1 1.50 1.50 -0.23 2.95 -1.02
D2 2 2.00 4.00 -0.23 2.95 -2.71
D6 2 1.00 2.00 -0.23 2.95 -1.36
D10 1 1.80 1.80 -0.23 2.95 -1.22
W2 1 2.00 2.00 -0.23 1.05 -0.48
W3 4 1.20 4.80 -0.23 1.85 -2.04
ramp
first step long wall 2 21.00 42.00 0.60 0.24 6.05
short wall 1 5.22 5.22 0.60 0.24 0.75
second step short wall 1 5.07 5.07 0.45 0.24 0.55
second step long wall 2 20.85 41.70 0.45 0.24 4.50
third step long wall 2 20.63 41.26 0.23 0.80 7.59
third step short wall 1 5.44 5.44 0.23 0.80 1.00
third step long wall 2 20.63 41.26 0.23 0.40 3.80
previous quintity -27.76
sill lintel -10.00
Total 1008.69 m3
Brick Masonary work With ( 1:4 )
8 Extra Same as 8th previous bill running Bill 85.35 m3
Cement mortar
On block -5
staff lokers long wall 1 6.83 6.83 0.10 3.53 2.41
staff lokers short wall 3 2.17 6.51 0.10 3.53 2.29
duct wall 1 1.55 1.55 0.10 3.53 0.55
sluice and bath room main wall 1 4.80 4.80 0.10 3.53 1.69
isolation and staff room wall 1 4.79 4.79 0.10 3.53 1.69
bath room 1 2.47 2.46 0.10 3.53 0.87
duct wall 1 1.32 1.31 0.10 3.53 0.46
isolation bed room 1 3.11 3.11 0.10 3.53 1.10
delevery room wall 1 4.57 4.56 0.10 3.53 1.61
pantry room 1 2.56 2.56 0.10 3.53 0.90
toilet wall 1 2.50 2.49 0.10 3.53 0.88
Wall for leaf 0.00
near grid 17 2 3.00 5.99 0.10 3.53 2.11
near grid 16 1 5.43 5.43 0.10 3.53 1.91
near grid 15 1 3.41 3.41 0.10 3.53 1.20
near grid 16 1 5.35 5.35 0.10 3.53 1.89
near grid 15 1 2.54 2.53 0.10 3.53 0.89
near grid 14 1 3.39 3.38 0.10 3.53 1.19
near grid 13 1 1.60 1.59 0.10 3.53 0.56
Deduction
D9 5 0.80 4.00 -0.10 2.95 -1.18
D5 1 1.20 1.20 -0.10 2.95 -0.35
V2 2 1.00 2.00 -0.10 0.45 -0.09
ramp 2 7.20 14.40 0.10 0.20 0.29
ramp 2 7.20 14.40 0.10 0.20 0.29
ramp 2 7.20 14.40 0.10 0.30 0.43
previous quintity -8.65
Total 100.27 M3

9 8 R.C.C. Work
10 8.1 P.C.C. 1:1.5:3 (M 20 ) Same as 8th previous bill running Bill 1331.55 m3
Lintel
5 1.60 8.00 0.23 0.15 0.28
w3 5 1.60 8.00 0.23 0.15 0.28
d5 11 1.80 19.80 0.23 0.15 0.68
w1 3 2.70 8.10 0.23 0.15 0.28
D1 4 2.70 10.80 0.23 0.15 0.37
D9 15 1.40 21.00 0.10 0.15 0.32
D9 7 1.40 9.80 0.23 0.15 0.34
D6 16 1.60 25.60 0.23 0.15 0.88
D7 11 1.60 17.60 0.23 0.15 0.61
D8 3 1.50 4.50 0.23 0.15 0.16
D2 1 2.60 2.60 0.23 0.15 0.09
D4 2 2.10 4.20 0.23 0.15 0.14
Sill band Block - 5
pantry room 2 1.29 2.58 0.23 0.075 0.04
1 3.02 3.02 0.23 0.075 0.05
toilet 1 3.08 3.08 0.23 0.075 0.05
1 1.10 1.10 0.23 0.075 0.02
wall 8 6.61 52.84 0.23 0.075 0.91
4 6.61 26.42 0.23 0.075 0.46
1 4.57 4.57 0.23 0.075 0.08
4 6.61 26.44 0.23 0.075 0.46
2 6.61 13.22 0.23 0.075 0.23
1 9.98 9.98 0.23 0.075 0.17
1 4.52 4.52 0.23 0.075 0.08
2 1.67 3.33 0.23 0.075 0.06
1 4.41 4.40 0.23 0.075 0.08
2 2.99 5.98 0.23 0.075 0.10
1 4.77 4.77 0.23 0.075 0.08
1 4.55 4.55 0.23 0.075 0.08
1 2.38 2.37 0.23 0.075 0.04
brick pillar 5 0.46 2.30 0.46 0.075 0.08
5 0.23 1.15 0.23 0.075 0.02
window wall w1 5 2.00 10.00 0.23 0.075 0.17
w2 3 2.00 6.00 0.23 0.075 0.10
v 1 2.00 2.00 0.23 0.075 0.03
w4 1 0.60 0.60 0.23 0.075 0.01
lift area 2 3.37 6.74 0.23 0.075 0.12
2 2.20 4.40 0.23 0.075 0.08
stair 2 6.61 13.22 0.23 0.075 0.23
stair 1 6.61 6.61 0.10 0.075 0.05
future expantion wall
first step 1 1.78 1.77 0.60 0.075 0.08
1 2.38 2.37 0.60 0.075 0.11
second step 1 1.93 1.92 0.45 0.075 0.06
1 2.38 2.38 0.45 0.075 0.08
third step up to sill level 1 2.15 2.14 0.23 0.075 0.04
1 2.38 2.38 0.23 0.075 0.04
Deduction
D9 6 0.80 4.80 -0.23 0.075 -0.08
D5 5 1.20 6.00 -0.23 0.075 -0.10
D1 3 2.00 6.00 -0.23 0.075 -0.10
D4 1 1.50 1.50 -0.23 0.075 -0.03
D2 2 2.00 4.00 -0.23 0.075 -0.07
D6 2 1.00 2.00 -0.23 0.075 -0.04
D10 1 1.80 1.80 -0.23 0.075 -0.03
W2 1 2.00 2.00 -0.23 0.075 -0.04
W3 4 1.20 4.80 -0.23 0.075 -0.08
1 6.83 6.83 0.10 0.075 0.05
3 2.17 6.51 0.10 0.075 0.05
1 1.55 1.55 0.10 0.075 0.01
1 4.80 4.80 0.10 0.075 0.04
1 4.79 4.79 0.10 0.075 0.04
1 3.58 3.58 0.10 0.075 0.03
1 2.47 2.46 0.10 0.075 0.02
1 1.32 1.31 0.10 0.075 0.01
1 3.11 3.11 0.10 0.075 0.02
1 4.57 4.56 0.10 0.075 0.03
1 2.56 2.56 0.10 0.075 0.02
1 2.50 2.49 0.10 0.075 0.02
wall for leaf (Voide) 0.00
2 3.00 5.99 0.10 0.075 0.04
1 5.43 5.43 0.10 0.075 0.04
1 3.41 3.41 0.10 0.075 0.03
1 5.35 5.35 0.10 0.075 0.04
1 2.54 2.53 0.10 0.075 0.02
1 3.39 3.38 0.10 0.075 0.03
1 1.60 1.59 0.10 0.075 0.01
deduction
D9 5 0.80 4.00 -0.10 0.075 -0.03
D5 1 1.20 1.20 -0.10 0.075 -0.01
V2 2 1.00 2.00 -0.10 0.075 -0.02
sunshed
W1 W2 2 5.95 11.90 0.75 0.075 0.67
W1 W1 15 5.95 89.25 0.75 0.075 5.02
W3 W4 18 3.75 67.50 0.75 0.075 3.80
W2 W2 2 5.95 11.90 0.75 0.075 0.67
W2 W4 1 4.55 4.55 0.75 0.075 0.26
W1 V 1 5.95 5.95 0.75 0.075 0.33
W1 W1 2 4.65 9.30 0.75 0.075 0.52
W1 W2 2 4.65 9.30 0.75 0.075 0.52
W2 W4 1 3.25 3.25 0.75 0.075 0.18
W1 V 1 4.65 4.65 0.75 0.075 0.26
Ramp 1 20.30 20.30 5.67 0.15 17.27
Lift
Base or mat 1 3.45 3.45 2.60 0.15 1.35
2 3.45 6.90 0.15 1.60 1.66
1 2.30 2.30 0.15 1.60 0.55
Beam 2 9.20 18.40 0.23 0.35 1.48
Total 1374.68 m3

11 8.2 P. C.C 1:1:2 ( M 25 ) Same as 8th previous bill running Bill 618.653 M3

12 8.3 Reinforcement works Same as 8th previous bill running Bill 302507.13 Kg
Lintel
12mm dia bars 20 1.60 32.00 0.890 28.48
w3 20 1.60 32.00 0.890 28.48
d5 44 1.80 79.20 0.890 70.48
w1 12 2.70 32.40 0.890 28.83
D1 16 2.70 43.20 0.890 38.44
D9 60 1.40 84.00 0.890 74.76
D9 28 1.40 39.20 0.890 34.88
D6 64 1.60 102.40 0.890 91.13
D7 44 1.60 70.40 0.890 62.65
D8 12 1.50 18.00 0.890 16.02
D2 4 2.60 10.40 0.890 9.25
D4 8 2.10 16.80 0.890 14.95
Stirrups 8 mm dia bars
59 0.79 46.61 0.395 18.41
w3 59 0.79 46.61 0.395 18.41
d5 143 0.79 112.97 0.395 44.62
w1 57 0.79 45.03 0.395 17.78
D1 76 0.79 60.04 0.395 23.71
D9 155 0.59 91.45 0.395 36.12
D9 73 0.91 66.43 0.395 26.23
D6 187 0.91 170.17 0.395 67.21
D7 129 0.91 117.39 0.395 46.36
D8 44 0.91 40.04 0.395 15.81
D2 19 0.91 17.29 0.395 6.82
D4 30 0.91 27.30 0.395 10.78
sill band 10 mm dia bars
pantry room 4 1.29 5.16 0.62 3.19
2 3.02 6.04 0.62 3.74
toilet 2 3.08 6.16 0.62 3.81
2 1.10 2.20 0.62 1.36
wall 16 6.61 105.68 0.62 65.52
8 6.61 52.84 0.62 32.76
2 4.57 9.14 0.62 5.66
8 6.61 52.88 0.62 32.78
4 6.61 26.44 0.62 16.39
2 9.98 19.96 0.62 12.37
2 4.52 9.04 0.62 5.60
4 1.67 6.66 0.62 4.12
2 4.41 8.81 0.62 5.46
4 2.99 11.96 0.62 7.41
2 4.77 9.54 0.62 5.91
2 4.55 9.10 0.62 5.64
2 2.38 4.75 0.62 2.94
brick pillar 10 0.46 4.60 0.62 2.85
10 0.23 2.30 0.62 1.42
window wall w1 10 2.00 20.00 0.62 12.40
w2 6 2.00 12.00 0.62 7.44
v 2 2.00 4.00 0.62 2.48
w4 2 0.60 1.20 0.62 0.74
lift area 4 3.37 13.48 0.62 8.35
4 2.20 8.80 0.62 5.45
stair 4 6.61 26.44 0.62 16.39
stair 2 6.61 13.22 0.62 8.19
future expantion wall
first step 2 1.78 3.55 0.62 2.20
2 2.38 4.75 0.62 2.94
second step 2 1.93 3.85 0.62 2.38
2 2.38 4.76 0.62 2.95
third step up to sill level 2 2.15 4.29 0.62 2.65
2 2.38 4.76 0.62 2.95
Deduction
D9 12 0.80 9.60 0.62 5.95
D5 10 1.20 12.00 0.62 7.44
D1 6 2.00 12.00 0.62 7.44
D4 2 1.50 3.00 0.62 1.86
D2 4 2.00 8.00 0.62 4.96
D6 4 1.00 4.00 0.62 2.48
D10 2 1.80 3.60 0.62 2.23
W2 2 2.00 4.00 0.62 2.48
W3 8 1.20 9.60 0.62 5.95

2 6.83 13.66 0.62 8.46


6 2.17 13.02 0.62 8.07
2 1.55 3.10 0.62 1.92
2 4.80 9.60 0.62 5.95
2 4.79 9.58 0.62 5.93
2 3.58 7.16 0.62 4.43
2 2.47 4.93 0.62 3.05
2 1.32 2.63 0.62 1.63
2 3.11 6.22 0.62 3.85
2 4.57 9.13 0.62 5.66
2 2.56 5.12 0.62 3.17
2 2.50 4.99 0.62 3.09
Wall for leaf
4 3.00 11.98 0.62 7.42
2 5.43 10.86 0.62 6.73
2 3.41 6.82 0.62 4.22
2 5.35 10.70 0.62 6.63
2 2.54 5.07 0.62 3.14
2 3.39 6.77 0.62 4.19
2 1.60 3.19 0.62 1.97
Deduction 0
D9 10 0.80 8.00 0.62 4.96
D5 2 1.20 2.40 0.62 1.48
V2 4 1.00 4.00 0.62 2.48
styrups 8 mm dia bars 1400 0.20 280.00 0.395 110.60
ramp
long 31 20.40 632.40 0.395 249.79
short 126 5.67 714.42 0.395 282.19
ring 34 0.85 28.90 0.395 11.41
beam 4 5.67 22.68 0.890 20.18
sunshed
W1 W2 24 5.90 141.60 0.395 55.93
W1 W1 180 5.90 1062.00 0.395 419.49
W3 W4 216 3.70 799.20 0.395 315.68
W2 W2 24 5.90 141.60 0.395 55.93
W2 W4 12 4.50 54.00 0.395 21.33
W1 V 12 5.90 70.80 0.395 27.96
Rod for extension storey on 5th block
32mm dia rod 4 5.00 20.00 6.321 126.41
4 5.40 21.60 6.321 136.53
2 2.50 5.00 6.321 31.60
2 2.10 4.20 6.321 26.54
2 2.50 5.00 6.321 31.60
2 2.10 4.20 6.321 26.54
4 2.05 8.20 6.321 51.83
2 2.60 5.20 6.321 32.86

25mm dia 4 5.80 23.20 3.858 89.50


4 6.20 24.80 3.858 95.67
8 5.75 46.00 3.858 177.46
4 5.40 21.60 3.858 83.33
1 2.00 2.00 3.858 7.71
7 5.40 37.80 3.858 145.83
2 2.10 4.20 3.858 16.20
2 4.50 9.00 3.858 34.72
4 2.20 8.80 3.858 33.95
8 2.10 16.80 3.858 64.81
4 2.20 8.80 3.858 33.95
4 4.00 16.00 3.858 61.72
8 2.75 22.00 3.858 84.87
8 2.80 22.40 3.858 86.41
12 2.85 34.20 3.858 131.94
8 2.70 21.60 3.858 83.33
4 5.40 21.60 3.858 83.33
10 6.20 62.00 3.858 239.19
9 5.80 52.20 3.858 201.38
8 5.75 46.00 3.858 177.46
3 5.60 16.80 3.858 64.81
4 5.80 23.20 3.858 89.50
8 2.80 22.40 3.858 86.41
6 2.95 17.70 3.858 68.28
2 3.95 7.90 3.858 30.47
3 2.95 8.85 3.858 34.14

20mm dia rod 8 5.10 40.80 2.469 100.74


4 2.15 8.60 2.469 21.23
8 5.50 44.00 2.469 108.64
4 3.20 12.80 2.469 31.60
4 4.80 19.20 2.469 47.40
3 5.00 15.00 2.469 37.03
7 2.65 18.55 2.469 45.80
7 3.20 22.40 2.469 55.30
8 2.65 21.20 2.469 52.34
8 2.80 22.40 2.469 55.30
2 2.60 5.20 2.469 12.83
2 1.65 3.30 2.469 8.14
2 2.80 5.60 2.469 13.82
2 1.60 3.20 2.469 7.90
2 3.20 6.40 2.469 15.80
2 4.20 8.40 2.469 20.74
2 4.00 8.00 2.469 19.75
16mm dia rod
1 37.40 37.40 1.580 59.09
1 15.20 15.20 1.580 24.01

Lift zone
Mat for lift base/foundation (double net)
12mm dia ro @ 150mm C/C both way 48 2.75 132.00 0.89 117.48
distrubation 12mm dia @ 150 C/C both way 38 3.60 136.80 0.89 121.75
Vertical bar share wall 96 1.94 186.24 0.89 165.75
Vertical bar for share wall 38 1.94 73.72 0.89 65.61
Stirrups 8mm dia @ 150mm C/C 22 9.65 212.30 0.395 83.85
Beam
4no bar 4 9.65 38.60 0.89 34.35
Sitrrups @ 150mm c/c 66 1.00 66.00 0.395 26.07
Beam at sill level
4no bar 4 1.00 4.00 0.89 3.56
Sitrrups @ 150mm c/c 66 1.00 66.00 0.395 26.07
Total 309496.12 kg

13 8.4 Form works Same as 8th previous bill running Bill 9547.64 m2
lintel
side 5 1.60 8.00 0.3 2.40
w3 5 1.60 8.00 0.3 2.40
d5 11 1.80 19.80 0.3 5.94
w1 3 2.70 8.10 0.3 2.43
D1 4 2.70 10.80 0.3 3.24
D9 15 1.40 21.00 0.3 6.30
D9 7 1.40 9.80 0.3 2.94
D6 16 1.60 25.60 0.3 7.68
D7 11 1.60 17.60 0.3 5.28
D8 3 1.50 4.50 0.3 1.35
D2 1 2.60 2.60 0.3 0.78
D4 2 2.10 4.20 0.3 1.26
base 1 1.60 1.60 0.23 0.36
w3 1 1.60 1.60 0.23 0.36
d5 1.2 1.80 2.16 0.23 0.49
w1 2.1 2.70 5.67 0.23 1.30
D1 2.1 2.70 5.67 0.23 1.30
D9 0.8 1.40 1.12 0.10 0.11
D9 0.8 1.40 1.12 0.23 0.25
D6 1 1.60 1.60 0.23 0.36
D7 1 1.60 1.60 0.23 0.36
D8 0.9 1.50 1.35 0.23 0.31
D2 2 2.60 5.20 0.23 1.19
D4 2 2.10 4.20 0.23 0.96
sill band 0.00
pantry room 2 1.29 2.58 0.20 0.51
1 3.02 3.02 0.20 0.60
toilet 1 3.08 3.08 0.20 0.61
1 1.10 1.10 0.20 0.22
wall 8 6.61 52.84 0.20 10.56
4 6.61 26.42 0.20 5.28
1 4.57 4.57 0.20 0.91
4 6.61 26.44 0.20 5.28
2 6.61 13.22 0.20 2.64
1 9.98 9.98 0.20 1.99
1 4.52 4.52 0.20 0.90
2 1.67 3.33 0.20 0.66
1 4.41 4.40 0.20 0.88
2 2.99 5.98 0.20 1.19
1 4.77 4.77 0.20 0.95
1 4.55 4.55 0.20 0.91
1 2.38 2.37 0.20 0.47
brick pillar 5 0.46 2.30 0.20 0.46
5 0.23 1.15 0.20 0.23
window wall w1 5 2.00 10.00 0.20 2.00
w2 3 2.00 6.00 0.20 1.20
v 1 2.00 2.00 0.20 0.40
w4 1 0.60 0.60 0.20 0.12
lift area 2 3.37 6.74 0.20 1.34
2 2.20 4.40 0.20 0.88
stair 2 6.61 13.22 0.20 2.64
stair 1 6.61 6.61 0.20 1.32
future expantion wall
first step 1 1.78 1.77 0.20 0.35
1 2.38 2.37 0.20 0.47
second step 1 1.93 1.92 0.20 0.38
1 2.38 2.38 0.20 0.47
third step up to sill level 1 2.15 2.14 0.20 0.42
1 2.38 2.38 0.20 0.47
deduction
D9 6 0.80 4.80 -0.20 -0.96
D5 5 1.20 6.00 -0.20 -1.20
D1 3 2.00 6.00 -0.20 -1.20
D4 1 1.50 1.50 -0.20 -0.30
D2 2 2.00 4.00 -0.20 -0.80
D6 2 1.00 2.00 -0.20 -0.40
D10 1 1.80 1.80 -0.20 -0.36
W2 1 2.00 2.00 -0.20 -0.40
W3 4 1.20 4.80 -0.20 -0.96
1 6.83 6.83 0.20 1.36
3 2.17 6.51 0.20 1.30
1 1.55 1.55 0.20 0.31
1 4.80 4.80 0.20 0.96
1 4.79 4.79 0.20 0.95
1 3.58 3.58 0.20 0.71
1 2.47 2.46 0.20 0.49
1 1.32 1.31 0.20 0.26
1 3.11 3.11 0.20 0.62
1 4.57 4.56 0.20 0.91
1 2.56 2.56 0.20 0.51
1 2.50 2.49 0.20 0.49
wall for leaf
2 3.00 5.99 0.20 1.19
1 5.43 5.43 0.20 1.08
1 3.41 3.41 0.20 0.68
1 5.35 5.35 0.20 1.07
1 2.54 2.53 0.20 0.50
1 3.39 3.38 0.20 0.67
1 1.60 1.59 0.20 0.31
deduction
D9 5 0.80 4.00 -0.20 -0.80
D5 1 1.20 1.20 -0.20 -0.24
V2 2 1.00 2.00 -0.20 -0.40
for sun shed
W1 W2 2 4.65 9.30 0.65 6.04
W1 W1 15 4.65 69.75 0.65 45.33
W3 W4 18 2.45 44.10 0.65 28.66
W2 W2 2 4.65 9.30 0.65 6.04
W2 W4 1 3.25 3.25 0.65 2.11
W1 V 1 4.65 4.65 0.65 3.02
W1 W2 2 11.90 23.80 0.75 17.85
W1 W1 15 11.90 178.50 0.75 133.87
W3 W4 18 7.50 135.00 0.75 101.25
W2 W2 2 11.90 23.80 0.75 17.85
W2 W4 1 9.10 9.10 0.75 6.82
W1 V 1 11.90 11.90 0.75 8.92
wall 2 1.78 3.55 0.075 0.26
2 2.38 4.75 0.075 0.35
ramp
first step long wall 4 21.00 84.00 0.075 6.30
short wall 2 5.22 10.44 0.075 0.78
Left
Outer side 1 9.50 9.50 1.600 15.20
Inner side 1 8.60 8.60 1.600 13.76
Beam 2 9.65 19.30 0.500 9.65
Total 10075.11 m2

14 10 12.5 mm Thick Wall Plaster in 1:4 Same as 8th previous bill running Bill 3798.63 m2
Block 1
trratment room 1 12.64 12.64 3.53 44.55
consultartion examination room 1 15.96 15.96 3.53 56.25
consultartion examination room 1 21.52 21.52 3.53 75.85
dressing tr 1 17.44 17.44 3.53 61.47
immunization room 1 17.44 17.44 3.53 61.47
consultartion examination room 1 21.14 21.14 3.53 74.51
trratment room 1 21.24 21.24 3.53 74.87
reseption and registration room 1 11.30 11.30 3.53 39.83
clinical room 1 12.36 12.36 3.53 43.56
consultartion examination room 1 11.66 11.66 3.53 41.10
dental hy 1 12.54 12.54 3.53 44.20
treatment and minor sursary 1 17.68 17.68 3.53 62.32
consultartion examination room 1 17.70 17.70 3.53 62.39
cariography 1 17.74 17.74 3.53 62.53
consultartion examination room 1 17.48 17.48 3.53 61.61
consultation treatment room 1 17.64 17.64 3.53 62.18
toilet 2 13.54 27.08 3.53 95.45
room 1 10.30 10.30 3.53 36.30
family planing clinic 1 7.18 7.18 3.53 25.30

passage 1 44.70 44.70 3.53 157.56


1 3.38 3.38 3.53 11.91
1 15.70 15.70 3.53 55.34
waiting area 1 21.10 21.10 3.53 74.37
1 11.20 11.20 3.53 39.48
secondary beam face 2 36.32 72.64 0.49 35.23
secondary beam face 5 16.45 82.25 0.49 39.89
primary beam 1 32.97 32.97 0.53 17.30
pillar 3 2.40 7.20 2.95 21.24
deduction
W1 -16 2.00 -32.00 1.90 -60.80
V1 -2 0.85 -1.70 1.90 -3.23
W3 -8 1.20 -9.60 1.90 -18.24
s -14 1.00 -14.00 2.90 -40.60
D5 -28 1.00 -28.00 2.90 -81.20
D9 -6 0.80 -4.80 2.90 -13.92
D6 -8 1.000 -8.00 2.90 -23.20
D1 -3 2.00 -6.00 2.90 -17.40
toilet wall 4 1.5 6.00 3.52 21.12
block 5
open 1 13.94 13.94 3.53 49.13
auto clean room 1 13.84 13.84 3.53 48.78
delevery room 1 16.46 16.46 3.53 58.02
labor room 1 17.04 17.04 3.53 60.06
sluiceroom 1 11.42 11.42 3.53 40.25
opration delivery 1 17.17 17.17 3.53 60.52
dirty utility 1 8.82 8.82 3.53 31.09
recovery room 1 16.46 16.46 3.53 58.02
bath room 1 6.44 6.44 3.53 22.70
nurse stn 1 9.54 9.54 3.53 33.62
staff locked 1 7.99 7.99 3.53 28.16
1 8.14 8.14 3.53 28.69
bath room 1 6.74 6.74 3.53 23.75
1 6.33 6.33 3.53 22.31
passage 1 17.26 17.26 3.53 60.84
pattent examination room 1 20.32 20.32 3.53 71.62
passage 1 34.34 34.34 3.53 121.04
passage 1 39.06 39.06 3.53 137.68
room 1 23.74 23.74 3.53 83.68
records room 1 19.20 19.20 3.53 67.68
treatment room 1 15.76 15.76 3.53 55.55
pre oprative 1 14.50 14.50 3.53 51.11
2 1.33 2.66 3.53 9.37
toilet 1 5.13 5.13 3.53 18.08
pantry 1 7.70 7.70 3.53 27.14
toilet 1 6.15 6.15 3.53 21.67
ICU 1 27.03 27.03 3.53 95.28
isolation bed room 1 12.00 12.00 3.53 42.30
staff change room 1 8.68 8.68 3.53 30.59
1 6.42 6.42 3.53 22.63
1 13.96 13.96 3.53 49.20
utility room 1 9.89 9.89 3.53 34.86
lift 1 12.70 12.70 3.53 44.76
passage 5 7.20 36.00 3.53 126.90
room 1 12.24 12.24 3.53 43.14
pillar 4 2.40 9.60 2.90 27.84
stair 2 7.20 14.40 3.32 47.80
stair 1 7.20 7.20 1.45 10.44
deduction
D10 -1 1.8 -1.80 2.90 -5.22
D1 -6 2.00 -12.00 2.90 -34.80
D2 -4 2.00 -8.00 2.90 -23.20
D4 -4 1.50 -6.00 2.90 -17.40
D5 -10 1.20 -12.00 2.90 -34.80
D9 -24 0.80 -19.20 2.90 -55.68
D6 -4 1.00 -4.00 2.90 -11.60
-2 1.20 -2.40 2.90 -6.96
W1 -6 2.00 -12.00 1.90 -22.80
W2 -5 2.00 -10.00 1.90 -19.00
W3 -10 1.20 -12.00 1.90 -22.80
W4 -1 0.60 -0.60 1.90 -1.14
V -1 2.00 -2.00 1.90 -3.80
outer face
2 15.07 30.14 4.25 128.09
1 15.26 15.25 4.25 64.81
deduction
W1 -6 2.00 -12.00 1.90 -22.80
W2 -3 2.00 -6.00 1.90 -11.40
W4 -1 0.60 -0.60 1.90 -1.14
V -1 2.00 -2.00 1.90 -3.80
D10 -1 1.8 -1.80 2.90 -5.22
secondary beam face 2 13.72 27.44 0.48 13.03
secondary beam face 2 12.75 25.50 0.48 12.11
primary beam 1 36.25 36.25 0.53 19.03
secondary beam face 2 15.225 30.45 0.48 14.46
secondary beam face 2 15.575 31.15 0.48 14.79
sunshed
W1 W2 2 11.90 23.80 0.70 16.66
W1 W1 15 11.90 178.50 0.70 124.95
W3 W4 18 7.50 135.00 0.70 94.50
W2 W2 2 11.90 23.80 0.70 16.66
W2 W4 1 9.10 9.10 0.70 6.37
W1 V 1 11.90 11.90 0.70 8.33
sill lintel and jamb
W1 6 7.80 46.80 0.23 10.76
W2 3 7.80 23.40 0.23 5.38
W4 1 5.00 5.00 0.23 1.15
V 1 7.80 7.80 0.23 1.79
D10 1 7.60 7.60 0.23 1.74
D10 1 7.60 7.60 0.23 1.74
D1 6 7.80 46.80 0.23 10.76
D2 4 7.80 31.20 0.23 7.17
D4 4 7.30 29.20 0.23 6.71
D5 10 7.00 70.00 0.23 16.10
D9 24 6.60 158.40 0.23 36.43
D6 4 6.80 27.20 0.23 6.25
2 7.00 14.00 0.23 3.22
W1 6 7.80 46.80 0.23 10.76
W2 5 7.80 39.00 0.23 8.97
W3 10 6.20 62.00 0.23 14.26
W4 1 5.00 5.00 0.23 1.15
V 1 7.80 7.80 0.23 1.79
Total 7341.88 m2

15 11 12.5 mm Thick Ceiling Plaster in 1:3 Plaster Same as 8th previous bill running Bill 1884.13 m2
block 1
trratment room 1 3.57 3.57 2.75 9.81
consultartion examination room 1 3.60 3.60 4.38 15.76
consultartion examination room 1 7.26 7.26 3.50 25.41
dressing tr 1 5.42 5.42 3.30 17.88
immunization room 1 5.42 5.42 3.30 17.88
consultartion examination room 1 3.37 3.37 7.20 24.26
trratment room 1 7.20 7.20 3.42 24.62
reseption and registration room 1 2.28 2.28 3.37 7.68
clinical room 1 2.78 2.78 3.40 9.45
consultartion examination room 1 3.55 3.55 2.28 8.09
dental hy 1 3.55 3.55 2.72 9.65
treatment and minor sursary 1 5.50 5.50 3.34 18.37
consultartion examination room 1 5.47 5.47 3.38 18.48
cariography 1 5.50 5.50 3.37 18.53
consultartion examination room 1 5.48 5.48 3.26 17.86
consultation treatment room 1 5.42 5.42 3.40 18.42
toilet 2 4.42 8.84 2.35 20.77
room 1 3.05 3.05 2.10 6.40
family planing clinic 1 7.18 7.18 7.18 51.55

passage 1 22.35 22.35 2.00 44.70


1 7.17 7.17 1.80 12.90
1 4.47 4.47 3.38 15.10
1 4.42 4.42 2.25 9.94
waiting area 1 6.75 6.75 11.00 74.25
1 7.35 7.35 5.45 40.05
block 5
open 1 4.45 4.45 2.52 11.21
auto clean room 1 4.55 4.55 2.37 10.78
delevery room 1 4.78 4.78 3.45 16.49
labor room 1 3.74 3.74 4.78 17.87
sluiceroom 1 3.48 3.48 2.23 7.76
opration delivery 1 4.04 4.03 4.55 18.33
dirty utility 1 2.04 2.03 2.38 4.82
recovery room 1 4.79 4.79 3.44 16.47
bath room 1 1.90 1.90 1.32 2.50
nurse stn 1 2.70 2.70 2.07 5.58
staff locked 1 1.83 1.82 2.17 3.94
1 1.90 1.90 2.17 4.12
bath room 1 1.20 1.20 2.17 2.60
1 1.56 1.55 1.61 2.49
passage 1 7.20 7.20 1.43 10.29
pattent examination room 1 6.83 6.83 3.33 22.74
passage 1 15.00 15.00 2.17 32.55
passage 1 16.91 16.91 2.62 44.30
ramp 1 7.20 7.20 2.83 20.37
ramp 1 7.20 7.20 3.18 22.89
1 5.88 5.88 2.40 14.11
1 3.30 3.30 1.33 4.38
1 5.92 5.92 3.37 19.95
1 6.68 6.68 11.98 80.02
1 3.28 3.28 4.86 15.94
1 4.86 4.86 3.69 17.93
room 1 7.86 7.86 4.01 31.51
records room 1 7.04 7.04 2.56 18.02
treatment room 1 4.89 4.89 2.99 14.62
pre oprative 1 4.89 4.89 2.36 11.54
1 1.81 1.81 1.33 2.40
toilet 1 1.29 1.29 1.28 1.64
pantry 1 1.29 1.29 2.56 3.30
toilet 1 1.99 1.98 1.09 2.15
ICU 1 6.92 6.91 6.60 45.60
isolation bed room 1 3.00 3.00 3.00 9.00
staff change room 1 1.34 1.34 3.00 4.02
1 2.31 2.31 0.90 2.07
1 3.11 3.11 3.87 12.03
utility room 1 2.04 2.03 2.91 5.90
sunshed
W1 W2 2 4.65 9.30 0.65 6.04
W1 W1 15 4.65 69.75 0.65 45.33
W3 W4 18 2.45 44.10 0.65 28.66
W2 W2 2 4.65 9.30 0.65 6.04
W2 W4 1 3.25 3.25 0.65 2.11
W1 V 1 4.65 4.65 0.65 3.02
arch area 1 1.00 1.00 5.55 5.55
arch area 1 1.00 1.00 5.55 5.55
Total 3118.47 m2

16 16.1 Sand Filling Work Same as 8th previous bill running Bill 244.47
Block 5
room 4 6.85 27.40 6.85 0.15 28.15
passage 1 16.86 16.85 2.50 0.15 6.32
down level
room 6 6.85 41.10 6.85 0.15 42.23
passage 1 23.03 23.02 2.50 0.15 8.63
passage 1 13.70 13.70 2.50 0.15 5.14
total 334.94 M3
### Moisac flooring work
Block-1
Treatment room 1 3.57 3.57 2.75 9.81
Consultartion examination room 1 3.60 3.60 4.38 15.76
Consultartion examination room 1 7.26 7.26 3.50 25.41
Dressing tr 1 5.42 5.42 3.30 17.88
Immunization room 1 5.42 5.42 3.30 17.88
Consultartion examination room 1 3.37 3.37 7.20 24.26
Treatment room 1 7.20 7.20 3.42 24.62
Reseption and registration room 1 2.28 2.28 3.37 7.68
Clinical room 1 2.78 2.78 3.40 9.45
Consultartion examination room 1 3.55 3.55 2.28 8.09
Dental hy 1 3.55 3.55 2.72 9.65
Treatment and minor sursary 1 5.50 5.50 3.34 18.37
Consultartion examination room 1 5.47 5.47 3.38 18.48
Cariography 1 5.50 5.50 3.37 18.53
Consultartion examination room 1 5.48 5.48 3.26 17.86
Consultation treatment room 1 5.42 5.42 3.40 18.42
Block-2 0.00 0.00
sample collection room 1 2.90 2.90 3.20 9.28
open 1 4.65 4.65 3.96 18.41
open 1 5.70 5.70 4.72 26.90
1 6.20 6.20 4.57 28.33
dedution -2 0.60 -1.20 0.60 -0.72
lab 1 3.36 3.36 6.93 23.28
lab 1 3.40 3.40 6.93 23.56
x ray room 1 5.90 5.90 4.16 24.54
cariography 1 2.75 2.75 1.45 3.98
dark room 1 2.75 2.75 1.70 4.67
control room 1 2.75 2.75 1.30 3.57
staff room 1 4.73 4.73 3.25 15.37
emergency block 1 13.15 13.15 6.90 90.73
1 5.90 5.90 3.85 22.71
1 3.85 3.85 2.50 9.62
1 4.20 4.20 2.85 11.97
room 1 3.38 3.38 3.45 11.66
room 1 3.40 3.40 3.45 11.73
sluiceroom 1 3.32 3.32 1.80 5.97
1 1.11 1.11 1.18 1.30
scrup up 1 2.84 2.84 2.15 6.10
sub 1 3.80 3.80 2.08 7.90
0pen 1 9.45 9.45 7.60 71.82
dedution -5 0.60 -3.00 0.60 -1.80
Block-3 0.00 0.00
passage 1 5.75 5.75 4.10 23.57
nurse room 1 5.40 5.40 3.47 18.73
room 1 5.42 5.42 2.42 13.11
nurse change 1 2.60 2.60 2.48 6.44
1 1.65 1.65 2.24 3.69
1 1.87 1.87 2.15 4.02
doctors change 1 2.28 2.28 2.60 5.92
1 4.40 4.40 2.60 11.44
room 1 1.46 1.46 1.96 2.86
room 1 1.48 1.48 2.15 3.18
anestic store 1 4.07 4.07 3.31 13.47
doctors wo\rk 1 4.07 4.07 3.60 14.65
passage 1 17.04 17.04 2.42 41.23
scrup 1 2.76 2.76 2.06 5.68
dedution -1 0.60 -0.60 0.60 -0.36
nurse room 1 5.40 5.40 3.47 18.73
Block -4 0.00 0.00
bed ward 1 6.96 6.96 7.20 50.11
bed ward 1 6.90 6.90 7.10 48.99
bed ward 1 7.12 7.12 7.00 49.84
1 2.82 2.82 0.27 0.76
passage 1 21.83 21.83 2.54 55.44
treatment room 1 3.60 3.60 2.76 9.93
passage 1 7.22 7.22 1.25 9.02
pantry room 1 1.72 1.72 2.48 4.26
trotley 1 2.08 2.08 2.46 5.11
store room 1 2.92 2.92 2.45 7.15
nurse room 1 2.56 2.56 5.04 12.90
doctors 1 2.76 2.76 5.05 13.93
open 1 7.14 7.14 2.06 14.70
bed room 1 7.08 7.08 4.20 29.73
CSSD 1 6.81 6.81 4.40 29.96
clean sterile 1 6.92 6.92 3.20 22.14
clean sterile 1 3.75 3.75 1.96 7.35
dirty sterile 1 2.83 2.83 1.95 5.51
Block-5 0.00 0.00
open 1 4.45 4.45 2.52 11.21
auto clean room 1 4.55 4.55 2.37 10.78
delevery room 1 4.78 4.78 3.45 16.49
labor room 1 3.74 3.74 4.78 17.87
sluiceroom 1 3.48 3.48 2.23 7.76
Total 1320.33 M2
### Kota stone flooring
block 1
family planing clinic 1 7.18 7.18 7.18 51.55

passage 1 22.35 22.35 2.00 44.70


1 7.17 7.17 1.80 12.90
1 4.47 4.47 3.38 15.10
1 4.42 4.42 2.25 9.94
waiting area 1 6.75 6.75 11.00 74.25
1 7.35 7.35 5.45 40.05
dedution -3 0.60 -1.80 0.60 -1.08
block 2
1 2.00 2.00 1.36 2.72
main lobby 1 13.40 13.40 2.07 27.73
1 14.05 14.05 20.14 282.96
circular area -3 3.14 -9.42 1.00 -9.42
dedution -8 0.60 -4.80 0.60 -2.88
arch area 1 1.00 1.00 5.55 5.55
arch area 1 1.00 1.00 5.55 5.55
Total 559.62 M2
### Marble flooring
circular area 3 3.14 9.42 1.00 9.42
scouting 1 84.78 84.78 0.15 12.71
pillar 16 2.40 38.40 0.15 5.76
1 6.39 6.38 0.15 0.95
Total 28.84 M2
zx/L ljsf; tyf ejg lgdf{0f ljefu, l8lehg sfof{no, ;'v]{t d=n]=k=kmf=g+= !^*

lansf] s|d ;+VofM– ;ftf}+ /lgË lan


7]Ssf ;DalGw aLn sfof{De cfb]z ldltM– )^$.)^.@&
of]hgfsf] gfdM– %) z}of c:ktfn ejg lgdf{0f sfo{ , ;'v]{t ;Dem\of}tf ldltM– @)^$.)^.!*
7]s]bf/sf] gfd M– /lagf , cflzif k|lti7f , g]kfn k|utL h]=eL= z}a' , sf7df08f}+ . sfd ;DkGg ug'{ kg]{ ldltM– @)^^.)@.!&-;Dem\of}tfsf] @) dlxgf _yk @)^^.)*.!& ;Dd
7]Ssf k6[fsf] ;+VofM– !) - @)^#÷)^$ _ sfd ;DkGg ePsf] ldltM– rfn'''''''
cl3Nnf] e"QmfgL lansf] s|d;+VofM– 5}7f}+ /lgË lan e"QmfgL efpr/ g+=–
cl3Nnf] e"QmfgL ef=g+=M– e"QmfgL ldltM–
gfkL lstfa g+= sf] k[i7 g+=M– b]lv ;Dd
cfO{ cBfjlw sfd ePsf] cl3Nnf] landf r9]sf] xfn ePsf] sfd
s||=;+ 6d sfdsf] laj/0f PsfO{ s}lkmot
g+== kl/df0f b/ hDdf d"No kl/df0f hDdf d"No kl/df0f hDdf d"No
A CIVIL WORKS
1 1.2 Earth work in Excavation in site Development m3 3799.23 100.00 379922.50 3799.23 379922.50 0.00 0.00
2 2 Earth work excavation in BM Soil on Foundation m3 2533.71 200.00 506741.40 2533.71 506741.40 0.00 0.00
3 3 Earth filling Work m3 3185.34 60.00 191120.22 3185.34 191120.22 0.00 0.00
4 4 150 mm thick stone soling with sand m3 516.92 2500.00 1292300.00 516.92 1292292.50 0.00 7.50
5 5 75mm thick lean concrete (1:3:6) in foundation m3 104.04 4500.00 468184.50 104.04 468184.50 0.00 0.00
6 6 P.C.C. (1:2:4) Work m3 155.54 5655.13 879598.92 155.54 879570.64 0.00 28.28
7 7 Brick Masonary work ( 1:6 ) m3 885.30 4576.61 4051668.25 857.74 3925536.88 27.56 126131.37
8 Extra Brick Masonary work With ( 1:4 ) Cement mortar m3 85.35 6778.67 578532.36 76.70 519903.65 8.65 58628.71
9 8 R.C.C. Works
10 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 1331.55 6529.70 8694641.62 1240.97 8103146.30 90.59 591495.32
11 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 618.65 8547.38 5287859.39 541.14 4625351.97 77.51 662507.42
12 8.3 Reinforcements works kg 302507.13 60.51 18304706.43 280401.93 16967120.78 22105.20 1337585.65
13 8.4 Form work m2 9547.64 313.00 2988411.32 8816.08 2759433.04 731.56 228978.28
14 10 12.5 mm Thick Wall Plaster in 1:4 m2 3798.63 120.00 455835.60 2425.58 291069.60 1373.05 164766.00
15 11 12.5 mm Thick Ceiling Plaster in 1:3 Plaster m2 1884.13 140.00 263778.20 1884.13 263778.20 0.00 0.00
16 16.1 Sand Filling Work m3 244.47 1300.00 317811.00 244.47 317811.00 0.00 0.00

TOTAL AMOUNT (without VAT) Rs. 44661111.71 Rs 41490983.18 Rs. 3170128.53

pko'{Qm adf]lhd 7Ls 5 egL k|dfl0ft ug]{sf] ;xLM–


==================================== ===================
cf]e/l;o/ O{lGhgLo/ 7]s]bf/sf] ;xL
of] lansf] hDdf -Eof6 afx]]s_ 44661111.71
cl3Nnf] e"QmfgL lanaf6 e"QmfgL ePsf] -Eof6 41490983.18
afFsL lbg' kg]{ -Eof6 afx]s_ 3170128.53
s6[L ug'{ kg]{ ?=M–
s_ k]ZsL–
v_ dfn;dfgsf] df]nM–
u_ d]zLg cf}hf/ axfnM–
3_ cfos/ !=%Ü M–
ª_ d"No clea[l4 s/ !# Ü M–
r_ w/f}6L %Ü M–
5_ cGo M–
v"b lbg' kg]{ -Eof6 ;d]t_ ?=M–
k]z ug]{sf] ;xLM– hfFr ug]{sf] ;xLM– :jLs[t ug]{sf] ;xLM–
hDdf ?= cIf]?kLM– sf] r]s g+= af6 k|fKt ePsf] egL ;xL ug]{ 7]s]bf/sf] ;xLM–
zx/L ljsf; tyf ejg lgdf{0f ljefu, l8lehg sfof{no, ;'v]{t d=n]=k=kmf=g+= !^*

lansf] s|d ;+VofM– ;ftf}+ /lgË lan


7]Ssf ;DalGw aLn sfof{De cfb]z ldltM– )^$.)^.@&
of]hgfsf] gfdM– %) z}of c:ktfn ejg lgdf{0f sfo{ , ;'v]{t ;Dem\of}tf ldltM– @)^$.)^.!*
7]s]bf/sf] gfd M– /lagf , cflzif k|lti7f , g]kfn k|utL h]=eL= z}a' , sf7df08f}+ . sfd ;DkGg ug'{ kg]{ ldltM– @)^^.)@.!&-;Dem\of}tfsf] @) dlxgf _yk @)^^.)*.!& ;Dd
7]Ssf k6[fsf] ;+VofM– !) - @)^#÷)^$ _ sfd ;DkGg ePsf] ldltM– rfn'''''''
cl3Nnf] e"QmfgL lansf] s|d;+VofM– 5}7f}+ /lgË lan e"QmfgL efpr/ g+=–
cl3Nnf] e"QmfgL ef=g+=M– e"QmfgL ldltM–
gfkL lstfa g+= sf] k[i7 g+=M– b]lv ;Dd
cfO{ cBfjlw sfd ePsf] cl3Nnf] landf r9]sf] xfn ePsf] sfd
s||=;+ 6d sfdsf] laj/0f PsfO{ s}lkmot
g+== kl/df0f b/ hDdf d"No kl/df0f hDdf d"No kl/df0f hDdf d"No
A CIVIL WORKS
1 1.2 Earth work in Excavation in site Development m3 3799.23 100.00 379922.50 3799.23 379922.50 0.00 0.00
2 2 Earth work excavation in BM Soil on Foundation m3 2533.71 200.00 506741.40 2533.71 506741.40 0.00 0.00
3 3 Earth filling Work m3 3185.34 60.00 191120.22 3185.34 191120.22 0.00 0.00
4 4 150 mm thick stone soling with sand m3 516.92 2500.00 1292292.50 339.00 847510.00 177.91 444782.50
5 5 75mm thick lean concrete (1:3:6) in foundation m3 104.04 4500.00 468184.50 104.04 468184.50 0.00 0.00
6 6 P.C.C. (1:2:4) Work m3 155.54 5655.13 879570.64 66.58 376518.55 88.96 503052.09
7 7 Brick Masonary work ( 1:6 ) m3 857.74 4576.61 3925536.88 654.42 2995025.11 203.32 930511.77
8 Extra Brick Masonary work With ( 1:4 ) Cement mortar m3 76.70 6778.67 519903.65 38.99 264300.34 37.71 255603.31
9 8 R.C.C. Works
10 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 1240.97 6529.70 8103146.30 1221.90 7978670.62 19.06 124475.68
11 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 541.14 8547.38 4625351.97 541.14 4625351.97 0.00 0.00
12 8.3 Reinforcements works kg 280401.93 60.51 16967120.78 267272.61 16172665.63 13129.32 794455.15
13 8.4 Form work m2 8816.08 313.00 2759433.04 8222.87 2573758.31 593.21 185674.73
14 10 12.5 mm Thick Wall Plaster in 1:4 m2 2425.58 120.00 291069.60 - - 2425.58 291069.60
15 11 12.5 mm Thick Ceiling Plaster in 1:3 Plaster m2 1884.13 140.00 263778.20 - - 1884.13 263778.20
16 16.1 Sand Filling Work m3 244.47 1300.00 317811.00 66.58 86554.00 177.89 231257.00

TOTAL AMOUNT (without VAT) Rs. 41490983.18 Rs 37466323.15 Rs. 4024660.03

pko'{Qm adf]lhd 7Ls 5 egL k|dfl0ft ug]{sf] ;xLM–


==================================== ===================
cf]e/l;o/ O{lGhgLo/ 7]s]bf/sf] ;xL
of] lansf] hDdf -Eof6 afx]]s_ 41490983.18
cl3Nnf] e"QmfgL lanaf6 e"QmfgL ePsf] -Eof6 37466323.15
afFsL lbg' kg]{ -Eof6 afx]s_ 4024660.03
s6[L ug'{ kg]{ ?=M–
s_ k]ZsL–
v_ dfn;dfgsf] df]nM–
u_ d]zLg cf}hf/ axfnM–
3_ cfos/ !=%Ü M–
ª_ d"No clea[l4 s/ !# Ü M–
r_ w/f}6L %Ü M–
5_ cGo M–
v"b lbg' kg]{ -Eof6 ;d]t_ ?=M–
k]z ug]{sf] ;xLM– hfFr ug]{sf] ;xLM– :jLs[t ug]{sf] ;xLM–
hDdf ?= cIf]?kLM– sf] r]s g+= af6 k|fKt ePsf] egL ;xL ug]{ 7]s]bf/sf] ;xLM–
8

Department of Urban Development & Building Construction


Birendranagar , Surkhet

Name of work :- 50 Bed Hospital Construction Work F/Y-066 - 067


Place :- Birendranagar - 3 , Kalagaon , Surkhet

DETAILS OF MEASUREMENT ( 8th. Bill )


S.N.Item No. Items No. Length T.Length Breadth Height
(A) CIVIL WORKS
1 Site Development work
Earth work in Excavation in site
1 1.2 Same as 7th previous bill running Bill
Development
Earth work excavation in BM Soil on
2 2 Foundation Same as 7th previous bill running Bill
3 3 Earth filling Work Same as 7th previous bill running Bill
4 4 150 mm thick stone soling in sand Same as 7th previous bill running Bill
5 5 Lean Concrete Base (1:3:6) Same as 7th previous bill running Bill
6 6 P.C.C. (1:2:4) Work Same as 7th previous bill running Bill
6 7 Brick Masonary work ( 1:6 ) Same as 7th previous bill running Bill

Block 5 1 13.20 13.20 0.25 2.95


Deduction D10 -1 1.80 -1.80 0.25 2.95
1 8.00 8.00 0.25 0.80
1 7.00 7.00 0.25 0.80
Brick pillar 4 0.35 1.40 0.35 2.95
1 13.20 13.20 0.25 2.95
Staircase under beam wall 1 1.25 1.25 0.35 1.50
1 2.90 2.90 0.35 1.15
1 1.70 1.70 0.35 0.45
1 0.60 0.60 0.35 0.45
1 6.60 6.60 0.35 1.15
2 1.00 2.00 0.35 0.25
1 1.80 1.80 0.35 0.25
Total
Brick Masonary work With ( 1:4 ) Cement
8 Extra Same as 7th previous bill running Bill
mortar

1 11.26 11.26 0.10 3.60


1 12.76 12.76 0.10 3.60
Total
9 8 R.C.C. Work
10 8.1 P.C.C. 1:1.5:3 (M 20 ) Same as 7th previous bill running Bill

Slab
Stair case slab along beam1 1 6.60 6.60 2.00 0.20
slab along beam2 1 6.55 6.54 2.00 0.20
slab along beam2 1 3.08 3.08 2.00 0.20
slab projection 1 2.76 2.76 0.52 0.20
Riser 1&2 25 2.00 50.00 0.02
Riser 3 10 1.00 10.00 0.02
slab pane 1 top 1 25.02 25.02 17.89 0.13
deduction for lift 1 2.59 2.59 3.37 -0.13
deduction 1 6.5 6.50 -7.20 0.13
Slab pane 2 down 1 17.86 17.85 15.00 0.13
5 1.00 5.00 0.10 0.10
Total
11 8.2 P. C.C 1:1:2 ( M 25 ) Same as 7th previous bill running Bill
primary beam
grid 14 1 15.49 15.48 0.35 0.75
grid 13 1 15.49 15.48 0.35 0.53
grid 11 1 15.49 15.48 0.35 0.53
grid 10 1 15.49 15.48 0.35 0.53
grid 9 1 15.49 15.48 0.35 0.53
grid L 1 22.03 22.02 0.35 0.53
grid m 1 22.03 22.02 0.35 0.53
grid n 1 22.03 22.02 0.35 0.53
grid 0 1 22.03 22.02 0.35 0.53
Secondary beam 0.00
acros grid 13 sidses 1 16.09 16.08 0.30 0.48
acros grid 11 sidses 1 13.2 13.20 0.30 0.48
acros grid 9 sidses 1 6.9 6.90 0.30 0.48
acros grid Msidses 1 15.43 15.42 0.30 0.48
Stair case Beam 0.00
Beam 1 1 6.95 6.95 0.35 0.45
Beam 2 1 6.90 6.89 0.35 0.45
Beam 3 1 7.08 7.08 0.35 0.45
primary beam 0.00
grid 15 1 13.20 13.20 0.35 0.53
grid 16 1 13.20 13.20 0.35 0.53
grid 17 1 13.20 13.20 0.35 0.53
grid L 1 15.46 15.45 0.35 0.53
grid m 1 15.46 15.45 0.35 0.53
grid n 1 15.46 15.45 0.35 0.53
Secondary beam 0.00
acros grid 16 sidses 1 13.70 13.70 0.30 0.48
acros grid 17 sidses 1 13.70 13.70 0.30 0.48
acros grid Msidses 1 15.01 15.00 0.30 0.48
acros grid Nsidses 1 15.01 15.00 0.30 0.48
Pillar 31 0.6 18.60 0.60 1.01
Total
12 8.3 Reinforcement works Same as 7th previous bill running Bill
Reinforcement Works of block 5
Staircase Beam -3
4 no. 20 mmdia bar 4 5.60 22.40 2.49
4 no. 20 mmdia bar 4 10.42 41.68 2.49
4 no. 20 mmdia bar 4 10.05 40.20 2.49
4 no. 20 mmdia bar 4 6.50 26.00 2.49
Lap length 10 1.30 13.00 2.49
Staircase Beam -2 0.00
4 no. 20 mmdia bar 4 9.85 39.40 2.49
4 no. 20 mmdia bar 4 7.20 28.80 2.49
4 no. 20 mmdia bar 4 5.95 23.80 2.49
4 no. 20 mmdia bar 4 9.85 39.40 2.49
Lap length 10 1.20 12.00 2.49
Staircase Beam -1 0.00
4 no. 20 mmdia bar 4 10.40 41.60 2.49
4 no. 20 mmdia bar 4 9.70 38.80 2.49
4 no. 20 mmdia bar 4 6.50 26.00 2.49
4 no. 20 mmdia bar 4 5.63 22.52 2.49
Lap length 10 1.20 12.00 2.49
Stirrups 0.00
large 212 1.95 413.40 0.39
Small 212 1.61 341.32 0.39
stair case slab 0.00
main bar(along beam 1) 29 8.70 252.30 0.89
distribution 84 2.45 205.80 0.89
cut piece 0.00
14 3.45 48.30 0.89
28 2.62 73.36 0.89
12 1.6 19.20 0.89
8 1.6 12.80 0.89
12 1.60 19.20 0.89
main bar(along beam 2) 28 9.10 254.80 0.89
distribution 88 2.45 215.60 0.89
From block -2 Stair 10 mm dia main bar 13 3.20 41.60 0.89
cut piece 0.00
14 3.40 47.60 0.89
14 3.60 50.40 0.89
14 2.30 32.20 0.89
main bar(along beam 3) 50 2.15 107.50 0.89
distribution 26 8.50 221.00 0.89
27 3.5 94.50 0.89
Stair case chair 32 0.62 19.84 0.61
primary beam 0.00
grid 14 for 0.00
20 dia 8nos 8 19.16 153.24 2.49
Lapping 8 1.20 9.60 2.49
2no 12mm sides bar 2 17.86 35.71 0.89
cut piece 20mm dia.2no. Bar 2 22.10 44.20 2.49
grid 13 for 20dia 8 nos. 8 19.16 153.24 2.49
Lapping 8 1.20 9.60 2.49
cut piece 20mm dia.4no. Bar 4 22.10 88.40 2.49
grid 11 for 20dia 8 nos. 8 19.16 153.24 2.49
Lapping 8 1.20 9.60 2.49
cut piece 20mm dia.2no. Bar 2 22.10 44.20 2.49
grid 10 for 20dia 8 nos. 8 19.16 153.24 2.49
Lapping 8 1.20 9.60 2.49
cut piece 20mm dia.2no. Bar 2 22.10 44.20 2.49
grid 9 for 20dia 8 nos. 8 22.76 182.04 2.49
Lapping 16 1.20 19.20 2.49
cut piece 20mm dia.2no. Bar 2 25.70 51.40 2.49
grid L 20 dia 8 nos 8 26.32 210.56 2.49
Lapping 0.00
cut piece 20mm dia.2no. Bar 2 30.40 60.80 2.49
grid M 20 dia 8 nos 8 28.72 229.76 2.49
Lapping 8 1.20 9.60 2.49
cut piece 20mm dia.4no. Bar 4 30.40 121.60 2.49
grid N 20 dia 8 nos 8 28.72 229.76 2.49
Lapping 16 1.20 19.20 2.49
cut piece 20mm dia.2no. Bar 2 30.40 60.80 2.49
grid O 20 dia 8 nos 8 26.32 210.56 2.49
Lapping 16 1.20 19.20 2.49
cut piece 20mm dia.2no. Bar 2 30.40 60.80 2.49
Stiirups 0.00
long 1196 1.95 2332.20 0.39
short 1196 1.61 1925.56 0.39
long 154 2.35 361.90 0.39
short 154 2.01 309.54 0.39
Secondary beam 0.00
acros grid 13 20 dia 8nos 8 19.66 157.24 2.49
Lapping 8 1.20 9.60 2.49
2no 12mm sides bar 2 17.86 35.71 0.89
acros grid 11 20 dia 8nos 8 16.80 134.40 2.49
Lapping 8 1.20 9.60 2.49
2no 12mm sides bar 2 15.00 30.00 0.89
acros grid 9 20 dia 8nos 8 9.50 76.00 2.49
Lapping 8 1.20 9.60 2.49
2no 12mm sides bar 2 7.80 15.60 0.89
acros grid M 20 dia 8nos 8 19.62 156.96 2.49
Lapping 8 1.20 9.60 2.49
2no 12mm sides bar 2 17.82 35.64 0.89
acros grid N 20 dia 8nos 8 11.45 91.60 2.49
Lapping 8 1.20 9.60 2.49
2no 12mm sides bar 2 10.05 20.10 0.89
Stirrups 0.00
long 750 1.75 1312.50 0.39
short 750 1.47 1102.50 0.39
slab 0.00
10 mm Dia. main bar 58 24.43 1416.65 0.61
10 mm Dia. main bar 78 18.02 1405.56 0.61
8mm Dia. Distribution bar 55.2 8.00 441.60 0.39
8mm Dia. Distribution bar 133 17.49 2325.50 0.39
cut piece 0.00
10 mm Dia. main bar 29 24.43 708.32 0.61
10 mm Dia. main bar 39 18.02 702.78 0.61
10 mm Dia. main bar 108 3.05 329.40 0.61
8mm Dia. Distribution bar 36 7.9 284.40 0.61
8mm Dia. Distribution bar 27.6 8.00 220.80 0.39
8mm Dia. Distribution bar 66.5 17.49 1162.75 0.39
8mm Dia. Distribution bar 53 1.20 63.60 0.39
8mm Dia. Distribution bar 79 1.80 142.20 0.39
8mm Dia. Distribution bar 79 2.50 197.50 0.39
8mm Dia. Distribution bar 27.6 8.00 220.80 0.39
Lap length 10 dia Distribution bar 204 0.60 122.40 0.61
Lap length 8mm dia Distribution bar 282.3 0.46 129.85 0.39
Lapping on pillar 0.00
C5 25mmdia 12no. 24 4.50 108.00 3.86
C3 25mm dia .12no. 96 4.50 432.00 3.86
C2 25mm dia.12 no 48 4.50 216.00 3.86
C1 25mm dia. 4no 8 4.50 36.00 3.86
C1 20mm dia.4no 16 4.20 67.20 2.49
Pillars Stirrups 0.00
large 100 2.25 225.00 0.39
small 200 1.75 350.00 0.39
20mm dia. pin rods 80 0.23 18.40 2.49
cantilever beam 0.00
8 no. 20 mmdia bar 8 4.56 36.44 2.49
Stirrups large 25 1.95 48.75 0.39
small 100 1.65 165.00 0.39
Chair rods for slab 150 0.80 120.00 0.61

Total

13 8.4 Form works Same as 7th previous bill running Bill


block 5
primary beam
grid 14 for base 1 15.485 15.48 0.35
grid 13 for base 1 15.485 15.48 0.35
grid 11 for base 1 15.485 15.48 0.35
grid 10 for base 1 15.485 15.48 0.35
grid 9 for base 1 15.485 15.48 0.35
grid 14 for sides 2 15.485 30.97 0.745
grid 13 for sides 2 15.485 30.97 0.525
grid 11 for sides 2 15.485 30.97 0.525
grid 10 for sides 2 15.485 30.97 0.525
grid 9 for sides 2 15.485 30.97 0.525
grid L base 1 22.03 22.02 0.35
grid m base 1 22.03 22.02 0.35
grid n base 1 22.03 22.02 0.35
grid o base 1 22.03 22.02 0.35
grid L for sides 2 22.03 44.05 0.525
grid M for sides 2 22.03 44.05 0.525
grid N for sides 2 22.03 44.05 0.525
grid O for sides 2 22.03 44.05 0.525
Secondary beam 0.00
acros grid 14 sidses 2 16.085 32.17 0.48
acros grid 13 sidses 2 16.085 32.17 0.48
acros grid 11 sidses 2 13.2 26.40 0.48
acros grid 9 sidses 2 6.9 13.80 0.48
acros grid Msidses 2 22.93 45.85 0.48
acros grid Nsidses 2 16.03 32.05 0.48
Slab 0.00
grid 14to 13 2 6.55 13.10 6.85
grid 13to 11 2 6.55 13.10 6.55
grid 11to 10 2 2.47 4.94 6.85
grid 10to 9 1 6.55 6.55 6.55
passage 1 23.02 23.02 2.54
Slab sides 1 40.275 40.27 0.13
For staircase 0.00
Beam 1 1 6.95 6.95 1.60
Beam 2 1 6.90 6.89 1.60
Beam 3 1 7.08 7.08 1.25
slab along beam1 1 6.60 6.60 2.00
slab along beam2 1 6.55 6.54 2.00
slab along beam3 1 3.08 3.08 1.45
slab projection 1 2.76 2.76 0.52
Riser 1&2 25 2.00 50.00 0.15
Riser 3 10 1.80 18.00 0.15
slab side 1 19.31 19.30 0.40
Pillar 20 0.60 12.00 0.80
Total
14 10 12.5 mm Thick Wall Plaster in 1:4 Same as 7th previous bill running Bill
block 3 for plaster
Outer face Block 4
1 15.60 15.60 3.70
1 26.61 26.61 3.70
1 3.85 3.85 3.70
W1 -4 2 -8.00 1.95
W3 -2 1.20 -2.40 1.95
W4 -4 0.60 -2.40 1.95
Windows height 1 39.00 39.00 0.25
Windows base 1 25.60 25.60 0.33
1 18.42 18.42 3.70
d1 -1 2 -2.00 2.85
D7 -2 1.00 -2.00 2.10
1 26.61 26.61 3.70
W1 -2 2 -4.00 1.95
W3 -5 1.20 -6.00 1.95
W4 -4 0.60 -2.40 1.95
1 3.85 3.85 3.70
Windows height 1 42.90 42.90 0.25
Windows base 1 24.80 24.80 0.33
3 0.83 2.49 2.95
0.00
Outer face Block 2 0.00
2 26.61 53.22 3.70
2 17.60 35.20 3.70
W1 -6 2 -12.00 1.95
W2 -2 2 -4.00 1.05
W3 -1 1.20 -1.20 1.95
W4 -1 0.60 -0.60 1.95
D1 -2 2.00 -4.00 2.85
face 1 6.88 6.87 3.50
door face 2 0.65 1.30 1.95
pillar 1 2.60 2.60 1.95
Windows height 1 35.60 35.60 0.25
Windows base 1 35.40 35.40 0.33
entrance beam 1 20.20 20.20 0.70
Outer face Block 1 0.00
1 36.60 36.60 3.70
2 17.600 35.20 3.70
1 37.68 37.68 3.70
W1 -16 2 -32.00 1.95
V1 -2 0.85 -1.70 0.75
D1 -5 2.00 -10.00 2.85
s -1 1.00 -1.00 1.95
Windows height 1 69.40 69.40 0.33
Windows base 1 65.40 65.40 0.25
face 1 8.80 8.80 3.70
Outer face Block 4 0.00
2 22.20 44.40 3.70
2 17.82 35.64 3.70
W1 -1 2 -2.00 1.95
W2 -2 2.00 -4.00 1.05
W3 -9 1.20 -10.80 1.95
W4 -7 0.6 -4.20 1.95
D1 -2 2.00 -4.00 2.85
face 1 6.60 6.60 3.70
Windows height 1 70.50 70.50 0.25
Windows base 1 42.00 42.00 0.33
Total
15 11 12.5 mm Thick Ceiling Plaster in 1:3 Plaster Same as 7th previous bill running Bill
16 16.1 Sand Filling Work Same as 7th previous bill running Bill
Construction

F/Y-066 - 067

h. Bill )
Quantity Unit

3799.225
2533.707 m3
3185.337 m3
516.920 m3
104.041 m3
155.540 m3
857.54 m3

9.74
-1.33
1.60
1.40
1.45
9.74
0.66
1.17
0.27
0.09
2.66
0.18
0.16
885.30 m3
76.70 m3

4.05
4.59
85.35 m3

1240.97 m3

2.64
2.62
1.23
0.29
1.12
0.22
55.94
-1.14
-5.85
33.47
0.05
1331.55 m3
541.143

4.04
2.84
2.84
2.84
2.84
4.05
4.05
4.05
4.05
0.00
2.29
1.88
0.98
2.20
0.00
1.09
1.09
1.12
0.00
2.43
2.43
2.43
2.84
2.84
2.84
0.00
1.97
1.97
2.16
2.16
11.22
618.65 m3
280401.93 Kg

55.77
103.78
100.09
64.74
32.37

98.10
71.71
59.26
98.10
29.88

103.58
96.61
64.74
56.07
29.88

161.22
133.11

224.26
182.93

42.93
65.20
17.06
11.37
17.06
226.48
191.64
36.97
0.00
42.31
44.80
28.62
95.55
196.44
84.00
12.10

381.56
23.90
31.78
110.05
381.56
23.90
220.11
381.56
23.90
110.05
381.56
23.90
110.05
453.27
47.80
127.98
524.29

151.39
572.10
23.90
302.78
572.10
47.80
151.39
524.29
47.80
151.39
0.00
909.55
750.96
141.14
120.72
0.00
391.52
23.90
31.78
334.65
23.90
26.70
189.24
23.90
13.88
390.83
23.90
31.71
228.08
23.90
17.88

511.87
429.97
0.00
864.15
857.39
172.22
906.94

432.07
428.69
200.93
173.48
86.11
453.47
24.80
55.45
77.02
86.11
74.66
50.64

416.66
1666.66
833.33
138.88
167.32
0.00
87.75
136.50
45.81

90.73
19.01
64.35
73.20

302507.13 kg

8816.08 m2

5.41
5.41
5.41
5.41
5.41
23.07
16.25
16.25
16.25
16.25
7.70
7.70
7.70
7.70
23.12
23.12
23.12
23.12
0.00
15.28
15.28
12.54
6.55
21.77
15.22
0.00
89.73
85.80
33.83
42.90
58.35
5.23
0.00
11.12
11.02
8.85
13.20
13.08
4.46
1.43
7.50
2.70
7.72
9.60
9547.64 m2
2425.58 m2

57.72
98.45
14.24
-15.60
-4.68
-4.68
9.75
8.32
68.15
-5.70
-4.20
98.45
-7.80
-11.70
-4.68
14.24
10.72
8.06
7.34
196.91
130.24
-23.40
-4.20
-2.34
-1.17
-11.40
24.04
2.53
5.07
8.90
11.50
14.14
0.00
135.42
130.24
139.41
-62.40
-1.28
-28.50
-1.95
22.90
16.35
32.56

164.28
131.86
-3.90
-4.20
-21.06
-8.19
-11.40
24.42
17.62
13.65
3798.63 m2
1884.13 m2
244.47 m2
Department of Urban Development And Building Construction
DIVISION OFFICE, Surkhet

Name of work :- 50 Bed Hospital Construction Work


Place :- Birendranagar - 3 , Kalagaon , Surkhet

8th. RUNNING BILL


S.N. Item No. Items Unit Quantity Unit Rate

A CIVIL WORKS

1 1.2 Earth work in Excavation in site Development m3 3799.23 100.00

2 2 Earth work excavation in BM Soil on Foundation m3 2533.71 200.00

3 3 Earth filling Work m3 3185.34 60.00

4 4 150 mm thick stone soling with sand m3 516.92 2500.00

5 5 75mm thick lean concrete (1:3:6) in foundation m3 155.54 4500.00

6 6 P.C.C. (1:2:4) Work m3 155.54 5655.13

7 7 Brick Masonary work ( 1:6 ) m3 885.30 4576.61

8 Extra Brick Masonary work With ( 1:4 ) Cement mortar m3 85.35 6778.67

9 8 R.C.C. Works

10 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 1331.55 6529.70

11 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 618.65 8547.38

12 8.3 Reinforcements works kg ### 60.51

13 8.4 Form work m2 9547.64 313.00

14 10 12.5 mm Thick Wall Plaster in 1:4 m2 3798.63 120.00

15 11 12.5 mm Thick Ceiling Plaster in 1:3 Plaster m2 1884.13 140.00

16 16.1 Sand Filling Work m3 244.47 1300.00

TOTAL 8th Bill AMOUNT Rs.


on

F/Y-066 - 067

Amount

379922.50

506741.40

191120.22

1292292.50

699930.00

879570.64

4051668.25

578532.36

8694641.62

5287859.39

18304706.43

2988411.32

455835.60

263778.20

317811.00

44892821.43
zx/L ljsf; tyf ejg lgdf{0f ljefu, l8lehg sfof{no, ;'v]{t

7]Ssf ;DalGw aLn


- 5}7f}+ :sfn]zg aLn _
lansf] s|d ;+VofM– ;ftf}+ /lgË lansf] :sfn]zg /lgË - 5}7f+} _lan
of]hgfsf] gfdM– %) z}of c:ktfn ejg lgdf{0f sfo{ , ;'v]{t
7]s]bf/sf] gfd M– /lagf , cflzif k|lti7f , g]kfn k|utL h]=eL= z}a' , sf7df08f}+ .
7]Ssf k6[fsf] ;+VofM– !) - @)^#÷)^$ _
cl3Nnf] e"QmfgL lansf] s|d;+VofM– 5}g
cl3Nnf] e"QmfgL ef=g+=M–

cfO{6d 5}7f}+
s||=;+= sfdsf] laj/0f PsfO{ /lgË
g+== l;d]G6 -Jofu_
lansf]
kl/df0f nfu]sf]
ACIVIL WORKS
1 4 150mm thick stone soling with sand m3 - -
0.22 mt /
2 5 75mm thick lean concrete (1:3:6) in foundatio m3 0.00 0.00
m3
0.32 mt /
3 6 P.C.C. (1:2:4) Work m3 0.00
m4
0.07 mt /
4 7 Brick Masonary work ( 1:6 ) m3 27.56 38.58
m3
5 Extra Brick Masonary work With ( 1:4 ) Cement mor m3 8.65 New rate of 2065/066
6 8 R.C.C. Works

0.40 mt /
7 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 90.59 724.68
m3
0.61 mt /
8 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 77.51 945.62
m3

9 8.3 Reinforcements works kg 22105.20 - -

10 Binding Wire m2 22105.20 -


0.538 mt /
11 10 12.5 mm Thick Wall Plaster in 1:4 m2 1373.05 147.74
100m2
0.625 mt /
12 11 12.5 mm Thick Ceiling Plaster in 1:3 Plaster m2 0.00
100 m2
13 16.1 Sand Filling Work m3
Total Quantity 1856.629
Rate Should be Add 152.50
Total Amount 283135.94
TOTAL AMOUNT (without VAT)
pko'{Qm adf]lhd 7Ls 5 egL k|dfl0ft ug]{sf] ;xLM–
=================
cf]e/l;o/

of] lansf] hDdf -Eof6 afx] 701410.96


cl3Nnf] e"QmfgL lanaf6 e"QmfgL ePsf] -Eof6 afx]s_] ?=
afFsL lbg' kg]{ -Eof6 afx 701410.96
s6[L ug'{ kg]{ ?=M–
s_ k]ZsL–
v_ dfn;dfgsf] df]nM–
u_ d]zLg cf}hf/ axfnM–
3_ cfos/ !=%Ü M–
ª_ d"No clea[l4 s/ !# Ü M–
r_ w/f}6L %Ü M–
5_ cGo M–
v"b lbg' kg]{ -Eof6 ;d]t_ ?=M–

k]z ug]{sf] ;xLM–

hDdf ?= cIf]?kLM– sf] r]s g+= af6 k|fKt ePsf] egL ;xL ug]{
g sfof{no, ;'v]{t

sfof{De cfb]z ldltM– )^$.)^.@&


;Dem\of}tf ldltM– @)^$.)^.!*
sfd ;DkGg ug'{ kg]{ ldltM– @)^^.)@.!&-;Dem\of}tfsf] @) dlxgf _yk @)^^.)*.!& ;D
sfd ;DkGg ePsf] ldltM– rfn'''''''
e"QmfgL efpr/ g+=–
e"QmfgL ldltM–
gfkL lstfa g+= sf] k[i7 g+=M– b]lv ;Dd
sfd ePsf]
nfu]sf] dfn;fdfg
O{§ afn'jf 9'Ëf afO{08LË jfo/ kmnfd] 808L
nfu]sf] nfu]sf] nfu]sf] nfu]sf] nfu]sf]

- - 0.71/m3 0.000 1.10/m3 0.000 - -

0.47/m3 0.00 - - - -

0.445/m4 0.00

560.00 15433.60 0.30/m3 8.27 - - - -

- - 0.425/m3 38.499 - - - -

- - 0.425/m3 32.942 - - - - - -
1050kg/1
- - - - - - - - 23210.460
000kg
10 kg per
- - - - - - 221.052
1000 kg
1.46/m3 20.047

1.28/m3 0.000

1.10/m3 0.000
15433.600 99.755 0.000 221.052 23210.460
2.05 450.00 130.00 34.00 14.40
31638.87 44889.77 0.00 7515.76 334230.62
Rs

=================
O{lGhgLo/

af6 k|fKt ePsf] egL ;xL ug]{ 7]s]bf/sf] ;xLM–


@) dlxgf _yk @)^^.)*.!& ;Dd

s}lkmot

701410.96

701410.96

=================
O{lGhgLo/
zx/L ljsf; tyf ejg lgdf{0f ljefu, l8lehg sfof{no, ;'v]{t
sfo{ ;DkGg k|ltj]bg
sfof{nosf] gfdM– lhNnf kz' ;]jf sfof{no, ;'v]{t
of]hgfsf] gfdM– 8fS6/ Sjf6/ dd{t ;'wf/ sfo{, lhNnf kz' ;]jf sfof{no , ;'v]{t
:yn M– jL/]Gb|gu/,;'v]{t
Oli6d]6sf] s"n c+sM– $@,($$.)@
vr{ ePsf] s"n c+s M– $@,!$).))
Oli6d]]6 adf]lhdsf]
l;=g+= sfdsf] laj/0f PsfO{
kl/df0f b/ hDdf d"No
1 12.5 mm Thick Cement sand Plaster with 1:4 ratio m2 65.26 119.29 7784.86
3 mm cement Punning Work m2 35.23 89.38 3148.85
Boulder Stone Soling Work m2 489.86 50.17 24576.27
Two Coat Enemal Paintig work over Primer m2 55.61 97.71 5434.04
2 #NAME? job 1.00 L.S. 1000.00
3 Site Clearance Before and after Construction job 1.00 L.S. 1000.00
TOTAL AMOUNT Rs. 42944.02
VAT 13 % Rs. 5582.72
GRAND TOTAL AMOUNT WITH VAT Rs. 48526.74

a9L ePdf -±_ 36L ePdf -–_ lrGx clÍt ug]{


Oli6d]6eGbf a9L vr{ ePsf] d"Vo sf/0f M–
:jLs[t l8hfO{g :k]l;lkms]zg adf]lhd sfd ePsf] egL k|dfl0ft ug]{ M–
========================= =================
;fO{{6 cf]e/l;o/ OlGhgLo/
of{no, ;'v]{t
d=n]=k=kmf=g+= !&^

Oli6d]6eGbf 36L a9L M– –+ 36L *)$.)@


36L a9Lsf] k|ltzt M– !=*& Ü 36L
sfd z'? ePsf] ldlt M–
sfd ;DkGg ePsf] ldltM–
sfd ;DkGg ug'{ kg]{ ldltM–
v"b ePsf] sfd km/s
s}lkmot
kl/df0f b/ hDdf d"Nokl/df0f b/ hDdf d"No
65.26 115.00 7504.90 0.00 -4.29 -279.96
35.23 70.00 2466.10 0.00 -19.38 -682.75
489.86 50.00 24493.00 0.00 -0.17 -83.27
55.60 100.00 5560.00 -0.01 2.29 125.96
1.00 L.S 1301.00 0.00 301.00 301.00
1.00 L.S 815.00 0.00 ### -185.00
42140.00 -804.02
5478.20 -104.52
47618.20 -908.54

804.02

============ =================
of]hgf k|d'v
Department of Urban Development And Building Construction
DIVISION OFFICE, Surkhet
F/Y-066 - 067
Name of work :- 50 Bed Hospital Construction Work
Place :- Birendranagar - 3 , Kalagaon , Surkhet

7th. RUNNING BILL


S.N. Item No. Items Unit Quantity Unit Rate Amount

A CIVIL WORKS

1 1.2 Earth work in Excavation in site Development m3 3799.23 100.00 379922.50

2 2 Earth work excavation in BM Soil on Foundati m3 2533.71 200.00 506741.40

3 3 Earth filling Work m3 3185.34 60.00 191120.22

4 4 150 mm thick stone soling with sand m3 516.92 2500.00 1292292.50

5 5 75mm thick lean concrete (1:3:6) in foundation m3 104.04 4500.00 468184.50

6 6 P.C.C. (1:2:4) Work m3 155.54 5655.13 879570.64

7 7 Brick Masonary work ( 1:6 ) m3 857.74 4576.61 3925536.88

8 Extra Brick Masonary work With ( 1:4 ) Cement mor m3 76.70 6778.67 519903.65

9 8 R.C.C. Works

10 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 1240.97 6529.70 8103146.30

11 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 541.14 8547.38 4625351.97

12 8.3 Reinforcements works kg 280401.93 60.51 16967120.78

13 8.4 Form work m2 8816.08 313.00 2759433.04

14 10 12.5 mm Thick Wall Plaster in 1:4 m2 2425.58 120.00 291069.60

15 11 12.5 mm Thick Ceiling Plaster in 1:3 Plaster m2 1884.13 140.00 263778.20

16 16.1 Sand Filling Work m3 244.47 1300.00 317811.00

TOTAL 7th Bill AMOUNT Rs. 41490983.18

Estimated By:- Checked By:- Approved By:-


Department of Urban Development & Building Construction
Birendranagar , Surkhet

Name of work :- 50 Bed Hospital Construction Work F/Y-066 - 067


Place :- Birendranagar - 3 , Kalagaon , Surkhet

DETAILS OF MEASUREMENT ( 7th. Bill )


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

(A) CIVIL WORKS


1 Site Development work

1 1.2 Earth work in Excavation in site Development Same as previous bill running Bill 3799.225

2 2 Earth work excavation in BM Soil on Foundation Same as Previous running Bill 2533.707 m3
3 3 Earth filling Work Same as Previous running Bill 3185.337 m3
4 4 150 mm thick stone soling in sand Same as Previous running Bill 339.004 m3
Block 2
1 19.53 19.52 15.10 0.15 44.20
1 24.86 24.86 15.89 0.15 59.25
1 6.33 6.32 6.85 0.15 6.49
1 19.45 19.45 2.70 0.15 7.88
Block 4 1 24.86 24.86 16.12 0.15 60.09
Total 516.92
5 5 Lean Concrete Base (1:3:6) Same previous running Bill 104.041 m3
6 6 P.C.C. (1:2:4) Work Same previous running Bill 66.580 m3

block 4 1 24.86 24.86 16.12 0.08 30.05

block 2 1 19.53 19.52 15.10 0.08 22.10


1 24.86 24.86 15.89 0.08 29.63
1 6.33 6.32 6.85 0.08 3.25
1 19.45 19.45 2.70 0.08 3.94
Total 155.54 m3
6 7 Brick Masonary work ( 1:6 ) Same as Previous running Bill 654.42
Block 4
2 2.66 5.32 0.23 2.90 3.55
-2 1.96 -3.92 0.23 2.00 -1.80
3 2.71 8.13 0.23 2.90 5.42
-3 1.96 -5.88 0.23 2.00 -2.71
1 3.80 3.80 0.23 2.90 2.53
1 6.60 6.60 0.23 2.90 4.40
1 4.50 4.50 0.23 3.45 3.57
2 5.02 10.04 0.23 3.45 7.97
1 6.93 6.93 0.23 3.45 5.50
1 6.55 6.55 0.23 2.90 4.37
1 1.58 1.58 0.23 2.90 1.05
2 0.28 0.56 0.23 3.45 0.44
2 0.80 1.60 0.23 2.90 1.07
1 2.73 2.73 0.23 2.90 1.82
-1 1.17 -1.17 0.23 2.00 -0.54
1 6.54 6.54 0.23 2.90 4.36
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

-1 3.11 -3.11 0.23 2.00 -1.43


1 2.48 2.48 0.23 2.90 1.65
-1 1.13 -1.13 0.23 2.00 -0.52
1 1.45 1.45 0.23 2.90 0.97
-1 0.93 -0.93 0.23 2.00 -0.43
1 0.20 0.20 0.23 2.90 0.13
1 2.72 2.72 0.23 2.90 1.81
-1 1.97 -1.97 0.23 2.00 -0.91
1 2.67 2.67 0.23 2.90 1.78
-1 1.94 -1.94 0.23 2.00 -0.89
1 6.53 6.53 0.23 2.90 4.36
1 2.73 2.73 0.23 3.45 2.17
1 4.57 4.57 0.23 3.45 3.63
1 4.25 4.25 0.23 3.45 3.37
1 0.23 0.23 0.23 3.45 0.18
2 2.28 4.56 0.23 3.45 3.62
1 6.45 6.45 0.23 2.90 4.30
1 5.93 5.93 0.23 3.45 4.71
1 5.22 5.22 0.23 3.45 4.14
1 0.97 0.97 0.23 3.45 0.77
1 5.24 5.24 0.23 3.45 4.16
1 6.60 6.60 0.23 3.45 5.24
1 0.27 0.27 0.23 2.55 0.16
1 2.15 2.15 0.23 0.90 0.45
1 1.45 1.45 0.23 0.90 0.30
3 0.45 1.35 0.50 3.45 2.33
1 2.05 2.05 0.23 0.90 0.42
4 2.00 8.00 0.23 0.90 1.66
1 6.52 6.52 0.23 3.45 5.17
1 6.65 6.65 0.23 3.45 5.28
4 2.00 8.00 0.23 0.90 1.66
3 0.50 1.50 0.45 3.45 2.33
2 2.05 4.10 0.23 0.90 0.85
2 0.23 0.46 0.23 2.00 0.21
1 0.50 0.50 0.23 2.90 0.33
1 2.07 2.07 0.23 0.90 0.43
1 0.23 0.23 0.23 2.00 0.11
deduction sill band of block 4
-2 2.66 -5.32 0.23 0.10 -0.12
-3 2.71 -8.13 0.23 0.10 -0.19
-1 3.80 -3.80 0.23 0.10 -0.09
-1 6.60 -6.60 0.23 0.10 -0.15
-1 4.50 -4.50 0.23 0.10 -0.10
-2 5.02 -10.04 0.23 0.10 -0.23
-1 6.93 -6.93 0.23 0.10 -0.16
-1 6.55 -6.55 0.23 0.10 -0.15
-1 1.58 -1.58 0.23 0.10 -0.04
-2 0.28 -0.56 0.23 0.10 -0.01
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

-2 0.80 -1.60 0.23 0.10 -0.04


-1 2.73 -2.73 0.23 0.10 -0.06
-1 6.54 -6.54 0.23 0.10 -0.15
-1 2.48 -2.48 0.23 0.10 -0.06
-1 1.45 -1.45 0.23 0.10 -0.03
-1 0.20 -0.20 0.23 0.10 -0.01
-1 2.72 -2.72 0.23 0.10 -0.06
-1 2.67 -2.67 0.23 0.10 -0.06
-1 6.53 -6.53 0.23 0.10 -0.15
-1 2.73 -2.73 0.23 0.10 -0.06
-1 4.57 -4.57 0.23 0.10 -0.11
-1 4.25 -4.25 0.23 0.10 -0.10
-1 0.23 -0.23 0.23 0.10 -0.01
-2 2.28 -4.56 0.23 0.10 -0.11
-1 6.45 -6.45 0.23 0.10 -0.15
-1 5.93 -5.93 0.23 0.10 -0.14
-1 5.22 -5.22 0.23 0.10 -0.12
-1 0.97 -0.97 0.23 0.10 -0.02
-1 5.24 -5.24 0.23 0.10 -0.12
-1 6.60 -6.60 0.23 0.10 -0.15
-1 0.27 -0.27 0.23 0.10 -0.01
-1 2.15 -2.15 0.23 0.10 -0.05
-1 1.45 -1.45 0.23 0.10 -0.03
-3 0.45 -1.35 0.50 0.10 -0.07
-1 2.05 -2.05 0.23 0.10 -0.05
-4 2.00 -8.00 0.23 0.10 -0.18
-1 6.52 -6.52 0.23 0.10 -0.15
-1 6.65 -6.65 0.23 0.10 -0.15
-4 2.00 -8.00 0.23 0.10 -0.18
-3 0.50 -1.50 0.45 0.10 -0.07
-2 2.05 -4.10 0.23 0.10 -0.10
-1 0.50 -0.50 0.23 0.10 -0.01
-1 2.07 -2.07 0.23 0.10 -0.05
deduction beam of block 4 -10 0.35 -3.50 0.23 0.55 -0.44
Block 2

1 3.20 3.20 0.36 0.35 0.40


1 7.93 7.93 0.23 3.45 6.29
1 2.81 2.81 0.23 3.45 2.23
1 6.60 6.60 0.23 2.90 4.40
1 3.45 3.45 0.23 3.45 2.74
1 6.00 6.00 0.23 2.90 4.00
1 5.00 5.00 0.23 2.90 3.34
1 6.60 6.60 0.23 2.90 4.40
1 3.20 3.20 0.23 2.90 2.13
-1 1.17 -1.17 0.23 1.95 -0.53
1 0.44 0.44 0.23 2.90 0.29
1 3.15 3.15 0.23 3.45 2.50
1 1.70 1.70 0.23 3.45 1.35
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 4.15 4.15 0.23 3.45 3.29


1 1.05 1.05 0.23 3.45 0.83
1 3.80 3.80 0.23 3.45 3.02
-2 0.60 -1.20 0.23 1.95 -0.54
-1 0.80 -0.80 0.23 2.85 -0.53
1 3.35 3.35 0.23 3.45 2.66
1 2.00 2.00 0.23 2.90 1.33
1 0.45 0.45 0.23 3.45 0.36
1 2.55 2.55 0.23 2.95 1.73
1 3.70 3.70 0.23 2.90 2.47
1 4.20 4.20 0.23 2.95 2.85
1 4.05 4.05 0.23 0.90 0.84
1 0.55 0.55 0.23 2.95 0.37
1 3.15 3.15 0.23 2.90 2.10
-1 0.95 -0.95 0.23 2.90 -0.63
1 4.50 4.50 0.23 2.90 3.00
1 2.10 2.10 0.23 2.90 1.40
1 4.75 4.75 0.23 3.45 3.77
1 5.25 5.25 0.23 3.45 4.17
1 2.40 2.40 0.36 3.45 2.98
1 2.22 2.22 0.23 3.45 1.76
1 1.12 1.12 0.23 3.45 0.89
2 0.50 1.00 0.45 3.45 1.55
4 2.00 8.00 0.23 0.90 1.66
2 1.65 3.30 0.23 0.90 0.68
1 2.10 2.10 0.23 0.90 0.43
2 6.60 13.20 0.23 3.45 10.47
1 4.10 4.10 0.23 3.45 3.25
2 2.00 4.00 0.23 0.90 0.83
3 0.45 1.35 0.45 3.45 2.10
2 2.00 4.00 0.23 0.90 0.83
1 1.15 1.15 0.23 0.90 0.24
1 1.20 1.20 0.23 0.90 0.25
1 3.50 3.50 0.23 2.90 2.33
3 0.35 1.05 0.35 0.90 0.33
1 2.53 2.53 0.23 0.90 0.52
1 6.56 6.55 0.35 2.90 6.65
1 2.43 2.43 0.35 2.90 2.47
deduction sill band of block 2
-1 7.93 -7.93 0.23 0.10 -0.18
-1 2.81 -2.81 0.23 0.10 -0.07
-1 6.60 -6.60 0.23 0.10 -0.15
-1 3.45 -3.45 0.23 0.10 -0.08
-1 6.00 -6.00 0.23 0.10 -0.14
-1 5.00 -5.00 0.23 0.10 -0.12
-1 6.60 -6.60 0.23 0.10 -0.15
-1 3.20 -3.20 0.23 0.10 -0.07
-1 0.44 -0.44 0.23 0.10 -0.01
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

-1 0.00 0.00 0.23 0.10 0.00


-1 1.70 -1.70 0.23 0.10 -0.04
-1 4.15 -4.15 0.23 0.10 -0.10
-1 1.05 -1.05 0.23 0.10 -0.03
-1 3.80 -3.80 0.23 0.10 -0.09
-1 3.35 -3.35 0.23 0.10 -0.08
-1 2.00 -2.00 0.23 0.10 -0.05
-1 0.45 -0.45 0.23 0.10 -0.01
-1 2.55 -2.55 0.23 0.10 -0.06
-1 3.70 -3.70 0.23 0.10 -0.09
-1 4.20 -4.20 0.23 0.10 -0.10
-1 4.05 -4.05 0.23 0.10 -0.09
-1 0.55 -0.55 0.23 0.10 -0.01
-1 3.15 -3.15 0.23 0.10 -0.07
-1 4.50 -4.50 0.23 0.10 -0.10
-1 2.10 -2.10 0.23 0.10 -0.05
-1 4.75 -4.75 0.23 0.10 -0.11
-1 5.25 -5.25 0.23 0.10 -0.12
-1 2.40 -2.40 0.36 0.10 -0.09
-1 2.22 -2.22 0.23 0.10 -0.05
-1 1.12 -1.12 0.23 0.10 -0.03
-2 0.50 -1.00 0.45 0.10 -0.05
-4 2.00 -8.00 0.23 0.10 -0.18
-2 1.65 -3.30 0.23 0.10 -0.08
-1 2.10 -2.10 0.23 0.10 -0.05
-2 6.60 -13.20 0.23 0.10 -0.30
-1 4.10 -4.10 0.23 0.10 -0.10
-2 2.00 -4.00 0.23 0.10 -0.09
-3 0.45 -1.35 0.45 0.10 -0.06
-2 2.00 -4.00 0.23 0.10 -0.09
-1 1.15 -1.15 0.23 0.10 -0.03
-1 1.20 -1.20 0.23 0.10 -0.03
deduction of beam of block 2 -12 0.35 -4.20 0.23 0.55 -0.53
Total 857.74
Brick Masonary work With ( 1:4 ) Cement
8 Extra Same previous running Bill 38.99
mortar
Block 4
2 1.50 3.00 0.10 3.45 1.04
1 3.03 3.03 0.10 3.45 1.05
1 3.00 3.00 0.10 3.20 0.96
1 7.50 7.50 0.10 3.20 2.40
1 6.00 6.00 0.10 3.20 1.92
1 6.14 6.14 0.10 3.20 1.96
1 4.00 4.00 0.10 3.20 1.28
1 3.90 3.90 0.10 3.20 1.25
1 6.02 6.02 0.10 3.20 1.93
1 6.10 6.10 0.10 3.20 1.95
1 6.72 6.72 0.10 3.20 2.15
1 2.30 2.30 0.10 3.20 0.74
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

0.00
deduction sill band of block 4 -2 1.50 -3.00 0.10 0.10 -0.03
-1 3.03 -3.03 0.10 0.10 -0.03
-1 3.00 -3.00 0.10 0.10 -0.03
-1 7.50 -7.50 0.10 0.10 -0.08
-1 6.00 -6.00 0.10 0.10 -0.06
-1 6.14 -6.14 0.10 0.10 -0.06
-1 4.00 -4.00 0.10 0.10 -0.04
-1 3.90 -3.90 0.10 0.10 -0.04
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

-1 6.02 -6.02 0.10 0.10 -0.06


-1 6.10 -6.10 0.10 0.10 -0.06
-1 6.72 -6.72 0.10 0.10 -0.07
-1 2.30 -2.30 0.10 0.10 -0.02
Block 2 0.00
1 6.70 6.70 0.10 2.95 1.98
1 1.15 1.15 0.10 3.45 0.40
1 2.70 2.70 0.10 2.95 0.80
1 2.40 2.40 0.10 3.20 0.77
3 7.00 21.00 0.10 3.20 6.72
1 3.92 3.92 0.10 3.20 1.25
1 4.00 4.00 0.10 3.20 1.28
2 3.50 7.00 0.10 3.20 2.24
1 3.94 3.94 0.10 3.20 1.26
1 3.80 3.80 0.10 3.20 1.22
1 3.50 3.50 0.10 3.20 1.12
1 2.60 2.60 0.10 3.45 0.90
1 1.58 1.58 0.10 2.00 0.32
dedution of sill band of block 2 -1 6.70 -6.70 0.10 0.10 -0.07
-1 1.15 -1.15 0.10 0.10 -0.01
-1 2.70 -2.70 0.10 0.10 -0.03
-1 2.40 -2.40 0.10 0.10 -0.02
-3 7.00 -21.00 0.10 0.10 -0.21
-1 3.92 -3.92 0.10 0.10 -0.04
-1 4.00 -4.00 0.10 0.10 -0.04
-2 3.50 -7.00 0.10 0.10 -0.07
-1 3.94 -3.94 0.10 0.10 -0.04
-1 3.80 -3.80 0.10 0.10 -0.04
Total 76.70
9 8 R.C.C. Work
10 8.1 P.C.C. 1:1.5:3 (M 20 ) Same as Previous running Bill 1221.90
sill level of block 4
2 2.66 5.32 0.23 0.10 0.12
3 2.71 8.13 0.23 0.10 0.19
1 3.80 3.80 0.23 0.10 0.09
1 6.60 6.60 0.23 0.10 0.15
1 4.50 4.50 0.23 0.10 0.10
2 5.02 10.04 0.23 0.10 0.23
1 6.93 6.93 0.23 0.10 0.16
1 6.55 6.55 0.23 0.10 0.15
1 1.58 1.58 0.23 0.10 0.04
2 0.28 0.56 0.23 0.10 0.01
2 0.80 1.60 0.23 0.10 0.04
1 2.73 2.73 0.23 0.10 0.06
1 6.54 6.54 0.23 0.10 0.15
1 2.48 2.48 0.23 0.10 0.06
1 1.45 1.45 0.23 0.10 0.03
1 0.20 0.20 0.23 0.10 0.00
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 2.72 2.72 0.23 0.10 0.06


1 2.67 2.67 0.23 0.10 0.06
1 6.53 6.53 0.23 0.10 0.15
1 2.73 2.73 0.23 0.10 0.06
1 4.57 4.57 0.23 0.10 0.11
1 4.25 4.25 0.23 0.10 0.10
1 0.23 0.23 0.23 0.10 0.01
2 2.28 4.56 0.23 0.10 0.10
1 6.45 6.45 0.23 0.10 0.15
1 5.93 5.93 0.23 0.10 0.14
1 5.22 5.22 0.23 0.10 0.12
1 0.97 0.97 0.23 0.10 0.02
1 5.24 5.24 0.23 0.10 0.12
1 6.60 6.60 0.23 0.10 0.15
1 0.27 0.27 0.23 0.10 0.01
1 2.15 2.15 0.23 0.10 0.05
1 1.45 1.45 0.23 0.10 0.03
3 0.45 1.35 0.50 0.10 0.07
1 2.05 2.05 0.23 0.10 0.05
4 2.00 8.00 0.23 0.10 0.18
1 6.52 6.52 0.23 0.10 0.15
1 6.65 6.65 0.23 0.10 0.15
4 2.00 8.00 0.23 0.10 0.18
3 0.50 1.50 0.45 0.10 0.07
2 2.05 4.10 0.23 0.10 0.09
1 0.50 0.50 0.23 0.10 0.01
1 2.07 2.07 0.23 0.10 0.05
2 1.50 3.00 0.10 0.10 0.03
1 3.03 3.03 0.10 0.10 0.03
1 3.00 3.00 0.10 0.10 0.03
1 7.50 7.50 0.10 0.10 0.08
1 6.00 6.00 0.10 0.10 0.06
1 6.14 6.14 0.10 0.10 0.06
1 4.00 4.00 0.10 0.10 0.04
1 3.90 3.90 0.10 0.10 0.04
1 6.02 6.02 0.10 0.10 0.06
1 6.10 6.10 0.10 0.10 0.06
1 6.72 6.72 0.10 0.10 0.07
1 2.30 2.30 0.10 0.10 0.02
sill level of block 2
1 7.93 7.93 0.23 0.10 0.18
1 2.81 2.81 0.23 0.10 0.06
1 6.60 6.60 0.23 0.10 0.15
1 3.45 3.45 0.23 0.10 0.08
1 6.00 6.00 0.23 0.10 0.14
1 5.00 5.00 0.23 0.10 0.12
1 6.60 6.60 0.23 0.10 0.15
1 3.20 3.20 0.23 0.10 0.07
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 0.44 0.44 0.23 0.10 0.01


1 3.15 3.15 0.23 0.10 0.07
1 1.70 1.70 0.23 0.10 0.04
1 4.15 4.15 0.23 0.10 0.10
1 1.05 1.05 0.23 0.10 0.02
1 3.80 3.80 0.23 0.10 0.09
-1 0.80 -0.80 0.23 0.10 -0.02
1 3.35 3.35 0.23 0.10 0.08
1 2.00 2.00 0.23 0.10 0.05
1 0.45 0.45 0.23 0.10 0.01
1 2.55 2.55 0.23 0.10 0.06
1 3.70 3.70 0.23 0.10 0.09
1 4.20 4.20 0.23 0.10 0.10
1 4.05 4.05 0.23 0.10 0.09
1 0.55 0.55 0.23 0.10 0.01
1 3.15 3.15 0.23 0.10 0.07
-1 0.95 -0.95 0.23 0.10 -0.02
1 4.50 4.50 0.23 0.10 0.10
1 2.10 2.10 0.23 0.10 0.05
1 4.75 4.75 0.23 0.10 0.11
1 5.25 5.25 0.23 0.10 0.12
1 2.40 2.40 0.36 0.10 0.09
1 2.22 2.22 0.23 0.10 0.05
1 1.12 1.12 0.23 0.10 0.03
2 0.50 1.00 0.45 0.10 0.05
4 2.00 8.00 0.23 0.10 0.18
2 1.65 3.30 0.23 0.10 0.08
1 2.10 2.10 0.23 0.10 0.05
2 6.60 13.20 0.23 0.10 0.30
1 4.10 4.10 0.23 0.10 0.09
2 2.00 4.00 0.23 0.10 0.09
3 0.45 1.35 0.45 0.10 0.06
2 2.00 4.00 0.23 0.10 0.09
1 1.15 1.15 0.23 0.10 0.03
1 1.20 1.20 0.23 0.10 0.03
1 6.70 6.70 0.10 0.10 0.07
1 1.15 1.15 0.10 0.10 0.01
1 2.70 2.70 0.10 0.10 0.03
1 2.40 2.40 0.10 0.10 0.02
3 7.00 21.00 0.10 0.10 0.21
1 3.92 3.92 0.10 0.10 0.04
1 4.00 4.00 0.10 0.10 0.04
2 3.50 7.00 0.10 0.10 0.07
1 3.94 3.94 0.10 0.10 0.04
1 3.80 3.80 0.10 0.10 0.04
sill level of block 1 8 2.00 16.00 0.23 0.10 0.37
4 0.45 1.80 0.45 0.10 0.08
1 1.15 1.15 0.23 0.10 0.03
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 6.60 6.60 0.23 0.10 0.15


1 5.45 5.45 0.23 0.10 0.12
1 1.90 1.90 0.23 0.10 0.04
1 1.95 1.95 0.23 0.10 0.04
1 3.50 3.50 0.23 0.10 0.08
1 1.00 1.00 0.23 0.10 0.02
1 5.40 5.40 0.23 0.10 0.12
2 1.70 3.40 0.23 0.10 0.08
2 0.25 0.50 0.23 0.10 0.01
1 1.00 1.00 0.23 0.10 0.02
1 5.40 5.40 0.23 0.10 0.12
1 4.60 4.60 0.23 0.10 0.11
1 1.00 1.00 0.23 0.10 0.02
1 6.60 6.60 0.23 0.10 0.15
1 2.30 2.30 0.23 0.10 0.05
1 0.30 0.30 0.23 0.10 0.01
1 0.80 0.80 0.23 0.10 0.02
1 1.75 1.75 0.23 0.10 0.04
1 0.30 0.30 0.23 0.10 0.01
5 6.60 33.00 0.23 0.10 0.75
1 2.25 2.25 0.23 0.10 0.05
1 2.10 2.10 0.23 0.10 0.05
1 0.50 0.50 0.23 0.10 0.01
1 1.20 1.20 0.23 0.10 0.03
1 5.50 5.50 0.23 0.10 0.13
2 2.56 5.12 0.10 0.10 0.05
4 5.50 22.00 0.10 0.10 0.22
1 2.40 2.40 0.10 0.10 0.02
1 0.23 0.23 0.10 0.10 0.00
1 3.40 3.40 0.10 0.10 0.03
1 3.40 3.40 0.10 0.10 0.03
sill level of block 3 1 6.55 6.55 0.23 0.10 0.15
1 6.55 6.55 0.23 0.10 0.15
1 2.60 2.60 0.23 0.10 0.06
1 1.45 1.45 0.23 0.10 0.03
1 0.23 0.23 0.23 0.10 0.01
1 6.60 6.60 0.23 0.10 0.15
1 0.45 0.45 0.23 0.10 0.01
1 0.45 0.45 0.23 0.10 0.01
1 2.00 2.00 0.23 0.10 0.05
1 2.00 2.00 0.23 0.10 0.05
2 2.00 4.00 0.23 0.10 0.09
1 1.70 1.70 0.23 0.10 0.04
1 1.70 1.70 0.23 0.10 0.04
1 2.22 2.22 0.23 0.10 0.05
1 0.25 0.25 0.25 0.10 0.01
1 6.60 6.60 0.23 0.10 0.15
1 0.80 0.80 0.23 0.10 0.02
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 2.10 2.10 0.23 0.10 0.05


1 7.50 7.50 0.23 0.10 0.17
1 0.45 0.45 0.23 0.10 0.01
1 0.70 0.70 0.23 0.10 0.02
3 0.45 1.35 0.45 0.10 0.06
1 1.75 1.75 0.45 0.10 0.08
1 4.00 4.00 0.23 0.10 0.09
1 2.85 2.85 0.23 0.10 0.07
1 0.25 0.25 0.25 0.10 0.01
1 1.06 1.06 0.23 0.10 0.02
1 1.06 1.06 0.23 0.10 0.02
1 1.60 1.60 0.23 0.10 0.04
1 1.90 1.90 0.23 0.10 0.04
1 1.25 1.25 0.23 0.10 0.03
1 0.23 0.23 0.23 0.10 0.01
1 2.02 2.02 0.23 0.10 0.05
1 2.50 2.50 0.23 0.10 0.06
1 1.95 1.95 0.23 0.10 0.04
1 1.75 1.75 0.23 0.10 0.04
1 0.23 0.23 0.23 0.10 0.01
1 0.55 0.55 0.23 0.10 0.01
1 7.20 7.20 0.23 0.10 0.16
3 0.45 1.35 0.45 0.10 0.06
6 2.00 12.00 0.23 0.10 0.27
3 0.35 1.05 0.35 0.10 0.04
1 5.45 5.45 0.10 0.10 0.06
1 5.45 5.45 0.10 0.10 0.06
1 1.20 1.20 0.10 0.10 0.01
1 6.97 6.97 0.10 0.10 0.07
2 3.15 6.30 0.10 0.10 0.06
2 4.06 8.12 0.10 0.10 0.08
1 5.60 5.60 0.10 0.10 0.06
1 6.65 6.65 0.10 0.10 0.07
1 4.10 4.10 0.10 0.10 0.04
1 3.95 3.95 0.10 0.10 0.04
1 1.90 1.90 0.10 0.10 0.02
1 2.70 2.70 0.10 0.10 0.03
1 3.05 3.05 0.10 0.10 0.03
4 2.70 10.80 0.10 0.10 0.11
4 0.25 1.00 0.10 0.10 0.01
4 0.25 1.00 0.10 0.10 0.01
1 2.90 2.90 0.10 0.10 0.03
1 0.23 0.23 0.10 0.10 0.00
sill level of veranda 1 23.00 23.00 0.65 0.10 1.50
1 23.00 23.00 0.45 0.10 1.04
1 21.00 21.00 0.35 0.10 0.74
1 2.10 2.10 0.35 0.10 0.07
1 23.00 23.00 0.35 0.10 0.81
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

5 1.00 5.00 0.10 0.10 0.05


Total 1240.97
11 8.2 P. C.C 1:1:2 ( M 25 ) Same as Previous running Bill 541.143
12 8.3 Reinforcement works Same as Previous running Bill 267272.61
Reinforcement Works of block 5
Primary Beams

Grid 15
Top and bottom 20mm dia bar 8 no 8 17.81 142.48 2.46 350.50

Lap length of 20 mm dia bar 8 1.60 12.80 2.46 31.48

Both side development length, Ld 16 0.85 13.60 2.46 33.45

Top end cut piece 20mm dia 4 3.60 14.40 2.46 35.42

Top middle cut piece 20mm dia 4 3.60 14.40 2.46 35.42

End top cut piece 20mm dia 4 2.00 8.00 2.46 19.68
Secondary beam between grid 15 - 16
Top and bottom 20mm dia bar 8 no 8 14.93 119.40 2.46 293.72

Lap length of 20 mm dia bar 8 1.60 12.80 2.46 31.48

Both side development length, Ld 16 0.60 9.60 2.46 23.61


Grid 16
Top and bottom 20mm dia bar 8 no 8 14.93 119.40 2.46 293.72

Lap length of 20 mm dia bar 8 1.60 12.80 2.46 31.48

Both side development length, Ld 16 0.85 13.60 2.46 33.45


Top end cut piece 20mm dia 4 2.00 8.00 2.46 19.68
Middle bottom 20mm dia 4 2.90 11.60 2.46 28.53
Middle top 20mm dia 4 4.60 18.40 2.46 45.26
Middle bottom 20mm dia 4 3.40 13.60 2.46 33.45
End bottom 20mm dia 4 2.20 8.80 2.46 21.64
Secondary beam between grid 16 - 17
Top and bottom 20mm dia bar 8 no 8 14.93 119.40 2.46 293.72

Lap length of 20 mm dia bar 8 1.65 13.20 2.46 32.47

Both side development length, Ld 16 0.60 9.60 2.46 23.61


Grid 17
Top and bottom 20mm dia bar 8 no 8 14.93 119.40 2.46 293.72

Lap length of 20 mm dia bar 8 1.65 13.20 2.46 32.47

Both side development length, Ld 16 0.85 13.60 2.46 33.45

Cut piece
end top 20mm dia 4 2.40 9.60 2.46 23.61

Middle bottom 20mm dia 4 3.70 14.80 2.46 36.40

Middle top 20mm dia 4 3.70 14.80 2.46 36.40

Middle bottom 20mm dia 4 3.85 15.40 2.46 37.88

end top 20mm dia 4 2.20 8.80 2.46 21.64


Grid L
Top and bottom 20mm dia bar 8 no 8 17.85 142.80 2.46 351.28

Lap length of 20 mm dia bar 8 1.55 12.40 2.46 30.50

Both side development length, Ld 16 0.85 13.60 2.46 33.45

Cut piece
end top 20mm dia 2 3.50 7.00 2.46 17.22

middle top 16mm dia 2 5.80 11.60 1.58 18.32

end top 16mm dia 2 6.40 12.80 1.58 20.22


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

Secondary beam between grid L - M


Top and bottom 20mm dia bar 8 no 8 17.85 142.80 2.46 351.28

Lap length of 20 mm dia bar 8 1.70 13.60 2.46 33.45

Both side development length, Ld 16 0.60 9.60 2.46 23.61


Grid M
Top and bottom 20mm dia bar 8 no 8 17.85 142.80 2.46 351.28

Lap length of 20 mm dia bar 8 1.40 11.20 2.46 27.55

Both side development length, Ld 16 0.85 13.60 2.46 33.45

Cut piece
end top 20mm dia 4 5.40 21.60 2.46 53.13

Middle bottom 20mm dia 4 2.70 10.80 2.46 26.56

Middle top 20mm dia 4 4.30 17.20 2.46 42.31

Middle bottom 20mm dia 4 3.30 13.20 2.46 32.47

end top 20mm dia 4 2.20 8.80 2.46 21.64


Secondary beam between grid M - N
Top and bottom 20mm dia bar 8 no 8 17.85 142.80 2.46 351.28

Lap length of 20 mm dia bar 8 1.68 13.44 2.46 33.06

Both side development length, Ld 16 0.60 9.60 2.46 23.61


Grid L
Top and bottom 20mm dia bar 8 no 8 17.85 142.80 2.46 351.28

Lap length of 20 mm dia bar 8 1.60 12.80 2.46 31.48

Both side development length, Ld 16 0.85 13.60 2.46 33.45

Cut piece
end top 20mm dia 2 1.40 2.80 2.46 6.88

Middle bottom 20mm dia 2 3.35 6.70 2.46 16.48

Middle top 20mm dia 2 4.55 9.10 2.46 22.38

Middle bottom 20mm dia 2 3.30 6.60 2.46 16.23

end top 20mm dia 2 4.00 8.00 2.46 19.68

Slab
Bottom bar (panel 1)
Main bar 10mm dia 110 14.93 1641.75 0.62 1012.95

Lap length 110 1.25 137.50 0.62 84.83

Distribution bar 8mm dia 92 17.85 1642.20 0.39 640.45

Lap length 92 1.25 115.00 0.39 44.85

Bottom bar (Panel 2)


Main bar 10mm dia 17 3.24 54.99 0.62 33.92

Distribution bar 8mm dia 17 3.20 54.40 0.39 21.21

Cut piece (N-S) (Panel 1)


Distribution bar including lap 8mm dia 48 15.80 758.40 0.39 295.77

Main bar 10mm dia 160 1.25 200.00 0.62 123.40

Main bar 10mm dia 169 2.20 371.80 0.62 229.40

Cut piece (E -W) (panel 1)


Distribution bar including lap 8mm dia 39 26.30 1025.70 0.39 400.02

Main bar 10mm dia 168 1.25 210.00 0.62 129.57

Main bar 10mm dia 286 2.20 629.20 0.62 388.21

Cut piece (Panel 2)


Main bar 10mm dia 34 1.25 42.50 0.62 26.22

Distribution bar 8mm dia 13 3.30 42.90 0.39 16.73


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

8 mm dia. bars in stirrups


Grid 15 88 2.00 176.00 0.39 68.64
88 1.70 149.60 0.39 58.34

Grid 16 80 2.00 160.00 0.39 62.40


80 1.70 136.00 0.39 53.04

Grid 17 87 2.00 174.00 0.39 67.86


87 1.70 147.90 0.39 57.68

Grid L 92 2.00 184.00 0.39 71.76


92 1.70 156.40 0.39 60.99

Grid M 94 2.00 188.00 0.39 73.32


94 1.70 159.80 0.39 62.32

Grid N 87 2.00 174.00 0.39 67.86


87 1.70 147.90 0.39 57.68
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

8 mm dia. bars in stirrups in secondary beam 85 1.90 161.50 0.39 62.98

85 1.60 136.00 0.39 53.04


85 1.90 161.50 0.39 62.98
85 1.60 136.00 0.39 53.04
100 1.90 190.00 0.39 74.10
100 1.60 160.00 0.39 62.40
98 1.90 186.20 0.39 72.61
98 1.60 156.80 0.39 61.15

Duct bar
16mm dia 4 4.15 16.60 1.58 26.22

stirrups 8mm dia 18 0.59 10.69 0.39 4.16

16mm dia 3 1.10 3.30 1.58 5.21

10mm dia 1 1.10 1.10 0.62 0.67

stirrups 8mm dia 4 0.59 2.37 0.39 0.92

16mm dia 4 4.15 16.60 1.58 26.22

stirrups 8mm dia 20 0.59 11.88 0.39 4.63

10mm dia 4 1.45 5.80 0.62 3.57

stirrups 8mm dia 6 0.59 3.56 0.39 1.38

Chair 105 0.45 47.25 0.62 29.29

Pillar
Pillar 1
32mm dia 1 3.00 3.00 6.31 18.93

32mm dia 1 2.85 2.85 6.31 17.98

32mm dia 1 2.72 2.72 6.31 17.16

32mm dia 1 2.51 2.51 6.31 15.83

25mm dia 1 4.20 4.20 3.85 16.17

25mm dia 1 4.00 4.00 3.85 15.40

25mm dia 1 4.02 4.02 3.85 15.47

25mm dia 1 3.50 3.50 3.85 13.47

25mm dia 1 3.20 3.20 3.85 12.32

25mm dia 1 2.46 2.46 3.85 9.47

large Stirrups 8mm dia 5 2.20 11.00 0.39 4.29

Small stirrups 8mm dia 5 1.55 7.75 0.39 3.02

Pillar 2
25mm dia 1 4.20 4.20 3.85 16.17

25mm dia 1 4.00 4.00 3.85 15.40

25mm dia 1 3.24 3.24 3.85 12.47

25mm dia 1 3.20 3.20 3.85 12.32

25mm dia 2 3.00 6.00 3.85 23.10

25mm dia 2 3.00 6.00 3.85 23.10

25mm dia 1 2.80 2.80 3.85 10.78

large Stirrups 8mm dia 5 2.20 11.00 0.39 4.29

Small stirrups 8mm dia 5 1.55 7.75 0.39 3.02

Pillar 3
32mm dia 1 3.00 3.00 6.31 18.93

25mm dia 1 3.90 3.90 3.85 15.01

25mm dia 1 3.80 3.80 3.85 14.63

25mm dia 1 3.65 3.65 3.85 14.05


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

25mm dia 1 3.50 3.50 3.85 13.47


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

25mm dia 1 3.29 3.29 3.85 12.66

25mm dia 1 3.05 3.05 3.85 11.74

25mm dia 1 3.00 3.00 3.85 11.55

25mm dia 1 3.10 3.10 3.85 11.93

25mm dia 1 3.10 3.10 3.85 11.93

20mm dia 1 3.70 3.70 2.46 9.10

large Stirrups 8mm dia 5 2.20 11.00 0.39 4.29

Small stirrups 8mm dia 5 1.55 7.75 0.39 3.02

Pillar 4
32mm dia 1 3.40 3.40 6.31 21.45

32mm dia 1 3.02 3.02 6.31 19.05

32mm dia 1 2.60 2.60 6.31 16.40

32mm dia 1 2.40 2.40 6.31 15.14

25mm dia 1 3.50 3.50 3.85 13.47

25mm dia 1 3.30 3.30 3.85 12.70

25mm dia 1 3.00 3.00 3.85 11.55

25mm dia 1 3.10 3.10 3.85 11.93

25mm dia 1 2.80 2.80 3.85 10.78

25mm dia 1 2.60 2.60 3.85 10.01

large Stirrups 8mm dia 5 2.20 11.00 0.39 4.29

Small stirrups 8mm dia 5 1.55 7.75 0.39 3.02

Pillar 5
32mm dia 1 3.00 3.00 6.31 18.93

32mm dia 1 2.80 2.80 6.31 17.66

25mm dia 1 4.20 4.20 3.85 16.17

25mm dia 1 3.80 3.80 3.85 14.63

25mm dia 1 3.00 3.00 3.85 11.55

25mm dia 1 3.50 3.50 3.85 13.47

25mm dia 1 3.21 3.21 3.85 12.35

25mm dia 1 3.10 3.10 3.85 11.93

25mm dia 1 2.80 2.80 3.85 10.78

25mm dia 1 2.60 2.60 3.85 10.01

large Stirrups 8mm dia 5 2.20 11.00 0.39 4.29

Small stirrups 8mm dia 5 1.55 7.75 0.39 3.02

Pillar 6
25mm dia 1 4.60 4.60 3.85 17.71

25mm dia 1 3.40 3.40 3.85 13.09

25mm dia 1 3.34 3.34 3.85 12.85

25mm dia 2 3.10 6.20 3.85 23.87

25mm dia 1 2.80 2.80 3.85 10.78

25mm dia 2 3.00 6.00 3.85 23.10

25mm dia 2 2.70 5.40 3.85 20.79

25mm dia 1 2.50 2.50 3.85 9.62

25mm dia 1 2.50 2.50 3.85 9.62

large Stirrups 8mm dia 5 2.20 11.00 0.39 4.29

Small stirrups 8mm dia 5 1.55 7.75 0.39 3.02

Pillar 7
32mm dia 2 3.50 7.00 6.31 44.17
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

32mm dia 2 2.50 5.00 6.31 31.55

25mm dia 1 4.30 4.30 3.85 16.55

25mm dia 1 3.50 3.50 3.85 13.47

25mm dia 1 2.80 2.80 3.85 10.78

25mm dia 3 2.80 8.40 3.85 32.34

25mm dia 1 2.50 2.50 3.85 9.62

25mm dia 1 2.40 2.40 3.85 9.24

large Stirrups 8mm dia 5 2.20 11.00 0.39 4.29

Small stirrups 8mm dia 5 1.55 7.75 0.39 3.02

Pillar 8
25mm dia 3 3.70 11.10 3.85 42.73

25mm dia 2 3.40 6.80 3.85 26.18

25mm dia 2 3.30 6.60 3.85 25.41

25mm dia 2 3.30 6.60 3.85 25.41

25mm dia 1 2.90 2.90 3.85 11.16

25mm dia 1 2.70 2.70 3.85 10.39

25mm dia 1 2.60 2.60 3.85 10.01

large Stirrups 8mm dia 5 2.20 11.00 0.39 4.29

Small stirrups 8mm dia 5 1.55 7.75 0.39 3.02

Pillar 9
32mm dia 1 3.00 3.00 6.31 18.93

32mm dia 2 2.60 5.20 6.31 32.81

32mm dia 1 2.50 2.50 6.31 15.77

25mm dia 2 4.20 8.40 3.85 32.34

25mm dia 1 4.00 4.00 3.85 15.40

25mm dia 2 3.80 7.60 3.85 29.26

25mm dia 1 2.70 2.70 3.85 10.39

25mm dia 1 2.60 2.60 3.85 10.01

25mm dia 1 2.30 2.30 3.85 8.85

large Stirrups 8mm dia 5 2.20 11.00 0.39 4.29

Small stirrups 8mm dia 5 1.55 7.75 0.39 3.02

Pillar 10
25mm dia 3 3.80 11.40 3.85 43.89

25mm dia 2 3.00 6.00 3.85 23.10

25mm dia 2 3.00 6.00 3.85 23.10

25mm dia 2 3.00 6.00 3.85 23.10

25mm dia 1 3.10 3.10 3.85 11.93

25mm dia 1 2.90 2.90 3.85 11.16

25mm dia 1 2.40 2.40 3.85 9.24

large Stirrups 8mm dia 5 2.20 11.00 0.39 4.29

Small stirrups 8mm dia 5 1.55 7.75 0.39 3.02

Pillar 11
25mm dia 2 3.30 6.60 3.85 25.41

25mm dia 1 3.20 3.20 3.85 12.32

25mm dia 2 3.00 6.00 3.85 23.10

25mm dia 2 3.00 6.00 3.85 23.10

25mm dia 1 2.90 2.90 3.85 11.16

20mm dia 1 3.10 3.10 2.46 7.62


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

20mm dia 1 2.70 2.70 2.46 6.64

20mm dia 2 2.70 5.40 2.46 13.28

Pillar 12
25mm dia 2 3.00 6.00 3.85 23.10

25mm dia 1 3.50 3.50 3.85 13.47

25mm dia 2 3.00 6.00 3.85 23.10

25mm dia 2 3.50 7.00 3.85 26.95

25mm dia 1 2.90 2.90 3.85 11.16

20mm dia 1 3.10 3.10 2.46 7.62

20mm dia 1 2.60 2.60 2.46 6.39

20mm dia 2 2.45 4.90 2.46 12.05

Pillar 13
25mm dia 2 3.40 6.80 3.85 26.18

25mm dia 2 3.20 6.40 3.85 24.64

25mm dia 3 3.50 10.50 3.85 40.42

25mm dia 1 3.10 3.10 3.85 11.93

large Stirrups 8mm dia 5 2.20 11.00 0.39 4.29

Small stirrups 8mm dia 5 1.55 7.75 0.39 3.02

Sill level longitudinal reinforcement of block 2


10mm dia 3 7.93 23.79 0.62 14.74
3 2.81 8.43 0.62 5.22
3 6.60 19.80 0.62 12.27
3 3.45 10.35 0.62 6.41
3 6.00 18.00 0.62 11.16
3 5.00 15.00 0.62 9.30
3 6.60 19.80 0.62 12.27
3 3.20 9.60 0.62 5.95
3 0.44 1.32 0.62 0.81
3 3.15 9.45 0.62 5.85
3 1.70 5.10 0.62 3.16
3 4.15 12.45 0.62 7.71
3 1.05 3.15 0.62 1.95
3 3.80 11.40 0.62 7.06
-2 0.80 -1.60 0.62 -1.00
3 3.35 10.05 0.62 6.23
3 2.00 6.00 0.62 3.72
3 0.45 1.35 0.62 0.83
3 2.55 7.65 0.62 4.74
3 3.70 11.10 0.62 6.88
3 4.20 12.60 0.62 7.81
3 4.05 12.15 0.62 7.53
3 0.55 1.65 0.62 1.02
3 3.15 9.45 0.62 5.85
-2 0.95 -1.90 0.62 -1.18
3 4.50 13.50 0.62 8.37
3 2.10 6.30 0.62 3.90
3 4.75 14.25 0.62 8.83
3 5.25 15.75 0.62 9.76
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

3 2.40 7.20 0.62 4.46


3 2.22 6.66 0.62 4.12
3 1.12 3.36 0.62 2.08
6 0.50 3.00 0.62 1.86
12 2.00 24.00 0.62 14.88
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

6 1.65 9.90 0.62 6.13


3 2.10 6.30 0.62 3.90
6 6.60 39.60 0.62 24.55
3 4.10 12.30 0.62 7.62
6 2.00 12.00 0.62 7.44
9 0.45 4.05 0.62 2.51
6 2.00 12.00 0.62 7.44
3 1.15 3.45 0.62 2.13
3 1.20 3.60 0.62 2.23
3 6.70 20.10 0.62 12.46
3 1.15 3.45 0.62 2.13
3 2.70 8.10 0.62 5.02
3 2.40 7.20 0.62 4.46
9 7.00 63.00 0.62 39.06
3 3.92 11.76 0.62 7.29
3 4.00 12.00 0.62 7.44
6 3.50 21.00 0.62 13.02
3 3.94 11.82 0.62 7.32
3 3.80 11.40 0.62 7.06

Sill level lateral reinforcement of block 2

8mm dia bar 64 0.23 14.72 0.39 5.74


23 0.23 5.29 0.39 2.06
53 0.23 12.19 0.39 4.75
28 0.23 6.44 0.39 2.51
49 0.23 11.27 0.39 4.39
41 0.23 9.43 0.39 3.67
53 0.23 12.19 0.39 4.75
26 0.23 5.98 0.39 2.33
4 0.23 0.92 0.39 0.35
26 0.23 5.98 0.39 2.33
14 0.23 3.22 0.39 1.25
34 0.23 7.82 0.39 3.04
9 0.23 2.07 0.39 0.80
31 0.23 7.13 0.39 2.78
7 0.23 1.61 0.39 0.62
27 0.23 6.21 0.39 2.42
17 0.23 3.91 0.39 1.52
4 0.23 0.92 0.39 0.35
21 0.23 4.83 0.39 1.88
30 0.23 6.90 0.39 2.69
34 0.23 7.82 0.39 3.04
33 0.23 7.59 0.39 2.96
5 0.23 1.15 0.39 0.44
26 0.23 5.98 0.39 2.33
8 0.23 1.84 0.39 0.71
37 0.23 8.51 0.39 3.31
17 0.23 3.91 0.39 1.52
39 0.23 8.97 0.39 3.49
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

43 0.23 9.89 0.39 3.85


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

20 0.36 7.20 0.39 2.80


18 0.23 4.14 0.39 1.61
9 0.23 2.07 0.39 0.80
5 0.45 2.25 0.39 0.87
17 0.23 3.91 0.39 1.52
14 0.23 3.22 0.39 1.25
17 0.23 3.91 0.39 1.52
53 0.23 12.19 0.39 4.75
33 0.23 7.59 0.39 2.96
17 0.23 3.91 0.39 1.52
4 0.45 1.80 0.39 0.70
17 0.23 3.91 0.39 1.52
10 0.23 2.30 0.39 0.89
10 0.23 2.30 0.39 0.89
54 0.10 5.40 0.39 2.10
10 0.10 1.00 0.39 0.39
22 0.10 2.20 0.39 0.85
20 0.10 2.00 0.39 0.78
57 0.10 5.70 0.39 2.22
32 0.10 3.20 0.39 1.24
33 0.10 3.30 0.39 1.28
29 0.10 2.90 0.39 1.13
32 0.10 3.20 0.39 1.24
31 0.10 3.10 0.39 1.20

Sill level longitudinal reinforcement of block 4

10mm dia bar 6 2.66 15.96 0.62 9.89


9 2.71 24.39 0.62 15.12
3 3.80 11.40 0.62 7.06
3 6.60 19.80 0.62 12.27
3 4.50 13.50 0.62 8.37
6 5.02 30.12 0.62 18.67
3 6.93 20.79 0.62 12.88
3 6.55 19.65 0.62 12.18
3 1.58 4.74 0.62 2.93
6 0.28 1.68 0.62 1.04
6 0.80 4.80 0.62 2.97
3 2.73 8.19 0.62 5.07
3 6.54 19.62 0.62 12.16
3 2.48 7.44 0.62 4.61
3 1.45 4.35 0.62 2.69
3 0.20 0.60 0.62 0.37
3 2.72 8.16 0.62 5.05
3 2.67 8.01 0.62 4.96
3 6.53 19.59 0.62 12.14
3 2.73 8.19 0.62 5.07
3 4.57 13.71 0.62 8.50
3 4.25 12.75 0.62 7.90
3 0.23 0.69 0.62 0.42
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

6 2.28 13.68 0.62 8.48


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

3 6.45 19.35 0.62 11.99


3 5.93 17.79 0.62 11.02
3 5.22 15.66 0.62 9.70
3 0.97 2.91 0.62 1.80
3 5.24 15.72 0.62 9.74
3 6.60 19.80 0.62 12.27
3 0.27 0.81 0.62 0.50
3 2.15 6.45 0.62 3.99
3 1.45 4.35 0.62 2.69
9 0.45 4.05 0.62 2.51
3 2.05 6.15 0.62 3.81
12 2.00 24.00 0.62 14.88
3 6.52 19.56 0.62 12.12
3 6.65 19.95 0.62 12.36
12 2.00 24.00 0.62 14.88
9 0.50 4.50 0.62 2.79
6 2.05 12.30 0.62 7.62
3 0.50 1.50 0.62 0.93
3 2.07 6.21 0.62 3.85
6 1.50 9.00 0.62 5.58
3 3.03 9.09 0.62 5.63
3 3.00 9.00 0.62 5.58
3 7.50 22.50 0.62 13.95
3 6.00 18.00 0.62 11.16
3 6.14 18.42 0.62 11.42
3 4.00 12.00 0.62 7.44
3 3.90 11.70 0.62 7.25
3 6.02 18.06 0.62 11.19
3 6.10 18.30 0.62 11.34
3 6.72 20.16 0.62 12.49
3 2.30 6.90 0.62 4.27
Sill level lateral reinforcement of block 4
8mm dia bar 22 0.23 5.06 0.39 1.97
22 0.23 5.06 0.39 1.97
31 0.23 7.13 0.39 2.78
53 0.23 12.19 0.39 4.75
37 0.23 8.51 0.39 3.31
41 0.23 9.43 0.39 3.67
56 0.23 12.88 0.39 5.02
53 0.23 12.19 0.39 4.75
13 0.23 2.99 0.39 1.16
3 0.23 0.69 0.39 0.26
7 0.23 1.61 0.39 0.62
22 0.23 5.06 0.39 1.97
53 0.23 12.19 0.39 4.75
20 0.23 4.60 0.39 1.79
12 0.23 2.76 0.39 1.07
2 0.23 0.46 0.39 0.17
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

22 0.23 5.06 0.39 1.97


22 0.23 5.06 0.39 1.97
53 0.23 12.19 0.39 4.75
22 0.23 5.06 0.39 1.97
37 0.23 8.51 0.39 3.31
35 0.23 8.05 0.39 3.13
2 0.23 0.46 0.39 0.17
19 0.23 4.37 0.39 1.70
52 0.23 11.96 0.39 4.66
48 0.23 11.04 0.39 4.30
42 0.23 9.66 0.39 3.76
8 0.23 1.84 0.39 0.71
42 0.23 9.66 0.39 3.76
53 0.23 12.19 0.39 4.75
3 0.23 0.69 0.39 0.26
18 0.23 4.14 0.39 1.61
12 0.23 2.76 0.39 1.07
4 0.50 2.00 0.39 0.78
17 0.23 3.91 0.39 1.52
17 0.23 3.91 0.39 1.52
53 0.23 12.19 0.39 4.75
54 0.23 12.42 0.39 4.84
17 0.23 3.91 0.39 1.52
5 0.45 2.25 0.39 0.87
17 0.23 3.91 0.39 1.52
5 0.23 1.15 0.39 0.44
17 0.23 3.91 0.39 1.52
13 0.10 1.30 0.39 0.50
25 0.10 2.50 0.39 0.97
25 0.10 2.50 0.39 0.97
61 0.10 6.10 0.39 2.37
49 0.10 4.90 0.39 1.91
50 0.10 5.00 0.39 1.95
33 0.10 3.30 0.39 1.28
32 0.10 3.20 0.39 1.24
49 0.10 4.90 0.39 1.91
49 0.10 4.90 0.39 1.91
54 0.10 5.40 0.39 2.10
19 0.10 1.90 0.39 0.74

Sill level longitudinal reinforcement of block 1

10mm dia bar 16 2.00 32.00 0.62 19.84


8 0.45 3.60 0.62 2.23
2 1.15 2.30 0.62 1.42
2 6.60 13.20 0.62 8.18
2 5.45 10.90 0.62 6.75
2 1.90 3.80 0.62 2.35
2 1.95 3.90 0.62 2.41
2 3.50 7.00 0.62 4.34
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

2 1.00 2.00 0.62 1.24


2 5.40 10.80 0.62 6.69
4 1.70 6.80 0.62 4.21
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

4 0.25 1.00 0.62 0.62


2 1.00 2.00 0.62 1.24
2 5.40 10.80 0.62 6.69
2 4.60 9.20 0.62 5.70
2 1.00 2.00 0.62 1.24
2 6.60 13.20 0.62 8.18
2 2.30 4.60 0.62 2.85
2 0.30 0.60 0.62 0.37
2 0.80 1.60 0.62 0.99
2 1.75 3.50 0.62 2.17
2 0.30 0.60 0.62 0.37
10 6.60 66.00 0.62 40.92
2 2.25 4.50 0.62 2.79
2 2.10 4.20 0.62 2.60
2 0.50 1.00 0.62 0.62
2 1.20 2.40 0.62 1.48
2 5.50 11.00 0.62 6.82
4 2.56 10.24 0.62 6.34
8 5.50 44.00 0.62 27.28
2 2.40 4.80 0.62 2.97
2 0.23 0.46 0.62 0.28
2 3.40 6.80 0.62 4.21
2 3.40 6.80 0.62 4.21
Sill level lateral reinforcement of block 1 129 0.23 29.48 0.39 11.49
8mm dia bar 15 0.45 6.75 0.39 2.63
10 0.23 2.28 0.39 0.88
53 0.23 12.11 0.39 4.72
44 0.23 10.05 0.39 3.91
16 0.23 3.65 0.39 1.42
16 0.23 3.65 0.39 1.42
29 0.23 6.62 0.39 2.58
9 0.23 2.05 0.39 0.79
44 0.23 10.05 0.39 3.91
28 0.23 6.40 0.39 2.49
5 0.23 1.14 0.39 0.44
9 0.23 2.05 0.39 0.79
44 0.23 10.05 0.39 3.91
37 0.23 8.45 0.39 3.29
9 0.23 2.05 0.39 0.79
53 0.23 12.11 0.39 4.72
19 0.23 4.34 0.39 1.69
3 0.23 0.68 0.39 0.26
7 0.23 1.60 0.39 0.62
15 0.23 3.42 0.39 1.33
3 0.23 0.68 0.39 0.26
265 0.23 60.57 0.39 23.62
19 0.23 4.34 0.39 1.69
17 0.23 3.88 0.39 1.51
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

5 0.23 1.14 0.39 0.44


10 0.23 2.28 0.39 0.88
45 0.23 10.28 0.39 4.00
41 0.10 4.16 0.39 1.62
177 0.10 17.98 0.39 7.01
20 0.10 2.03 0.39 0.79
2 0.10 0.20 0.39 0.07
28 0.10 2.84 0.39 1.10
28 0.10 2.84 0.39 1.10

Sill level longitudinal reinforcement of block 3 2 6.55 13.10 0.62 8.12

10mm dia bar 2 6.55 13.10 0.62 8.12

2 2.60 5.20 0.62 3.22


2 1.45 2.90 0.62 1.79
2 0.23 0.46 0.62 0.28
2 6.60 13.20 0.62 8.18
2 0.45 0.90 0.62 0.55
2 0.45 0.90 0.62 0.55
2 2.00 4.00 0.62 2.48
2 2.00 4.00 0.62 2.48
4 2.00 8.00 0.62 4.96
2 1.70 3.40 0.62 2.10
2 1.70 3.40 0.62 2.10
2 2.22 4.44 0.62 2.75
2 0.25 0.50 0.62 0.31
2 6.60 13.20 0.62 8.18
2 0.80 1.60 0.62 0.99
2 2.10 4.20 0.62 2.60
2 7.50 15.00 0.62 9.30
2 0.45 0.90 0.62 0.55
2 0.70 1.40 0.62 0.86
6 0.45 2.70 0.62 1.67
2 1.75 3.50 0.62 2.17
2 4.00 8.00 0.62 4.96
2 2.85 5.70 0.62 3.53
2 0.25 0.50 0.62 0.31
2 1.06 2.12 0.62 1.31
2 1.06 2.12 0.62 1.31
2 1.60 3.20 0.62 1.98
2 1.90 3.80 0.62 2.35
2 1.25 2.50 0.62 1.55
2 0.23 0.46 0.62 0.28
2 2.02 4.04 0.62 2.50
2 2.50 5.00 0.62 3.10
2 1.95 3.90 0.62 2.41
2 1.75 3.50 0.62 2.17
2 0.23 0.46 0.62 0.28
2 0.55 1.10 0.62 0.68
2 7.20 14.40 0.62 8.92
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

6 0.45 2.70 0.62 1.67


12 2.00 24.00 0.62 14.88
6 0.35 2.10 0.62 1.30
2 5.45 10.90 0.62 6.75
2 5.45 10.90 0.62 6.75
2 1.20 2.40 0.62 1.48
2 6.97 13.94 0.62 8.64
4 3.15 12.60 0.62 7.81
4 4.06 16.24 0.62 10.06
2 5.60 11.20 0.62 6.94
2 6.65 13.30 0.62 8.24
2 4.10 8.20 0.62 5.08
2 3.95 7.90 0.62 4.89
2 1.90 3.80 0.62 2.35
2 2.70 5.40 0.62 3.34
2 3.05 6.10 0.62 3.78
8 2.70 21.60 0.62 13.39
8 0.25 2.00 0.62 1.24
8 0.25 2.00 0.62 1.24
2 2.90 5.80 0.62 3.59
2 0.23 0.46 0.62 0.28
Sill level lateral reinforcement of block 3 53 0.23 12.11 0.39 4.72
8mm dia bar 53 0.23 12.11 0.39 4.72
21 0.23 4.80 0.39 1.87
12 0.23 2.74 0.39 1.06
2 0.23 0.45 0.39 0.17
53 0.23 12.11 0.39 4.72
4 0.23 0.91 0.39 0.35
4 0.23 0.91 0.39 0.35
17 0.23 3.88 0.39 1.51
17 0.23 3.88 0.39 1.51
33 0.23 7.54 0.39 2.94
14 0.23 3.20 0.39 1.24
14 0.23 3.20 0.39 1.24
18 0.23 4.11 0.39 1.60
3 0.25 0.75 0.39 0.29
53 0.23 12.11 0.39 4.72
7 0.23 1.60 0.39 0.62
17 0.23 3.88 0.39 1.51
61 0.23 13.94 0.39 5.43
4 0.23 0.91 0.39 0.35
6 0.23 1.37 0.39 0.53
11 0.45 4.95 0.39 1.93
15 0.45 6.75 0.39 2.63
33 0.23 7.54 0.39 2.94
23 0.23 5.25 0.39 2.04
3 0.25 0.75 0.39 0.29
9 0.23 2.05 0.39 0.79
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

9 0.23 2.05 0.39 0.79


13 0.23 2.97 0.39 1.15
16 0.23 3.65 0.39 1.42
11 0.23 2.51 0.39 0.97
2 0.23 0.45 0.39 0.17
17 0.23 3.88 0.39 1.51
21 0.23 4.80 0.39 1.87
16 0.23 3.65 0.39 1.42
15 0.23 3.42 0.39 1.33
2 0.23 0.45 0.39 0.17
5 0.23 1.14 0.39 0.44
58 0.23 13.25 0.39 5.16
11 0.45 4.95 0.39 1.93
97 0.23 22.17 0.39 8.64
9 0.35 3.15 0.39 1.22
44 0.10 4.47 0.39 1.74
44 0.10 4.47 0.39 1.74
10 0.10 1.01 0.39 0.39
56 0.10 5.68 0.39 2.21
51 0.10 5.18 0.39 2.02
65 0.10 6.60 0.39 2.57
45 0.10 4.57 0.39 1.78
54 0.10 5.48 0.39 2.13
33 0.10 3.35 0.39 1.30
32 0.10 3.25 0.39 1.26
16 0.10 1.62 0.39 0.63
22 0.10 2.23 0.39 0.86
25 0.10 2.54 0.39 0.99
87 0.10 8.83 0.39 3.44
9 0.10 0.91 0.39 0.35
9 0.10 0.91 0.39 0.35
24 0.10 2.43 0.39 0.94
2 0.10 0.20 0.39 0.07

Sill level longitudinal reinforcement of Veranda


10mm dia bar 2 5.65 11.30 0.62 7.00

Sill level lateral reinforcement of Veranda


8 mm 47 0.45 21.15 0.39 8.24

Embedded sill band rod in pillar (block 1,2,3,4,5) 10 172 1.40 240.80 0.62 149.29
mm

Total 280401.93

13 8.4 Form works Same as Previous running Bill 8222.87


block 5
slab base 1 17.41 17.40 14.93 259.69
slab base 1 2.85 2.85 2.89 8.22
deduction of pillar -13 0.60 -7.80 0.60 -4.68
Side vertical form work(N-S) 4 6.60 26.40 0.65 17.16
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

Side vertical form work(N-S) 1 2.25 2.25 0.65 1.46


Side vertical form work(N-S) 1 2.70 2.69 0.13 0.33
Side vertical form work(E-W) 2 6.60 13.20 0.65 8.58
Side vertical form work(E-W) 1 2.70 2.69 0.65 1.74
mid vertical primary formwork 12 6.60 79.20 0.53 41.58
dedution of intersection of formwork -12 0.30 -3.60 0.53 -1.89
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

mid vertical primary formwork(small) 1 2.89 2.88 0.53 1.51


mid vertical primary formwork(small) 1 2.29 2.28 0.53 1.19
mid vertical primary formwork 8 6.60 52.80 0.53 27.72
dedution of intersection of formwork -8 0.30 -2.40 0.53 -1.26
mid vertical primary formwork 5 2.23 11.12 0.53 5.83
mid vertical secondary formwork 8 6.98 55.80 0.48 26.50
dedution of intersection of formwork -8 0.30 -2.40 0.48 -1.14
mid vertical secondary formwork 4 2.41 9.62 0.48 4.56
mid vertical secondary formwork 8 6.98 55.80 0.48 26.50
dedution of intersection of formwork -8 0.30 -2.40 0.48 -1.14
pillar formwork 9 2.40 21.60 0.20 4.32
pillar formwork of grid 14 4 2.40 9.60 1.28 12.24

sill level of block 4


bothside 4 2.66 10.64 0.10 1.06
6 2.71 16.26 0.10 1.62
2 3.80 7.60 0.10 0.76
2 6.60 13.20 0.10 1.32
2 4.50 9.00 0.10 0.90
4 5.02 20.08 0.10 2.00
2 6.93 13.86 0.10 1.38
2 6.55 13.10 0.10 1.31
2 1.58 3.16 0.10 0.31
4 0.28 1.12 0.10 0.11
4 0.80 3.20 0.10 0.32
2 2.73 5.46 0.10 0.54
2 6.54 13.08 0.10 1.30
2 2.48 4.96 0.10 0.49
2 1.45 2.90 0.10 0.29
2 0.20 0.40 0.10 0.04
2 2.72 5.44 0.10 0.54
2 2.67 5.34 0.10 0.53
2 6.53 13.06 0.10 1.30
2 2.73 5.46 0.10 0.54
2 4.57 9.14 0.10 0.91
2 4.25 8.50 0.10 0.85
2 0.23 0.46 0.10 0.04
4 2.28 9.12 0.10 0.91
2 6.45 12.90 0.10 1.29
2 5.93 11.86 0.10 1.18
2 5.22 10.44 0.10 1.04
2 0.97 1.94 0.10 0.19
2 5.24 10.48 0.10 1.04
2 6.60 13.20 0.10 1.32
2 0.27 0.54 0.10 0.05
2 2.15 4.30 0.10 0.43
2 1.45 2.90 0.10 0.29
6 0.45 2.70 0.10 0.27
2 2.05 4.10 0.10 0.41
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

8 2.00 16.00 0.10 1.60


2 6.52 13.04 0.10 1.30
2 6.65 13.30 0.10 1.33
8 2.00 16.00 0.10 1.60
6 0.50 3.00 0.10 0.30
4 2.05 8.20 0.10 0.82
2 0.50 1.00 0.10 0.10
2 2.07 4.14 0.10 0.41
4 1.50 6.00 0.10 0.60
2 3.03 6.06 0.10 0.60
2 3.00 6.00 0.10 0.60
2 7.50 15.00 0.10 1.50
2 6.00 12.00 0.10 1.20
2 6.14 12.28 0.10 1.22
2 4.00 8.00 0.10 0.80
2 3.90 7.80 0.10 0.78
2 6.02 12.04 0.10 1.20
2 6.10 12.20 0.10 1.22
2 6.72 13.44 0.10 1.34
2 2.30 4.60 0.10 0.46

sill level of block 2


bothside 2 7.93 15.86 0.10 1.58
2 2.81 5.62 0.10 0.56
2 6.60 13.20 0.10 1.32
2 3.45 6.90 0.10 0.69
2 6.00 12.00 0.10 1.20
2 5.00 10.00 0.10 1.00
2 6.60 13.20 0.10 1.32
2 3.20 6.40 0.10 0.64
2 0.44 0.88 0.10 0.08
2 3.15 6.30 0.10 0.63
2 1.70 3.40 0.10 0.34
2 4.15 8.30 0.10 0.83
2 1.05 2.10 0.10 0.21
2 3.80 7.60 0.10 0.76
-2 0.80 -1.60 0.10 -0.16
2 3.35 6.70 0.10 0.67
2 2.00 4.00 0.10 0.40
2 0.45 0.90 0.10 0.09
2 2.55 5.10 0.10 0.51
2 3.70 7.40 0.10 0.74
2 4.20 8.40 0.10 0.84
2 4.05 8.10 0.10 0.81
2 0.55 1.10 0.10 0.11
2 3.15 6.30 0.10 0.63
-2 0.95 -1.90 0.10 -0.19
2 4.50 9.00 0.10 0.90
2 2.10 4.20 0.10 0.42
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

2 4.75 9.50 0.10 0.95


2 5.25 10.50 0.10 1.05
2 2.40 4.80 0.10 0.48
2 2.22 4.44 0.10 0.44
2 1.12 2.24 0.10 0.22
4 0.50 2.00 0.10 0.20
8 2.00 16.00 0.10 1.60
4 1.65 6.60 0.10 0.66
2 2.10 4.20 0.10 0.42
4 6.60 26.40 0.10 2.64
2 4.10 8.20 0.10 0.82
4 2.00 8.00 0.10 0.80
6 0.45 2.70 0.10 0.27
4 2.00 8.00 0.10 0.80
2 1.15 2.30 0.10 0.23
2 1.20 2.40 0.10 0.24
2 6.70 13.40 0.10 1.34
2 1.15 2.30 0.10 0.23
2 2.70 5.40 0.10 0.54
2 2.40 4.80 0.10 0.48
6 7.00 42.00 0.10 4.20
2 3.92 7.84 0.10 0.78
2 4.00 8.00 0.10 0.80
4 3.50 14.00 0.10 1.40
2 3.94 7.88 0.10 0.78
2 3.80 7.60 0.10 0.76

sill level of block 1


16 2.00 32.00 0.10 3.20
8 0.45 3.60 0.10 0.36
2 1.15 2.30 0.10 0.23
2 6.60 13.20 0.10 1.32
2 5.45 10.90 0.10 1.09
2 1.90 3.80 0.10 0.38
2 1.95 3.90 0.10 0.39
2 3.50 7.00 0.10 0.70
2 1.00 2.00 0.10 0.20
2 5.40 10.80 0.10 1.08
4 1.70 6.80 0.10 0.68
4 0.25 1.00 0.10 0.10
2 1.00 2.00 0.10 0.20
2 5.40 10.80 0.10 1.08
2 4.60 9.20 0.10 0.92
2 1.00 2.00 0.10 0.20
2 6.60 13.20 0.10 1.32
2 2.30 4.60 0.10 0.46
2 0.30 0.60 0.10 0.06
2 0.80 1.60 0.10 0.16
2 1.75 3.50 0.10 0.35
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

2 0.30 0.60 0.10 0.06


10 6.60 66.00 0.10 6.60
2 2.25 4.50 0.10 0.45
2 2.10 4.20 0.10 0.42
2 0.50 1.00 0.10 0.10
2 1.20 2.40 0.10 0.24
2 5.50 11.00 0.10 1.10
4 2.56 10.24 0.10 1.02
8 5.50 44.00 0.10 4.40
2 2.40 4.80 0.10 0.48
2 0.23 0.46 0.10 0.04
2 3.40 6.80 0.10 0.68
2 3.40 6.80 0.10 0.68
sill level of block 3
2 6.55 13.10 0.10 1.31
2 6.55 13.10 0.10 1.31
2 2.60 5.20 0.10 0.52
2 1.45 2.90 0.10 0.29
2 0.23 0.46 0.10 0.04
2 6.60 13.20 0.10 1.32
2 0.45 0.90 0.10 0.09
2 0.45 0.90 0.10 0.09
2 2.00 4.00 0.10 0.40
2 2.00 4.00 0.10 0.40
4 2.00 8.00 0.10 0.80
2 1.70 3.40 0.10 0.34
2 1.70 3.40 0.10 0.34
2 2.22 4.44 0.10 0.44
2 0.25 0.50 0.10 0.05
2 6.60 13.20 0.10 1.32
2 0.80 1.60 0.10 0.16
2 2.10 4.20 0.10 0.42
2 7.50 15.00 0.10 1.50
2 0.45 0.90 0.10 0.09
2 0.70 1.40 0.10 0.14
6 0.45 2.70 0.10 0.27
2 1.75 3.50 0.10 0.35
2 4.00 8.00 0.10 0.80
2 2.85 5.70 0.10 0.57
2 0.25 0.50 0.10 0.05
2 1.06 2.12 0.10 0.21
2 1.06 2.12 0.10 0.21
2 1.60 3.20 0.10 0.32
2 1.90 3.80 0.10 0.38
2 1.25 2.50 0.10 0.25
2 0.23 0.46 0.10 0.04
2 2.02 4.04 0.10 0.40
2 2.50 5.00 0.10 0.50
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

2 1.95 3.90 0.10 0.39


2 1.75 3.50 0.10 0.35
2 0.23 0.46 0.10 0.04
2 0.55 1.10 0.10 0.11
2 7.20 14.40 0.10 1.44
6 0.45 2.70 0.10 0.27
12 2.00 24.00 0.10 2.40
6 0.35 2.10 0.10 0.21
2 5.45 10.90 0.10 1.09
2 5.45 10.90 0.10 1.09
2 1.20 2.40 0.10 0.24
2 6.97 13.94 0.10 1.39
4 3.15 12.60 0.10 1.26
4 4.06 16.24 0.10 1.62
2 5.60 11.20 0.10 1.12
2 6.65 13.30 0.10 1.33
2 4.10 8.20 0.10 0.82
2 3.95 7.90 0.10 0.79
2 1.90 3.80 0.10 0.38
2 2.70 5.40 0.10 0.54
2 3.05 6.10 0.10 0.61
8 2.70 21.60 0.10 2.16
8 0.25 2.00 0.10 0.20
8 0.25 2.00 0.10 0.20
2 2.90 5.80 0.10 0.58
2 0.23 0.46 0.10 0.04
sill level of veranda 2 5.65 11.30 0.10 1.13
Total 8816.08
14 10 12.5 mm Thick Wall Plaster in 1:4
block 3 for plaster
1 5.18 5.18 2.92 15.12
2 2.52 5.04 3.51 17.69
2 1.45 2.90 0.90 2.61
1 0.28 0.28 3.51 0.98
1 0.29 0.29 1.45 0.42
1 7.62 7.62 0.90 6.85
1 2.05 2.05 1.45 2.97
1 0.48 0.48 2.05 0.98
1 1.75 1.75 2.05 3.58
1 3.45 3.45 2.90 10.00
1 2.49 2.49 3.51 8.73
-1 0.74 -0.74 2.64 -1.96
1 3.89 3.89 2.90 11.28
1 5.20 5.20 3.51 18.25
1 1.17 1.17 0.90 1.05
1 2.67 2.67 0.90 2.40
2 0.80 1.60 3.51 5.61
1 1.53 1.53 2.01 3.07
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 1.80 1.80 3.51 6.31


1 1.20 1.20 3.51 4.21
-1 0.40 -0.40 0.59 -0.24
1 2.60 2.60 2.91 7.56
1 5.28 5.28 3.51 18.53
-2 0.40 -0.80 0.59 -0.48
1 0.45 0.45 2.91 1.30
1 0.75 0.75 0.90 0.67
1 4.04 4.04 0.90 3.63
1 3.42 3.42 3.51 12.00
2 4.30 8.60 2.90 24.94
1 1.04 1.04 2.01 2.09
1 0.47 0.47 2.01 0.94
2 4.98 9.96 2.90 28.88
1 0.41 0.41 3.50 1.43
1 3.39 3.39 2.90 9.83
1 5.43 5.43 3.51 19.05
1 4.38 4.38 2.90 12.70
-1 0.40 -0.40 0.59 -0.24
1 5.10 5.10 2.90 14.79
1 2.28 2.28 2.90 6.61
1 3.80 3.80 2.90 11.02
-1 1.15 -1.15 2.00 -2.30
1 0.28 0.28 1.15 0.32
2 7.00 14.00 3.51 49.14
1 2.23 2.23 2.90 6.46
-1 0.60 -0.60 2.00 -1.20
1 7.55 7.55 2.90 21.89
1 5.09 5.09 2.90 14.76
-1 3.35 -3.35 2.00 -6.70
1 5.70 5.70 2.90 16.53
1 5.20 5.20 2.90 15.08
1 2.20 2.20 2.90 6.38
-1 1.17 -1.17 2.00 -2.34
2 7.20 14.40 3.50 50.40
-2 0.40 -0.80 0.55 -0.44
1 4.45 4.45 2.90 12.90
-1 2.33 -2.33 2.00 -4.66
2 6.93 13.86 2.90 40.19
1 2.64 2.64 2.90 7.65
-1 1.10 -1.10 2.00 -2.20
2 5.44 10.88 3.51 38.18
-1 0.41 -0.41 0.55 -0.23
1 3.86 3.86 3.51 13.54
1 3.43 3.43 2.90 9.94
-1 2.75 -2.75 2.00 -5.50
1 5.39 5.39 3.51 18.91
-1 0.40 -0.40 0.59 -0.24
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 4.55 4.55 3.51 15.97


1 4.26 4.26 2.90 12.35
1 6.20 6.20 0.59 3.65
2 2.59 5.18 3.51 18.18
1 7.20 7.20 3.51 25.27
1 2.50 2.50 3.51 8.77
1 1.28 1.28 0.90 1.15
1 1.60 1.60 2.90 4.64
1 3.50 3.50 3.51 12.28
-2 0.40 -0.80 0.55 -0.44
1 3.00 3.00 3.51 10.53
2 1.45 2.90 3.51 10.17
1 2.00 2.00 3.50 7.00
1 2.88 2.88 2.91 8.38
-1 1.30 -1.30 2.00 -2.60
2 7.00 14.00 3.51 49.14
-1 0.41 -0.41 0.59 -0.25
2 1.04 2.08 3.51 7.30
1 2.20 2.20 2.91 6.40
1 5.05 5.05 2.90 14.64
1 2.57 2.57 2.90 7.45
block 4 for plaster 0.00 0.00
1 11.14 11.14 2.90 32.30
1 8.00 8.00 2.90 23.20
-1 4.00 -4.00 4.00 -16.00
2 2.00 4.00 0.28 1.12
1 14.98 14.98 2.90 43.44
-1 4.00 -4.00 4.00 -16.00
2 0.28 0.56 2.00 1.12
1 18.60 18.60 2.90 53.94
-1 4.00 -4.00 4.00 -16.00
4 0.28 1.12 2.00 2.24
2 1.95 3.90 0.90 3.51
-1 4.00 -4.00 4.00 -16.00
1 1.50 1.50 2.90 4.35
1 6.40 6.40 3.50 22.40
1 7.50 7.50 2.90 21.75
-1 1.16 -1.16 2.00 -2.32
1 14.70 14.70 3.51 51.59
-4 0.40 -1.60 0.55 -0.88
1 2.76 2.76 2.90 8.00
-1 1.80 -1.80 2.00 -3.60
1 6.10 6.10 3.50 21.35
-1 0.40 -0.40 0.55 -0.22
1 10.33 10.33 3.51 36.25
-3 0.40 -1.20 0.55 -0.66
1 18.70 18.70 2.90 54.23
-1 1.87 -1.87 2.00 -3.74
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 0.28 0.28 1.87 0.52


1 34.70 34.70 2.90 100.63
1 0.28 0.28 8.00 2.24
-1 8.00 -8.00 8.00 -64.00
1 5.30 5.30 2.90 15.37
1 6.65 6.65 3.51 23.34
-2 0.40 -0.80 0.55 -0.44
1 3.45 3.45 2.90 10.00
-1 0.90 -0.90 2.00 -1.80
1 3.75 3.75 2.90 10.87
-1 1.10 -1.10 2.00 -2.20
1 2.47 2.47 3.50 8.64
1 1.95 1.95 3.50 6.82
2 2.78 5.56 3.51 19.51
2 2.06 4.12 3.51 14.46
-1 1.00 -1.00 3.51 -3.51
1 4.82 4.82 3.51 16.91
-2 0.40 -0.80 0.55 -0.44
2 1.57 3.14 3.51 11.02
2 0.28 0.56 3.51 1.96
2 2.78 5.56 2.90 16.12
2 2.53 5.06 3.50 17.71
1 2.53 2.53 3.50 8.85
1 0.80 0.80 3.51 2.80
1 0.80 0.80 3.51 2.80
1 14.50 14.50 2.90 42.05
-1 4.30 -4.30 6.00 -25.80
2 0.28 0.56 4.30 2.40
1 15.73 15.73 2.90 45.61
2 0.28 0.56 4.40 2.46
-1 4.40 -4.40 2.00 -8.80
1 6.20 6.20 3.51 21.76
-2 0.40 -0.80 0.55 -0.44
1 5.65 5.65 3.50 19.77
-1 0.40 -0.40 0.55 -0.22
1 3.61 3.61 2.90 10.46
-1 1.15 -1.15 2.00 -2.30
2 0.28 0.56 1.15 0.64
1 8.00 8.00 2.90 23.20
1 0.28 0.28 2.85 0.79
-1 2.85 -2.85 4.00 -11.40
1 5.75 5.75 3.50 20.12
-1 0.40 -0.40 0.55 -0.22
1 14.72 14.72 3.50 51.52
-3 0.40 -1.20 0.55 -0.66
2 1.86 3.72 3.50 13.02
1 0.28 0.28 3.50 0.98
1 1.18 1.18 2.90 3.42
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

block 2 for plaster 0.00 0.00


1 2.30 2.30 3.50 8.05
1 8.55 8.55 3.50 29.92
-2 0.40 -0.80 0.59 -0.48
1 5.23 5.23 2.90 15.16
1 0.65 0.65 0.90 0.58
1 8.64 8.64 2.90 25.05
-1 3.13 -3.13 2.00 -6.26
1 3.74 3.74 3.50 13.09
1 4.10 4.10 3.50 14.35
1 21.06 21.06 2.90 61.07
-1 1.17 -1.17 2.00 -2.34
2 0.28 0.56 1.17 0.65
1 7.27 7.27 2.90 21.08
-1 1.20 -1.20 2.00 -2.40
1 6.10 6.10 3.50 21.35
-2 0.60 -1.20 2.00 -2.40
1 1.83 1.83 2.90 5.30
1 4.30 4.30 3.50 15.05
1 1.20 1.20 2.90 3.48
1 37.70 37.70 2.90 109.33
-1 4.00 -4.00 4.00 -16.00
1 0.28 0.28 4.00 1.12
1 2.48 2.48 2.90 7.19
2 4.33 8.66 0.90 7.79
2 0.28 0.56 2.00 1.12
2 2.45 4.90 2.90 14.21
1 11.00 11.00 2.90 31.90
1 9.89 9.89 2.90 28.68
2 1.63 3.26 0.90 2.93
1 44.08 44.08 2.90 127.83
-1 1.20 -1.20 2.00 -2.40
-1 2.00 -2.00 2.00 -4.00
-1 2.00 -2.00 2.00 -4.00
1 0.28 0.28 5.20 1.45
1 10.18 10.18 3.50 35.63
1 11.58 11.58 2.90 33.58
1 10.90 10.90 2.90 31.61
1 3.40 3.40 3.50 11.90
1 12.62 12.62 2.90 36.59
-1 2.00 -2.00 2.00 -4.00
2 0.28 0.56 2.00 1.12
1 6.50 6.50 3.50 22.75
-3 0.40 -1.20 0.55 -0.66
1 8.40 8.40 3.50 29.40
-2 0.40 -0.80 0.55 -0.44
1 9.60 9.60 2.90 27.84
1 2.04 2.04 3.50 7.14
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 10.50 10.50 2.90 30.45


-1 4.00 -4.00 4.00 -16.00
2 0.28 0.56 4.00 2.24
1 6.60 6.60 2.90 19.14
2 6.60 13.20 2.95 38.94
2 1.58 3.16 2.90 9.16
2 3.45 6.90 2.65 18.28
1 5.70 5.70 3.50 19.95
Total 2425.58 m2

15 11 12.5 mm Thick Ceiling Plaster in 1:3 Plaster

block 3 for plaster

1 7.11 7.10 5.45 38.69


1 6.90 6.90 0.59 4.07
2 5.45 10.90 0.59 6.43
-2 0.30 -0.60 0.55 -0.33
2 3.40 6.80 0.55 3.74
2 3.40 6.80 0.55 3.74
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

2 3.40 6.80 0.55 3.74


2 3.40 6.80 0.55 3.74
1 7.48 7.48 2.69 20.12
1 1.88 1.88 2.75 5.17
1 4.04 4.04 3.58 14.46
1 2.40 2.40 0.59 1.41
1 0.75 0.75 0.25 0.18
2 3.45 6.90 0.55 3.79
1 6.90 6.90 0.59 4.07
2 4.04 8.08 0.55 4.44
-2 0.40 -0.80 0.55 -0.44
4 2.39 9.56 0.55 5.25
1 7.20 7.20 2.40 17.28
6 2.60 15.60 0.59 9.20
2 4.24 8.48 0.59 5.00
1 5.45 5.45 4.13 22.50
2 2.40 4.80 0.59 2.83
2 1.60 3.20 0.59 1.88
1 1.98 1.98 1.21 2.39
2 3.45 6.90 0.59 4.07
2 6.60 13.20 0.59 7.78
2 2.50 5.00 0.55 2.75
1 7.35 7.35 1.97 14.47
1 6.59 6.59 0.59 3.88
3 1.84 5.52 0.59 3.25
1 4.90 4.90 6.65 32.58
6 3.40 20.40 0.55 11.22
2 1.30 2.60 0.55 1.43
1 4.89 4.89 0.59 2.88
-1 0.40 -0.40 0.59 -0.24
2 6.93 13.86 0.59 8.17
-2 0.40 -0.80 0.59 -0.48
1 7.40 7.40 2.42 17.90
-3 2.42 -7.26 0.55 -4.00
1 4.25 4.25 6.93 29.45
6 3.40 20.40 0.55 11.22
3 0.50 1.50 0.59 0.88
1 3.30 3.30 0.59 1.94
1 5.45 5.45 2.40 13.08
3 2.40 7.20 0.55 3.96
1 5.40 5.40 3.47 18.73
3 0.50 1.50 0.55 0.82
3 2.91 8.73 0.55 4.80
1 3.30 3.30 0.55 1.81
2 1.63 3.26 0.55 1.79
1 2.10 2.10 0.59 1.23
1 6.58 6.58 4.60 30.26
6 2.59 15.54 0.55 8.54
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

2 1.40 2.80 0.55 1.54


2 6.84 13.68 0.59 8.07
-2 0.40 -0.80 0.59 -0.48
1 2.65 2.65 0.59 1.56
1 2.68 2.68 2.27 6.08
1 4.45 4.45 1.43 6.36
3 1.14 3.42 0.55 1.88
1 2.26 2.26 1.26 2.84
1 1.26 1.26 0.59 0.74
1 2.87 2.87 2.48 7.11
2 3.34 6.68 0.55 3.67
1 2.25 2.25 1.64 3.69
2 3.34 6.68 0.55 3.67
2 2.80 5.60 0.55 3.08
1 1.40 1.40 0.59 0.82
1 2.16 2.16 1.84 3.97
1 1.50 1.50 1.90 2.85
1 2.70 2.70 2.30 6.21
1 2.30 2.30 4.19 9.63
1 4.19 4.19 0.59 2.47
-1 0.41 -0.41 0.59 -0.25
2 2.24 4.48 0.55 2.46
block 4 for ceiling plaster
1 26.05 26.05 2.50 65.12
3 2.40 7.20 0.55 3.96
4 2.40 9.60 0.59 5.66
14 3.20 44.80 0.57 25.53
1 7.15 7.15 6.86 49.04
8 3.40 27.20 0.56 15.23
8 3.40 27.20 0.59 16.04
1 6.88 6.88 7.03 48.36
8 3.40 27.20 0.55 14.96
8 3.40 27.20 0.59 16.04
1 5.05 5.05 2.58 13.02
3 2.58 7.74 0.55 4.25
1 5.05 5.05 0.58 2.92
-1 0.40 -0.40 0.59 -0.24
1 2.06 2.06 5.06 10.42
2 3.40 6.80 0.55 3.74
2 1.33 2.66 0.55 1.46
3 0.50 1.50 0.55 0.82
3 2.00 6.00 0.55 3.30
1 7.10 7.10 2.16 15.33
2 3.40 6.80 0.59 4.01
4 1.70 6.80 0.55 3.74
1 4.24 4.24 7.14 30.27
6 3.40 20.40 0.55 11.22
8 3.40 27.20 0.55 14.96
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 7.20 7.20 7.10 51.12


8 3.40 27.20 0.58 15.77
1 3.96 3.96 2.78 11.00
2 2.78 5.56 0.55 3.05
1 7.28 7.28 1.26 9.17
1 2.49 2.49 1.74 4.33
1 2.07 2.07 2.78 5.75
2 2.78 5.56 0.55 3.05
2 7.20 14.40 0.55 7.92
-2 0.40 -0.80 0.55 -0.44
4 0.80 3.20 0.59 1.88
1 3.15 3.15 2.06 6.48
2 2.06 4.12 0.59 2.43
1 2.53 2.53 1.32 3.33
1 2.53 2.53 0.59 1.49
1 1.32 1.32 0.59 0.77
1 1.65 1.65 2.53 4.17
1 1.63 1.63 0.59 0.96
1 7.00 7.00 4.40 30.80
10 3.40 34.00 0.55 18.70
4 0.80 3.20 0.59 1.88
1 6.82 6.82 3.24 22.09
4 3.40 13.60 0.58 7.88
4 2.20 8.80 0.58 5.10
4 0.60 2.40 0.58 1.39
1 1.95 1.95 2.92 5.69
1 4.55 4.55 0.59 2.68
1 1.95 1.95 3.83 7.46
3 1.95 5.85 0.55 3.21
1 6.95 6.95 1.10 7.64
1 6.95 6.95 0.59 4.10
-1 0.40 -0.40 0.59 -0.24
4 1.10 4.40 0.58 2.55
block 2 for ceiling plaster
1 22.80 22.80 6.90 157.32
16 3.40 54.40 0.58 31.55
12 3.40 40.80 0.55 22.44
6 2.27 13.62 0.58 7.89
12 3.40 40.80 0.55 22.44
12 3.40 40.80 0.58 23.66
1 3.83 3.83 2.09 8.00
1 3.83 3.83 0.59 2.25
3 1.88 5.64 0.55 3.10
1 4.86 4.86 3.85 18.71
6 3.40 20.40 0.56 11.42
3 1.27 3.81 0.56 2.13
1 2.92 2.92 3.13 9.13
1 2.92 2.92 0.59 1.72
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 3.13 3.13 0.59 1.84


1 4.25 4.25 3.13 13.30
3 2.90 8.70 0.56 4.87
1 4.00 4.00 0.59 2.36
-1 0.40 -0.40 0.55 -0.22
1 2.09 2.09 3.36 7.02
1 3.36 3.36 0.59 1.98
1 2.09 2.09 0.59 1.23
1 3.50 3.50 1.16 4.06
2 1.16 2.32 0.58 1.34
2 3.50 7.00 0.55 3.85
1 3.55 3.55 3.65 12.95
1 3.45 3.45 0.59 2.03
1 3.36 3.36 0.59 1.98
1 4.15 4.15 3.60 14.94
4 3.15 12.60 0.58 7.30
1 7.45 7.45 2.50 18.62
1 7.45 7.45 0.59 4.39
-2 0.40 -0.80 0.59 -0.48
4 2.50 10.00 0.56 5.60
1 3.60 3.60 3.40 12.24
2 3.35 6.70 0.55 3.68
2 3.35 6.70 0.58 3.88
1 4.73 4.73 3.20 15.13
1 4.30 4.30 0.59 2.53
3 3.23 9.69 0.56 5.42
1 7.20 7.20 4.60 33.12
6 3.40 20.40 0.59 12.03
4 2.15 8.60 0.55 4.73
6 2.20 13.20 0.59 7.78
1 7.00 7.00 3.43 24.01
2 3.40 6.80 0.55 3.74
1 3.40 3.40 0.59 2.00
4 3.40 13.60 0.55 7.48
1 7.00 7.00 2.30 16.10
2 2.25 4.50 0.55 2.47
2 2.25 4.50 0.59 2.65
2 3.40 6.80 0.59 4.01
2 3.40 6.80 0.55 3.74
1 3.20 3.20 3.40 10.88
2 2.90 5.80 0.55 3.19
1 3.30 3.30 0.59 1.94
1 3.30 3.30 1.54 5.08
1 3.30 3.30 0.55 1.81
2 1.05 2.10 0.59 1.23
1 4.64 4.64 3.30 15.31
2 3.34 6.68 0.59 3.94
2 4.30 8.60 0.57 4.90
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 2.65 2.65 1.26 3.33


1 1.20 1.20 0.55 0.66
2 2.60 5.20 0.55 2.86
1 2.75 2.75 2.00 5.50
1 1.70 1.70 0.55 0.93
1 3.40 3.40 1.30 4.42
1 1.25 1.25 0.55 0.68
1 3.26 3.26 0.59 1.92
1 6.60 6.60 5.40 35.64
1 3.40 3.40 3.20 10.88
1 4.20 4.20 6.80 28.56
2 6.00 12.00 0.59 7.08
2 3.20 6.40 0.55 3.52
1 2.30 2.30 2.00 4.60

Total 1884.13 m2

16 16.1 Sand Filling Work Same as Previous running Bill 66.58

block 4 1 24.86 24.86 16.12 0.15 60.09

block 2 1 19.53 19.52 15.10 0.15 44.19


1 24.86 24.86 15.89 0.15 59.25
1 6.33 6.32 6.85 0.15 6.49
1 19.45 19.45 2.70 0.15 7.87

Total 244.47
zx/L ljsf; tyf ejg lgdf{0f ljefu, l8lehg sfof{no, ;'v]{t d=n]=k=kmf=g+= !^*

lansf] s|d ;+VofM– 5}7f} /lgË lan


7]Ssf ;DalGw aLn sfof{De cfb]z ldltM– )^$.)^.@&
of]hgfsf] gfdM– %) z}of c:ktfn ejg lgdf{0f sfo{ , ;'v]{t ;Dem\of}tf ldltM– @)^$.)^.!*
7]s]bf/sf] gfd M– /lagf , cflzif k|lti7f , g]kfn k|utL h]=eL= z}a' , sf7df08f}+ . sfd ;DkGg ug'{ kg]{ ldltM– @)^^.)@.!&-;Dem\of}tfsf] @) dlxgf _
7]Ssf k6[fsf] ;+VofM– !) - @)^#÷)^$ _ sfd ;DkGg ePsf] ldltM– rfn'''''''
cl3Nnf] e"QmfgL lansf] s|d;+VofM– kfrf}+ /lgË lan e"QmfgL efpr/ g+=–
cl3Nnf] e"QmfgL ef=g+=M– e"QmfgL ldltM–
gfkL lstfa g+= sf] k[i7 g+=M– b]lv ;Dd
cfO{ cBfjlw sfd ePsf] cl3Nnf] landf r9]sf] xfn ePsf] sfd
s||=;+ 6d sfdsf] laj/0f PsfO{ s}lkmot
g+== kl/df0f b/ hDdf d"No kl/df0f hDdf d"No kl/df0f hDdf d"No
A CIVIL WORKS
1 1.2 Earth work in Excavation in site Development m3 3799.225 100.00 379922.50 3799.225 379922.50 0.000 0.00
2 2 Earth work excavation in BM Soil on Foundation m3 2533.707 200.00 506741.40 2533.707 506741.40 0.000 0.00
3 3 Earth filling Work m3 3185.337 60.00 191120.22 - - 3185.337 191120.22
3 4 150 mm thick stone soling with sand m3 339.004 2500.00 847510.00 203.502 508755.00 135.502 338755.00
4 5 75mm thick lean concrete (1:3:6) in foundation m3 104.041 4500.00 468184.50 104.041 468184.50 0.000 0.00
5 6 P.C.C. (1:2:4) Work m3 66.580 5655.13 376518.55 - - 66.580 376518.55
6 7 Brick Masonary work ( 1:6 ) m3 654.420 4576.61 2995025.11 508.43 2326885.82 145.990 668139.29
7 Extra Brick Masonary work With ( 1:4 ) Cement mortar m3 38.990 6778.67 264300.34 - - 0.000 264300.34
8 8 R.C.C. Works
9 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 1221.905 6529.70 7978670.62 1109.711 7246079.91 112.194 732590.71
10 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 541.143 8547.38 4625351.97 427.516 3654141.70 113.627 971210.27
11 8.3 Reinforcements works kg 267272.610 60.51 16172665.63 223224.990 13507344.14 44047.620 2665321.49
12 8.4 Form work m2 8222.870 313.00 2573758.31 6630.24 2075265.12 1592.630 498493.19
13 16.1 Sand Filling Work m3 66.580 1300.00 86554.00 - - 66.580 86554.00

TOTAL AMOUNT (without VAT) Rs. 37466323.15 Rs 30673320.09 Rs. 6793003.06

pko'{Qm adf]lhd 7Ls 5 egL k|dfl0ft ug]{sf] ;xLM–


==================================== ===================
cf]e/l;o/ O{lGhgLo/ 7]s]bf/sf] ;xL
of] lansf] hDdf -Eof6 afx]]s_ 37466323.15
cl3Nnf] e"QmfgL lanaf6 e"QmfgL ePsf] -Eof6 30673320.09
afFsL lbg' kg]{ -Eof6 afx]s_ 6793003.06
s6[L ug'{ kg]{ ?=M–
s_ k]ZsL–
v_ dfn;dfgsf] df]nM–
u_ d]zLg cf}hf/ axfnM–
3_ cfos/ !=%Ü M–
ª_ d"No clea[l4 s/ !# Ü M–
r_ w/f}6L %Ü M–
5_ cGo M–
v"b lbg' kg]{ -Eof6 ;d]t_ ?=M–
k]z ug]{sf] ;xLM– hfFr ug]{sf] ;xLM– :jLs[t ug]{sf] ;xLM–
hDdf ?= cIf]?kLM– sf] r]s g+= af6 k|fKt ePsf] egL ;xL ug]{ 7]s]bf/sf] ;xLM–
Department of Urban Development And Building Construction
DIVISION OFFICE
Surkhet
Name of work :- 50 Bed Hospital Construction Work F/Y-064 - 065
Place :- Birendranagar - 3 , Kalagaon , Surkhet

DETAILS OF MEASUREMENT ( 6th. Bill )


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

(A) CIVIL WORKS

1 Site Development work

1 1.2 Earth work in Excavation in site Development Same as previous bill running Bill 3799.225

2 2 Earth work excavation in BM Soil on Foundation Same as Previous running Bill 2533.707 m3

3 3 Earth filling Work

Earthwork in filling (block 1)

15 6.850 102.75 6.850 1.150 809.413

Earthwork in filling (block 2)

Floor 1 1 2.590 2.59 2.250 1.150 6.701

Floor 2 1 6.85 6.85 2.25 1.150 17.724

Floor 3 1 6.85 6.85 2.25 1.150 17.724

Floor 4 1 2.61 2.61 2.25 1.150 6.753

Floor 5 1 4.683 4.68 6.85 1.150 36.890

Floor 6 1 6.85 6.85 6.85 1.150 53.960

Floor 7 1 6.85 6.85 6.85 1.150 53.960

Floor 8 1 6.85 6.85 6.85 1.150 53.960

Floor 9 1 2.59 2.59 6.85 1.150 20.402

Floor 10 1 6.85 6.85 6.85 1.150 53.960

Floor 11 1 6.85 6.85 6.85 1.150 53.960

Floor 12 1 2.61 2.61 6.85 1.150 20.560

Floor 13 1 4.683 4.68 2.25 1.150 12.117

Floor 14 1 6.85 6.85 2.25 1.150 17.724

Floor 15 1 6.85 6.85 2.25 1.150 17.724

Floor 16 1 6.85 6.85 2.25 1.150 17.724

Floor 17 1 2.59 2.59 6.85 1.150 20.402

Floor 18 1 6.85 6.85 6.85 1.150 53.960

Floor 19 1 6.85 6.85 6.85 1.150 53.960

Floor 20 1 2.61 2.61 6.85 1.150 20.560

Floor 21 1 4.683 4.68 6.85 1.150 36.890

Floor 22 1 6.85 6.85 6.85 1.150 53.960

Floor 23 1 6.85 6.85 6.85 1.150 53.960

Floor 24 1 6.85 6.85 6.85 1.150 53.960

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Earthwork in filling (block 3)

6 6.850 41.10 6.850 1.150 323.765

3 6.850 20.55 2.50 1.150 59.081

Earthwork in filling (Block 4)

2 4.135 8.27 6.850 1.150 65.146

6 6.850 41.10 6.850 1.150 323.765

1 4.135 4.14 2.500 1.150 11.888

3 6.850 20.55 2.25 1.150 53.173

Earthfilling of block 5

Floor 1 1 6.850 6.85 2.610 1.150 20.560

Floor 2 1 2.475 2.48 2.610 1.150 7.428

Floor 3 1 4.025 4.03 2.610 1.150 12.081

Floor 4 1 2.500 2.50 2.610 1.150 7.503

Floor 5 1 6.850 6.85 2.610 1.150 20.560

Floor 6 1 2.500 2.50 2.610 1.150 7.503

Floor 7 1 6.850 6.85 2.610 1.150 20.560

Floor 8 1 6.850 6.85 2.610 1.150 20.560

Floor 9 1 6.850 6.85 6.850 1.150 53.960

Floor 10 1 2.475 2.48 6.850 1.150 19.496

Floor 11 1 4.025 4.03 6.850 1.150 31.706

Floor 12 1 2.500 2.50 6.850 1.150 19.693

Floor 13 1 6.850 6.85 6.850 1.150 53.960

Floor 14 1 2.500 2.50 6.850 1.150 19.693

Floor 15 1 6.850 6.85 6.850 1.150 53.960

Floor 16 1 6.850 6.85 6.850 1.150 53.960

Floor 17 1 6.850 6.85 6.850 1.150 53.960

Floor 18 1 2.475 2.48 6.850 1.150 19.496

Floor 19 1 4.025 4.03 6.850 1.150 31.706

Floor 20 1 2.500 2.50 6.850 1.150 19.693

Floor 21 1 6.850 6.85 6.850 1.150 53.960

Floor 22 1 2.500 2.50 6.850 1.150 19.693

Floor 23 1 6.850 6.85 6.850 1.150 53.960

Floor 24 1 6.850 6.85 6.850 1.150 53.960

Total 3185.337 m3

3 4 150 mm thick stone soling with sand Same as Previous running Bill 203.502 m3

Block 1

Room 10 6.85 68.5 6.85 0.15 70.383

Passage 5 6.85 34.25 2.5 0.15 12.843

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Block 3

Room 6 6.85 41.1 6.85 0.150 42.230

Passage 3 6.85 20.55 2.5 0.150 7.706

Front side veranda, foundation tie beam(Soling) 1 24.00 24 0.65 0.150 2.340

Total 339.004

4 5 Lean Concrete Bae (1:3:6) Same previous running Bill 104.041 m3

5 6 P.C.C. (1:2:4) Work

Block 1 & 3

Room 10 6.85 68.5 6.85 0.075 35.191

Passage 5 6.85 34.25 2.5 0.075 6.421

Room 6 6.85 41.1 6.85 0.075 21.115

Passage 3 6.85 20.55 2.5 0.075 3.853

Total 66.580 m3

6 7 Brick Masonary work ( 1:6 ) Same as Previous running Bill 508.430

Block 1

8 2.00 16.00 0.23 0.80 2.926

4 0.45 1.80 0.45 3.40 2.754

1 1.15 1.15 0.23 0.80 0.210

1 6.60 6.60 0.23 3.40 5.129

1 5.45 5.45 0.23 3.00 3.737

1 1.90 1.90 0.23 3.00 1.303

1 1.95 1.95 0.23 3.40 1.515

1 3.50 3.50 0.23 3.00 2.400

1 1.00 1.00 0.23 3.00 0.685

1 5.40 5.40 0.23 3.00 3.703

2 1.70 3.40 0.23 0.80 0.621

2 0.25 0.50 0.23 2.50 0.285

1 1.00 1 0.23 3.40 0.777

1 5.40 5.4 0.23 3.00 3.703

1 4.60 4.6 0.23 3.00 3.154

1 1.00 1 0.23 3.00 0.685

1 6.60 6.6 0.23 3.00 4.526

1 2.30 2.3 0.23 0.80 0.420

1 0.30 0.3 0.23 2.50 0.171

1 0.80 0.8 0.23 2.50 0.457

1 1.75 1.75 0.23 0.80 0.320

1 0.30 0.3 0.23 2.50 0.171

5 6.60 33 0.23 3.00 22.631

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 2.25 2.25 0.23 3.00 1.543

1 2.10 2.1 0.23 3.00 1.440

1 0.50 0.5 0.23 3.00 0.342

1 1.20 1.2 0.23 3.00 0.822

1 5.50 5.5 0.23 3.00 3.771

Block 3 1 6.55 6.55 0.23 3.40 5.09

1 6.55 6.55 0.23 3.40 5.09

1 2.60 2.60 0.23 3.40 2.02

1 1.45 1.45 0.23 0.80 0.27

1 0.23 0.23 0.23 2.50 0.13

1 6.60 6.60 0.23 0.80 1.21

1 0.45 0.45 0.23 0.80 0.08

1 0.45 0.45 0.23 2.50 0.26

1 2.00 2.00 0.23 0.80 0.37

1 2.00 2.00 0.23 0.80 0.37

2 2.00 4.00 0.23 0.80 0.73

1 1.70 1.70 0.23 3.00 1.17

1 1.70 1.70 0.23 3.40 1.32

1 2.22 2.22 0.23 3.40 1.73

1 0.25 0.25 0.25 3.40 0.21

1 6.60 6.60 0.23 3.00 4.53

1 0.80 0.80 0.23 3.00 0.55

1 2.10 2.10 0.23 3.00 1.44

1 7.50 7.50 0.23 3.40 5.83

1 0.45 0.45 0.23 3.40 0.35

1 0.70 0.70 0.23 3.00 0.48

3 0.45 1.35 0.45 3.40 2.07

1 1.75 1.75 0.45 3.40 2.68

1 4.00 4.00 0.23 3.00 2.74

1 2.85 2.85 0.23 3.00 1.95

1 0.25 0.25 0.25 3.40 0.21

1 1.06 1.06 0.23 3.00 0.73

1 1.06 1.06 0.23 3.00 0.73

1 1.60 1.60 0.23 3.00 1.10

1 1.90 1.90 0.23 3.00 1.30

1 1.25 1.25 0.23 2.50 0.71

1 0.23 0.23 0.23 2.50 0.13

1 2.02 2.02 0.23 3.00 1.39

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

1 2.50 2.50 0.23 3.00 1.71

1 1.95 1.95 0.23 3.00 1.34

1 1.75 1.75 0.23 0.80 0.32

1 0.23 0.23 0.23 2.50 0.13

1 0.55 0.55 0.23 2.50 0.31

1 7.20 7.20 0.23 3.40 5.60

3 0.45 1.35 0.45 3.40 2.07

6 2.00 12.00 0.23 0.80 2.19

3 0.35 1.05 0.35 2.50 0.92

For veranda 1 23.00 23.00 0.65 0.23 3.44

1 23.00 23.00 0.45 0.23 2.38

1 21.00 21.00 0.35 0.35 2.57

1 2.10 2.10 0.35 0.35 0.26

1 23.00 23.00 0.35 0.45 3.62

Total 654.420 m3

7 Extra Brick Masonary work With ( 1:4 ) Cement mortar

Block 1

2 2.56 5.12 0.10 3.40 1.77

4 5.50 22.00 0.10 3.40 7.60

1 2.40 2.40 0.10 1.80 0.44

1 0.23 0.23 0.10 3.00 0.07

1 3.40 3.40 0.10 3.40 1.17

1 3.40 3.40 0.10 3.40 1.17

Block 3 1 5.45 5.45 0.10 3.40 1.88

1 5.45 5.45 0.10 3.40 1.88

1 1.20 1.20 0.10 3.40 0.41

1 6.97 6.97 0.10 3.40 2.41

2 3.15 6.30 0.10 3.40 2.18

2 4.06 8.12 0.10 3.40 2.80

1 5.60 5.60 0.10 3.40 1.93

1 6.65 6.65 0.10 3.40 2.30

1 4.10 4.10 0.10 3.40 1.42

1 3.95 3.95 0.10 3.00 1.20

1 1.90 1.90 0.10 3.00 0.58

1 2.70 2.70 0.10 3.40 0.93

1 3.05 3.05 0.10 3.40 1.05

4 2.70 10.80 0.10 2.50 2.74

4 0.25 1.00 0.10 1.80 0.18

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

4 0.25 1.00 0.10 1.80 0.18

1 2.90 2.90 0.10 3.40 1.00

1 0.23 0.23 0.10 3.00 0.07

For veranda 5 1.00 5.00 0.10 3.17 1.61

Total 38.990 m3

8 8 R.C.C. Work

9 8.1 P.C.C. 1:1.5:3 (M 20 ) Same as Previous running Bill 1109.711

Block 2

Slab

Panel 1 1 47.70 47.70 17.50 0.125 104.34

Panel 2 1 8.00 8.00 6.00 0.125 6.00

Panel 3 1 21.20 21.20 2.40 0.125 6.36

Deduction (Slab Corner) 1 6.40 6.40 2.00 -0.13 -1.60

Front side veranda, foundation tie beam (1:1:2) 1 21.00 21.00 0.35 0.35 2.57

1 2.00 2.00 0.35 0.35 0.25

Upto DPC beam(1:1:2) 1 21.00 21.00 0.35 0.23 1.69

1 2.00 2.00 0.35 0.35 0.25

Deduction

East - West

Grid 8 -1 42.74 -42.74 0.35 0.125 -1.87

Grid 2,5,6 -3 23.61 -70.83 0.35 0.125 -3.10

Porch -1 6.60 -6.60 0.35 0.125 -0.29

Grid 3,7 -2 18.53 -37.05 0.35 0.125 -1.62

Grid 4 -1 17.93 -17.93 0.35 0.125 -0.78

Total 1221.905 m3

10 8.2 P. C.C 1:1:2 ( M 25 ) Same as Previous running Bill 427.516

Block 2

Pillar 36 0.60 21.60 0.60 0.83 10.69

1.5 0.60 0.90 0.60 0.83 0.45

Wall (1:1:2) 4 1.00 4.00 0.35 0.53 0.74

1 0.60 0.60 0.35 0.53 0.11

North - South

Grid P,Q,R,S,T 5 15.20 76.00 0.35 0.65 17.29

Grid P ie. veranda 1 2.00 2.00 0.35 0.65 0.46

Grid of porch 2 4.83 9.65 0.35 0.65 2.20

Grid L, N, M 3 16.99 50.96 0.35 0.65 11.59

Grid J 1 11.09 11.09 0.35 0.65 2.52

East - West

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Grid 8 1 42.74 42.74 0.35 0.65 9.72

Grid 2,5,6 3 23.61 70.83 0.35 0.65 16.11

Porch 1 6.60 6.60 0.35 0.65 1.50

Grid 3,7 2 18.53 37.05 0.35 0.65 8.43

Grid 4 1 17.93 17.93 0.35 0.65 4.08

9" height beam, veranda 1 20.93 20.93 0.35 0.30 2.20

Secondary beam (1:1:2)

North - South

Pannel 2 2 16.20 32.40 0.30 0.48 4.62

Pannel porch 1 4.83 4.83 0.30 0.48 0.69

Pannel 1 3 15.50 46.50 0.30 0.48 6.63

9" height beam 2 2.49 4.97 0.30 0.30 0.45

East - West

pannel 1 and 2 1 43.24 43.24 0.30 0.48 6.16

Pannel 2 1 23.71 23.71 0.30 0.48 3.38

Panel porch 2 3.15 6.30 0.30 0.48 0.90

pannel 1 1 19.18 19.18 0.30 0.48 2.73

Total 541.143 m3

11 8.3 Reinforcement works Same as Previous running Bill 223224.990

Grid J

Top and bottom 20mm dia 8 no of bars Length 8 13.84 110.68 2.46 272.27

Stirrups(8mm dia)

Small 95 1.70 161.50 0.39 62.98

Large 95 2.00 190.00 0.39 74.10

Overlaping of 20mm dia 8 no of bars 8 1.30 10.40 2.46 25.58

Cut piece

Edge 16mm dia 4 2.35 9.40 1.58 14.85

Middle 16mm dia 2 9.20 18.40 1.58 29.07

Side bars 12mm dia 2 20.00 40.00 0.88 35.20

Overlaping of side bar 2 0.75 1.50 0.88 1.32

Grid L

Top and bottom 20mm dia 8 no of bars Length 8 20.34 162.68 2.46 400.19

Stirrups(8mm dia)

Small 140 1.70 238.00 0.39 92.82

Large 140 2.00 280.00 0.39 109.20

Overlaping of 20mm dia 8 no of bars 16 2.70 43.20 2.46 106.27

Cut piece 0.00

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Edge 20mm dia 4 2.65 10.60 2.46 26.07

Middle 16mm dia 2 16.00 32.00 1.58 50.56

Side bars 12mm dia 2 20.14 40.27 0.88 35.43

Overlaping of side bar 2 2.15 4.30 0.88 3.78

Secondary beam(2 no of beam)

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Top and bottom 20mm dia 8 no of bars Length 16 17.50 280.00 2.46 688.80

Overlaping of 20mm dia 8 no of bars 16 1.30 20.80 2.46 51.16

Stirrups(8mm dia)

Small 260 1.60 416.00 0.39 162.24

Large 260 1.90 494.00 0.39 192.66

Side bars 12mm dia 4 17.30 69.20 0.88 60.89

Overlaping of side bar 8 0.70 5.60 0.88 4.92

Grid M

Top and bottom 20mm dia 8 no of bars Length 8 20.35 162.80 2.46 400.48

Stirrups(8mm dia) 0.00

Small 135 1.70 229.50 0.39 89.50

Large 135 2.00 270.00 0.39 105.30

Overlaping of 20mm dia 8 no of bars 8 2.70 21.60 2.46 53.13

Cut piece

Edge 20mm dia 4 3.60 14.40 2.46 35.42

Middle 20mm dia 2 14.00 28.00 2.46 68.88

Side bars 12mm dia 2 20.00 40.00 0.88 35.20

Overlaping of side bar 2 2.80 5.60 0.88 4.92

Grid N

Top and bottom 20mm dia 8 no of bars Length 8 20.35 162.80 2.46 400.48

Stirrups(8mm dia)

Small 140 1.70 238.00 0.39 92.82

Large 140 2.00 280.00 0.39 109.20

Overlaping of 20mm dia 8 no of bars 8 2.70 21.60 2.47 53.33

Cut piece

Edge 16mm dia 4 3.60 14.40 1.58 22.75

Middle 16mm dia 2 13.70 27.40 1.58 43.29

Side bars 12mm dia 2 20.00 40.00 0.88 35.20

Overlaping of side bar 2 1.50 3.00 0.88 2.64

Grid P, Q, R, S, T

Top and bottom 20mm dia 8 no of bars Length 40 18.95 758.00 2.46 1864.68

Stirrups(8mm dia) 0.00

Small 680 1.70 1156.00 0.39 450.84

Large 680 2.00 1360.00 0.39 530.40

Overlaping of 20mm dia 8 no of bars 40 2.70 108.00 2.46 265.68

Side bars 12mm dia 10 17.52 175.20 0.88 154.17

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Overlaping of side bar 10 1.40 14.00 0.88 12.32

Cut piece

Grid P

Edge 16mm dia 4 3.60 14.40 1.58 22.75

Middle 16mm dia 2 15.60 31.20 1.58 49.29

Grid Q

Edge 20mm dia 8 2.60 20.80 2.46 51.16

Middle 20mm dia 8 14.00 112.00 2.46 275.52

Grid R

Edge 20mm dia 4 3.05 12.20 2.46 30.01

Middle 20mm dia 8 13.00 104.00 2.46 255.84

Grid S

Edge 20mm dia 8 2.60 20.80 2.46 51.16

Middle 20mm dia 4 13.00 52.00 2.46 127.92

Grid T

Edge 20mm dia 8 3.10 24.80 2.46 61.00

Middle 20mm dia bottom 2 6.20 12.40 2.46 30.50

Middle 20mm dia top 4 6.00 24.00 2.46 59.04

Secondary Beams(3 no of beam)

Top and bottom 20mm dia 8 no of bars Length 24 18.95 454.80 2.46 1118.80

Overlaping of 20mm dia 8 no of bars 24 2.70 64.80 2.46 159.40

Stirrups(8mm dia)

Small 390 1.60 624.00 0.39 243.36

Large 390 1.90 741.00 0.39 288.99

Side bars 12mm dia 6 17.52 105.12 0.88 92.50

Overlaping of side bar 6 1.40 8.40 0.88 7.39

Verandah - Beam

2 no. Of short span beam

Top and bottom 6no,16mm dia bar(Ld and length) 12 4.40 52.80 1.58 83.42

Stirrups 50 1.36 68.00 0.39 26.52

Long span

Top and bottom 6no, 16mm dia bar(Ld and length) 6 23.30 139.80 1.58 220.88

Overlapping 12 1.50 18.00 1.58 28.44

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Stirrups 145 1.36 197.20 0.39 76.90

Porch

Short span (3 no of beam)


Top and bottom 20mm dia 8 no of Bars Ld
24 7.60 182.40 2.46 448.70
(Bothway) and length
Stirrups(8mm dia)

Small 120 1.70 204.00 0.39 79.56

Large 120 2.00 240.00 0.39 93.60

Overlaping of 20mm dia 8 no of bars 24 1.35 32.40 2.46 79.70

Cut piece

Edge 16mm dia 4 2.20 8.80 1.58 13.90

Middle 20mm dia 4 3.00 12.00 2.46 29.52

Side bars 12mm dia 6 6.90 41.40 0.88 36.43

Long span (2 no of beam)


Top and bottom 20mm dia 8 no of Bars Ld
16 9.00 144.00 2.46 354.24
(Bothway) and length
Overlaping of 20mm dia 8 no of bars 16 1.50 24.00 2.46 59.04

Stirrups(8mm dia)

Small 120 1.70 204.00 0.39 79.56

Large 120 2.00 240.00 0.39 93.60

Cut piece

Edge 16mm dia 4 2.65 10.60 1.58 16.74

Middle 16mm dia 2 3.50 7.00 1.58 11.06

Side bars 12mm dia 4 7.70 30.80 0.88 27.10

Overlaping of side bar 4 0.75 3.00 0.88 2.64

Grid 8

Top and bottom 20mm dia 8 no of bars Length 8 48.90 391.20 2.46 962.35

Stirrups(8mm dia)

Small 320 1.70 544.00 0.39 212.16

Large 320 2.00 640.00 0.39 249.60

Overlaping of 20mm dia 8 no of bars 40 1.35 54.00 2.46 132.84

Cut piece

Edge 20mm dia 4 3.60 14.40 2.46 35.42

Middle 16mm dia bottom 2 18.00 36.00 1.58 56.88

Middle 20mm dia top 2 21.15 42.30 2.46 104.05

Side bars 12mm dia 2 48.86 97.71 0.88 85.98

Overlaping of side bar 8 0.70 5.60 0.88 4.92

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Secondary beam long way

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Top and bottom 20mm dia 8 no of bars Length 8 48.88 391.04 2.46 961.95

Stirrups(8mm dia)

Small 325 1.70 552.50 0.39 215.47

Large 325 2.00 650.00 0.39 253.50

Overlaping of 20mm dia 8 no of bars 40 1.35 54.00 2.46 132.84

Side bars 12mm dia 2 47.46 94.91 0.88 83.52

Overlaping of side bar 8 0.70 5.60 0.88 4.92

Grid 6,5,2

Top and bottom 20mm dia 8 no of bars Length 24 28.00 672.00 2.46 1653.12

Stirrups(8mm dia)

Small 660 1.70 1122.00 0.39 437.58

Large 660 2.00 1320.00 0.39 514.80

Overlaping of 20mm dia 8 no of bars 48 1.50 72.00 2.46 177.12

10 6 26.00 156.00 0.88 137.28

Overlaping of side bar 12 0.70 8.40 0.88 7.39

Cut piece

Grid 6 and 5

Edge 20mm dia 16 2.60 41.60 2.46 102.33

Middle 20mm dia bottom 4 12.00 48.00 2.46 118.08

Middle 20mm dia top 8 10.00 80.00 2.46 196.80

Grid 2

Edge 20mm dia 4 2.60 10.40 2.46 25.58

Middle 16mm dia bottom 2 12.00 24.00 1.58 37.92

Middle 20mm dia top 2 10.00 20.00 2.46 49.20

Secondary beam

Top and bottom 20mm dia 8 no of bars Length 8 28.00 224.00 2.46 551.04

Stirrups(8mm dia)

Small 220 1.70 374.00 0.39 145.86

Large 220 2.00 440.00 0.39 171.60

Overlaping of 20mm dia 8 no of bars 8 1.50 12.00 2.46 29.52

Side bars 12mm dia 2 26.61 53.22 0.88 46.83

Overlaping of side bar 4 0.70 2.80 0.88 2.46

Grid 3,4,7

Top and bottom 20mm dia 8 no of bars Length 24 22.32 535.68 2.46 1317.77

Stirrups(8mm dia)

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Small 420 1.70 714.00 0.39 278.46

Large 420 2.00 840.00 0.39 327.60

Overlaping of 20mm dia 8 no of bars 24 2.80 67.20 2.46 165.31

Side bars 12mm dia 6 20.92 125.54 0.88 110.47

Overlaping of side bar 6 1.40 8.40 0.88 7.39

Cut piece

Grid 7

Edge 20mm dia 8 3.00 24.00 2.46 59.04

Middle 20mm dia bottom 4 8.00 32.00 2.46 78.72

Middle 20mm dia top 4 6.20 24.80 2.46 61.00

Grid 3

Edge 20mm dia 4 3.00 12.00 2.46 29.52

Middle 16mm dia bottom 2 7.50 15.00 1.58 23.70

Middle 20mm dia top 2 12.00 24.00 2.46 59.04

Grid 4

Edge and middle 16mm dia 2 23.00 46.00 1.58 72.68

Secondary beam

Top and bottom 20mm dia 8 no of bars Length 8 22.00 176.00 2.47 434.54

Stirrups(8mm dia)

Small 145 1.60 232.00 0.39 90.48

Large 145 1.80 261.00 0.39 101.79

Overlaping of 20mm dia 8 no of bars 8 2.70 21.60 2.46 53.13

Side bars 12mm dia 2 20.92 41.85 0.88 36.82

Overlaping of side bar 2 1.40 2.80 0.88 2.46

Slab Details

1st panel

Bottom bar

Main bars(10mm dia bar) 156 19.90 3104.40 0.61 1893.68

Overlap of main bar(10mm dia bar) 156 1.60 249.60 0.61 152.25

Distribution bar(10mm dia bar) 125 21.30 2662.50 0.61 1624.12

Overlap of distribution bar(10mm dia bar) 125 1.70 212.50 0.61 129.62

Distribution bar(8mm dia bar) 20 21.30 426.00 0.39 166.14

Overlap of distribution bar(8mm dia bar) 20 1.70 34.00 0.39 13.26

For passage

Cut piece for L/4

Distribution bar 8mm dia bars 30 21.30 639.00 0.39 249.21

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Over lap of distribution bar 30 1.40 42.00 0.39 16.38

Main bars 10mm dia bars 130 5.00 650.00 0.61 396.50

Main bar (N - S)(10mm dia bar) 270 1.40 378.00 0.61 230.58

Main bar (E - W)(10mm dia bar) 42 1.40 58.80 0.61 35.86

Main bar (N - S)(10mm dia bar) 420 2.10 882.00 0.61 538.02

Main bar (E - W)(10mm dia bar) 316 2.10 663.60 0.61 404.79

Distribution bar (N - S) 8mm dia bars 5 6.60 33.00 0.39 12.87

Overlap of distribution bar 5 0.35 1.75 0.39 0.68

Distribution bar (N - S) 8mm dia bars 156 11.55 1801.80 0.39 702.70

Distribution bar (E - W) 8mm dia bars 48 21.70 1041.60 0.39 406.22

Distribution bar (E - W) 10mm dia bars 10 21.70 217.00 0.61 132.37

Deduction

distribution bar(E-W) 8mm dia bar -20 0.50 -10.00 0.40 -3.95

Slab details For panel - 2

Bottom bar

Main bars(10mm dia bar) 200 17.80 3560.00 0.61 2171.60

Overlap of main bar(10mm dia bar) 200 2.25 450.00 0.61 274.50

Distribution bar(10mm dia bar) 125 26.71 3338.75 0.61 2036.63

Overlap of distribution bar(10mm dia bar) 125 2.25 281.25 0.61 171.56

Distribution bar(8mm dia bar) 15 26.71 400.65 0.39 156.25

Overlap of distribution bar(8mm dia bar) 15 2.25 33.75 0.39 13.16

For passage

Cut piece for L/4

Distribution bar 8mm dia bars 28 26.71 747.88 0.39 291.67

Over lap of distribution bar 84 1.50 126.00 0.39 49.14

Main bars 10mm dia bars 169 4.76 804.44 0.61 490.70

Main bars 10mm dia bars 25 5.10 127.50 0.61 77.77

Main bar (N - S)(10mm dia bar) 316 1.65 521.40 0.61 318.05

Main bar (E - W)(10mm dia bar) 60 1.65 99.00 0.61 60.39

Main bar (N - S)(10mm dia bar) 390 2.15 838.50 0.61 511.48

Main bar (E - W)(10mm dia bar) 360 2.10 756.00 0.61 461.16

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Distribution bar (E - W) 8mm dia bars 32 26.71 854.72 0.39 333.34

Overlap of main bar(10mm dia bar) 96 0.75 72.00 0.61 43.92

Distribution bar (E - W) 10mm dia bars 5 26.71 133.55 0.61 81.46

Overlap of distribution bar(10mm dia bar) 15 0.75 11.25 0.61 6.86

Distribution bar (N - S) 8mm dia bars with overlap 73 10.80 788.40 0.39 307.47

Overlap of distribution bar(10mm dia bar) 73 0.30 21.90 0.61 13.35

Slab details For panel - 3

Bottom bar

Main bars(10mm dia bar) 55 6.10 335.50 0.61 204.65

Overlap of main bar(10mm dia bar) 55 1.10 60.50 0.61 36.90

Distribution bar(10mm dia bar) 36 7.90 284.40 0.61 173.48

Overlap of distribution bar(10mm dia bar) 36 0.60 21.60 0.61 13.17

Cut piece for L/4

Main bar (E - W)(10mm dia bar) 28 1.70 47.60 0.61 29.03

Main bar (N - S)(10mm dia bar) 49 1.70 83.30 0.61 50.81

Main bar(N - S)(10mm dia bar) 94 2.10 197.40 0.61 120.41

Distribution bar (N - S) 8mm dia bars 25 4.10 102.50 0.39 39.97

Pillars

Pillars No. 1

25mm dia 4 2.90 11.60 3.86 44.75

20mm dia 3 3.40 10.20 2.46 25.09

20mm dia 4 3.80 15.20 2.46 37.39

Pillar no. 2

20mm dia 2 3.80 7.60 2.46 18.69

20mm dia 2 3.40 6.80 2.46 16.72

20mm dia 4 3.90 15.60 2.46 38.37

Pillar no. 3

20mm dia 2 2.50 5.00 2.46 12.30

20mm dia 4 3.20 12.80 2.46 31.48

Pillar no.4

20mm dia 4 3.60 14.40 2.46 35.42

20mm dia 4 4.00 16.00 2.46 39.36

Pillar no.5

20mm dia 3 3.50 10.50 2.46 25.83

20mm dia 5 3.90 19.50 2.46 47.97

Pillar no.6

20mm dia 9 3.50 31.50 2.46 77.49

Pillar no.8

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

20mm dia 10 3.50 35.00 2.46 86.10

20mm dia 1 3.40 3.40 2.46 8.36

20mm dia 1 3.20 3.20 2.46 7.87

Pillar no.9

20mm dia 6 3.60 21.60 2.46 53.13

20mm dia 5 3.90 19.50 2.46 47.97

Pillar no.10 0.00

20mm dia 8 3.50 28.00 2.47 69.13

20mm dia 1 3.90 3.90 2.47 9.62

Pillar no.12

20mm dia 4 3.00 12.00 2.46 29.52

20mm dia 3 4.50 13.50 2.46 33.21

20mm dia 1 5.00 5.00 2.46 12.30

Pillar no.13

20mm dia 8 4.50 36.00 2.46 88.56

Pillar no.14

20mm dia 2 3.80 7.60 2.46 18.69

20mm dia 4 3.00 12.00 2.46 29.52

Pillar no.16

20mm dia 2 4.60 9.20 2.46 22.63

20mm dia 2 4.30 8.60 2.46 21.15

20mm dia 2 3.50 7.00 2.46 17.22

20mm dia 4 3.80 15.20 2.46 37.39

Pillar no.17

20mm dia 2 3.00 6.00 2.46 14.76

20mm dia 4 3.10 12.40 2.46 30.50

20mm dia 3 3.50 10.50 2.46 25.83

20mm dia 3 4.00 12.00 2.46 29.52

Pillar no.18

20mm dia 4 3.10 12.40 2.46 30.50

20mm dia 4 2.90 11.60 2.46 28.53

20mm dia 2 3.50 7.00 2.46 17.22

20mm dia 2 3.00 6.00 2.46 14.76

Pillar no.19

20mm dia 7 3.50 24.50 2.46 60.27

20mm dia 2 3.00 6.00 2.46 14.76

20mm dia 2 3.30 6.60 2.46 16.23

20mm dia 1 3.65 3.65 2.46 8.97

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Pillar no.20

20mm dia 4 4.10 16.40 2.46 40.34

20mm dia 5 3.10 15.50 2.46 38.13

Pillar no.21

20mm dia 4 3.50 14.00 2.46 34.44

20mm dia 4 3.20 12.80 2.46 31.48

20mm dia 1 3.00 3.00 2.46 7.38

20mm dia 3 3.70 11.10 2.46 27.30

Pillar no.22

20mm dia 5 3.80 19.00 2.46 46.74

20mm dia 7 3.50 24.50 2.46 60.27

Pillar no.23

20mm dia 4 3.70 14.80 2.46 36.40

20mm dia 6 3.30 19.80 2.46 48.70

20mm dia 2 2.40 4.80 2.46 11.80

Pillar no.24

20mm dia 6 3.00 18.00 2.46 44.28

20mm dia 2 3.50 7.00 2.46 17.22

20mm dia 1 3.00 3.00 2.46 7.38

Pillar no 25

25mm dia 1 5.00 5.00 3.85 19.25

25mm dia 2 3.50 7.00 3.85 26.95

25mm dia 1 3.00 3.00 3.85 11.55

20mm dia 1 3.65 3.65 2.46 8.97

20mm dia 1 2.90 2.90 2.46 7.13

20mm dia 4 3.50 14.00 2.46 34.44

20mm dia 1 4.70 4.70 2.46 11.56

20mm dia 2 5.00 10.00 2.46 24.60

Pillar no 26

25mm dia 2 2.70 5.40 3.85 20.79

25mm dia 1 3.20 3.20 3.85 12.32

25mm dia 3 3.40 10.20 3.85 39.27

25mm dia 2 5.00 10.00 3.85 38.50

20mm dia 2 3.50 7.00 2.46 17.22

20mm dia 2 2.90 5.80 2.46 14.26

Pillar no 27

25mm dia 4 3.50 14.00 3.85 53.90

25mm dia 1 3.00 3.00 3.85 11.55

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

25mm dia 3 3.60 10.80 3.85 41.58

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

20mm dia 2 2.00 4.00 2.47 9.87

20mm dia 2 2.80 5.60 2.47 13.82

Pillar no 28

25mm dia 2 3.50 7.00 3.85 26.95

25mm dia 2 3.80 7.60 3.85 29.26

25mm dia 4 3.00 12.00 3.85 46.20

20mm dia 2 2.80 5.60 1.58 8.84

25mm dia 9 3.60 32.40 3.85 124.74

Pillar no 30

25mm dia 8 3.60 28.80 3.85 110.88

Pillar no 31

25mm dia 8 3.60 28.80 3.85 110.88

Pillar no 33

25mm dia 8 3.60 28.80 3.86 111.11

Pillar no 34

32mm dia 1 3.50 3.50 6.31 22.08

32mm dia 2 3.00 6.00 6.31 37.86

32mm dia 1 4.00 4.00 6.31 25.24

25mm dia 1 3.00 3.00 3.85 11.55

25mm dia 1 2.10 2.10 3.85 8.08

25mm dia 2 2.50 5.00 3.85 19.25

25mm dia 4 3.50 14.00 3.85 53.90

Pillar no 35

32mm dia 4 3.75 15.00 6.31 94.65

25mm dia 1 3.50 3.50 3.85 13.47

25mm dia 3 3.00 9.00 3.85 34.65

25mm dia 4 3.00 12.00 3.85 46.20

Pillar no 36

25mm dia 4 3.80 15.20 3.85 58.52

25mm dia 3 3.00 9.00 3.85 34.65

25mm dia 1 3.20 3.20 3.85 12.32

Pillar no 37

16mm dia 8 3.50 28.00 1.58 44.24

Pillar no 38

16mm dia 2 2.80 5.60 1.58 8.84

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

16mm dia 2 2.60 5.20 1.58 8.21

16mm dia 4 3.00 12.00 1.58 18.96

Chair 300 0.60 180.00 0.39 70.20

Pillar stirrups (8mm dia) 36*5 2.30 579.60 0.39 226.04

Pin (20mm dia) 40 0.30 12.00 2.46 29.52

Foundation tiebeam

Stirrups(8mm dia) 145 1.40 203.00 0.39 79.17

Stirrups(8mm dia) 15 1.40 21.00 0.39 8.19

Strap Beam

Upper bars and lower bars(20 mm dia) 8 22.30 178.40 2.46 438.86

Upper bars and lower bars(16 mm dia) 8 2.70 21.60 1.58 34.12

lap of 16mm dia bar 8 1.20 9.60 1.58 15.16

lap of 16mm dia bar 8 1.20 9.60 1.58 15.16

DPC

Stirrups(8mm dia) 145 1.10 159.50 0.39 62.20

Stirrups(8mm dia) 15 1.10 16.50 0.39 6.43

Upper bars and lower bars(20 mm dia) 8 22.30 178.40 2.58 460.27

Upper bars and lower bars(16 mm dia) 8 2.70 21.60 2.46 53.13

lap of 20mm dia bar 8 1.20 9.60 2.46 23.61

lap of 20mm dia bar 8 1.20 9.60 2.46 23.61

Brick pillar Bar 5 5.50 27.50 1.58 43.45

Verandah Pillar (16mmmdia.bar) 16 6.50 104.00 1.58 164.32

267272.61 kg

12 8.4 Form works Same as Previous running Bill 6630.24

Block - 2

Pillar form work 36 2.40 86.40 0.20 17.28

wall (inner face) 4 0.65 2.60 0.65 1.69

wall (inner face) 1 0.25 0.25 0.65 0.16

wall (sideface) 2 0.35 0.70 0.65 0.45

wall inner side below veranda beam 8 0.35 2.80 0.28 0.77

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

wall (Outer face) 4 1.00 4.00 0.50 2.00

wall (Outer face) 1 0.60 0.60 0.50 0.30

Porch pillar 2 2.40 4.80 0.20 0.96

Pillar outside(grid J)(N-S) 3 0.60 1.80 0.65 1.17

Pillar inside (grid J)(N-S) 3 0.30 0.90 0.53 0.47

Pillar inside(grid J-N)(N-S) 24 0.30 7.20 0.53 3.78

Pillar inside (grid O)(N-S) 2 0.30 0.60 0.53 0.31

Pillar Outside(grid T)(N-S) 4 0.60 2.40 0.65 1.56

Pillar inside(grid P-T)(N-S) 24 0.30 7.20 0.53 3.78

Pillar inside (grid T and P)(N-S) 8 0.30 2.40 0.53 1.26

Pillar inside (grid P)(N-S) 3 0.60 1.80 0.53 0.94

Pillar inside (grid P)(North corner) 1 0.30 0.30 0.53 0.15

pillar outside (grid R,S)(N-S) 2 0.60 1.20 0.53 0.63

Pillar inside(porch)(N-S) 2 0.30 0.60 0.53 0.31

Pillar outside (grid 8) (E-W) 8 0.60 4.80 0.53 2.52

Pillar inside (grid 8)(E-W) 8 0.30 2.40 0.53 1.26

pillar outside (grid 7) 1 0.60 0.60 0.53 0.31

pillar inside (grid 7) 7 0.30 2.10 0.53 1.10

pillar inside (grid 4) 10 0.30 3.00 0.53 1.57

pillar inside (grid 3) 4 0.30 1.20 0.53 0.63

pillar outside (grid 3) 4 0.60 2.40 0.53 1.26

pillar inside(grid 2,5,6) 25 0.30 7.50 0.53 3.93

pillar outside (grid 2) 5 0.60 3.00 0.53 1.57

pillar porch outside 2 0.60 1.20 0.53 0.63

Pillar porch inside 2 0.30 0.60 0.53 0.31

Bottom Formwork

Primary Beam

North - South

Pannel 1 3 5.90 17.70 0.35 6.19

Pannel 1 4 6.60 26.40 0.35 9.24

Pannel 1 4 2.00 8.00 0.35 2.80

Pannel 2 10 6.60 66.00 0.35 23.10

Pannel 2 5 2.00 10.00 0.35 3.50

Pannel 3 2 5.70 11.40 0.35 3.99

Veranda 4 2.49 9.94 0.35 3.47

Veranda 1 1.79 1.79 0.35 0.62

East - west

pannel 1 3 2.34 7.02 0.35 2.45

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

pannel 1 1 0.95 0.95 0.35 0.33

pannel 1 8 6.60 52.80 0.35 18.48

pannel 1 3 2.99 8.96 0.35 3.13

pannel 1 1 2.39 2.39 0.35 0.83

porch 1 7.05 7.05 0.35 2.46

pannel 2 4 3.81 15.24 0.35 5.33

pannel 2 12 6.60 79.20 0.35 27.72

veranda 1 1.94 1.94 0.35 0.67

veranda 2 6.20 12.40 0.35 4.34

veranda 1 2.59 2.59 0.35 0.90

Secondary beam

(north - south & east - west)

Pannel 1(E - W) 1 19.53 19.53 0.30 5.85

pannel 1 with cantilever 1 18.04 18.04 0.30 5.41

pannel 1 (N - S) 2 14.50 28.99 0.30 8.69

Pannel 2 (E - W) 2 24.58 49.16 0.30 14.74

pannel 2(N - S) 3 15.29 45.87 0.30 13.76

porch (N - S) 1 5.85 5.85 0.30 1.75

porch (E - W) 1 7.05 7.05 0.30 2.11

Veranda (N - S) 2 2.89 5.77 0.30 1.73

Side formwork

Primary Beam

North - South

Pannel 1 inside and outside form(L-N) 6 5.60 33.60 0.53 17.64

pannel 1 outside form(grid J) 1 6.60 6.60 0.53 3.46

pannel 1 inside form(grid J-N) 7 6.30 44.10 0.53 23.15

Pannel 1 inside and outside form(J-N) 8 2.00 16.00 0.53 8.40

Pannel 2 inside (grid P-T) 18 6.30 113.40 0.53 59.53

Pannel 2 outside (grid P-T) 2 6.60 13.20 0.53 6.93

pannel 2 inside and outside(grid P-T) 10 2.00 20.00 0.53 10.50

Pannel 3 inside (grid R-S) 2 5.70 11.40 0.53 5.98

Pannel 3 outside (grid R-S) 2 5.85 11.70 0.53 6.14

veranda inside and outside(grid J-P) 10 2.49 24.85 0.53 13.04

East - west

pannel 1 (grid 8 cantilever) 1 1.10 1.10 0.53 0.57

pannel 1 inside and outside(grid 3,4,7) 6 2.34 14.04 0.53 7.37

pannel 1outside(grid 3,8) 4 6.60 26.40 0.53 13.86

pannel 1 inside (grid 3,4,7,8) 12 6.30 75.60 0.53 39.69

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

pannel 1 inside and outside(grid 3,7,8) 6 2.99 17.91 0.53 9.40

pannel 1 inside (grid 4) 2 2.39 4.77 0.53 2.50

pannel 2 inside and outside(grid 2,5,6,8) 8 3.81 30.48 0.53 16.00

pannel 2 outside (grid 2,8) 5 6.60 33.00 0.53 17.32

pannel 2 inside (grid 2,5,6,8) 19 6.30 119.70 0.53 62.84

pannel 3 outside 1 6.75 6.75 0.53 3.54

pannel 3 inside 1 6.75 6.75 0.53 3.54

wall west side 2 1.94 3.88 0.23 0.87

wall outside 2 6.20 12.40 0.23 2.79

wall east side 2 2.59 5.17 0.23 1.16

wall inside 2 5.90 11.80 0.23 2.65

Secondary beam

(north - south & east - west)

pannel 1 (E-W) with cantilever 2 18.93 37.85 0.50 18.92

pannel 1 (E-W) full length 2 17.44 34.87 0.50 17.43

pannel 1(N-S) 4 14.50 57.98 0.50 28.99

pannel 2 (E-W) 4 23.96 95.84 0.50 47.92

pannel 2 (N-S) 6 15.29 91.74 0.50 45.87

pannel 3 (E-W) 2 6.75 13.50 0.50 6.75

pannel 3 (N-S) 2 5.43 10.85 0.50 5.42

varenda (N-S) 4 2.89 11.54 0.23 2.59

Slab

Pannel 2 1 26.61 26.61 17.60 468.33

pannel 1 1 20.93 20.93 10.40 217.62

pannel 1 1 17.99 17.99 6.50 116.90

pannel 3 1 6.15 6.15 7.95 48.89

varenda 1 20.93 20.93 1.94 40.48

Deduction Slab area 1 6.40 6.40 -2.40 -15.36

Slab side formwork

north side form(E-W)(grid 8) 1 44.60 44.60 0.13 5.57

West cantilever side, side form (N-S) 1 6.50 6.50 0.13 0.81

north side form(E-W)(grid 7) 1 1.84 1.84 0.13 0.23

west side form (N-S)(grid J) 1 13.24 13.24 0.13 1.65

veranda(E-W) 1 21.53 21.53 0.13 2.69

grid P(N-S) 1 2.14 2.14 0.13 0.26

South side(E-W) (grid 2 and porch) 1 26.01 26.01 0.13 3.25

porch (N-S) (grid R,S) 2 5.97 11.94 0.13 1.49

1 17.60 17.60 0.13 2.20

Estimaded By :- Checked By :- Approved By :-


S.N.Item No. Items No. Length T.Length Breadth Height Quantity Unit

Deduction

Pillar 36 0.60 21.60 -0.60 -12.96

Pillar 2 0.60 1.20 -0.45 -0.54

Total beam `

Wall 4 1.00 4.00 -0.35 -1.40

wall 1 0.60 0.60 -0.35 -0.21

Front side veranda 1 23.00 23.00 -0.70 -16.10

Foundation tie beam

Upto DPC beam 1 23.00 23.00 -0.46 -10.58

Total 8222.87 m2

13 16.1 Sand Filling Work

Block 1

Room 10 6.85 68.50 6.85 0.08 35.19

Passage 5 6.85 34.25 2.50 0.08 6.42

Block 3

Room 6 6.85 41.10 6.85 0.08 21.12

Passage 3 6.85 20.55 2.50 0.08 3.85

Total 66.58 m3

Estimaded By :- Checked By :- Approved By :-


zx/L ljsf; tyf ejg lgdf{0f ljefu, l8lehg sfof{no, ;'v]{t d=n]=k=kmf=g+= !^*

lansf] s|d ;+VofM– kfrf}+ /lgË lan


7]Ssf ;DalGw aLn sfof{De cfb]z ldltM– )^$.)^.@&
of]hgfsf] gfdM– %) z}of c:ktfn ejg lgdf{0f sfo{ , ;'v]{t ;Dem\of}tf ldltM– @)^$.)^.!*
7]s]bf/sf] gfd M– /lagf , cflzif k|lti7f , g]kfn k|utL h]=eL= z}a' , sf7df08f}+ . sfd ;DkGg ug'{ kg]{ ldltM– @)^^.)@.!&-;Dem\of}tfsf] @) dlxgf _
7]Ssf k6[fsf] ;+VofM– !) - @)^#÷)^$ _ sfd ;DkGg ePsf] ldltM– rfn'''''''
cl3Nnf] e"QmfgL lansf] s|d;+VofM– rf}yf] /lgË lan e"QmfgL efpr/ g+=–
cl3Nnf] e"QmfgL ef=g+=M– e"QmfgL ldltM–
gfkL lstfa g+= sf] k[i7 g+=M– b]lv ;Dd
cfO{ cBfjlw sfd ePsf] cl3Nnf] landf r9]sf] xfn ePsf] sfd
s||=;+ 6d sfdsf] laj/0f PsfO{ s}lkmot
g+== kl/df0f b/ hDdf d"No kl/df0f hDdf d"No kl/df0f hDdf d"No
A CIVIL WORKS
1 1.2 Earth work in Excavation in site Development m3 3799.225 100.00 379922.50 3799.225 379922.50 0.000 0.00
2 2 Earth work excavation in BM Soil on Foundation m3 2533.707 200.00 506741.40 2533.707 506741.40 0.000 0.00
3 4 150mm thick stone soling with sand m3 203.502 2500.00 508755.00 203.502 508755.00 0.000 0.00
4 5 75mm thick lean concrete (1:3:6) in foundation m3 104.041 4500.00 468184.50 104.041 468184.50 0.000 0.00
5 7 Brick Masonary work ( 1:6 ) m3 508.430 4576.61 2326885.82 508.430 2326885.82 0.000 0.00
6 8 R.C.C. Works
7 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 1109.711 6529.70 7246079.91 1049.636 6853808.18 60.075 392271.73
8 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 427.516 8547.38 3654141.70 375.832 3212378.92 51.684 441762.78
9 8.3 Reinforcements works kg 223224.990 60.51 13507344.14 203510.9 12314445.16 ### 1192898.98
10 8.4 Form work m2 6630.240 313.00 2075265.12 5850.94 1831344.22 779.300 243920.90

TOTAL AMOUNT (without VAT) Rs. 30673320.09 Rs 28402465.70 Rs. 2270854.39

pko'{Qm adf]lhd 7Ls 5 egL k|dfl0ft ug]{sf] ;xLM–


=========== ============ =========
cf]e/l;o/ O{lGhgLo/ 7]s]bf/sf] ;xL
of] lansf] hDdf -Eof6 afx]]s_ 30673320.09
cl3Nnf] e"QmfgL lanaf6 e"QmfgL ePsf] -Eof6 28402465.70
afFsL lbg' kg]{ -Eof6 afx]s_ 2270854.39
s6[L ug'{ kg]{ ?=M–
s_ k]ZsL–
v_ dfn;dfgsf] df]nM–
u_ d]zLg cf}hf/ axfnM–
3_ cfos/ !=%Ü M–
ª_ d"No clea[l4 s/ !# Ü M–
r_ w/f}6L %Ü M–
5_ cGo M–
v"b lbg' kg]{ -Eof6 ;d]t_ ?=M–
k]z ug]{sf] ;xLM– hfFr ug]{sf] ;xLM– :jLs[t ug]{sf] ;xLM–
hDdf ?= cIf]?kLM– sf] r]s g+= af6 k|fKt ePsf] egL ;xL ug]{ 7]s]bf/sf] ;xLM–
Department of Urban Development And Building Construction
DIVISION OFFICE, Surkhet
F/Y-064 - 065
Name of work :- 50 Bed Hospital Construction Work
Place :- Birendranagar - 3 , Kalagaon , Surkhet

5th. RUNNING BILL


S.N. Item No. Items Unit Quantity Unit Rate Amount

A CIVIL WORKS

1 1.2 Earth work in Excavation in site Development m3 3799.225 100.00 379922.50

2 2 Earth work excavation in BM Soil on Foundati m3 2533.707 200.00 506741.40

3 4 150mm thick stone soling with sand m3 203.502 2500.00 508755.00

4 5 75mm thick lean concrete (1:3:6) in foundation m3 104.041 4500.00 468184.50

5 7 Brick Masonary work ( 1:6 ) m3 508.430 4576.61 2326885.82

6 8 R.C.C. Works

7 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 1109.711 6529.70 7246079.91

8 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 427.516 8547.38 3654141.70

9 8.3 Reinforcements works kg 223224.990 60.51 13507344.14

10 8.4 Form work m2 6630.240 313.00 2075265.12

TOTAL 5nd Bill AMOUNT Rs. 30673320.09

Estimated By:- Checked By:- Approved By:-


Department of Urban Development And Building Construction
DIVISION OFFICE
Surkhet
Name of work :- 50 Bed Hospital Construction Work F/Y-064 - 065
Place :- Birendranagar - 3 , Kalagaon , Surkhet

DETAILS OF MEASUREMENT ( 5 th. Bill )


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

(A) CIVIL WORKS

1 1 Site Development work

2 1.2 Earth work in Excavation in site Development Same as previous bill running Bill 3799.225

3 2 Earth work excavation in BM Soil on Foundation Same as Previous running Bill 2533.707 m3

4 4 150mm thick stone soling with sand Same as Previous running Bill 203.502 m3

5 5 Lean Concrete Bae (1:3:6) Same previous running Bill 104.041 m3

6 7 Brick Masonary work ( 1:6 ) Same as Previous running Bill 508.430

7 8 R.C.C. Work

8 8.1 P.C.C. 1:1.5:3 (M 20 ) Same as Previous running Bill 1049.636

Block 4

Slab 1 26.70 26.70 18.00 0.125 60.075

Total 1109.71 m3

9 8.2 P. C.C 1:1:2 ( M 25 ) Same as Previous running Bill 375.832

Block 4

Pillar 20 0.600 12.000 0.600 0.900 6.480

Primary beam

PCC for RCC beam (1:1:2) M25 (P,Q,R,S,T & 10,1 22 6.60 145.200 0.350 0.525 26.680

PCC for RCC beam (1:1:2) M25 ( 13,12) 5 2.25 11.250 0.350 0.525 2.067

PCC for RCC beam (1:1:2) M25 (P,Q) 4 3.81 15.240 0.350 0.525 2.800

Secondary Beam

PCC for RCC beam (1:1:2) M25 (north - south) 6 6.86 41.160 0.300 0.475 5.865

PCC for RCC beam (1:1:2) M25 (north - south) (B4 3 2.43 7.270 0.300 0.475 1.035

PCC for RCC beam (1:1:2) M25 (East - west) 2 4.06 8.120 0.300 0.475 1.157

PCC for RCC beam (1:1:2) M25 (East - west) 6 6.55 39.300 0.300 0.475 5.600

Total 427.516 m3

10 8.3 Reinforcement works Same as Previous running Bill 203510.910

Block 4

East - West

Primary beam

4th block slab beam

grid 10, 12, 13 and 14 24 27.80 667.200 2.46 1641.310

Upper bars and lower bars(20 mm dia) 6 27.80 166.800 2.46 410.320

Checked By :-
Estimaded By :- Approved By :-
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

lower bar (16mm dia) 2 27.80 55.600 1.58 87.840

1 27.80 27.800 1.58 43.920

Stirrups(8mm dia)

large 732 2.00 1464.000 0.39 570.960

small 732 1.70 1244.400 0.39 485.310

Extra bar (middle)

cut piece 16 mm dia 8 4.20 33.600 1.58 53.080

32 2.70 86.400 1.58 136.510

48 4.30 206.400 1.58 326.110

Side bar(12mm dia) (primary and secondary) 12 26.60 319.200 0.88 280.890

Secondary beam (20 mm dia)

8 27.80 222.400 2.46 547.100

6 27.80 166.800 2.46 410.320

16mm dia 2 27.80 55.600 1.58 87.840

stirrups(8mm dia)

large 366 1.78 651.480 0.39 254.070

small 366 1.58 578.280 0.39 225.520

North - south

Primary beam

Grid P, Q, R, S and T 40 18.80 752.000 2.46 1849.920

Secondary beam 24 18.60 446.400 2.46 1098.140

Extra bar

Cut piece(20mm dia)(endbar) 8 2.70 21.600 2.46 53.130

Checked By :-
Estimaded By :- Approved By :-
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

Cut piece(20mm dia)(middle bar) 20 5.70 114.000 2.46 280.440

Cut piece(20mm dia)(end bar) 24 2.70 64.800 2.46 159.400

Cut piece(16 mm dia)(end bar) 8 4.20 33.600 1.58 53.080

24 4.20 100.800 1.58 159.260

Side bar(12mm dia) 18 17.60 316.800 0.88 278.780

Stirrups (Primary beam 8mm dia)

large 600 2.00 1200.000 0.39 468.000

small 600 1.70 1020.000 0.39 397.800

Stirrups (Secondary beam 8mm dia) 360 1.78 640.800 0.39 249.910

360 1.58 568.800 0.39 221.830

Main bar slab (10 mm dia) East - West 116 26.70 3097.200 0.61 1889.290

Distribution bar (10 mm dia) North - South 168 18.00 3024.000 0.61 1844.640

Cut piece(10 mm dia) East - West 100 1.30 130.000 0.61 79.300

300 1.93 579.000 0.61 353.190

Cut piece(10 mm dia) North - South 350 1.40 490.000 0.61 298.900

350 1.90 665.000 0.61 405.650

175 4.90 857.500 0.61 523.070

Checked By :-
Estimaded By :- Approved By :-
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

8mm distribution bar (East - West) 58 26.70 1548.600 0.39 603.950

8mm distribution bar (North - South) 280 3.10 868.000 0.39 338.520

5 18.00 90.000 0.39 35.100

lapping (8mm dia) East - West 174 0.48 83.520 0.39 32.570

lapping (10mm dia) East - West 348 0.48 167.040 0.61 101.890

lapping (10mm dia) North - South 168 0.60 100.800 0.61 61.480

lapping (8mm dia) North - South 5 0.60 3.000 0.39 1.170

chair (10mm dia) 595 0.30 178.500 0.61 108.880

Overlap of beam bar

Primary beam overlap 20mm dia (East - West) 6 1.25 7.500 2.46 18.450

48 1.25 60.000 2.46 147.600

Primary beam overlap 16mm dia (East - West) 3 0.95 2.850 1.58 4.500

Secondary beam overlap 20mm dia 16 1.25 20.000 2.46 49.200

Secondary beam overlap 16mm dia 4 0.95 3.800 1.58 6.000

Primary beam overlap 20mm dia (North - South) 40 1.25 50.000 2.46 123.000

Secondary beam 20mm dia 24 1.25 30.000 2.46 73.800

Pillar Laping

Pillar 1 (32mm dia) 1 3.70 3.700 6.31 23.340

1 4.10 4.100 6.31 25.870

Pillar 1 (25mm dia) 2 2.60 5.200 3.85 20.020

1 3.60 3.600 3.85 13.860

1 2.70 2.700 3.85 10.390

1 4.10 4.100 3.85 15.780

Pillar 2 (32mm dia) 1 4.10 4.100 6.31 25.870

1 3.70 3.700 6.31 23.340

Pillar 2 (25mm dia) 5 2.50 12.500 3.85 48.120

2 3.30 6.600 3.85 25.410

Pillar 3 (25mm dia) 1 3.80 3.800 3.85 14.630

2 3.00 6.000 3.85 23.100

5 2.50 12.500 3.85 48.120

Pillar 3 (20mm dia) 4 3.00 12.000 2.46 29.520

Pillar 4 (25mm dia) 3 3.00 9.000 3.85 34.650

1 2.80 2.800 3.85 10.780

Pillar 4 (20mm dia) 8 3.10 24.800 2.46 61.000

Pillar 5 (25mm dia) 2 2.70 5.400 3.85 20.790

2 3.50 7.000 3.85 26.950

Pillar 5 (20mm dia) 6 3.30 19.800 2.46 48.700

Pillar 6 (25mm dia) 1 2.80 2.800 3.85 10.780

1 3.30 3.300 3.85 12.700

Checked By :-
Estimaded By :- Approved By :-
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

2 3.00 6.000 3.85 23.100

Pillar 6 (20mm dia) 4 2.90 11.600 2.46 28.530

Pillar 7 (25mm dia) 8 2.80 22.400 3.85 86.240

Pillar 8 (25mm dia) 4 2.70 10.800 3.85 41.580

Pillar 8 (20mm dia) 8 2.90 23.200 2.46 57.070

Pillar 9 (20mm dia) 1 3.00 3.000 2.46 7.380

Pillar 10 (25mm dia) 7 3.00 21.000 3.85 80.850

1 6.00 6.000 3.85 23.100

Pillar 10 (20mm dia) 4 3.00 12.000 2.46 29.520

Pillar 12 (25mm dia) 8 3.00 24.000 3.85 92.400

Pillar 12 (20mm dia) 4 3.10 12.400 2.46 30.500

Pillar 13 (25mm dia) 4 2.50 10.000 3.85 38.500

4 2.80 11.200 3.85 43.120

Pillar 13 (20mm dia) 4 2.50 10.000 2.46 24.600

Pillar 14 (25mm dia) 8 2.90 23.200 3.85 89.320

Pillar 14 (20mm dia) 3 3.30 9.900 2.46 24.350

1 3.60 3.600 2.46 8.850

Pillar 15 (25mm dia) 4 3.00 12.000 3.85 46.200

2 3.50 7.000 3.85 26.950

2 2.50 5.000 3.85 19.250

Pillar 16 (25mm dia) 4 3.00 12.000 3.85 46.200

Pillar 16 (20mm dia) 2 2.10 4.200 2.46 10.330

Pillar 17 (25mm dia) 4 3.00 12.000 3.85 46.200

Pillar 17 (20mm dia) 7 3.00 21.000 2.46 51.660

1 2.50 2.500 2.46 6.150

Pillar 18 (25mm dia) 4 3.00 12.000 3.85 46.200

Pillar 18 (20mm dia) 6 3.10 18.600 2.46 45.750

1 2.50 2.500 2.46 6.150

Pillar 19 (25mm dia) 4 2.80 11.200 3.85 43.120

6 3.00 18.000 3.85 69.300

Pillar 20 (25mm dia) 8 2.90 23.200 3.85 89.320

Stirrups(8mm dia) 40 2.25 90.000 0.39 35.100


over payment on 4 th bill on rod weight as per below
shown
Lapping on Block1

pillars no. 13 ,8-20 mm dia. Bar -1 20.80 -20.80 1.39 -28.920

pillars no. 14 ,4-20 mm dia. Bar -1 10.00 -10.00 1.39 -13.900

pillars no. 15 ,4-20 mm dia. Bar -1 11.20 -11.20 1.39 -15.570

pillars no. 16 ,8-20 mm dia. Bar -1 22.40 -22.40 1.39 -31.140

Lapping on Block1

Checked By :-
Estimaded By :- Approved By :-
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

pillars no 13 ,4 -20mm dia. Bar -1 12.90 -12.90 1.39 -17.940

Total 223224.990 kg

Checked By :-
Estimaded By :- Approved By :-
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

11 8.4 Form works Same as Previous running Bill 5850.940

Block - 4

slab area 1 26.700 26.700 18.000 480.600

slab sides (N&S) 2 26.700 53.400 0.125 6.670

slab sides (E&W) 2 18.000 36.000 0.125 4.500

Pillar area 80 0.600 48.000 0.725 34.800

Deduction pillar base -20 0.600 -12.000 0.600 -7.200

Deduction pillar Side -62 0.350 -21.700 0.525 -11.400

Primary beam

(P,Q,R,S,T & 10,12,13,14) 44 6.600 290.400 0.525 152.460

( 13,12) 10 2.250 22.500 0.525 11.810

(P,Q) 8 3.810 30.480 0.525 16.000

Secondary Beam

(north - south) 12 6.860 82.320 0.475 39.100

(north - south) (B4) 6 2.430 14.580 0.475 6.920

(East - west) 4 4.060 16.240 0.475 7.710

(East - west) 12 6.550 78.600 0.475 37.330

Total 6630.240 m2

Deduction Error in 5 th Bill


Lapping on Block1
pillars no. 13 ,8-20 mm dia. Bar 1 20.80 20.80 3.85 80.08
pillars no. 14 ,4-20 mm dia. Bar 1 10.00 10.00 3.85 38.50
pillars no. 15 ,4-20 mm dia. Bar 1 11.20 11.20 3.85 43.12
pillars no. 16 ,8-20 mm dia. Bar 1 22.40 22.40 3.85 86.24

Different = 3.85-2.46=1.38 kg per m

Lapping on Block1
pillars no 13 ,4 -20mm dia. Bar 1 12.90 12.90 3.85 49.66

Checked By :-
Estimaded By :- Approved By :-
Department of Urban Development And Building Construction
DIVISION OFFICE, Surkhet
F/Y-064 - 065
Name of work :- 50 Bed Hospital Construction Work
Place :- Birendranagar - 3 , Kalagaon , Surkhet

4th. RUNNING BILL


S.N. Item No. Items Unit Quantity Unit Rate Amount

A CIVIL WORKS

1 1.2 Earth work in Excavation in site Development m3 3799.225 100.00 379922.50

2 2 Earth work excavation in BM Soil on Foundati m3 2533.707 200.00 506741.40

3 4 150mm thick stone soling with sand m3 203.502 2500.00 508755.00

4 5 75mm thick lean concrete (1:3:6) in foundation m3 104.041 4500.00 468184.50

5 7 Brick Masonary work ( 1:6 ) m3 508.430 4576.61 2326885.82

6 8 R.C.C. Works

7 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 1049.636 6529.70 6853808.18

8 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 375.832 8547.38 3212378.92

9 8.3 Reinforcements works kg 203510.910 60.51 12314445.16

10 8.4 Form work m2 5850.940 313.00 1831344.22

TOTAL 3nd Bill AMOUNT Rs. 28402465.70

Estimated By:- Checked By:- Approved By:-


zx/L ljsf; tyf ejg lgdf{0f ljefu, l8lehg sfof{no, ;'v]{t d=n]=k=kmf=g+= !^*

lansf] s|d ;+VofM– rf}yf] /lgË lan


7]Ssf ;DalGw aLn sfof{De cfb]z ldltM– )^$.)^.@&
of]hgfsf] gfdM– %) z}of c:ktfn ejg lgdf{0f sfo{ , ;'v]{t ;Dem\of}tf ldltM– @)^$.)^.!*
7]s]bf/sf] gfd M– /lagf , cflzif k|lti7f , g]kfn k|utL h]=eL= z}a' , sf7df08f}+ . sfd ;DkGg ug'{ kg]{ ldltM– @)^^.)@.!&-;Dem\of}tfsf] @) dlxgf _
7]Ssf k6[fsf] ;+VofM– !) - @)^#÷)^$ _ sfd ;DkGg ePsf] ldltM– rfn'''''''
cl3Nnf] e"QmfgL lansf] s|d;+VofM– t]>f] /lgË lan e"QmfgL efpr/ g+=–
cl3Nnf] e"QmfgL ef=g+=M– e"QmfgL ldltM–
gfkL lstfa g+= sf] k[i7 g+=M– b]lv ;Dd
cfO{ cBfjlw sfd ePsf] cl3Nnf] landf r9]sf] xfn ePsf] sfd
s||=;+ 6d sfdsf] laj/0f PsfO{ s}lkmot
g+== kl/df0f b/ hDdf d"No kl/df0f hDdf d"No kl/df0f hDdf d"No
A CIVIL WORKS
1 1.2 Earth work in Excavation in site Development m3 3799.225 100.00 379922.50 3799.225 379922.50 0.000 0.00
2 2 Earth work excavation in BM Soil on Foundation m3 2533.707 200.00 506741.40 2533.707 506741.40 0.000 0.00
3 4 150mm thick stone soling with sand m3 203.502 2500.00 508755.00 203.502 508755.00 0.000 0.00
4 5 75mm thick lean concrete (1:3:6) in foundation m3 104.041 4500.00 468184.50 104.041 468184.50 0.000 0.00
5 7 Brick Masonary work ( 1:6 ) m3 508.430 4576.61 2326885.82 508.430 2326885.82 0.000 0.00
6 8 R.C.C. Works
7 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 1049.636 6529.70 6853808.18 933.006 6092249.27 116.630 761558.91
8 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 375.832 8547.38 3212378.92 235.602 2013779.82 140.230 1198599.10
9 8.3 Reinforcements works kg ### 60.51 12314445.16 144501.8 8743805.73 ### 3570639.43
10 8.4 Form work m2 5850.940 313.00 1831344.22 3942.40 1233971.20 1908.540 597373.02

TOTAL AMOUNT (without VAT) Rs. 28402465.70 Rs 22274295.24 Rs. 6128170.46

pko'{Qm adf]lhd 7Ls 5 egL k|dfl0ft ug]{sf] ;xLM–


===================================== ==============
cf]e/l;o/ O{lGhgLo/ 7]s]bf/sf] ;xL
of] lansf] hDdf -Eof6 afx]]s_ 28402465.70
cl3Nnf] e"QmfgL lanaf6 e"QmfgL ePsf] 22274295.24
afFsL lbg' kg]{ -Eof6 afx]s_ 6128170.46
s6[L ug'{ kg]{ ?=M–
s_ k]ZsL–
v_ dfn;dfgsf] df]nM–
u_ d]zLg cf}hf/ axfnM–
3_ cfos/ !=%Ü M–
ª_ d"No clea[l4 s/ !# Ü M–
r_ w/f}6L %Ü M–
5_ cGo M–
v"b lbg' kg]{ -Eof6 ;d]t_ ?=M–
k]z ug]{sf] ;xLM– hfFr ug]{sf] ;xLM– :jLs[t ug]{sf] ;xLM–
hDdf ?= cIf]?kLM– sf] r]s g+= af6 k|fKt ePsf] egL ;xL ug]{ 7]s]bf/sf] ;xLM–
Department of Urban Development And Building Construction
DIVISION OFFICE
Surkhet
Name of work :- 50 Bed Hospital Construction Work F/Y-064 - 065
Place :- Birendranagar - 3 , Kalagaon , Surkhet

DETAILS OF MEASUREMENT ( 4 th. Bill )


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

(A) CIVIL WORKS

1 1 Site Development work

2 1.2 Earth work in Excavation in site Development Same as previous bill rnning Bill 3799.225

3 2 Earth work excavation in BM Soil on Foundation Same as Previous rnning Bill 2533.707 m3

4 4 150mm thick stone soling with sand Same as Previous rnning Bill 203.502 m3

5 5 Lean Concrete Bae (1:3:6) Same previous rnning Bill 104.041 m3

6 7 Brick Masonary work ( 1:6 ) Same as Previous rnning Bill 508.430

7 8 R.C.C. Work

8 8.1 P.C.C. 1:1.5:3 (M 20 ) Same as Previous rnning Bill 933.006

slab Block 1 1 36.80 36.80 17.80 0.125 81.88

SunShed Both Way 8 4.90 39.20 1.35 0.10 5.29

Arch Volume =0.92m3 2 0.92 1.84 0.92

Deduction

columns -24 0.60 -14.40 0.60 0.125 -1.08

Beams

primary beam for long way -20 6.60 -132.00 0.35 0.125 -5.78

Secondary beam for long way 10 6.90 69.00 -0.30 0.125 -2.59

primary beam for short way 12 6.60 79.20 -0.35 0.125 -3.47

Secondary beam for short way 10 6.90 69.00 -0.30 0.125 -2.59

Primary Beam For passage 6 2.00 12.00 -0.35 0.125 -0.53

Secondary Beam For passage 5 2.30 11.50 -0.30 0.125 -0.44


Adding in cross point of Secondary beam in
10 0.30 3.00 0.30 0.125 0.11
Block 1
Slab Block 3 1 22.40 22.40 18.03 0.125 50.47

Sun Shed Both Way 6 4.90 29.40 1.35 0.10 3.96

BLOCK 3

Deduction

primary beam for long way 12 6.60 79.20 -0.35 0.125 -3.47

Secondary beam for long way 6 6.90 41.40 -0.30 0.125 -1.56

primary beam for short way 8 6.60 52.80 -0.35 0.125 -2.31

Secondary beam for short way 6 6.90 41.40 -0.30 0.125 -1.56

Primary Beam For passage 4 2.23 8.90 -0.35 0.125 -0.39

Secondary Beam For passage 3 2.53 7.57 -0.30 0.125 -0.29


Adding in cross point of Secondary beam in
6 0.30 1.80 0.30 0.125 0.06
block 3
Total 1049.636 m3

Checked By :-
Estimaded By :- Approved By :-
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

9 8.2 P. C.C 1:1:2 ( M 25 ) Same as Previous rnning Bill 235.602

Pillers 24 0.60 14.40 0.60 1.15 9.93

Primary Beam For Long Way 20 6.60 132.00 0.35 0.65 30.03

Secondary Beam For Long Way 10 6.90 69.00 0.30 0.60 12.42

Primary Beam For Short Way 12 6.60 79.20 0.35 0.65 18.01

Primary Beam For passage 6 2.00 12.00 0.35 0.65 2.73

Secondary Beam For Short Way 10 5.90 59.00 0.30 0.60 10.62

Secondary Beam For passage 5 2.30 11.50 0.30 0.60 2.07

Deduction in cross point of Secondary beam 10 0.30 3.00 -0.30 0.60 -0.54

Arch Beam 2 1.55 3.10 0.30 0.40 0.37

Concrete Work M 25 (In Block 3)

Pillers 16 0.60 9.60 0.60 1.15 6.62

Primary Beam For Long Way 12 6.60 79.20 0.35 0.65 18.01

Secondary Beam For Long Way 6 6.90 41.40 0.30 0.60 7.45

Primary Beam For Short Way 8 6.60 52.80 0.35 0.65 12.01

Primary Beam For passage 4 2.23 8.90 0.35 0.65 2.02

Secondary Beam For passage 3 2.53 7.57 0.30 0.60 1.36

Secondary Beam For Short Way 6 6.90 41.40 0.30 0.60 7.45

Deduction in cross point of Secondary beam 6 0.30 1.80 0.30 -0.60 -0.33

Total 375.832 m3

10 8.3 Reinforcement works Same as Previous rnning Bill 144501.830

Block 1

Primary Beams
Grid 1,7,4,3( Top and Bottom Bar fo 20 mm dia,
32 38.30 1225.60 2.46 3014.97
LD=0.85m Both way
Cut Piece Grid 1 & 7,2-20mm Dia Edge section
8 2.5 20.00 2.46 49.20
Both Way
Cut Piece Grid 4,3,4 No-20mm Dia Edge section
16 2.80 44.80 2.46 110.20
Both Way
Cut Piece Grid 4,3,2 No-20mm Dia Mid section 4 35.20 140.80 2.46 346.36

Cut Piece Grid 1 & 7,2-20mm Dia Mid section 4 36.20 144.80 2.46 356.20

Grid 1,7,4,3( 12 mm dia, side Bar) 8 39.60 316.80 0.89 281.95

Grid 1,7,4,3( Lapping Rod of 20mm Dia) 32 5.40 172.80 2.46 425.08

Stirrups 8 mm Dia (Large) 1060 2.25 2385.00 0.39 930.15

Stirrups 8 mm Dia (Small) 1060 1.7 1802.00 0.39 702.78

Secondary Beam For Long Way


2 No. Secondary Beam 20mm dia Top & Bottom
16 38.30 612.80 2.46 1507.48
Bar LD=0.85 m both Way
2 No of 12mm Side Bar 4 39.60 158.40 0.89 140.97

Lapping rod 20 mm Dia 16 6.75 108.00 2.46 265.68

Stirrups 8 mm Dia (Large) 530 2.25 1192.50 0.39 465.07

Stirrups 8 mm Dia (Small) 530 1.70 901.00 0.39 351.39

Primary Beams Short Way

Checked By :-
Estimaded By :- Approved By :-
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
Grid A,B C,E,G & I (Top & Bottom 20mm Dia
48 19.40 931.20 2.46 2290.75
Bar LD=0.9m Both Way)
Cut Piece Grid A & I, 2 No.20 mm Dia Bar
8 2.88 23.04 2.46 56.67
Edge Section Both Way
Cut Piece Grid A & I, 2 No.16 mm Dia Bar Mid
4 13.80 55.20 1.58 87.21
Section
Cut Piece Grid B,C,E,G 4 No.20 mm Dia Bar
32 2.65 84.80 2.46 208.60
Edge Section Both Way
Cut Piece Grid B,C,E,G 4 No.20 mm Dia Bar
16 16.20 259.20 2.46 637.63
Mid Section
Grid B,C,E,G & A,I, 2 No.12 mm Dia side Bar 12 18.35 220.20 0.89 195.97

Stirrups 8 mm Dia (Large) 780 2.25 1755.00 0.39 684.45

Stirrups 8 mm Dia (Small) 780 1.70 1326.00 0.39 517.14

Secondary Beam For Short Way


5 No. Of secondary Beam 20 mm dia Top &
40 19.30 772.00 2.46 1899.12
bottom Bar LD=0.85m Both Way
Lapping rod 20 mm Dia 40 1.35 54.00 2.46 132.84

2 No of 12mm Side Bar 10 18.35 183.50 0.89 163.31

Stirrups 8 mm Dia (Large) 650 2.25 1462.50 0.39 570.37

Stirrups 8 mm Dia (Small) 650 1.70 1105.00 0.39 430.95

Slab Reinforcement deatails

Distribution 10 mm Dia Bar 144 36.80 5299.20 0.62 3269.60

Lapping rod 10 mm Dia (Distribution Bar) 144 4.08 587.52 0.62 364.26

Main Bar 10mm Dia 292 17.80 5197.60 0.62 3222.51

Lapping Rod 10 mm Dia (Main Bar) 292 1.95 569.40 0.62 353.02

Sunshead Two Way (Distribution Bar) 32 4.70 150.40 0.62 93.24

Sunshead Two Way (Main Bar) 296 1.30 384.80 0.62 238.57

Arch Slab 2 No (Main Bar) 100 2.65 265.00 0.62 164.30

Arch Slab 2 No (Distribution Bar) 24 3.00 72.00 0.62 44.64

Bender Bar For Long Way 8mm Dia Bar 60 39.30 2358.00 0.39 919.62

Top Bar Cut Piece For Long Way 10 mm Dia Bar 1728 1.40 2419.20 0.62 1499.90
Top Bar Cut Piece For Long Way 10 mm Dia
288 4.80 1382.40 0.62 857.08
Bar (For Passage)
Bender Bar For Short Way 8mm Dia Bar 144 19.75 2844.00 0.39 1109.16

Top Bar Cut Piece For Short Way 10 mm Dia Bar 1440 1.40 2016.00 0.62 1249.92

Chair Rod 8mm dia Bar 600 0.50 300.00 0.39 117.00

Stirrups for Arch Beam 24 1.45 34.80 0.39 13.57

Arch Beam 16 mm Dia 12 4.20 50.40 1.58 79.63

Pillars stirrups in block 1 216 2.65 572.40 0.39 223.23

Pillars stirrups in block 3 144 2.65 381.60 0.39 148.82

Block 3

Primary Beams
Grid 9,10,11,13( Top and Bottom Bar for 20 mm
32 23.90 764.80 2.46 1881.40
dia, LD=0.85m Both way)
Cut Piece Grid 9,10,11,13(20mm Dia Continuous 16 25.5 408.00 2.46 1003.68

Grid 9,10,11,13( 12 mm dia, side Bar) 8 25.20 201.60 0.89 179.42

Grid 9,10,11,13( Lapping Rod of 20mm Dia) 32 8.00 256.00 2.46 629.76

Checked By :-
Estimaded By :- Approved By :-
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

Stirrups 8 mm Dia (Large) 700 2.25 1575.00 0.39 614.25

Stirrups 8 mm Dia (Small) 700 1.7 1190.00 0.39 464.10

Secondary Beam For Long Way


2 No. Secondary Beam 20mm dia Top & Bottom
16 23.90 382.40 2.46 940.70
Bar LD=0.85 m both Way
2 No of 12mm Side Bar 4 25.95 103.80 0.89 92.38

Lapping rod 20 mm Dia 16 6.00 96.00 2.46 236.16

Stirrups 8 mm Dia (Large) 350 2.25 787.50 0.39 307.12

Stirrups 8 mm Dia (Small) 350 1.70 595.00 0.39 232.05

Primary Beams Short Way


Grid D,F,H,K(Top & Bottom 20mm Dia Bar
32 19.62 627.84 2.46 1544.48
LD=0.9m Both Way)
Cut Piece Grid D,H,F,K 4 No.20 mm Dia Bar
16 4.00 64.00 2.46 157.44
continuous
Grid D,H,F,K 2 No.12 mm Dia side Bar 8 19.85 158.80 0.89 141.33

Lapping rod 20 mm Dia 32 7.50 240.00 2.46 590.40

Stirrups 8 mm Dia (Large) 568 2.25 1278.00 0.39 498.42

Stirrups 8 mm Dia (Small) 568 1.70 965.60 0.39 376.58

Secondary Beam For Short Way


3 No. Of secondary Beam 20 mm dia Top &
24 19.30 463.20 2.46 1139.47
bottom Bar LD=0.85m Both Way
Lapping rod 20 mm Dia 24 4.35 104.40 2.46 256.82

2 No of 12mm Side Bar 6 19.10 114.60 0.89 101.99

Stirrups 8 mm Dia (Large) 426 2.25 958.50 0.39 373.81

Stirrups 8 mm Dia (Small) 426 1.70 724.20 0.39 282.43

Slab Reinforcement deatails

Distribution 10 mm Dia Bar 144 24.30 3499.20 0.62 2169.50

Main Bar 10mm Dia 178 19.00 3382.00 0.62 2096.84

Sunshead Two Way (Distribution Bar) 6 4.70 28.20 0.62 17.48

Sunshead Two Way (Main Bar) 222 1.30 288.60 0.62 178.93

Bender Bar For Long Way 10mm Dia Bar 86 26.60 2287.60 0.62 1418.31

Cut Piece For Long Way 10 mm Dia Bar 1068 1.40 1495.20 0.62 927.02
Cut Piece For Long Way 10 mm Dia Bar (For
178 5.55 987.90 0.62 612.49
Passage)
Bender Bar For Short Way 10mm Dia Bar 96 18.65 1790.40 0.62 1110.04

Cut Piece For Short Way 10 mm Dia Bar 684 1.40 957.60 0.62 593.71

Chair Rod 8mm dia Bar 320 0.35 112.00 0.39 43.68

20 mm Dia Pin Rod 96 0.30 28.80 2.46 70.84

Lapping of Pillers in block -1

4-25mmm dia. Bar 4 4.50 18.00 3.85 69.30

2-25mmm dia. Bar 2 4.00 8.00 3.85 30.80

1-25mmm dia. Bar 1 4.00 4.00 3.85 15.40

1-25mmm dia. Bar 1 3.80 3.80 3.85 14.63

2-20mmm dia. Bar 2 4.50 9.00 2.46 22.14

2-20mmm dia. Bar 2 4.00 8.00 2.46 19.68

Checked By :-
Estimaded By :- Approved By :-
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

pillars no. 2

12-25mmm dia. Bar 1 36.00 36.00 3.85 138.60

pillars no. 3, 12-25mm dia. Bar 1 38.00 38.00 3.85 146.30

pillars no. 4 ,8-25mm dia. Bar 1 25.60 25.60 3.85 98.56

pillars no. 4 ,4-20mm dia. Bar 1 10.80 10.80 2.46 26.56

pillars no. 5 ,4-25 mm dia. Bar 1 12.80 12.80 3.85 49.28

pillars no. 5 ,8-20 mm dia. Bar 1 20.40 20.40 2.46 50.18

pillars no. 6 ,8-25mm dia. Bar 1 23.90 23.90 3.85 92.01

pillars no. 6 ,4-20 mm dia. Bar 1 10.80 10.80 3.85 41.58

pillars no. 7 ,8-25mm dia. Bar 1 22.65 22.65 3.85 87.20

pillars no. 7 ,4-20 mm dia. Bar 1 10.00 10.00 2.46 24.60

pillars no. 8,4-25mm dia. Bar 1 10.60 10.60 3.85 40.81

pillars no. 8 ,8-20 mm dia. Bar 1 21.20 21.20 3.85 81.62

pillars no. 9 ,4-25mm dia. Bar 1 12.40 12.40 3.85 47.74

pillars no. 9 ,8-20 mm dia. Bar 1 27.00 27.00 3.85 103.95

pillars no. 10 ,8-25mm dia. Bar 1 23.80 23.80 3.85 91.63

pillars no. 10 ,4-20 mm dia. Bar 1 10.60 10.60 2.46 26.07

pillars no. 11 ,8-25mm dia. Bar 1 24.60 24.60 3.85 94.71

pillars no. 11 ,4-20 mm dia. Bar 1 9.60 9.60 2.46 23.61

pillars no. 12 ,4-25 mm dia. Bar 1 13.00 13.00 3.85 50.05

pillars no. 12 ,8-20 mm dia. Bar 1 23.40 23.40 3.85 90.09

pillars no. 13 ,4-25 mm dia. Bar 1 14.60 14.60 3.85 56.21

pillars no. 13 ,8-20 mm dia. Bar 1 20.80 20.80 3.85 80.08

pillars no. 14 ,8-25mm dia. Bar 1 26.40 26.40 3.85 101.64

pillars no. 14 ,4-20 mm dia. Bar 1 10.00 10.00 3.85 38.50

pillars no. 15 ,8-25mm dia. Bar 1 25.40 25.40 3.85 97.79

pillars no. 15 ,4-20 mm dia. Bar 1 11.20 11.20 3.85 43.12

pillars no. 16 ,4-25 mm dia. Bar 1 13.20 13.20 3.85 50.82

pillars no. 16 ,8-20 mm dia. Bar 1 22.40 22.40 3.85 86.24

pillars no. 17,4-25 mm dia. Bar 1 12.80 12.80 3.85 49.28

pillars no. 17 8-20 mm dia. Bar 1 22.40 22.40 2.46 55.10

pillars no. 18 ,8-25mm dia. Bar 1 28.60 28.60 3.85 110.11

pillars no. 18 ,4-20 mm dia. Bar 1 12.80 12.80 2.46 31.48

pillars no. 19 ,8-25mm dia. Bar 1 26.00 26.00 3.85 100.10

pillars no. 19 ,4-20 mm dia. Bar 1 13.70 13.70 2.46 33.70

pillars no. 20 ,4-25mm dia. Bar 1 12.80 12.80 3.85 49.28

pillars no. 20 ,8-20 mm dia. Bar 1 21.00 21.00 2.46 51.66

pillars no. 21 ,8-25mm dia. Bar 1 25.40 25.40 3.85 97.79

pillars no. 21 ,4-20 mm dia. Bar 1 10.40 10.40 2.46 25.58

pillars no. 22 ,4-25mm dia. Bar 1 13.20 13.20 3.85 50.82

Checked By :-
Estimaded By :- Approved By :-
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

pillars no. 22 ,8-20 mm dia. Bar 1 12.50 12.50 2.46 30.75

Lapping of Pillers in block -3 0.00

pillars no. 1 ,8-25mm dia. Bar 1 28.90 28.90 3.85 111.26

pillars no. 1 ,4-20 mm dia. Bar 1 16.00 16.00 2.46 39.36

pillars no. 2 ,8-25mm dia. Bar 1 31.00 31.00 3.85 119.35

pillars no. 3 ,8-25mm dia. Bar 1 29.60 29.60 3.85 113.96

pillars no. 4 ,4-20 mm dia. Bar 1 16.60 16.60 2.46 40.83

pillars no. 4 ,4-25mm dia. Bar 1 13.20 13.20 3.85 50.82

pillars no. 5 ,8 -20 mm dia. Bar 1 30.10 30.10 2.46 74.04

pillars no 5 ,4-25mm dia. Bar 1 17.00 17.00 3.85 65.45

pillars no. 6, 12-25mm dia. Bar 1 32.05 32.05 3.85 123.39

pillars no. 7 , 12-25mm dia. Bar 1 41.30 41.30 3.85 159.00

pillars no. 8 ,4 -20 mm dia. Bar 1 14.00 14.00 2.46 34.44

pillars no 8 ,8 -25mm dia. Bar 1 25.50 25.50 3.85 98.17

pillars no 9 ,8 -25mm dia. Bar 1 30.30 30.30 3.85 116.65

pillars no. 9 ,4 -20 mm dia. Bar 1 15.20 15.20 2.46 37.39

pillars no. 10 , 12-25mm dia. Bar 1 39.20 39.20 3.85 150.92

pillars no. 11 , 12-25mm dia. Bar 1 23.20 23.20 3.85 89.32

pillars no 12 ,8 -25mm dia. Bar 1 22.95 22.95 3.85 88.35

pillars no 12 ,4 -20mm dia. Bar 1 13.60 13.60 2.46 33.45

pillars no 13 ,4 -20mm dia. Bar 1 12.90 12.90 3.85 49.66

pillars no. 14 , 12-25mm dia. Bar 1 33.80 33.80 3.85 130.13

pillars no. 15 , 12-25mm dia. Bar 1 23.80 23.80 3.85 91.63

pillars no 16 ,4 -20mm dia. Bar 1 16.00 16.00 2.46 39.36

pillars no 16 ,4 -25mm dia. Bar 1 14.46 14.46 3.85 55.67


Missed Item of Reinforcement (Foundation
Strap Beam)
for Block 3

Grid 9,10,11,13 24 1.10 26.40 1.58 41.71

Grid D,H,F,K 24 0.95 22.80 1.58 36.02

For Block 1

Grid 7 12 1.00 12.00 1.58 18.96

Grid 3 & 3 12 1.00 12.00 1.58 18.96

Grid 1 12 0.90 10.80 1.58 17.06

For Block 2

Grid 2,5,6 18 1.00 18.00 1.58 28.44

Grid 8 12 0.93 11.16 1.58 17.63

For Block 4

Grid 10,11,12,13,14 30 1.00 30.00 1.58 47.40

For Block 5

Grid L,M&N 18 1.00 18.00 1.58 28.44

Checked By :-
Estimaded By :- Approved By :-
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

Piller Lapping 20 mm Dia for Grid C1,C2,C4 165 1.25 206.25 2.46 507.37

Grid C3,C2,C1 (25mm Dia) 250 1.50 375.00 3.85 1443.75

Total 203510.910 kg

11 8.4 Form works Same as Previous rnning Bill 3942.400

Block - 1

Pillers 96 0.60 57.60 1.00 57.60

Deduction in pillars sides 76 -0.35 -26.60 0.525 -13.97

Primary Beam For Long Way (base) 20 6.60 132.00 0.35 46.20

Primary Beam For Long Way (Depth both Sides) 40 6.60 264.00 0.525 138.60

Secondary Beam For Long Way (base) 10 6.90 69.00 0.30 20.70

secondary Beam For Long Way (Depth both Sides) 20 6.90 138.00 0.475 65.55

Primary Beam For Short Way (base) 12 6.60 79.20 0.35 27.72

Primary Beam For Short Way (Depth both Sides) 24 6.60 158.40 0.525 83.16

Primary Beam For passage (base) 6 2.00 12.00 0.35 4.20

Primary Beam For passage (depth both sides) 12 2.00 24.00 0.525 12.60

Secondary Beam For Short Way (base) 10 5.90 59.00 0.30 17.70

Secondary Beam For Short Way (depth both side 20 5.90 118.00 0.475 56.05

Secondary Beam For passage (base) 5 2.30 11.50 0.30 3.45

Secondary Beam For passage (depth both sides) 10 2.30 23.00 0.475 10.92

Arch Area =7.06m2 2 7.06 14.12 14.12


Arch Beam Elongated through Secondary Beam
4 1.50 6.00 0.275 1.65
2 No.(depth both sides)
Slab sides (for long way) 2 36.80 73.60 0.15 11.04

Slab sides (for long way) 2 18.03 36.06 0.15 5.40

Slab 1 36.80 36.80 18.02 663.13

For Slab (174.5m2 Deduction of Beam Base) -1 174.50 -174.50 -174.50

Sun Shed Both Way 8 2.00 16.00 4.800 76.80

In Block 3

Pillers 64 0.60 38.40 1.00 38.40

Deduction in pillars sides 48 -0.35 -16.80 0.650 -10.92

primary beam for long way (base) 12 6.60 79.20 0.35 27.72

primary beam for long way (depth both sides) 24 6.60 158.40 0.650 102.96

Secondary beam for long way (base) 6 6.90 41.40 0.30 12.42

Secondary beam for long way (depth both sides 12 6.90 82.80 0.600 49.68

primary beam for short way (base) 8 6.60 52.80 0.35 18.48

primary beam for short way (depth both sides) 16 6.60 105.60 0.650 68.64

Secondary beam for short way (base) 6 6.90 41.40 0.30 12.42

Secondary beam for short way (depth both sid 12 6.90 82.80 0.600 49.68

Primary Beam For passage (base) 4 2.23 8.90 0.35 3.11

Primary Beam For passage (depth both sides) 8 2.23 17.80 0.650 11.57

Secondary Beam For passage (base) 3 2.53 7.57 0.30 2.27

Checked By :-
Estimaded By :- Approved By :-
S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

Secondary Beam For passage (depth both sides) 6 2.53 15.15 0.600 9.09

Slab 1 22.40 22.40 18.03 403.76

For Slab (86.56m2 Deduction of Beam Base) -1 86.56 -86.56 -86.56

Sun Shed Both Way 6 2.00 12.00 4.80 57.60

Slab sides (for long way) 2 22.40 44.80 0.125 5.60

Slab sides (for long way) 2 18.03 36.06 0.125 4.50

Total 5850.940 m2

Checked By :-
Estimaded By :- Approved By :-
zx/L ljsf; tyf ejg lgdf{0f ljefu, l8lehg sfof{no, ;'v]{t d=n]=k=kmf=g+= !^*

lansf] s|d ;+VofM– t]>f] /lgË lan


7]Ssf ;DalGw aLn sfof{De cfb]z ldltM– )^$.)^.@&
of]hgfsf] gfdM– %) z}of c:ktfn ejg lgdf{0f sfo{ , ;'v]{t ;Dem\of}tf ldltM– @)^$.)^.!*
7]s]bf/sf] gfd M– /lagf , cflzif k|lti7f , g]kfn k|utL h]=eL= z}a' , sf7df08f}+ . sfd ;DkGg ug'{ kg]{ ldltM– @)^^.)@.!&-;Dem\of}tfsf] @) dlxgf _
7]Ssf k6[fsf] ;+VofM– !) - @)^#÷)^$ _ sfd ;DkGg ePsf] ldltM– rfn'''''''
cl3Nnf] e"QmfgL lansf] s|d;+VofM– bf]>f] /lgË lan e"QmfgL efpr/ g+=–
cl3Nnf] e"QmfgL ef=g+=M– e"QmfgL ldltM–
gfkL lstfa g+= sf] k[i7 g+=M– b]lv ;Dd
cfO{ cBfjlw sfd ePsf] cl3Nnf] landf r9]sf] xfn ePsf] sfd
s||=;+ 6d sfdsf] laj/0f PsfO{ s}lkmot
kl/df0f b/ hDdf d"No kl/df0f hDdf d"No kl/df0f hDdf d"No
g+==
A CIVIL WORKS
1 1.2 Earth work in Excavation in site Development m3 3799.225 100.00 379922.50 3799.225 379922.50 0.000 0.00
2 2 Earth work excavation in BM Soil on Foundation m3 2533.707 200.00 506741.40 2464.361 492872.20 69.346 13869.20
3 4 150mm thick stone soling with sand m3 203.502 2500.00 508755.00 197.248 493120.00 6.254 15635.00
4 5 75mm thick lean concrete (1:3:6) in foundation m3 104.041 4500.00 468184.50 100.915 454117.50 3.126 14067.00
5 7 Brick Masonary work ( 1:6 ) m3 508.430 4576.61 2326885.82 412.716 1888840.17 95.714 438045.65
6 8 R.C.C. Works
7 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 933.006 6529.70 6092249.27 886.176 5786463.42 46.830 305785.85
8 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 235.602 8547.38 2013779.82 88.938 760186.88 146.664 1253592.94
9 8.3 Reinforcements works kg ### 60.51 8743805.73 134830.9 8158620.17 ### 585185.56
10 8.4 Form work m2 3942.400 313.00 1233971.20 2683.91 840063.83 ### 393907.37

TOTAL AMOUNT (without VAT) Rs. 22274295.24 Rs 19254206.67 Rs. 3020088.57

pko'{Qm adf]lhd 7Ls 5 egL k|dfl0ft ug]{sf] ;xLM–


===================================== ==============
cf]e/l;o/ O{lGhgLo/ 7]s]bf/sf] ;xL
of] lansf] hDdf -Eof6 afx]]s_ 22274295.24
cl3Nnf] e"QmfgL lanaf6 e"QmfgL ePsf] 19254206.67
afFsL lbg' kg]{ -Eof6 afx]s_ 3020088.57
s6[L ug'{ kg]{ ?=M–
s_ k]ZsL–
v_ dfn;dfgsf] df]nM–
u_ d]zLg cf}hf/ axfnM–
3_ cfos/ !=%Ü M–
ª_ d"No clea[l4 s/ !# Ü M–
r_ w/f}6L %Ü M–
5_ cGo M–
v"b lbg' kg]{ -Eof6 ;d]t_ ?=M–
k]z ug]{sf] ;xLM– hfFr ug]{sf] ;xLM– :jLs[t ug]{sf] ;xLM–
hDdf ?= cIf]?kLM– sf] r]s g+= af6 k|fKt ePsf] egL ;xL ug]{ 7]s]bf/sf] ;xLM–
Department of Urban Development And Building Construction
DIVISION OFFICE, Surkhet
F/Y-064 - 065
Name of work :- 50 Bed Hospital Construction Work
Place :- Birendranagar - 3 , Kalagaon , Surkhet

3rd RUNNING BILL


S.N. Item No. Items Unit Quantity Unit Rate Amount

A CIVIL WORKS

1 1.2 Earth work in Excavation in site Development m3 3799.225 100.00 379922.50

2 2 Earth work excavation in BM Soil on Foundati m3 2533.707 200.00 506741.40

3 4 150mm thick stone soling with sand m3 203.502 2500.00 508755.00

4 5 75mm thick lean concrete (1:3:6) in foundation m3 104.041 4500.00 468184.50

5 7 Brick Masonary work ( 1:6 ) m3 508.430 4576.61 2326885.82

6 8 R.C.C. Works

7 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 933.006 6529.70 6092249.27

8 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 235.602 8547.38 2013779.82

9 8.3 Reinforcements works kg 144501.830 60.51 8743805.73

10 8.4 Form work m2 3942.400 313.00 1233971.20

TOTAL 3nd Bill AMOUNT Rs. 22274295.24

Estimated By:- Checked By:- Approved By:-


Department of Urban Development And Building Construction
DIVISION OFFICE
Surkhet
Name of work :- 50 Bed Hospital Construction Work F/Y-064 - 065
Place :- Birendranagar - 3 , Kalagaon , Surkhet

DETAILS OF MEASUREMENT ( 3nd Bill )


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

(A) CIVIL WORKS

1 1 Site Development work

2 1.2 Earth work in Excavation in site Development Same as 1 st rnning Bill 3799.225

3 2 Earth work excavation in BM Soil on Foundation Same as 1 st rnning Bill 2464.361

Grid A-B ,E-G in arch 2 7.30 14.60 0.90 1.82 23.914

Emergency verandah pillar 2 3.00 6.00 3.00 1.82 32.760

Emergency strap beam 2 5.43 10.85 0.60 1.20 7.812

Pillar connection 1 6.75 6.75 0.60 1.20 4.860

Total 2533.707 m3

4 4 150mm thick stone soling with sand Same as 1 st rnning Bill 197.248

1st Block arc 2 7.30 14.60 0.90 0.15 1.971

Emergency verandah pillar 2 3.00 6.00 3.00 0.15 2.700

Emergency strap beam 2 5.43 10.85 0.60 0.15 0.976

Pillar connection beam 1 6.75 6.75 0.60 0.15 0.607

Total 203.502 m3

5 5 Lean Concrete Bae (1:3:6) Same as 1 st rnning Bill 100.915

1st Block arc 2 7.30 14.60 0.90 0.08 0.985

Emergency verandah pillar 2 3.00 6.00 3.00 0.08 1.350

Emergency strap beam 2 5.43 10.85 0.60 0.08 0.488

Pillar connection beam 1 6.75 6.75 0.60 0.08 0.303

Total 104.041 m3

6 7 Brick Masonary work ( 1:6 ) Same as 1 st and 2nd rnning Bill 412.716

4th Block

Grid P,Q,R,S,T 5 15.43 77.12 0.35 1.00 26.992

Grid 10,11,12,13,14 5 23.61 118.05 0.35 1.00 41.317

2nd Block

Grid I,J 2 6.60 13.20 0.35 0.75 3.465

1st Block

Arc masonary 2 7.30 14.60 0.50 2.10 15.330

Emergency strap beam above maonary 2 5.43 10.85 0.35 0.75 2.848

Pillar connection beam above masonary 1 6.75 6.75 0.35 0.75 1.771

2nd block Grid I,L,N,O 4 1.75 7.00 0.35 0.75 1.837

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

2nd Block Grid 4,7, 2 2.28 4.56 0.35 0.85 1.356

4th Block Grid 14 1 2.28 2.28 0.35 1.00 0.798

Total 508.430 m3

7 8 R.C.C. Work

8 8.1 P.C.C. 1:1.5:3 (M 20 ) Same as 1 st and 2nd rnning Bill 886.176

Emergency verandah pillar trapezodial portion

Lower portion 2 2.50 5.00 2.50 0.20 2.500

Trap. portion 2 0.90 1.80 1.800

Plinth beam Grid P,Q,R,S,T 5 15.43 77.12 0.35 0.45 12.146

Grid 10,11,12,13,14 5 23.61 118.05 0.35 0.45 18.592

1st Block arc 2 7.30 14.60 0.35 0.45 2.299

Emergency strap beam 2 5.43 10.85 0.35 0.45 1.708

Pillar connection strap beam 1 6.75 6.75 0.35 0.45 1.063

Emergency Plinth beam 2 5.43 10.85 0.35 0.45 1.708

Pillar connection plinth beam 1 6.75 6.75 0.35 0.45 1.063

5th Block

Cantiliver projection 1 27.33 27.32 0.20 0.10 0.546

3rd Block

Cantiliver projection 1 33.04 33.03 0.20 0.10 0.660

1st Block

Cantiliver projection 1 30.54 30.54 0.20 0.10 0.610

2nd Block

Cantiliver projection 1 44.09 44.08 0.20 0.10 0.881

4th Block

Cantiliver projection 1 62.74 62.74 0.20 0.10 1.254

Total 933.006 m3

9 8.2 P. C.C 1:1:2 ( M 25 ) Same as 1 st and 2nd rnning Bill 88.938

4th Block (below in plinth beam)

Pillars 20 0.60 12.00 0.60 1.90 13.680

Pillars above plinth beam 126 0.60 75.60 0.60 2.85 129.276

Emergency verandah pillar (Deduction 0.927) 2 0.60 1.20 0.60 5.15 3.708

Total 235.602 m3

10 8.3 Reinforcement works Same as 1 st and 2nd rnning Bill 134830.940

4th Block plinth beam

Grid P,Q,R,S,T

Upper bars 15 18.72 280.80 1.58 443.660

Lower bars 15 19.42 291.30 1.58 460.250

stirrups 875 1.58 1382.50 0.39 539.170

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

Grid 10,11,12,13,14 0.00 0.000

Upper bars 15 27.510 412.65 1.58 651.980

Lower bars 15 28.21 423.15 1.58 668.570

stirrups 1175 1.580 1856.50 0.39 724.030

Grid P,Q,R,S,T overlap

Upper bars 15 1.10 16.50 1.58 26.070

Lower bars 15 0.90 13.50 1.58 21.330

Grid 10,11,12,13,14

Upper bars 20 1.10 22.00 1.58 34.760

Lower bars 20 0.95 19.00 1.58 30.020

Grid I

Upper bars 3 8.36 25.08 1.58 39.620

Lower bars 3 9.65 28.95 1.58 45.740

1st Block rounding plinth beam

Upper bars 6 8.35 50.10 1.58 79.150

Lower bars 6 8.30 49.80 1.58 78.680

stirrups 100 1.58 158.00 0.39 61.620

Emergency entrance pillar

Basement bar 16mmdia. bar@125mmc/c 80 2.60 208.00 1.58 328.640

Pillars 16mmdia. 8 9.00 72.00 1.58 113.760

Pillars 16mmdia. 8 8.50 68.00 1.58 107.440

stirrups 200 2.00 400.00 0.39 156.000

Emergency strap $plinth beam 24 7.20 172.80 1.58 273.020

stirrups 120 1.58 189.60 0.39 73.940

Pillar connection strap $plinth beam 12 8.50 102.00 1.58 161.160

stirrups 70 1.58 110.60 0.39 43.130

5th Block

Cantiliver projection main bar 10mmdia. 2 27.33 54.65 0.61 33.330

Distribution bar 10mmdia. @10c\c 275 0.46 126.50 0.61 77.160

3rd Block 0.00 0.000

Cantiliver projection main bar 10mmdia. 2 33.04 66.07 0.61 40.300

Distribution bar 10mmdia. @10c\c 330 0.46 151.80 0.61 92.590

1st Block 0.00 0.000

Cantiliver projection main bar 10mmdia. 2 30.54 61.08 0.61 37.250

Distribution bar 10mmdia. @10c\c 306 0.46 140.76 0.61 85.860

2nd Block 0.00 0.000

Cantiliver projection main bar 10mmdia. 2 44.09 88.17 0.61 53.780

Distribution bar 10mmdia. @10c\c 440 0.46 202.40 0.61 123.460

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

4th Block

Cantiliver projection main bar 10mmdia. 2 62.74 125.48 0.61 76.540

Distribution bar 10mmdia. @10c\c 627 0.46 288.42 0.61 175.930

overlapping for pillars

C5,32mmDia .bar 20 1.95 39.00 6.31 246.090

28 1.95 54.60 6.31 344.520

25mmdia .bar 128 1.60 204.80 3.58 733.180

C4,20mmdia .bar 88 1.25 110.00 2.46 270.600

C3,25mmdia. bar 76 1.55 117.80 3.58 421.720

C3,25mmdia. bar 56 1.44 80.64 3.58 288.690

C2,25mm dia .bar 88 1.60 140.80 3.58 504.060

20mmdia bar 88 1.25 110.00 2.46 270.600

C1,20mmdia .bar 120 1.25 150.00 2.46 369.000

Gride 16 mm Dia. LMN 18 8.00 144.00 1.58 227.520

8 mm Dia.Stirrups 60 1.58 94.80 0.39 36.970

144501.830 kg

11 8.4 Form works Same as 1 st and 2nd rnning Bill 2683.910

Plinth beam Grid P,Q,R,S,T 10 15.425 154.25 0.45 69.410

Grid 10,11,12,13,14 10 23.61 236.10 0.45 106.240

Pillars(below plinth beam) 80 0.60 48.00 1.90 91.200

Pillars 504 0.6 302.40 2.85 861.840

1st Block arc beam 4 7.3 29.20 0.45 13.140

Emergency verandah pillar 4 2.5 10.00 0.1 1.000

Emergency strap $plinth beam 8 5.43 43.40 0.45 19.530

Pillar connection strap$ plinth beam 4 6.75 27.00 0.45 12.150

5th Block

Cantiliver projection base 1 27.33 27.32 0.20 5.460

Ends 1 27.33 27.33 0.10 2.730

3rd Block

Cantiliver projection base 1 33.04 33.03 0.20 6.600

Ends 1 33.03 33.03 0.100 3.300

1st Block

Cantiliver projection base 1 30.54 30.54 0.20 6.100

Ends 1 30.54 30.54 0.100 3.050

2nd Block

Cantiliver projection base 1 44.09 44.08 0.20 8.810

Ends 1 44.09 44.08 0.100 4.400

4th Block

Cantiliver projection base 1 62.74 62.74 0.20 12.540

Ends 1 62.74 62.74 0.100 6.270

Emergency verandah pillar 8 0.60 4.80 5.150 24.720

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

3942.400 m2

Estimaded By :- Checked By :- Approved By :-


zx/L ljsf; tyf ejg lgdf{0f ljefu, l8lehg sfof{no, ;'v]{t d=n]=k=kmf=g+= !^*

lansf] s|d ;+VofM– bf]>f] /lgË lan


7]Ssf ;DalGw aLn sfof{De cfb]z ldltM– )^$.)^.@&
of]hgfsf] gfdM– %) z}of c:ktfn ejg lgdf{0f sfo{ , ;'v]{t ;Dem\of}tf ldltM– @)^$.)^.!*
7]s]bf/sf] gfd M– /lagf , cflzif k|lti7f , g]kfn k|utL h]=eL= z}a' , sf7df08f}+ . sfd ;DkGg ug'{ kg]{ ldltM– @)^^.)@.!&-;Dem\of}tfsf] @) dlxgf _
7]Ssf k6[fsf] ;+VofM– !) - @)^#÷)^$ _ sfd ;DkGg ePsf] ldltM– rfn'''''''
cl3Nnf] e"QmfgL lansf] s|d;+VofM– k|yd /lgË lan e"QmfgL efpr/ g+=–
cl3Nnf] e"QmfgL ef=g+=M– e"QmfgL ldltM–
gfkL lstfa g+= sf] k[i7 g+=M– b]lv ;Dd
cfO{ cBfjlw sfd ePsf] cl3Nnf] landf r9]sf] xfn ePsf] sfd
s||=;+ 6d sfdsf] laj/0f PsfO{ s}lkmot
kl/df0f b/ hDdf d"No kl/df0f hDdf d"No kl/df0f hDdf d"No
g+==
A CIVIL WORKS
1 1.2 Earth work in Excavation in site Development m3 3799.225 100.00 379922.50 3799.225 379922.50 - -
2 2 Earth work excavation in BM Soil on Foundation m3 2464.361 200.00 492872.20 2464.361 492872.20 - -
3 4 150mm thick stone soling with sand m3 197.248 2500.00 493120.00 197.248 493120.00 - -
4 5 75mm thick lean concrete (1:3:6) in foundation m3 100.915 4500.00 454117.50 100.915 454117.50 - -
5 7 Brick Masonary work ( 1:6 ) m3 412.716 4576.61 1888840.17 56.824 260061.28 355.89 1628778.89
6 8 R.C.C. Works
7 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 886.176 6529.70 5786463.42 425.278 2776937.75 460.90 3009525.67
8 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 88.938 8547.38 760186.88 - - 88.94 760186.88
9 8.3 Reinforcements works kg ### 60.51 8158620.17 75114.59 4545183.84 ### 3613436.33
10 8.4 Form work m2 2683.910 313.00 840063.83 500.57 156678.41 2183.34 683385.42

TOTAL AMOUNT (without VAT) Rs. 19254206.67 Rs 9558893.48 Rs. 9695313.19

pko'{Qm adf]lhd 7Ls 5 egL k|dfl0ft ug]{sf] ;xLM–


============== ============== =============
cf]e/l;o/ O{lGhgLo/ 7]s]bf/sf] ;xL
of] lansf] hDdf -Eof6 afx]]s_ 19254206.67
cl3Nnf] e"QmfgL lanaf6 e"QmfgL ePsf] - 9558893.48
afFsL lbg' kg]{ -Eof6 afx]s_ 9695313.19
s6[L ug'{ kg]{ ?=M–
s_ k]ZsL–
v_ dfn;dfgsf] df]nM–
u_ d]zLg cf}hf/ axfnM–
3_ cfos/ !=%Ü M–
ª_ d"No clea[l4 s/ !# Ü M–
r_ w/f}6L %Ü M–
5_ cGo M–
v"b lbg' kg]{ -Eof6 ;d]t_ ?=M–
k]z ug]{sf] ;xLM– hfFr ug]{sf] ;xLM– :jLs[t ug]{sf] ;xLM–
hDdf ?= cIf]?kLM– sf] r]s g+= af6 k|fKt ePsf] egL ;xL ug]{ 7]s]bf/sf] ;xLM–
Department of Urban Development And Building Construction
DIVISION OFFICE
Surkhet
Name of work :- 50 Bed Hospital Construction Work F/Y-064 - 065
Place :- Birendranagar - 3 , Kalagaon , Surkhet

DETAILS OF MEASUREMENT ( 2nd Bill )


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

(A) CIVIL WORKS

1 Site Development work

2 1.2 Earth work in Excavation in site Development Same as 1 st rnning Bill 3799.225

3 2 Earth work excavation in BM Soil on Foundation Same as 1 st rnning Bill 2464.361

4 4 150mm thick stone soling with sand Same as 1 st rnning Bill 197.248

5 5 75mm thick lean concrete (1:3:6) in foundation Same as 1 st rnning Bill 100.915

6 7 Brick Masonary work ( 1:6 ) Same as 1 st rnning Bill 56.824

Grid 1,3,4,5 4 33.00 132.00 0.35 2.00 92.400

Grid A,B,CE,G 5 15.20 76.00 0.35 2.00 53.200

Grid I-I 1 6.60 6.60 0.35 2.00 4.620

Grid I,J 1 8.60 8.60 1.05 2.00 18.060

2nd block

Grid 2,5,6 3 23.61 70.83 0.35 2.00 49.581

Grid 3,4,7 3 17.83 53.47 0.35 2.00 37.429

Grid T,S,R,Q,P,N,M,L 8 8.60 68.80 0.35 2.00 48.160

Grid P,Q,R,S, 5 6.60 33.00 0.35 0.75 8.662

Grird L,M,N 3 5.90 17.70 0.35 0.75 4.646

3rd block (90cm-45cm in 1 st bill)

Grid 9 ,10,11,13 4 19.80 79.20 0.35 0.45 12.474

Grid D,F,H, 3 15.43 46.27 0.35 0.45 7.287

Grid K,L, 1 15.43 15.42 1.05 0.45 7.285

Below strap beam

pillar 304,501,to308,505 1 6.60 6.60 1.20 0.45 3.564

1st block &2nd block

Pillar no.101,

E. side tri.portion 1 0.09 0.09 0.090

N.Side tri. Portion 1 0.09 0.08 0.080

Pillar no.102

W&E. side tri.portion 2 0.13 0.26 0.260

N.Side Rec .Portion 1 0.25 0.25 0.35 0.35 0.030

W&E. side Rec. portion 2 0.20 0.40 0.35 0.50 0.070

Pillar no.103,104,105

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

W&E. side tri.portion 6 0.08 0.45 0.450

N.Side Rec .Portion 3 0.20 0.60 0.35 0.25 0.052

W&E. side Rec. portion 6 0.22 1.32 0.35 0.35 0.161

N.Side Tri. .Portion 3 0.04 0.12 0.120

Pillar no.106

W&N. side tri.portion 2 0.07 0.13 0.130

W&N.Side Rec .Portion 2 0.15 0.30 0.35 0.35 0.036

Pillar no.107,113

N&S side Rec, portion 2 0.10 0.20 0.36 0.10 0.007

E. side tri.portion 2 0.08 0.15 0.150

E. side Rec. portion 2 0.10 0.20 0.35 0.35 0.024

Pillar no.115,116,117,114

W&E. side tri.portion 16 0.11 1.72 1.720

W&E. side Rec. .portion 16 0.15 2.40 0.35 0.35 0.294

Pillar no.119

E. side tri.portion 1 0.08 0.07 0.070

S. side tri.portion 1 0.08 0.07 0.070

Pillar no.120.121,123,122 0.000

W&E. side tri.portion 8 0.07 0.54 0.540

W&E. side Rec..portion 8 0.15 1.20 0.35 0.30 0.126

S. side tri.portion 4 0.07 0.27 0.270

S. side Rec..portion 4 0.15 0.60 0.35 0.30 0.063

Pillar no.124,125,226,227

W&E. side tri.portion 8 0.06 0.46 0.460

W&E. side Rec..portion 8 0.15 1.20 0.35 0.20 0.084

S. side tri.portion 4 0.08 0.31 0.310

S. side Rec..portion 4 0.15 0.60 0.36 0.30 0.064

Pillar no.212,208

W&E. side tri.portion 4 0.08 0.33 0.330

Pillar no.202,203,204

W&E. side tri.portion 6 0.10 0.60 0.600

N. Side Tra. Por. 3 0.11 0.33 0.330

Pillar no.205

W&N. Side Tra. Por. 2 0.08 0.16 0.160

Pillar no.221,216,224,219

W&E. Side Tra. Por. 8 0.1085 0.86 0.860

W&E. Side Rec . Por. 8 0.15 1.20 0.35 0.39 0.163

Pillar no.222,217,223,218

W&E. Side Tra. Por. 4 0.09 0.35 0.350

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

Total 412.716 m3

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit

7 8 R.C.C. Work
8 8.1 R.C.C.For P.C.C.(1;1.5:3) M 20 Same as 1 st rnning Bill 425.28

F1
Rec. Portion 2 2.50 5.00 2.50 0.20 2.500
Trap.Portion 2 1.45 2.90 2.900
F2 5 no
Rec. Portion 5 3.00 15.00 3.00 0.20 9.000
Trap.Portion 5 2.50 12.50 12.500
F3,4 no
Rec. Portion 4 3.50 14.00 3.50 0.300 14.000
Trap.Portion 4 3.42 13.69 13.690
CF2,2no
Rec. Portion 2 5.60 11.20 3.60 0.300 11.200
Trap.Portion 2 5.29 10.58 10.580
CF6,2NO
Rec. Portion 2 6.45 12.90 3.60 0.300 13.932
Trap.Portion 2 6.06 12.11 12.110
CF8
Rec. Portion 1 6.00 6.00 3.60 0.300 6.480
Trap.Portion 1 5.65 5.65 5.650
CF12
Rec. Portion 1 5.36 5.36 3.70 0.300 5.949
Trap.Portion 1 5.21 5.20 5.200
CF13
Rec. Portion 1 4.15 4.15 3.60 0.300 4.482
Trap.Portion 1 4.31 4.30 4.300
T2Area=34.82m2 1 34.82 34.82 0.400 13.920
T3 Area=33.667 m2 1 33.67 33.66 0.400 13.460
T4Area=27.706m2 1 27.706 27.70 0.400 11.080
Foundation combined beams
CF1 1 5.000 5.00 0.40 0.250 0.500
CF2 7 5.60 39.20 0.50 0.20 3.920
CF3 1 5.60 5.60 0.40 0.25 0.560
CF4 2 5.60 11.20 0.50 0.40 2.240
CF6 2 6.45 12.90 0.60 0.20 1.548
CF7 1 5.25 5.25 0.40 0.25 0.525
CF8 1 6.00 6.00 0.50 0.20 0.600
CF9
One ways 3 5.00 15.00 0.40 0.40 2.400
Other ways 2 6.04 12.08 0.40 0.40 1.932
CF10 1 6.04 6.04 0.50 0.40 1.208

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
CF11
One ways 1 4.60 4.60 0.50 0.60 1.380
Other ways 1 4.50 4.50 0.50 0.60 1.350
Other ways 1 4.96 4.96 0.50 0.60 1.488
Other ways 1 5.20 5.20 0.50 0.60 1.560
CF12 2 5.36 10.72 1.20 0.20 2.572
CF14 2 6.50 13.00 1.20 0.40 6.240
T1
One ways 1 5.25 5.25 0.50 0.20 0.525
Other ways 1 6.01 6.00 0.50 0.20 0.600
Diognal beam 1 5.50 5.50 0.50 0.60 1.650
T2
One ways 1 6.00 6.00 1.20 0.40 2.880
Other ways 1 5.51 5.50 0.50 0.40 1.100
Diognal beam 1 4.20 4.20 0.50 0.40 0.840
T3
One ways 1 6.51 6.50 0.50 0.40 1.300
Other ways 1 5.98 5.97 0.50 0.40 1.194
Diognal beam 1 4.60 4.60 0.50 0.40 0.920
T4
One ways 1 5.67 5.67 0.50 0.40 1.134
Other ways 1 5.40 5.40 0.50 0.40 1.080
Foundation strap beam ,4th level
Grid,1,3,4,7 4 33.00 132.00 0.35 0.45 20.790
Grid,B,C,E,G 4 10.80 43.20 0.35 0.45 6.804
Grid I-I 1 6.60 6.60 0.35 0.45 1.039
Grid ,I,J 1 8.60 8.60 1.05 0.45 4.063
Block 2
Grid 2-2 1 23.61 23.61 0.35 0.45 3.718
Grid 3-3 1 13.20 13.20 0.35 0.45 2.079
Grid 4-4 1 13.20 13.20 0.35 0.45 2.079
Grid 5,6 2 23.61 47.22 0.35 0.45 7.437
Grid 7-7 1 13.20 13.20 0.35 0.45 2.079
Grid 8-8 1 36.81 36.81 0.35 0.45 5.797
Grid,L,M,N 3 14.50 43.50 0.35 0.45 6.851
Grid,P,Q,R,S,T 5 15.20 76.00 0.35 0.45 11.970
Block 4
Grid, 10,12,13,14 4 23.61 94.44 0.35 0.45 14.874
Grid T-T 1 11.37 11.36 0.35 0.45 1.789
Grid,R,S 2 10.78 21.55 0.35 0.45 3.394
Grid Q-Q 1 11.03 11.02 0.35 0.45 1.735
Grid Combined O,P 1 13.20 13.20 1.05 0.45 6.237
Grid O-O 1 6.60 6.60 0.35 0.45 1.039
Block 5
Grid ,9,10,11,13 4 13.20 52.80 0.35 0.45 8.316

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
Grid ,L,M,N 3 19.80 59.40 0.35 0.45 9.355
Grid combined beam O,P&K,L 2 17.00 34.00 0.10 0.45 1.530
R.C.C.For Plinth tie beam
1st Level
Grid 15,16,17 3 13.20 39.60 0.35 0.45 6.237
Grid 14-14 1 15.48 15.48 0.35 0.45 2.438
Grid L,M,N 3 15.45 46.35 0.35 0.45 7.300
Block 3
Grid 9,10,11,13 4 19.80 79.20 0.35 0.45 12.474
Grid D,F,H,K 4 15.43 61.70 0.35 0.45 9.717
4th Level
Grid 7-7 1 50.37 50.36 0.35 0.45 7.931
Grid 4-4 1 56.27 56.26 0.35 0.45 8.860
Grid 3-3 1 50.37 50.36 0.35 0.45 7.931
Grid 1-1 1 32.40 32.40 0.35 0.45 5.103
Grid 2,5,6 3 23.01 69.03 0.35 0.45 10.872
Grid 8-8 1 40.900 40.90 0.35 0.45 6.441
Grid P,Q,R,S,T 5 14.60 73.00 0.35 0.45 11.497
Grid L,M,N 3 14.67 44.01 0.35 0.45 6.931
Grid J-J 1 15.37 15.37 0.35 0.45 2.420
Grid A,B,C,E,G,I 6 14.60 87.60 0.35 0.45 13.797
Grid A-A 1 11.40 11.40 0.35 0.45 1.795
Total 886.176 m3
9 8.2 R.C.C. work for pillars M25
Below D.P.C.
1St Level 10no.of pillar 10 0.60 6.00 0.60 1.86 6.696
2nd Level 15 no.of pillar 15 0.60 9.00 0.60 1.95 10.530
3rd Level 6 no. of pillar 6 0.60 3.60 0.60 2.20 4.752
4th Level 60 no.of pillar 60 0.60 36.00 0.60 3.10 66.960
Total 88.938 m3
10 8.3 Reinforcement works
Same as 1 st rnning Bill 75114.590
Basements bars
F1 2no.12mmdia. Rods @125c/c both ways 80 2.58 206.08 0.89 183.410
F2,1NO.12mm dia. rods@100c/c both ways 60 3.07 184.02 0.89 163.770
CF2, 2no. 16mmdia .rods @125c/c both ways
One ways 58 5.75 333.38 1.58 526.740
Other ways 90 3.75 337.32 1.58 532.960
CF8,1 No.16mm dia.rods @125c/c both ways
One ways 29 6.15 178.29 1.58 281.690
Other ways 48 3.75 179.90 1.58 284.240
CF12 Change to F4 90 4.65 418.32 1.58 660.940
CF12 ,16mm dia.rods@125c/c bothways
One ways 30 5.51 165.24 1.58 261.070
Other ways 43 3.85 165.46 1.58 261.420
CF13,2no.16mmdia.rods@125c/c bothways
One ways 58 4.30 249.28 1.58 393.860

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
Other ways 66 3.75 247.36 1.58 390.820

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
CF14,16mmdia.rods.@125c/c both ways
One ways 33 6.65 219.38 1.58 346.620
Other ways 52 4.30 223.49 1.58 353.110
T2,16mmdiarods@125c/c bothways
One ways Rectangle por. 24 6.66 159.74 1.58 252.380
Tra. Por. 1 118.94 118.94 1.58 187.920
Other ways Rectangle por. 29 6.15 178.29 1.58 281.690
Tra. Por. 1 113.41 113.41 1.58 179.180
T3,16mmdiarods@125c/c bothways
One ways Rectangle por. 24 6.12 146.95 1.58 232.180
Tra. Por. 1 125.16 125.16 1.58 197.750
Other ways Rectangle por. 24 6.66 159.74 1.58 252.380
Tra. Por. 1 123.13 123.12 1.58 194.520
T4,16mmdiarods@125c/c bothways
One ways Rectangle por. 20 5.82 116.44 1.58 183.970
Tra. Por. 1 111.08 111.07 1.580 175.490
Other ways Rectangle por. 20 5.96 119.14 1.580 188.240
Tra. Por. 1 115.23 115.23 1.580 182.060
Foundation combined beams
CF2, 2Nos. Of beam
8no25mmdia.up &down bent bar 16 7.32 117.12 3.850 450.910
2no.25mmdia.st. bar overlap 1.2m 4 6.66 26.64 3.850 102.560
2no. 16mmdia.side bar overlap95cm 4 6.41 25.64 1.580 40.510
8mmdia,beam stirrups
Large 90 2.98 268.20 0.390 104.590
Small 90 2.43 218.70 0.390 85.290
CF6, 2Nos. Of beam
12no25mmdia.up &down bent bar overlap 1.15m 24 9.32 223.68 3.850 861.160
6no.25mmdia.st. bar overlap 1.2m 12 7.51 90.12 3.850 346.960
2no. 16mmdia.side bar overlap95cm 4 7.26 29.04 1.580 45.880
8mmdia,beam stirrups
Large 106 3.18 337.08 0.390 131.460
Small 106 2.70 286.20 0.390 111.610
Very small 106 2.30 243.80 0.390 95.080
Pin rods 25mmdia 12 0.50 6.00 3.850 23.100
CF8, 1Nos. Of beam
8no25mmdia.up &down bent bar overlap 1.25m 8 8.83 70.64 3.850 271.960
4no.25mmdia.st. bar overlap 1.2m 4 7.36 29.44 3.850 113.340
2no. 16mmdia.side bar overlap95cm 2 6.81 13.62 1.580 21.510
8mmdia,beam stirrups 0.000
Large 47 2.98 140.06 0.390 54.620
Small 47 2.58 121.26 0.390 47.290
Pin rods 25mmdia 8 0.50 4.00 3.850 15.400
CF12, Double beam
2*8no25mmdia.up &down bent bar overlap 1.25m 16 8.20 131.20 3.850 505.120

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
2*6no.25mmdia.st. bar overlap 1.2m 12 6.42 77.04 3.850 296.600
2*2no. 16mmdia.side bar overlap95cm 4 6.17 24.68 1.580 38.990
8mmdia,beam stirrups
Large 40 2.98 119.20 0.390 46.480
Small 40 2.58 103.20 0.390 40.240
Pin rods 25mmdia 16 0.50 8.00 3.850 30.800
T2 ,Combined pillar beam 406to411,&512to516
2*8no25mmdia.up &down bent bar overlap 1.25m 16 8.61 137.76 3.850 530.370
2*6no.25mmdia.st. bar overlap 1.2m 12 7.06 84.72 3.850 326.170
2*2no. 16mmdia.side bar overlap95cm 4 6.81 27.24 1.580 43.030
8mmdia,beam stirrups
Large 96 2.58 247.68 0.390 96.590
Small 96 2.05 196.80 0.390 76.750
Pin rods 25mmdia 16 0.50 8.00 3.850 30.800
Combined pillar beam 515to411
8no25mmdia.up &down bent bar overlap 1.3m 8 9.17 73.36 3.850 282.430
6no.25mmdia.st. bar overlap 1.2m 6 7.57 45.42 3.850 174.860
2no. 16mmdia.side bar overlap 1.1m 2 7.47 14.94 1.580 23.600
8mmdia,beam stirrups
Large 50 2.58 129.00 0.390 50.310
Small 50 2.05 102.50 0.390 39.970
Pin rods 25mmdia 8 0.50 4.00 3.850 15.400
Combined pillar beam 515to512
8no25mmdia.up &down bent bar overlap 1.2m 8 6.62 52.96 3.850 203.890
6no.25mmdia.st. bar overlap 1.2m 6 5.30 31.80 3.850 122.430
2no. 16mmdia.side bar overlap 1.1m 2 5.20 10.40 1.580 16.430
8mmdia,beam stirrups
Large 23 2.58 59.34 0.390 23.140
Small 23 2.05 47.15 0.390 18.380
Pin rods 25mmdia 8 0.50 4.00 3.850 15.400
T3 Combined pillar beam
Combined pillar beam 507to508
8no25mmdia.up &down bent bar overlap 1.3m 8 10.59 84.70 3.850 326.090
6no.25mmdia.st. bar overlap 1.2m 6 7.56 45.36 3.850 174.630
2no. 16mmdia.side bar overlap 1.1m 2 7.46 14.92 1.580 23.570
8mmdia,beam stirrups
Large 45 2.58 116.10 0.39 45.270
Small 45 2.05 92.25 0.39 92.25
Pin rods 25mmdia 6 0.50 3.00 3.85 3.00
Combined pillar beam 507to511
8no25mmdia.up &down bent bar overlap 1.15m 8 8.310 66.48 3.85 66.48
6no.25mmdia.st. bar overlap 1.2m 6 7.04 42.21 3.85 42.21
2no. 16mmdia.side bar overlap 1.1m 2 6.935 13.87 1.58 13.87
8mmdia,beam stirrups
Large 45 2.58 116.10 0.39 116.10

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
Small 45 2.05 92.25 0.39 35.970
Pin rods 25mmdia 8 0.50 4.00 3.85 4.000
Combined pillar beam 511to401
8no25mmdia.up &down bent bar overlap 1.25m 8 7.17 57.36 3.85 220.830
6no.25mmdia.st. bar overlap 1.2m 6 5.80 34.800 3.85 133.980
2no. 16mmdia.side bar overlap 1.1m 2 5.60 11.200 1.58 17.690
8mmdia,beam stirrups
Large 26 2.58 67.080 0.39 26.160
Small 26 2.05 53.300 0.39 20.780
Pin rods 25mmdia 8 0.50 4.000 3.85 15.400
T4 Combined pillar beam
Combined pillar beam 220to215
8no20mmdia.up &down bent bar overlap 1.15m 8 8.01 64.080 2.46 157.630
6no.25mmdia.st. bar overlap 1.2m 6 6.74 40.440 2.46 99.480
2no. 16mmdia.side bar overlap 1.1m 2 6.64 13.280 1.58 20.980
8mmdia,beam stirrups
Large 35 2.58 90.300 0.39 35.210
Small 35 2.05 71.750 0.39 27.980
Pin rods 25mmdia 8 0.50 4.000 3.85 15.400
Combined pillar beam 228 to220
8no20mmdia.up &down bent bar overlap 1.15m 8 8.17 65.36 2.46 160.780
6no.20mmdia.st. bar overlap 1.2m 6 6.90 41.40 2.46 101.840
2no. 16mmdia.side bar overlap 1.1m 2 6.82 13.64 1.58 21.550
8mmdia,beam stirrups
Large 30 2.58 77.40 0.39 77.400
Small 30 2.05 61.50 0.39 61.500
Pin rods 25mmdia 8 0.50 4.00 3.85 15.400
Starp beam 1st Block
Grid 1,3,4,7 overlap(2*6*1.1)m 24 39.42 946.08 1.58 1494.800
8mmdia,beam stirrups 880 1.58 1390.40 0.39 542.250
GridA,B,C,E overlap(1*6*1)m 24 16.84 404.16 1.58 638.570
GridA,J,I overlap(1*6*1)m 12 17.84 214.08 1.58 338.240
8mmdia,beam stirrups 530 1.58 837.40 0.39 326.580
Starp beam 2nd Block
Grid 2-2 overlap (1*6*1.1)m 6 28.33 169.98 1.58 268.560
8mmdia,beam stirrups 155 1.58 244.90 0.39 95.510
Grid ,3-3 overlap (1*6*1.1)m 6 19.66 117.96 1.58 186.370
8mmdia,beam stirrups 100 1.58 158.00 0.39 61.620
Grid 4-4, overlap (1*6*1.1)m 6 19.66 117.96 1.58 186.370
8mmdia,beam stirrups 100 1.58 158.00 0.39 61.620
Grid ,5,6 overlap(2*6*1)m 12 29.03 348.36 1.58 550.400
8mmdia,beam stirrups 304 1.58 480.32 0.39 187.320
Grid 7-7 6 15.62 93.72 1.58 148.070
8mmdia,beam stirrups 85 1.58 134.30 0.39 52.370
Grid 8-8 overlap(2*6*1.1) 6 44.85 269.10 1.58 425.170

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
8mmdia,beam stirrups 240 1.58 379.20 0.39 147.880
Grid P,Q,R,S,T 30 24.04 721.20 1.58 1139.490
8mmdia,beam stirrups 440 1.58 695.20 0.39 271.120
Grid L,M,N Overlap (1*6*1.1)m 18 23.44 421.92 1.58 666.630
8mmdia,beam stirrups 255 1.58 402.90 0.39 157.130
Starp beam 4th Block
Grid 10,12,13,14 ,overlap(2*6*.95)m 24 29.13 699.12 1.58 1104.600
8mmdia,beam stirrups 620 1.58 979.60 0.39 382.040
Grid ,P,Q,R,S,T Overlap(1*6*1)m 30 18.84 565.20 1.58 893.010
8mmdia,beam stirrups 450 1.58 711.00 0.39 277.290
Starp beam 5th Block
Grid,O-O overlap (2*6*1)m 6 27.26 163.56 1.58 258.420
8mmdia,beam stirrups 135 1.58 213.30 0.39 83.180
Grid, L,M,N overlap (1*6*1)m 18 22.84 411.12 1.58 649.560
8mmdia,beam stirrups 270 1.58 426.60 0.39 166.370
Grid,9,10,11,13, overlap (1*6*1)m 24 22.62 542.88 1.58 857.750
8mmdia,beam stirrups 360 1.58 568.80 0.39 221.830
Plinth tie beam 5th block
Grid ,16,17,overlap(2*6*1)m 12 17.62 211.44 1.58 334.070
8mmdia,beam stirrups 180 1.58 284.40 0.39 110.910
Grid ,14,15, overlap (1*6*1)m 12 21.46 257.46 1.58 406.780
8mmdia,beam stirrups 196 1.58 309.68 0.39 120.770
Plinth tie beam 3rd block 0.000
Grid,D,F,H,K overlap (1*6*1.1)m 24 19.03 456.60 1.58 721.420
8mmdia,beam stirrups 404 1.58 638.32 0.39 248.940
Grid ,9,10,11, Overlap (1*6*1.1)m 18 23.92 430.56 1.58 680.280
8mmdia,beam stirrups 396 1.58 625.68 0.39 244.010
Grid 13 6 24.42 146.52 1.58 231.500
8mmdia,beam stirrups 132 1.58 208.56 0.39 81.330
4th Level Plinth tie beam
Grid 7-7 overlap (5*6*.85)m 6 60.62 363.69 1.58 574.630
8mmdia,beam stirrups 360 1.58 568.80 0.39 221.830
Grid 4-4 overlap (6*6*.9)m 6 68.27 409.59 1.58 647.150
8mmdia,beam stirrups 360 1.58 568.80 0.39 221.830
Grid 3-3 overlap (6*6*.9)m 6 68.27 409.59 1.58 647.150
8mmdia,beam stirrups 360 1.58 568.80 0.39 221.830
Grid 1-1 bent up bar (2*.8+over.3*6*.85)m 6 40.15 240.90 1.58 380.620
8mmdia,beam stirrups 225 1.58 355.50 0.39 138.640
Grid2-2 bent up bar (2*.8+over.2*6*.9)m 6 29.51 177.06 1.58 279.750
8mmdia,beam stirrups 165 1.58 260.70 0.39 101.670
Grid ,5 ,6 bent up bar (2*.8+over.2*6*.9)m 12 66.27 795.18 1.58 1256.380
8mmdia,beam stirrups 720 1.58 1137.60 0.39 443.660
Grid 8-8 bent up bar (2*.9+over.3*6*.9)m 6 50.81 304.83 1.58 481.630
8mmdia,beam stirrups 290 1.58 458.20 0.39 178.690
Grid ,P,Q,R,S,T bent up bar (2*.9+over.3*6*.9)m 30 21.50 645.00 1.58 1019.100

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
8mmdia,beam stirrups 535 1.58 845.30 0.39 329.660
Grid ,L,M,N bent up bar (2*.9+over.3*6*.9)m 18 21.57 388.26 1.58 613.450
8mmdia,beam stirrups 321 1.58 507.18 0.39 197.800
Grid ,J bent up bar (2*.9+over.3*6*.9)m 6 20.87 125.22 1.58 197.840
8mmdia,beam stirrups 107 1.58 169.06 0.39 65.930
Grid ,A,B,C,,E,G,I bent up bar (2*.9+over.2*6*.9)m 36 21.50 774.00 1.58 1222.920
8mmdia,beam stirrups 618 1.58 976.44 0.39 380.810
R einforcement works for columns 2nd level
Pillars no.410,418,417,412,407,413are in C1
4 -25mm dia .rods 24 8.40 201.60 3.85 776.160
8 -20mm dia .rods 48 8.25 396.00 2.46 974.160
Pillars
no.420,515,411,406,414,409,408,403,404,402,508,a
re in C2
8 -25mm dia .rods 88 8.40 739.20 3.85 2845.920
4 -20mm dia .rods 44 8.25 363.00 2.46 892.980
Pillars. No 516,512,510,506,511,507,401,405,are in C3
12 -25mm dia .rods 96 8.40 806.40 3.85 3104.640
Pillars. No 410,415,are in C5
4 -32mm dia .rods 8 8.40 67.20 6.31 424.030
8 -25mm dia .rods 16 8.40 134.40 3.86 518.510
27 nos.of pillars stirrups
Large 1215 2.20 2673.00 0.39 1042.470
Small 2430 1.55 3766.50 0.39 1468.930
For 4th level
Pillars no.217,222,are in C2
8 -25mm dia .rods 16 9.15 146.40 3.85 563.640
4 -20mm dia .rods 8 9.00 72.00 2.46 177.120
Pillars no.215,220,228,are in C4
12 -20mm dia .rods 36 9.00 324.00 2.46 797.040
5 nos.of pillars stirrups
Large 250 2.20 550.00 0.39 214.500
Small 500 1.55 775.00 0.39 302.250
For 3rd level
Pillars no.231,232,233,are in C1
4 -25mm dia .rods 12 8.85 106.20 3.85 408.870
4 -20mm dia .rods 12 8.70 104.40 2.46 256.820

4 -20mm dia .rods 12 8.64 103.68 2.46 255.050

Pillars no.502,503,are in C2
4 -25mm dia .rods 8 8.85 70.80 3.85 272.580
4 -25mm dia .rods 8 8.70 69.60 3.85 267.960
4 -20mm dia .rods 8 8.65 69.20 2.46 170.230
Pillars no.504,236,are in C3
4 -25mm dia .rods 8 8.80 70.40 3.85 271.040
4 -25mm dia .rods 8 8.75 70.00 3.85 269.500
4 -25mm dia .rods 8 8.65 69.20 3.85 266.420

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
Pillars no.231,234,are in C4
4 -20mm dia .rods 8 8.80 70.40 2.46 173.180
4 -20mm dia .rods 8 8.75 70.00 2.46 172.200
4 -20mm dia .rods 8 8.65 69.20 2.46 170.230
Pillars no.237,are in C5
4 -32mm dia .rods 4 8.80 35.20 6.31 222.110
4 -25mm dia .rods 4 8.75 35.00 3.85 134.750
4 -25mm dia .rods 4 8.65 34.60 3.85 133.210
10 nos.of pillars stirrups
Large 500 2.20 1100.00 0.39 429.000
Small 1000 1.55 1550.00 0.39 604.500
Total 134830.940 kg
11 8.4 Form work
Same as 1 st rnning Bill 500.570
F1 3 10.00 30.00 0.20 6.000
F2 5 12.00 60.00 0.20 12.000
F3 4 14.00 56.00 0.30 16.800
CF2 3 18.40 55.20 0.30 16.560
CF6 2 20.10 40.20 0.30 12.060
CF8 1 19.20 19.20 0.30 5.760
CF12 1 18.12 18.12 0.30 5.430
CF13 1 15.50 15.50 0.30 4.650
T2 Perimeter=23.11m 1 23.11 23.11 0.40 9.240
T3 Perimeter=23.07m 1 23.07 23.07 0.40 9.220
T4 Perimeter=21.06m 1 21.06 21.06 0.40 8.420
For foundation combined beam
CF1 1 11.00 11.00 0.25 2.750
CF2 7 12.20 85.40 0.20 17.080
CF3 1 12.00 12.00 0.25 3.000
CF4 3 12.20 36.60 0.40 14.640
CF5 2 13.70 27.40 0.20 5.480
CF6 3 14.10 42.30 0.20 8.460
CF7 2 11.30 22.60 0.25 5.650
CF8 1 13.00 13.00 0.20 2.600
CF9 one ways 3 10.80 32.40 0.40 12.960
CF9 other ways 2 9.28 18.56 0.40 7.420
CF10 1 13.08 13.08 0.40 5.230
CF11 one ways 1 10.20 10.20 0.60 6.120
Dignoal beam 1 10.00 10.00 0.60 6.000
CF11other ways 1 10.92 10.92 0.60 6.550
Dignoal beam 1 11.40 11.40 0.60 6.840
CF12 1 13.12 13.12 0.30 3.930
CF14 1 16.60 16.60 0.40 6.640
T1 One ways 1 13.02 13.01 0.20 2.600

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
T1 Other ways 1 10.50 10.50 0.20 2.100
T1 Other ways 1 12.00 12.00 0.60 7.200
T2 One ways 1 12.02 12.01 0.40 4.800
T2 Other ways 2 14.40 28.80 0.40 11.520
T2 Other ways 1 9.40 9.40 0.40 3.760
T3 One ways 1 14.02 14.01 0.40 5.600
T3 Other ways 1 13.02 13.01 0.40 5.200
T3 Other ways 1 10.20 10.20 0.40 4.080
T4 One ways 1 12.35 12.34 0.40 4.930
T4 Other ways 1 11.80 11.80 0.40 4.720
For strap beam 4th level 1st block
Grid ,1,3,4,7, 8 33.00 264.00 0.45 118.800
Grid ,A-A 2 11.40 22.80 0.45 10.260
Grid ,B,C,G,E 8 10.80 86.40 0.45 38.880
Grid I-I 2 6.60 13.20 0.45 5.940
Grid ,I,J 2 8.60 17.20 0.45 7.740
2nd block
Grid 2-2 2 23.61 47.22 0.45 21.240
Grid 3-3 2 13.20 26.40 0.45 11.880
Grid 4-4 2 13.20 26.40 0.45 11.880
Grid ,5,6 4 23.61 94.44 0.45 42.490
Grid 7-7 2 13.20 26.40 0.45 11.880
Grid 8-8 2 36.81 73.62 0.45 33.120
Grid P,Q,R,S,T 10 15.20 152.00 0.45 68.400
Grid L,M,N 6 14.50 87.00 0.45 39.150
4th block
Grid 10,12,13,14 8 23.61 188.88 0.45 84.990
Grid T-T 2 11.38 22.75 0.45 10.230
Grid R&S 4 10.78 43.10 0.45 19.390
Grid Q,-Q 2 11.03 22.05 0.45 9.920
Grid O,P 2 13.20 26.40 0.45 11.880
Grid O-O 2 6.60 13.20 0.45 5.940
5th block
Grid 9,10,11,13 8 13.20 105.60 0.45 47.520
Grid L,M,N 6 19.80 118.80 0.45 53.460
For Plinth beam 1st level
Grid 15,16,17 6 13.20 79.20 0.45 35.640
Grid 14-14 2 15.39 30.78 0.45 13.850
Grid L,M,N 6 15.45 92.70 0.45 41.710
3rd block
Grid 9,10,11,13 8 19.80 158.40 0.45 71.280
Grid D,F,H,K 8 15.43 123.40 0.45 55.530

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
4th level
Grid 7,3 4 50.37 201.46 0.45 90.650
Grid 4-4 2 56.27 112.53 0.45 50.630
Grid1-1 2 32.40 64.80 0.45 29.160
Grid 2,5,6 6 23.01 138.06 0.45 62.120
Grid 8-8 2 40.90 81.80 0.45 36.810
Grid P,Q,R,S,T 10 14.60 146.00 0.45 65.700
Grid L,M,N 6 14.67 88.02 0.45 39.600
Grid J-J 2 15.37 30.74 0.45 13.830
Grid A,B,C,E,G,I 12 14.60 175.20 0.45 78.840
For pillars 1st level
10no. Of pillars 10 2.40 24.00 1.86 44.640
21no .of pillars 2nd level 21 2.40 50.40 1.95 98.280
6no. Of pillars 3rd level 6 2.40 14.40 2.20 31.680
52no. Of pillars 4th level 52 2.40 124.80 3.00 374.400
Total 2683.910 m2

Estimaded By :- Checked By :- Approved By :-


Department of Urban Development And Building Construction
DIVISION OFFICE, Surkhet
F/Y-064 - 065
Name of work :- 50 Bed Hospital Construction Work
Place :- Birendranagar - 3 , Kalagaon , Surkhet

2nd RUNNING BILL


S.N. Item No. Items Unit Quantity Unit Rate Amount

A CIVIL WORKS

1 1.2 Earth work in Excavation in site Development m3 3799.225 100.00 379922.50

2 2 Earth work excavation in BM Soil on Foundati m3 2464.361 200.00 492872.20

3 4 150mm thick stone soling with sand m3 197.248 2500.00 493120.00

4 5 75mm thick lean concrete (1:3:6) in foundation m3 100.915 4500.00 454117.50

5 7 Brick Masonary work ( 1:6 ) m3 412.716 4576.61 1888840.17

6 8 R.C.C. Works

7 8.1 P.C.C. for R.C.C(1:1.5:3) M 20 m3 886.176 6529.70 5786463.42

8 8.2 P.C.C. for R.C.C(1:1:2) M 25 m3 88.938 8547.38 760186.88

9 8.3 Reinforcements works kg 134830.940 60.51 8158620.17

10 8.4 Form work m2 2683.910 313.00 840063.83

TOTAL 2nd Bill AMOUNT Rs. 19254206.67

Estimated By:- Checked By:- Approved By:-


zx/L ljsf; tyf ejg lgdf{0f ljefu, l8lehg sfof{no, ;'v]{t d=n]=k=kmf=g+= !^*

7]Ssf ;DalGw aLn


lansf] s|d ;+VofM– klxnf] /lgË lan sfof{De cfb]z ldltM– )^$.)^.@&
of]hgfsf] gfdM– %) z}of c:ktfn ejg lgdf{0f sfo{ , ;'v]{t ;Dem\of}tf ldltM– @)^$.)^.!*
7]s]bf/sf] gfd M– /lagf , cflzif k|lti7f , g]kfn k|utL h]=eL= z}a' , sf7df08f}+ . sfd ;DkGg ug'{ kg]{ ldltM– @)^^.)@.!&-;Dem\of}tfsf] @) dlxgf _
7]Ssf k6[fsf] ;+VofM– !) - @)^#÷)^$ _ sfd ;DkGg ePsf] ldltM– rfn'''''''
cl3Nnf] e"QmfgL lansf] s|d;+VofM– 5}g e"QmfgL efpr/ g+=–
cl3Nnf] e"QmfgL ef=g+=M– e"QmfgL ldltM–
gfkL lstfa g+= sf] k[i7 g+=M– b]lv ;Dd
cBfjlw sfd ePsf] cl3Nnf] landf r9]sf] xfn ePsf] sfd
s||=;+ sfdsf] laj/0f PsfO{ s}lkmot
kl/df0f b/ hDdf d"No kl/df0fhDdf d"Nokl/df0f hDdf d"No
1 Earth work in Excavation in site Development m3 3799.225 100.00 379922.50 - - 3799.23 379922.50
2 Earth work excavation in BM Soil on Foundation m3 2464.361 200.00 492872.20 - - 2464.36 492872.20
3 150mm thick stone soling with sand m3 197.248 2500.00 493120.00 - - 197.25 493120.00
4 75mm thick lean concrete (1:3:6) in foundation m3 100.915 4500.00 454117.50 - - 100.92 454117.50
5 P.C.C. for R.C.C(1:1.5:3) m3 425.278 6529.70 2776937.75 - - 425.28 2776937.75
6 Reinforcements works kg 75114.590 60.51 4545183.84 - - 75114.59 4545183.84
7 Form work m2 500.570 313.00 156678.41 - - 500.57 156678.41
8 Brick Masonary work (1:6) m3 56.824 4576.61 260061.28 - - 56.82 260061.28
TOTAL AMOUNT (without VAT) Rs. 9558893.48 - Rs. 9558893.48
pko'{Qm adf]lhd 7Ls 5 egL k|dfl0ft ug]{sf] ;xLM–
================= ================= =====================
cf]e/l;o/ O{lGhgLo/ 7]s]bf/sf] ;xL
of] lansf] hDdf -Eof6 afx]]s_ ? #REF!
cl3Nnf] e"QmfgL lanaf6 e"QmfgL ePsf] -E %}g
afFsL lbg' kg]{ -Eof6 afx]s_ #REF!
s6[L ug'{ kg]{ ?=M–
s_ k]ZsL–
v_ dfn;dfgsf] df]nM–
u_ d]zLg cf}hf/ axfnM–
3_ cfos/ !=%Ü M–
ª_ d"No clea[l4 s/ !# Ü M–
r_ w/f}6L %Ü M–
5_ cGo M–
v"b lbg' kg]{ -Eof6 ;d]t_ ?=M–
k]z ug]{sf] ;xLM– hfFr ug]{sf] ;xLM– :jLs[t ug]{sf] ;xLM–

hDdf ?= cIf]?kLM– sf] r]s g+= af6 k|fKt ePsf] egL ;xL ug]{ 7]s]bf/sf] ;xLM–
S.N. Items Unit Quantity Unit Rate Amount

S.N. Items Unit Quantity Unit Rate Amount


1 Earth work in Excavation in site Development m3 3799.225 0.00
2 Earth work excavation in BM Soil on Foundation m3 2533.707 0.00
3 Earth work filling in BM Soil on Foundation m3 3185.337 0.00
4 150mm thick stone soling with sand m3 516.920 75.00 38769.00
5 75mm thick lean concrete (1:3:6) in foundation m3 104.041 488.00 50772.01
6 P.C.C. for R.C.C(1:1.5:3) m3 1331.553 485.00 645803.21
7 Reinforcements works kg 302507.130 3.25 983148.17
8 Form work m2 9547.640 75.25 718459.91
9 Brick Masonary work ( 1:6 ) m3 885.299 388.00 343496.01
10 Brick Masonary work ( 1:4 ) m2 853.460 75.00 64009.50
11 P.C.C. for R.C.C(1:1:2) m3 618.653 485.00 300046.54
12 plastering M2 2500.00 60 150000.00

TOTAL 3294504.35

Estimated By:- Checked By:- Approved By:-


Department of Urban Development And Building Construction
DIVISION OFFICE
Surkhet
Name of work :- 50 Bed Hospital Construction Work F/Y-064 - 065
Place :- Birendranagar - 3 , Kalagaon , Surkhet

DETAILS OF MEASUREMENT ( 1st Bill )


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
1 Earth work in Excavation in site Development
1st Level 1 96.00 96.00 26.45 0.56 1429.569
2nd Level 1 96.00 96.00 20.05 0.51 990.309
3rd Level 1 96.00 96.00 7.20 0.20 140.659
4 th Level 1 96.00 96.00 22.00 0.59 1238.688
Total 3799.225 m3
2 Earth work excavation in BM Soil on Foundation
F1 9 2.60 23.40 2.60 1.725 104.949
F2 18 3.10 55.80 3.10 1.725 298.390
F3 12 3.60 43.20 3.60 1.725 268.272
F4 2 4.60 9.20 4.60 1.725 73.002
CF1 1 5.10 5.10 2.60 1.725 22.873
CF2 7 5.70 39.90 3.70 1.725 254.661
CF3 1 5.70 5.70 2.60 1.725 25.564
CF4 3 5.70 17.10 3.30 1.725 97.341
CF5 2 6.35 12.70 3.70 1.725 81.057
CF6 3 6.55 19.65 3.70 1.725 125.416
CF7 2 5.35 10.70 2.60 1.725 47.989
CF8 1 6.10 6.10 3.70 1.725 38.933
CF9 1 5.99 5.99 5.10 1.725 52.697
CF10 1 5.99 5.99 3.10 1.725 32.031
CF11 1 5.06 5.06 4.70 1.725 41.023
CF12 1 4.60 4.60 4.60 1.725 36.501
CF12 1 5.46 5.46 3.65 1.725 34.377
CF13 2 4.25 8.50 3.70 1.725 54.251
CF14 1 6.60 6.60 4.25 1.725 48.386
T1Area=27.153m2 1 27.15 27.15 1.725 46.830
T2Area=36.085 1 36.085 36.08 1.725 62.230
T3Area=34.92m2 1 34.92 34.92 1.725 60.230
T4Area=28.863m2 1 28.863 28.86 1.725 49.780
Earth work excavation in tie beam
Block 1
Grid 1-1 1 21.50 21.50 0.60 1.45 18.705
GRID2-2,3-3 2 19.15 38.30 0.60 1.45 33.321
Grid 4-4 1 21.55 21.55 0.60 1.45 18.748
Grid B,C,D,E 4 8.40 33.60 0.60 1.45 29.232
Grid F-F 1 9.25 9.25 0.60 1.45 8.047
Block2
Grid 1-1 1 25.09 25.09 0.60 1.45 21.828
Grid 2-2 1 9.70 9.70 0.60 1.45 8.439

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
Grid 3-3 1 7.39 7.39 0.60 1.45 6.429
Grid 4-4 1 15.84 15.84 0.60 1.45 13.780
Grid 4-4 1 17.59 17.59 0.60 1.45 15.303
Grid A,B 2 9.00 18.00 0.60 1.45 15.660
GridC-C 1 7.60 7.60 0.60 1.45 6.612
Grid D,E 2 6.80 13.60 0.60 1.45 11.832
Grid F,G,H 3 8.40 25.20 0.60 1.45 21.924
Grid I-I 1 8.90 8.90 0.60 1.45 7.743
Block 3
Grid 1-1 1 9.76 9.76 0.60 1.45 8.491
Grid 2-2 1 11.00 11.00 0.60 1.45 9.570
Grid 3-3 1 11.00 11.00 0.60 1.45 9.570
Grid 4-4 1 11.55 11.55 0.60 1.45 10.048
Grid A-A 1 9.15 9.15 0.60 1.45 7.960
Grid B-B 1 7.50 7.50 0.60 1.45 6.525
Grid C-C 1 7.50 7.50 0.60 1.45 6.525
Grid D-D 1 7.53 7.52 0.60 1.45 6.542
Block 4
Grid 1-1 1 13.59 13.59 0.60 1.45 11.823
Grid 2-2 1 12.54 12.54 0.60 1.45 10.909
Grid 3-3 1 12.54 12.54 0.60 1.45 10.909
Grid 4-4 1 13.54 13.54 0.60 1.45 11.779
Grid A-A 1 8.65 8.65 0.60 1.45 7.525
Grid B-B 1 8.65 8.65 0.60 1.45 7.525
Grid C-C 1 7.30 7.30 0.60 1.45 6.351
Grid D-D 1 7.30 7.30 0.60 1.45 6.351
Grid E-E 1 9.50 9.50 0.60 1.45 8.265
Block 5
Grid 1-1 1 8.40 8.39 0.60 1.45 7.299
Grid 2-2 1 7.75 7.75 0.60 1.45 6.742
Grid 3-3 1 7.75 7.74 0.60 1.45 6.733
Grid 4-4 1 15.86 15.85 0.60 1.45 13.789
Grid 5-5 1 6.60 6.59 0.60 1.45 5.733
Grid 6-6 1 8.05 8.04 0.60 1.45 6.994
Grid 7-7 1 8.05 8.04 0.60 1.45 6.994
Grid 8-8 1 6.40 6.39 0.60 1.45 5.559
Grid 9-9 1 7.90 7.89 0.60 1.45 6.864
Grid A-A 1 19.93 19.92 0.60 1.45 17.330
Grid B-B 1 16.70 16.70 0.60 1.45 14.529
Grid C-C 1 18.18 18.17 0.60 1.45 15.807
Grid D-D 1 10.28 10.27 0.60 1.45 8.934
Total 2464.361 m3
3 150mm thick stone soling with sand
Foundation F1 9 2.50 22.50 2.50 0.15 8.437
F2 18 3.00 54.00 3.00 0.15 24.300

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
F3 12 3.50 42.00 3.50 0.15 22.050
F4 2 4.50 9.00 4.50 0.15 6.075
CF1 1 5.00 5.00 2.50 0.15 1.875
CF2 7 5.60 39.20 3.60 0.15 21.168
CF3 1 5.60 5.60 2.50 0.15 2.100
CF4 3 5.60 16.80 3.20 0.15 8.064
CF5 2 6.25 12.50 3.60 0.15 6.750
CF6 3 6.45 19.35 3.60 0.15 10.449
CF8 1 6.00 6.00 3.60 0.15 3.240
CF9 1 5.89 5.89 5.00 0.15 4.417
CF10 1 5.89 5.89 3.00 0.15 2.650
CF11 1 4.96 4.96 4.60 0.15 3.422
CF12 1 4.50 4.50 4.50 0.15 3.037
CF12 1 5.36 5.36 3.55 0.15 2.854
CF13 2 4.15 8.30 3.60 0.15 4.482
CF14 1 6.43 6.42 4.15 0.15 3.996
T1Area=27.153m2 1 27.045 27.04 0.15 4.050
T2Area=36.085 1 33.87 33.87 0.15 5.080
T3Area=34.92m2 1 33.08 33.08 0.15 4.960
T4Area=28.863m2 1 24.00 24.00 0.15 3.600
Tie beams
Grid A-A 1 9.50 9.50 0.45 0.15 0.641
Grid B-B 1 10.40 10.40 0.45 0.15 0.702
Grid C-C 1 10.40 10.40 0.45 0.15 0.702
Grid D-D 1 9.13 9.12 0.45 0.15 0.615
Grid E-E 1 10.40 10.40 0.45 0.15 0.702
Grid F-F 1 7.48 7.47 0.45 0.15 0.504
Grid G-G 1 10.40 10.40 0.45 0.15 0.702
Grid H-H 1 7.48 7.47 0.45 0.15 0.504
Grid I-I 1 8.85 8.85 0.45 0.15 0.597
Grid J-J 1 7.60 7.60 0.45 0.15 0.513
Grid K-K 1 7.48 7.47 0.45 0.15 0.504
Grid L-L 1 26.73 26.72 0.45 0.15 1.803
Grid M-M 1 23.73 23.72 0.45 0.15 1.601
Grid N-N 1 25.23 25.22 0.45 0.15 1.702
Grid O-O 1 12.45 12.45 0.45 0.15 0.840
Grid P-P 1 12.88 12.87 0.45 0.15 0.868
Grid Q-Q 1 19.85 19.85 0.45 0.15 1.339
Grid R-R 1 18.50 18.50 0.45 0.15 1.248
Grid S-S 1 18.50 18.50 0.45 0.15 1.248
Grid T-T 1 21.20 21.20 0.45 0.15 1.431
Grid 17-17 1 7.90 7.90 0.45 0.15 0.533
Grid 16-16 1 6.40 6.40 0.45 0.15 0.432
Grid 15-15 1 8.30 8.30 0.45 0.15 0.560
Grid 14-14 1 8.30 8.30 0.45 0.15 0.560

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
Grid 13-13 1 31.39 31.38 0.45 0.15 2.118
Grid 12-12 1 12.46 12.46 0.45 0.15 0.841
Grid 11-11 1 18.65 18.65 0.45 0.15 1.258
Grid 10-10 1 31.99 31.98 0.45 0.15 2.158
Grid 9-9 1 19.45 19.44 0.45 0.15 1.312
Grid 8-8 1 22.89 22.88 0.45 0.15 1.544
Grid 7-7 1 30.14 30.13 0.45 0.15 2.033
Grid 6-6 1 12.90 12.89 0.45 0.15 0.870
Grid 5-5 1 12.90 12.89 0.45 0.15 0.870
Grid 4-4 1 29.19 29.19 0.45 0.15 1.970
Grid 3-3 1 29.19 29.19 0.45 0.15 1.970
Grid 2-2 1 14.02 14.02 0.45 0.15 0.946
Grid 1-1 1 21.50 21.50 0.45 0.15 1.451
Total 197.248 m3
4 75mm thick lean concrete (1:3:6) in foundation
F1 9 2.50 22.50 2.50 0.075 4.218
F2 18 3.00 54.00 3.00 0.075 12.150
F3 12 3.50 42.00 3.50 0.075 11.025
F4 2 4.50 9.00 4.50 0.075 3.037
CF1 1 5.00 5.00 2.50 0.075 0.937
CF2 7 5.60 39.20 3.60 0.075 10.584
CF3 1 5.60 5.60 2.50 0.075 1.050
CF4 3 5.60 16.80 3.20 0.075 4.032
CF5 2 6.25 12.50 3.60 0.075 3.375
CF6 3 6.45 19.35 3.60 0.075 5.224
CF7 2 5.25 10.50 2.50 0.075 1.968
CF8 1 6.00 6.00 3.60 0.075 1.620
CF9 1 5.89 5.89 5.00 0.075 2.208
CF10 1 5.89 5.89 3.00 0.075 1.325
CF11 1 4.96 4.96 4.60 0.075 1.711
CF12 1 4.50 4.50 4.50 0.075 1.518
CF12 1 5.36 5.36 3.55 0.075 1.427
CF13 2 4.15 8.30 3.60 0.075 2.241
CF14 1 6.43 6.42 4.15 0.075 1.998
T1Area=27.153m2 1 27.05 27.04 0.075 2.020
T2Area=36.085 1 33.87 33.87 0.075 2.540
T3Area=34.92m2 1 33.08 33.08 0.075 2.480
T4Area=28.863m2 1 24.00 24.00 0.075 1.800
For foundation tie beam
Grid A-A 1 9.50 9.50 0.45 0.075 0.320
Grid B-B 1 10.40 10.40 0.45 0.075 0.351
Grid C-C 1 10.40 10.40 0.45 0.075 0.351
Grid D-D 1 9.13 9.12 0.45 0.075 0.307
Grid E-E 1 10.40 10.40 0.45 0.075 0.351
Grid F-F 1 7.48 7.47 0.45 0.075 0.252

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
Grid G-G 1 10.40 10.40 0.45 0.075 0.351
Grid H-H 1 7.48 7.47 0.45 0.075 0.252
Grid I-I 1 8.85 8.85 0.45 0.075 0.298
Grid J-J 1 7.60 7.60 0.45 0.075 0.256
Grid K-K 1 7.48 7.47 0.45 0.075 0.252
Grid L-L 1 26.73 26.72 0.45 0.075 0.901
Grid M-M 1 23.73 23.72 0.45 0.075 0.800
Grid N-N 1 25.23 25.22 0.45 0.075 0.851
Grid O-O 1 12.45 12.45 0.45 0.075 0.420
Grid P-P 1 12.88 12.87 0.45 0.075 0.434
Grid Q-Q 1 19.85 19.85 0.45 0.075 0.669
Grid R-R 1 18.50 18.50 0.45 0.075 0.624
Grid S-S 1 18.50 18.50 0.45 0.075 0.624
Grid T-T 1 21.20 21.20 0.45 0.075 0.715
Grid 17-17 1 7.90 7.90 0.45 0.075 0.266
Grid 16-16 1 6.40 6.40 0.45 0.075 0.216
Grid 15-15 1 8.30 8.30 0.45 0.075 0.280
Grid 14-14 1 8.30 8.30 0.45 0.075 0.280
Grid 13-13 1 31.39 31.38 0.45 0.075 1.059
Grid 12-12 1 12.46 12.46 0.45 0.075 0.420
Grid 11-11 1 18.65 18.65 0.45 0.075 0.629
Grid 10-10 1 31.99 31.98 0.45 0.075 1.079
Grid 9-9 1 19.45 19.44 0.45 0.075 0.656
Grid 8-8 1 22.89 22.88 0.45 0.075 0.772
Grid 7-7 1 30.14 30.13 0.45 0.075 1.016
Grid 6-6 1 12.90 12.89 0.45 0.075 0.435
Grid 5-5 1 22.90 22.89 0.45 0.075 0.772
Grid 4-4 1 29.19 29.19 0.45 0.075 0.985
Grid 3-3 1 29.19 29.19 0.45 0.075 0.985
Grid 2-2 1 14.02 14.02 0.45 0.075 0.473
Grid 1-1 1 21.50 21.50 0.45 0.075 0.725
Total 100.915 m3
5 P.C.C. for R.C.C(1:1.5:3)
F1,7 Nos. pillars no. 313,301,119,101,106,205,237
Rec. Portion 7 2.50 17.50 2.50 0.20 8.750
Trap.Portion 7 21.75 152.25 0.0667 10.150
F2 ,13nos. Pillrs no. 102,103,104,105,120,121,122, 13 3.00 39.00 3.00 0.20 23.400
123,202,203,204,527,000 13 2.50 32.50 32.50
F3,8nos,pillars no,
526,524,528,315,314,302,303,227
Rec. Portion 8 3.50 28.00 3.50 0.30 29.400
Trap.Portion 8 3.423 27.38 27.380
F4 ,2Nos.pillars no ,525,514
Rec. Portion 2 4.500 9.00 4.50 0.30 12.150
Trap.Portion 2 7.592 15.18 15.180
CF1,4th level

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
Rec. Portion 1 5.00 5.00 2.50 0.20 2.500
Trap.Portion 1 2.36 2.360 2.360
CF2,5Nos. 4th level
Rec. Portion 5 5.60 28.00 3.60 0.30 30.240
Trap.Portion 5 5.29 26.450 26.450
CF3,2nd block ,4th level
Rec. Portion 1 5.60 5.60 2.50 0.20 2.800
Trap.Portion 1 2.63 2.62 2.620
CF4, 3Nos.pillars no.305,219,216
Rec. Portion 3 5.60 16.80 3.20 0.20 10.752
Trap.Portion 3 3.78 11.35 11.350
CF5,2Nos.3rd block
Rec. Portion 2 6.25 12.50 3.60 0.30 13.500
Trap.Portion 2 5.88 11.75 11.750
CF6,5th block
Rec. Portion 1 6.45 6.45 3.60 0.30 6.966
Trap.Portion 1 6.06 6.05 6.050
CF7,2nos.5th block
Rec. Portion 2 5.25 10.50 2.50 0.20 5.250
Trap.Portion 2 2.47 4.94 4.940
CF9, 4Th level
Rec. Portion 1 5.00 5.00 6.04 0.60 18.120
CF10,1Nos. 4th level
Rec. Portion 1 6.04 6.04 3.00 0.20 3.624
Trap.Portion 1 3.82 3.82 3.820
CF11,1 Nos. 4Th level
Rec. Portion 1 4.60 4.60 4.96 0.60 13.689
CF12 ,Change to F4 3rd level
Rec. Portion 1 4.50 4.50 4.50 0.30 6.075
Trap.Portion 1 7.59 7.59 7.590
CF13,1Nos 2nd level
Rec. Portion 1 4.15 4.15 3.60 0.30 4.482
Trap.Portion 1 4.31 4.30 4.300
CF14,1Nos. 2nd level
Rec. Portion 1 6.50 6.50 4.15 0.30 8.092
Trap.Portion 1 5.70 5.70 5.70
T1 Area=26.71m2 1 26.71 26.71 0.60 16.020
Foundation combined beams
CF7 1 5.25 5.25 0.35 0.25 0.459
CF6 1 6.45 6.45 0.60 0.20 0.774
CF5 2 6.25 12.50 0.60 0.20 1.500
CF4 1 5.60 5.60 0.60 0.40 1.344
Foundation tie beams for 1st level 0.000
Grid 17-17,16-16 2 13.20 26.40 0.35 0.45 4.158
Grid 15-15,14-14 2 13.20 26.40 0.35 0.45 4.158

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
Grid L-L 1 12.30 12.30 0.35 0.45 1.937
Grid M-M 1 11.77 11.77 0.35 0.45 1.853
Grid N-N 1 13.20 13.20 0.35 0.45 2.079
3rd block
Grid 13-13 1 19.80 19.80 0.35 0.45 3.118
Grid 11-11 1 19.80 19.80 0.35 0.45 3.118
Grid 10-10 1 19.80 19.80 0.35 0.45 3.118
Grid 9-9 1 19.80 19.80 0.35 0.45 3.118
Grid D-D 1 11.02 11.02 0.35 0.45 1.735
Grird F-F 1 10.37 10.37 0.35 0.45 1.633
Grid H-H 1 10.37 10.37 0.35 0.45 1.633
Grid K-K 1 10.13 10.12 0.35 0.45 1.593
Total 425.278 m3
6 Reinforcements works
Basements bars
F1,7Nos.2*20 12mmdia rods 280 2.58 721.28 0.89 641.930
F2,13Nos.2*30,12mmdia.rods 780 3.08 2399.28 0.89 2135.350
F3,8Nos.2*28,16mmdia.rods 448 3.65 1634.30 1.58 2582.190
F4, 2Nos.,2*45,16mmdia.rods 180 4.65 836.64 1.58 1321.890
CF1,1Nos.12mmdia.rods
One ways 50 2.58 128.80 0.89 114.630
Other ways 25 5.08 126.90 0.89 112.940
CF2,5Nos.,16mmdia.rods
One ways 145 5.75 833.46 1.58 1316.860
Other ways 225 3.75 843.30 1.58 1332.410
CF3,1Nos12mmdia.rods
One ways 20 5.68 113.52 0.89 101.030
Other ways 47 2.58 121.07 0.89 107.750
CF4,3Nos.16mmdia.rods
One ways 78 5.75 448.34 1.58 708.370
Other ways 135 3.35 451.98 1.58 714.120
CF5,2Nos. 16mmdia. Rods
One ways 58 6.40 371.08 1.58 586.300
Other ways 100 3.75 374.78 1.58 592.150
CF6,1Nos.16mmdia.rods
One ways 29 6.60 191.34 1.58 302.310
Other ways 59 3.75 221.13 1.58 349.380
CF7,2Nos,12mmdia.rods
One ways 40 5.33 213.04 0.89 189.600
Other ways 84 5.58 468.38 0.89 416.850
CF9,2Nos.12mmdia.rods
One ways 80 6.12 489.28 0.89 435.450
Other ways 100 5.08 507.60 0.89 451.760
CF10,1Nos. 16mmdia.rods
One ways 24 6.19 148.51 1.58 234.640

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
Other ways 48 3.15 151.10 1.58 238.730
CF11,2Nos.16mmdia.rods
One ways 74 5.11 377.99 1.58 597.220
Other ways 80 4.75 379.84 1.58 600.140
Chairs rods 16mmdia.rods
5 4.00 20.00 1.58 31.600
4 3.00 12.00 1.58 18.960
3 2.50 7.50 1.58 11.850
T1,1Nos.16mmdia .rods
One ways Rectangle por. 20 5.40 107.96 1.58 170.570
Triangle por. 1 110.64 1.58 174.810
Other ways Rectangle por. 20 6.15 123.00 1.58 194.340
Triangle por. 1 95.55 1.58 150.960
Foundation only for basements rods
F3,4Nos.16mmdia rods 224 3.65 817.15 1.58 1291.090
CF6,2Nos.16mmdia .rods
One ways 58 6.60 382.68 1.58 604.630
Other ways 102 3.75 382.29 1.58 604.010
F2,4Nos.12mmdia.rods 240 3.08 738.24 0.89 657.030
For column 1st level ,pillars
no.527,528,529,524,525,526,521,all are in C5
C5,7Nos.32mmdia.rods
4*7,32mmdia.rods 28 7.87 220.36 6.31 1390.470
4*7,25mmdia.rods 28 5.45 152.60 3.85 587.510
4*7,25mmdia.rods 28 5.35 149.80 3.85 576.730
Pillars no.517,522 are C3
2*4,25mmdia.rods 8 7.87 62.96 3.85 242.390
2*4,25mmdia.rods 8 7.80 62.40 3.85 240.240
2*4,25mmdia.rods 8 7.64 61.12 3.85 235.310
Pillars No.522are C2
4 Nos, 25mm dia. Rods 4 7.87 31.48 3.85 121.190
4 Nos, 25mm dia. Rods 4 7.80 31.20 3.85 120.120
4 Nos, 20mm dia. Rods 4 7.65 30.60 2.46 75.270
10Nos.of Pillars Stirrups 8mmdia.rods
Large 400 2.20 880.00 0.39 343.200
Small 800 1.55 1240.00 0.39 483.600

2nd level Pillars no.314,315,513 are in C1

4*3,25mmdia.rods 12 8.40 100.80 3.85 388.080


4*3,20mmdia.rods 12 8.25 99.00 2.46 243.540
4*3,20mmdia.rods 12 8.00 96.00 2.46 236.160
Pillars no.313,316 ,are in C2
2*4,25mmdia.rods 8 8.40 67.20 3.85 258.720
2*4,25mmdia.rods 8 8.25 66.00 3.85 254.100
2*4,20mmdia.rods 8 8.00 64.00 2.46 157.440
C3,8nos.Pillars no.
309,310,311,312,305,306,307,308

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
8*4,25mmdia.rods 32 8.35 267.20 3.85 1028.720
8*4,25mmdia.rods 32 8.25 264.00 3.85 1016.400
8*4,25mmdia.rods 32 8.05 257.60 3.85 991.760
C5,2nos,pillars no.505,509
4*2,32mmdia.rods 8 8.35 66.80 6.31 421.500
4*2,25 mmdia.rods 8 8.20 65.60 3.85 252.560
4*2,25mmdia.rods 8 8.10 64.80 3.85 249.480
15Nos. Of pillar Stirrups
Large 675 2.20 1485.00 0.39 579.150
Small 1350 1.55 2092.50 0.39 816.070
Pillars no.514 are in C1
4Nos.25mm dia.rods 4 8.40 33.60 3.85 129.360
4Nos.20mm dia.rods 4 8.25 33.00 2.46 81.180
4Nos.20mm dia.rods 4 8.00 32.00 2.46 78.720
Pillars no.523,520 are in C5
2*4,32 mmdia.rods 8 8.40 67.20 6.31 424.030
2*4,25mmdia.rods 8 8.25 66.00 3.85 254.100
2*4,25mmdia.rods 8 8.00 64.00 3.85 246.400
Pillars no.416, are inC2
1*4,25mmdia.rods 4 8.40 33.60 3.85 129.360
1*4,25mmdia.rods 4 8.25 33.00 3.85 127.050
1*4,20mmdia.rods 4 8.00 32.00 2.46 78.720
Pillars no.515 are in C3
1*4,25mmdia.rods 4 8.40 33.60 3.85 129.360
1*4,25mmdia.rods 4 8.30 33.20 3.85 127.820
1*4,25mmdia.rods 4 8.15 32.60 3.85 125.510
5 Nos. of Pillars Stirrups
Large 225 2.20 495.00 0.39 193.050
Small 450 1.55 697.50 0.39 272.020
3rd level Pillars no,302,303 are in C1
2*4Nos.25mm dia.rods 8 8.85 70.80 3.85 272.580
2*4Nos.20mm dia.rods 8 8.70 69.60 2.46 171.210
2*4Nos.20mm dia.rods 8 8.65 69.20 2.46 170.230
Pillars no. 301,304,230 are in C2
3*4,25mmdia.rods 12 8.85 106.20 3.85 408.870
3*4,25mmdia.rods 12 8.70 104.40 3.85 401.940
3*4,20mmdia.rods 12 8.65 103.80 2.46 255.340
Pillars no. Are in C3
1*4,25mmdia.rods 4 8.80 35.20 3.85 135.520
1*4,25mmdia.rods 4 8.75 35.00 3.85 134.750
1*4,25mmdia.rods 4 8.65 34.60 3.85 133.210
6Nos.of Pillars Stirrups
Large 300 2.20 660.00 0.39 257.400
Small 600 1.55 930.00 0.39 362.700

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
4th level Pillars
no.120,121,122,123,102,103,104,105,210,211,207,2
13,209,214,201,203 ,are in C1
16*4Nos.25mm dia.rods 64 9.14 584.96 3.85 2252.090
16*4Nos.20mm dia.rods 64 9.00 576.00 2.46 1416.960
16*4Nos.20mm dia.rods 64 8.75 560.00 2.46 1377.600
Pillars
no.119,124,114,115,116,117,108,109,110,111,206,1
01,106,are in C2
13*4,25mmdia.rods 52 9.14 475.28 3.85 1829.820
13*4,25mmdia.rods 52 9.00 468.00 3.85 1801.800
13*4,20mmdia.rods 52 8.75 455.00 2.46 1119.300
Pillars no.113,117,118,112,204,205,223,218 are in
C3
8*4,25mmdia.rods 32 9.12 291.84 3.85 1123.580
8*4,25mmdia.rods 32 8.90 284.80 3.85 1096.480
8*4,25mmdia.rods 32 8.75 280.00 3.85 1078.000
Pillars no.225,226,202,212,208,227,221,216 are in
C4
8*4,20mm dia. Rods 32 9.15 292.80 2.46 720.280
8*4,20mm dia. Rods 32 9.00 288.00 2.46 708.480
8*4,20mm dia. Rods 32 8.90 284.80 2.46 700.600
Pillars no.415,410,237,224,219 are in C5
4*5,32mmdia.rods 20 8.87 177.40 6.31 1119.390
4*5,25 mmdia.rods 20 8.50 170.00 3.85 654.500
4*5,25mmdia.rods 20 7.65 153.00 3.85 589.050
50Nos. Of pillar Stirrups
Large 2500 2.20 5500.00 0.39 2145.000
Small 5000 1.55 7750.00 0.39 3022.500
Reinforcements for combined pillars beams
For CF1,Combined pillars (107 to 109)
20mmdia upand down bent bar 8 6.32 50.56 2.46 124.370
20mm dia.straight bars 2 4.86 9.72 2.46 23.910
16mmdia.sides bars 2 2 4.86 9.72 1.58 15.350
Beam stirrups
Large 39 2.38 92.82 0.39 36.190
Small 39 1.93 75.34 0.39 29.380
CF2,combined pillars (108to109,110to111)
8*5,25mmdia upand down bent bar 40 7.32 292.80 3.85 1127.280
25mmdia.2*5,80cm overlap 10 6.26 62.60 3.85 241.010
16mmdia.sides bars 2 10 6.06 60.60 1.58 225.000
Beam stirrups
Large 225 2.98 670.50 0.39 261.490
Small 225 2.43 546.75 0.39 213.230
CF3,combined pillars(208 to212)
20mmdia.up and down rods 8 6.92 55.36 2.46 136.180
20mmdia.60cm overlap straighr bars 4 6.06 24.24 2.46 59.630
16mmdia. Sides bars 2 5.46 10.92 1.58 17.250

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
20mmdia.pin rods 6 0.60 3.60 2.46 8.850
Beam stirrups
Large 45 2.38 107.10 0.39 41.760
Small 45 1.95 87.75 0.39 34.220
CF4,3nos of Combined beams, pillars no,219,309,216
3*8,25mmdia .upand down bars 24 7.32 175.68 3.85 676.360
3*2,25mmdia,straight 80cm overlap 6 6.26 37.56 3.85 144.600
3*2,16mmdia.sides 60cm overlap 6 6.06 36.36 1.58 57.440
Beam stirrups
Large 135 2.98 402.30 0.39 156.890
Small 135 2.43 328.05 0.39 127.930
CF5,2nos.of combined beams pillars no.306,307
2*10,25mmdia.up and down bent bars 20 7.97 159.40 3.85 613.690
2*5,25mmdia straight 90cm overlap 10 7.01 70.10 3.85 269.880
2*2,16mmdia .sides 70cm overlap 4 6.81 27.24 1.58 43.030
20mmdia.pin rods 12 0.50 6.00 2.46 14.760
Beam stirrups
Large 102 2.98 303.96 0.39 118.540
Small 102 2.58 263.16 0.39 102.630
CF6,1nos of combined beams pillars no.518
25mmdia.upand down bent bars 12 8.17 98.04 3.85 377.450
25mmdia.straight 70cm overlap 6 7.01 42.06 3.85 161.930
16mmdia sides bars 2 6.31 12.62 1.58 19.930
Beam stirrups
Large 53 3.18 168.54 0.39 65.730
Small 53 2.70 143.10 0.39 55.800
Very small 53 2.33 123.49 0.39 48.160
CF7,2nos.of combined beams pillars no 410,517
2*8 20mmdia.up and down bars 16 5.57 89.12 2.46 219.230
2*6,20mmdia,70cm overlap 12 5.81 69.72 2.46 171.510
16mmdia.sides bars70cm overlap 4 5.81 23.24 1.58 36.710
20mmdia .pin rods 12 0.60 7.20 2.46 17.710
Beam stirrups
Large 82 2.38 195.16 0.39 76.110
Small 82 1.95 160.06 0.39 62.420
CF9,1nos.of combined beams pillars
no.118to112,210to206,211to207
3*8,20mmdia.upand down bent bars 24 6.32 151.68 2.46 373.130
3*6,20mmdiastraight 70cm overlap 18 5.56 100.08 2.46 246.190
3*2,16mmdia sides bars 60cm overlap 6 5.46 32.76 1.58 51.760
3*6,20mmdia pin rods 18 0.50 9.00 2.46 22.140
Beam stirrups
Large 117 2.38 278.46 0.39 108.590
Small 117 1.95 228.15 0.39 88.970
pillars no.118to211,112to207
2*8,20mmdia.up and down bars 16 7.36 117.76 2.46 289.680

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
2*6,20mmdia.straight 80cm overlap 12 6.70 80.40 2.46 197.780
2*2,16mmdia.sides bar 60cm overlap 4 6.50 26.00 1.58 41.080
20mmdia.pin rods 12 0.50 6.00 2.46 14.760
12mmdia.chairs pin rods 15 3.55 53.25 0.89 47.390
Beam stirrups
Large 88 2.30 202.40 0.39 78.930
Small 88 1.95 171.60 0.39 66.920
CF10, 1nos.combined beams pillars no.225
8nos.of 25mmdia upand down bent bars 8 7.76 62.08 3.85 239.000
6no.25mmdia straight bars 70cm overlap 6 6.60 39.60 3.85 152.460
2nos.16mmdia.sides bars 65cm overlap 2 6.55 13.10 1.58 20.690
25mmdia.pin rods 6 0.50 3.00 3.85 11.550
Beam stirrups
Large 44 2.38 104.72 0.39 40.840
Small 44 1.95 85.80 0.39 33.460

CF11,1nos.of combined beams pillars


no.213to214
8no.25mmdia.up and down bent bars75cm overlap 8 7.53 60.24 3.85 231.920
2no.25mmdia straight bars 80cm overlap 2 5.62 11.24 3.85 43.270
2no.16mmdia.sides bars 70cm overap 2 5.52 11.04 1.58 17.440
Beam stirrups
Large 39 2.98 116.22 0.39 45.320
Small 39 2.43 94.77 0.39 36.960
combined beams pillars no.209to201
8no.25mmdia upand down bent bars 1.6m overlaprs 8 6.80 54.40 3.85 209.440
2no.25mmdia straight bars1.6m overlap 2 6.80 13.60 3.85 52.360
2no.16mmdia sides bar1.5m overlap 2 6.70 13.40 1.58 21.170
Beam stirrups
Large 56 2.98 166.88 0.39 65.080
Small 56 2.43 136.08 0.39 53.070
combined beams pillars no.214to201
8no.25mmdia upand down bent bars 1.7m overlaprs 8 7.60 60.80 3.85 234.080
2no.25mmdia straight bars1.6m overlap 2 6.10 12.20 3.85 46.970
2no.16mmdia sides bar1.5m overlap 2 6.00 12.00 1.58 18.960
Beam stirrups
Large 56 2.98 166.88 0.39 65.080
Small 56 2.43 136.08 0.39 53.070
CF14,1nos.combined beams pillars no .
312to308,509to505
2*8,25mmdiaupand down bent bars 80cm overlap 16 9.02 144.32 3.85 555.630
2*4,25mmdia.st. bars 80cm overlap 8 7.16 57.28 3.85 220.520
2*2,16mmdia.sides bar 60cm overlap 4 6.96 27.84 1.58 43.980
25mmdia.pin rods 12 0.50 6.00 3.85 23.100
Beam stirrups
Large 108 2.98 321.84 0.39 125.510
Small 108 2.43 262.44 0.39 102.350
T1,combined beams pillars no.519to416

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
8no.25mmdia.up and down bent bars75cm overlap 8 8.07 64.56 3.85 248.550
6no.25mmdia straight bars 70cm overlap 6 6.56 39.36 3.85 151.530
2no.16mmdia sides bar60cm overlap 2 6.46 12.92 1.58 20.410
20mmdia pin rods 8 0.50 4.00 2.46 9.840
Beam stirrups
Large 44 2.58 113.52 0.39 44.270
Small 44 2.03 89.32 0.39 34.830
Pillarsno.523to519 0.00
8no.25mmdia.up and down bent bars80cm overlap 8 7.37 58.96 3.85 226.990
6no.25mmdia straight bars 70cm overlap 6 5.81 34.86 3.85 134.210
2no.16mmdia sides bar60cm overlap 2 5.71 11.42 1.58 18.040
25mmdia pin rods 8 0.50 4.00 3.85 15.400
Beam stirrups
Large 42 2.58 108.36 0.39 42.260
Small 42 2.03 85.26 0.39 33.250
Pillars no.523to416
8no.25mmdia.up and down bent bars 80cm overlap 8 6.60 52.80 3.85 203.280
6no.25mmdia straight bars 80cm overlap 6 6.40 38.40 3.85 147.840
2no.16mmdia sides bars70cm overlap 2 6.20 12.40 1.58 19.590
25mmdiapin rods 6 0.50 3.00 3.85 11.550
Beam stirrups
Large 45 2.58 116.10 0.39 45.270
Small 45 2.03 91.35 0.39 35.620
Reinforcements for tie beams 16mmdia.bars ,1st
level
Grid 17-17
upper bars 3 27.74 83.22 1.58 131.480
lower bars 3 28.40 85.20 1.58 134.610
Grid 16-16
upper bars 3 16.69 50.07 1.58 79.110
lower bars 3 17.75 53.25 1.58 84.130
Grid 15-15
upper bars 3 18.11 54.33 1.58 85.840
lower bars 3 18.90 56.70 1.58 89.580
Grid 14-14
upper bars 3 12.21 36.63 1.58 57.870
lower bars 3 12.40 37.20 1.58 58.770
Grid L-Lpillars no,527to517
uppers bars 3 21.23 63.69 1.58 100.630
Lower bars 3 21.40 64.20 1.58 101.430
Grid M-M
upper bars 3 20.14 60.42 1.58 95.460
lower bars 3 20.15 60.45 1.58 95.510
Grid N-N
upper bars 3 15.29 45.87 1.58 72.470

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
lower bars 3 15.92 47.76 1.58 75.460
Stirrups for 1st level tie beams 498 1.58 786.84 0.39 306.860
Reinforcements for tie beams 16mmdia.bars ,2nd
level
Grid D-D
upper bars 3 19.02 57.06 1.58 90.150
lower bars 3 19.15 57.45 1.58 90.770
Grid E-E
upper bars 3 19.40 58.20 1.58 91.950
lower bars 3 19.70 59.10 1.58 93.370
GridH-H,K-K
upper bars 6 19.25 115.50 1.58 182.490
lower bars 6 19.70 118.20 1.58 186.750
Grid 13-13,11-11,10-10,9-9
upper bars 12 24.99 299.88 1.58 473.810
lower bars 12 25.44 305.28 1.58 482.340
Stirrups 856 1.58 1352.48 0.39 527.460
Total 75114.590 kg
7 Form work
Base F1,9NO*4 36 2.50 90.00 0.075 6.750
F2,18No.*4 72 3.00 216.00 0.075 16.200
F3,12No.*4 48 3.50 168.00 0.075 12.600
F4,2No.*4 8 4.50 36.00 0.075 2.700
CF1 1 15.00 15.00 0.075 1.120
CF2,7No. 7 18.40 128.80 0.075 9.660
CF3 1 16.20 16.20 0.075 1.210
CF4,3N0. 3 17.60 52.80 0.075 3.960
CF5,2No. 2 19.70 39.40 0.075 2.950
CF6,3No. 3 20.10 60.30 0.075 4.520
CF7,2No. 2 15.50 31.00 0.075 2.320
CF8 1 19.20 19.20 0.075 1.440
CF9 1 22.08 22.08 0.075 1.650
CF10 1 18.08 18.08 0.075 1.350
CF11 1 19.12 19.12 0.075 1.430
CF12 1 18.00 18.00 0.075 1.350
CF12 1 18.12 18.12 0.075 1.350
CF13 2 15.50 31.00 0.075 2.320
CF14 1 21.30 21.30 0.075 1.590
T1 Peri. =20.708m 1 20.71 20.70 0.075 1.550
T2Peri.=23.11m 1 23.11 23.11 0.075 1.730
T3Peri=23.07m 1 23.07 23.07 0.075 1.730
T4Peri=21.06m 1 21.06 21.06 0.075 1.570
Form work for R.C.C.in foundation
F1,6NO*4 24 2.50 60.00 0.20 12.000
F2,13No.*4 52 3.00 156.00 0.20 31.200
F3,8No.*4 32 3.50 112.00 0.30 33.600

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
F4,2No.*4 8 4.50 36.00 0.30 10.800
CF1 1 15.00 15.00 0.20 3.000
CF2,4No. 4 18.40 73.60 0.30 22.080
CF3 1 16.20 16.20 0.20 3.240
CF4,3N0. 3 17.60 52.80 0.20 10.560
CF5,2No. 2 19.70 39.40 0.30 11.820
CF6,1No. 1 20.10 20.10 0.30 6.030
CF7,2No. 2 15.50 31.00 0.20 6.200
CF8
CF9 1 22.08 22.08 0.60 13.240
CF10 1 18.08 18.08 0.20 3.610
CF11 1 19.12 19.12 0.60 11.470
CF12 Change to F4 1 18.00 18.00 0.30 5.400
CF12 1
CF13 1 15.50 15.50 0.30 4.650
CF14 1 21.30 21.30 0.30 6.390
T1 Peri. =20.708m 1 20.71 20.70 0.30 6.210
For foundation tie beam 1st level 0.00 0.30 0.000
Grid 17-17 2 13.20 26.40 0.45 11.880
Grid 16-16 2 13.20 26.40 0.45 11.880
Grid 15-15 2 13.20 26.40 0.45 11.880
Grid 14-14 2 13.20 26.40 0.45 11.880
Grid L-L 2 15.45 30.90 0.45 13.900
Grid M-M 2 15.45 30.90 0.45 13.900
Grid N-N 2 15.45 30.90 0.45 13.900
2nd level Grid 13-13 2 19.80 39.60 0.45 17.820
Grid 11-11 2 19.80 39.60 0.45 17.820
Grid 10-10 2 19.80 39.60 0.45 17.820
Grid 9-9 2 19.80 39.60 0.45 17.820
Grid D-D 2 15.43 30.85 0.45 13.880
Grid F-F 2 15.43 30.85 0.45 13.880
Grid H-h 2 15.43 30.86 0.45 13.880
Grid K-K 2 15.43 30.85 0.45 13.880
Total 500.570 m2
8 Brick Masonary work (1:6)
Pillars No.527
S. Side Re. Por. 1 0.30 0.30 0.35 0.49 0.051
Tra. Por. 1 0.13 0.12 0.49 0.050
E Side Tra. Por. 1 0.19 0.19 0.48 0.090
Pillars No.528 1
E Side Tra. Por. 1 0.22 0.21 0.50 0.100
W. Side Tra. Por. 1 0.23 0.22 0.47 0.100
S. Side Tra. Por. 1 0.28 0.28 0.48 0.130
Pillars No.529
S. Side Tra. Por. 1 0.20 0.20 0.45 0.090

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
W. Side Tra. Por. 1 0.20 0.20 0.48 0.090
Pillars No.526 0.000
S. Side Tra. Por. 1 0.18 0.17 0.45 0.070
W. Side Tra. Por. 1 0.20 0.19 0.45 0.080
N. Side Tra. Por. 1 0.19 0.19 0.48 0.090
Pillars No.525
S&N. Side Tra. Por. 2 0.32 0.63 0.45 0.280
W. Side Tra. Por. 1 0.29 0.28 0.42 0.110
E. Side Tra. Por. 1 0.33 0.32 0.42 0.130
Pillars No.524
N. Side Tra. Por. 1 0.22 0.22 0.44 0.090
E. Side Tra. Por. 1 0.11 0.11 0.47 0.050
E. Side Rec.. Por. 1 0.81 0.81 0.35 0.47 0.133
S. Side Rec.. Por. 1 0.56 0.56 0.35 0.42 0.082
S. Side Tra. Por. 1 0.14 0.14 0.42 0.050
Pillars No521&.517
E. Side Tra. Por. 2 0.18 0.35 0.48 0.160
E. Side Rec.. Por. 2 0.20 0.40 0.10 0.35 0.014
Pillars No522&.518
Tra. Por. 4 0.25 0.98 0.47 0.460
Re. Por. 4 0.56 2.24 0.35 0.08 0.062
Pillars No.313
E. Side Rec.. Por. 1 0.95 0.95 0.35 0.35 0.116
S. Side Rec.. Por. 1 1.10 1.10 0.35 0.25 0.096
Pillars No.314
E. Side Rec.. Por. 1 1.40 1.40 0.35 0.25 0.122
W. side Rec. Por. 1 1.50 1.50 0.35 0.30 0.157
S. Side Rec.. Por. 1 1.35 1.35 0.35 0.25 0.118
Pillars No.315
E. Side Tra. Por. 1 0.21 0.21 0.35 0.070
W. Side Tra. Por. 1 0.25 0.24 0.35 0.080
S. Side Tra. Por. 1 0.18 0.18 0.35 0.060
Pillars No.316
W. side Rec. Por. 1 2.10 2.10 0.35 0.30 0.220
S. Side Rec.. Por. 2 2.10 4.20 0.35 0.30 0.441
Pillars No.309&305
E. Side Tra. Por. 1 0.26 0.26 0.20 0.050
E. Side Tra. Por. 1 0.24 0.23 0.36 0.080
Pillars No.310
E. side Rec. Por. 1 0.25 0.25 0.40 0.36 0.036
W. Side Tra. Por. 1 0.14 0.13 0.35 0.040
Pillars No.306
E. Side Tra. Por. 1 0.25 0.24 0.35 0.080
W. Side Tra. Por. 1 0.16 0.16 0.35 0.050
Pillars No.311

Estimaded By :- Checked By :- Approved By :-


S.N. Item No. Items No. Length T.Length Breadth Height Quantity Unit
E. side Rec. Por. 1 0.50 0.50 0.35 0.35 0.061
E. Side Tra. Por. 1 0.24 0.23 0.35 0.080
W. Side Tra. Por. 1 0.30 0.29 0.35 0.100
Pillars No.307
W. side Rec. Por. 1 0.60 0.60 0.33 0.35 0.069
W. Side Tra. Por. 1 0.20 0.19 0.35 0.060
E. side Rec. Por. 1 0.60 0.60 0.33 0.35 0.069
E. Side Tra. Por. 1 0.20 0.19 0.35 0.060
Pillars No.308
W. side Rec. Por. 1 0.60 0.60 0.35 0.35 0.073
W. Side Tra. Por. 1 0.21 0.21 0.35 0.070
Pillars No.301
E. side Rec. Por. 1 1.20 1.20 0.35 0.50 0.210
E. Side Tra. Por. 1 0.17 0.16 0.36 0.050
N. side Rec. Por. 1 1.30 1.30 0.35 0.63 0.284
Pillars No.302
E. side Rec. Por. 1 1.80 1.80 0.35 0.45 0.283
E. Side Tra. Por. 1 0.23 0.22 0.35 0.070
W. side Rec. Por. 1 1.70 1.70 0.35 0.50 0.297
W. Side Tra. Por. 1 0.21 0.21 0.35 0.070
N. side Rec. Por. 1 1.70 1.70 0.35 0.61 0.362
Brick work for 1st level (above tie beam)
Grid 17-17,16-16,15-15,14-14 4 13.20 52.80 0.35 0.50 9.240
Grid L-L,M-M,N-N 3 15.45 46.35 0.35 0.50 8.111
Brick work for 2nd level (above tie beam)
Grid ,13-13,11-11,10-10,9-9 4 19.80 79.20 0.35 0.60 16.632
Grid D-D,F-F,H-H,K-K,L-L 5 15.43 77.12 0.35 0.60 16.195
Total 56.824 m3

Estimaded By :- Checked By :- Approved By :-


Department of Urban Development And Building Construction
DIVISION OFFICE, Surkhet
F/Y-064 - 065
Name of work :- 50 Bed Hospital Construction Work
Place :- Birendranagar - 3 , Kalagaon , Surkhet

ABSTRACT OF COST
S.N. Items Unit Quantity Unit Rate Amount

1 Brick Masonary in 1:4 Cement sand mortar m3 31.14 6147.92 191446.22

2 Salwood Work For Chawkhat m3 0.88 48540.76 42715.86

3 R.C.C. Work

A) 1:2:4 P.C.C. Work For R.C.C. m2 24.62 7548.60 185846.53

B) Tor Steel kg 2415.84 102.86 248493.04

C) Form Work m2 236.09 349.00 82395.41

4 Salwood panelled Door Shutter m2 14.96 3010.45 45036.33

5 Salwood Glaxed Window Shutter m2 7.00 2387.46 16712.22

6 P.C.C. 1:2:4 Work on floor m3 5.85 7190.95 42067.05

7 12.5 mm thick Plaster work in 1:4 on floor m2 117.49 157.79 18538.74

8 3 mm thick Cement Punning work on floor m2 117.49 117.84 13845.02

9 Fixing of 4 mm glass with listi m2 8.25 536.67 4427.52

10 12.5 mm thick Plaster work in 1:4 on Wall m2 469.11 157.79 74020.86

11 12.5 mm thick Plaster work in 1:3 on Ceili m2 167.26 181.07 30285.76

12 Applying 2 Coat of Snowcem Pinting work m2 636.37 53.16 33829.42

13 Applying 2 Coat of Enemal Pinting work m2 62.64 115.00 7203.60

14 Supplying and Laying of Tile work m2 23.22 1454.32 33769.31

15 Sanitary Work

A) 500 mm W.C. Pan set 2.00 6625.47 13250.94

B) Wash Basin 50*40 cm set 2.00 3983.64 7967.28

C) Shower set 2.00 488.75 977.50

D) Bib cock set 4.00 605.99 2423.96

E) Stop cock set 2.00 684.48 1368.96

F) Angle cock set 2.00 599.95 1199.90

G) Floor trap set 2.00 246.53 493.06

H) Looking Mprror 50*40 cm set 2.00 576.61 1153.22

I) Soap dish set 2.00 262.48 524.96

J) Glass Self set 2.00 661.06 1322.12

K) Towel Rod 60 cm long set 2.00 578.68 1157.36

L) 110 mm dia PVC pipe m 30.00 339.69 10190.70

M) 50 mm dia PVC pipe m 30.00 116.29 3488.70

N) 110 mm dia PVC Tee , Bent , Socket no 6.00 150.28 901.68

Estimated By:- Checked By:- Approved By:-


S.N. Items Unit Quantity Unit Rate Amount

O) 50 mm dia PVC Tee , Bent , Socket no 6.00 90.00 540.00

P) 20 mm dia GI Pipe m 15.00 248.54 3728.10

Q) 1/2 " mm dia GI Pipe m 25.00 212.64 5316.00

R) 1/2 "* 3/4 " mm dia GI Pipe Fittings job 1.00 L.S. 7500.00

S) 1000 liter Plastic Water Tank no 1.00 9453.00 9453.00

T) Urinals no 2.00 2125.20 4250.40

U) Over Flow System Valve no 1.00 500.00 500.00

16 Electricity Work

1) Consiled Wiring work Using standersd MatePoint 60.00 460.00 27600.00

2) 48 " Ceiling Fan set 6.00 2925.03 17550.18

3) 8" Dome light Set set 5.00 431.54 2157.70

4) Power Socket set 7.00 195.50 1368.50

5) Tube light 4 ' long set 8.00 446.15 3569.20

5) MCB set 3.00 262.06 786.18

6) Main Switch set 1.00 726.00 726.00

17 Site Clearance Before and after Constructio job 1.00 L.S. 3000.00

TOTAL AMOUNT Rs. 1205098.49

Vat 13 % Rs. 156662.80

Contiengency 5 % Rs. 60254.92

TOTAL AMOUNT Rs. 1422016.21

Estimated By:- Checked By:- Approved By:-


Department of Urban Development And Building Construction
DIVISION OFFICE
Surkhet
Name of work :- 50 Bed Hospital Construction Work F/Y-064 - 065
Place :- Birendranagar - 3 , Kalagaon , Surkhet

DETAILED ESTIMATE
S.N. Items No. Length T.Length Breadth Height Quantity Unit
1 Brick Masonary in 1:4 Cement sand mortar
L. wall 1 11.35 11.35 0.23 2.75 7.17
3 4.96 14.88 0.23 2.75 9.41
2 4.96 9.92 0.23 2.75 6.27
S.wall 4 2.27 9.08 0.23 2.75 5.74
1 2.27 2.27 0.10 2.75 0.62
2 6.96 13.92 0.23 2.75 8.80
2 3.00 6.00 0.23 2.75 3.79
2 3.49 6.98 0.23 2.75 4.41
2 4.02 8.04 0.23 2.75 5.08
0.5 4.49 2.24 0.23 1.38 0.70
1 1.45 1.45 0.23 1.38 0.45
Extra for pillar 12 0.12 1.44 0.12 2.75 0.47
3 0.35 1.05 0.12 2.75 0.34
Deduction Parapet wall -1 11.35 -11.35 0.23 0.70 -1.83
-2 10.12 -20.24 0.23 0.70 -3.26
Lintel Band ( 15 cm thick )
L. wall -1 11.35 -11.35 0.23 0.15 -0.40
-3 4.96 -14.88 0.23 0.15 -0.52
-2 4.96 -9.92 0.23 0.15 -0.35
S.wall -4 2.27 -9.08 0.23 0.15 -0.32
-2 6.96 -13.92 0.23 0.15 -0.49
-2 3.00 -6.00 0.23 0.15 -0.21
-2 3.49 -6.98 0.23 0.15 -0.25
-2 4.02 -8.04 0.23 0.15 -0.28
-1 4.49 -4.49 0.23 0.15 -0.16
-1 1.45 -1.45 0.23 0.15 -0.06
Tie Beam of Ceiling ( 25 cm thick ) L. wall -1 11.35 -11.35 0.23 0.25 -0.66
-3 4.96 -14.88 0.23 0.25 -0.86
-2 4.96 -9.92 0.23 0.25 -0.58
S.wall -4 2.27 -9.08 0.23 0.25 -0.53
-2 6.96 -13.92 0.23 0.25 -0.81
-2 3.00 -6.00 0.23 0.25 -0.35
-2 3.49 -6.98 0.23 0.25 -0.41
-2 4.02 -8.04 0.23 0.25 -0.47
-1 4.49 -4.49 0.23 0.25 -0.26

Estimaded By :- Checked By :- Approved By :-


S.N. Items No. Length T.Length Breadth Height Quantity Unit
-1 1.45 -1.45 0.23 0.25 -0.09
Opening W -5 2.40 -12.00 0.23 1.45 -4.01
W 1 -2 1.00 -2.00 0.23 1.45 -0.67
V -2 1.00 -2.00 0.23 0.50 -0.23
D -6 0.90 -5.40 0.23 2.10 -2.61
D 1 -2 0.75 -1.50 0.23 2.10 -0.73
D 2 -1 1.45 -1.45 0.23 2.10 -0.71
31.14 m3
2 Salwood Work For Chawkhat
W - 5 no. 10 2.40 24.00
20 1.45 29.00
W 1 - 2 no. 4 1.00 4.00
6 1.45 8.70
V - 2 no. 4 1.00 4.00
4 0.50 2.00
D - 6 no. 6 0.90 5.40
12 2.10 25.20
D 1 - 2 no. 2 0.75 1.50
4 2.10 8.40
D 2 - 1 no. 1 1.45 1.45
2 2.10 4.20
Total 1 117.85 117.85 0.10 0.08 0.88 m3
3 R.C.C. Work
A) 1:2:4 P.C.C. Work For R.C.C.
Lintel Band ( 15 cm thick )
L. wall 1 11.35 11.35 0.23 0.15 0.39
3 4.96 14.88 0.23 0.15 0.51
2 4.96 9.92 0.23 0.15 0.34
S.wall 4 2.27 9.08 0.23 0.15 0.31
2 6.96 13.92 0.23 0.15 0.48
2 3.00 6.00 0.23 0.15 0.20
2 3.49 6.98 0.23 0.15 0.24
2 4.02 8.04 0.23 0.15 0.27
1 4.49 4.49 0.23 0.15 0.15
1 1.45 1.45 0.23 0.15 0.05
Tie Beam of Ceiling ( 25 cm thick ) L. wall 1 11.35 11.35 0.23 0.25 0.65
3 4.96 14.88 0.23 0.25 0.85
2 4.96 9.92 0.23 0.25 0.57
S.wall 4 2.27 9.08 0.23 0.25 0.52
2 6.96 13.92 0.23 0.25 0.80
2 3.00 6.00 0.23 0.25 0.34
2 3.49 6.98 0.23 0.25 0.40

Estimaded By :- Checked By :- Approved By :-


S.N. Items No. Length T.Length Breadth Height Quantity Unit
2 4.02 8.04 0.23 0.25 0.46
1 4.49 4.49 0.23 0.25 0.25
1 1.45 1.45 0.23 0.25 0.08
Slab ( projection 85 cm ) 1 13.05 13.05 12.85 0.10 16.76
Total 24.62 m3
B) Tor Steel steel 1.25 % 2415.84 kg
C) Form Work
Lintel Band ( 15 cm thick )
L. wall 2 11.35 22.70 0.15 3.40
6 4.96 29.76 0.15 4.46
4 4.96 19.84 0.15 2.97
S.wall 8 2.27 18.16 0.15 2.72
4 6.96 27.84 0.15 4.17
4 3.00 12.00 0.15 1.80
4 3.49 13.96 0.15 2.09
4 4.02 16.08 0.15 2.41
2 4.49 8.98 0.15 1.34
2 1.45 2.90 0.15 0.43
Tie Beam of Ceiling ( 25 cm thick ) L. wall 2 11.35 22.70 0.25 5.67
6 4.96 29.76 0.25 7.44
4 4.96 19.84 0.25 4.96
S.wall 8 2.27 18.16 0.25 4.54
4 6.96 27.84 0.25 6.96
4 3.00 12.00 0.25 3.00
4 3.49 13.96 0.25 3.49
4 4.02 16.08 0.25 4.02
2 4.49 8.98 0.25 2.24
2 1.45 2.90 0.25 0.72
Slab room 2 4.50 9.00 2.27 20.43
1 6.96 6.96 4.50 31.32
1 3.00 3.00 4.50 13.50
1 3.50 3.50 4.50 15.75
1 4.02 4.02 4.50 18.09
passage 1 12.69 12.69 1.45 18.40
Projection 2 14.85 29.70 0.95 28.21

2 11.35 22.70 0.95 21.56


Total 236.09 m2
4 Salwood panelled Door Shutter
D - 6 no. 6 0.80 4.80 2.05 9.84
D 1 - 1 no. 2 0.60 1.20 2.05 2.46
D 2 - 1 no. 1 1.30 1.30 2.05 2.66
Total 14.96 m2

Estimaded By :- Checked By :- Approved By :-


S.N. Items No. Length T.Length Breadth Height Quantity Unit
5 Salwood Glaxed Window Shutter
W - 5 no. ( 5*2 ) 10 0.35 3.50 1.27 4.44
W1 - 1 no. (double palla ) 2 0.82 1.64 1.27 2.08
V - 2 no. 2 0.80 1.60 0.30 0.48
Total 7.00 m2
6 P.C.C. 1:2:4 Work on floor
room 2 4.50 9.00 2.27 0.05 1.02
1 6.96 6.96 4.50 0.05 1.56
1 3.00 3.00 4.50 0.05 0.67
1 3.50 3.50 4.50 0.05 0.78
1 4.02 4.02 4.50 0.05 0.90
passage 1 12.69 12.69 1.45 0.05 0.92
Total 5.85 m3
7 12.5 mm thick Plaster work in 1:4 on floor
floor room 2 4.50 9.00 2.27 20.43
1 6.96 6.96 4.50 31.32
1 3.00 3.00 4.50 13.50
1 3.50 3.50 4.50 15.75
1 4.02 4.02 4.50 18.09
passage 1 12.69 12.69 1.45 18.40
Total 117.49 m2
8 3 mm thick Cement Punning work on floor
floor room 2 4.50 9.00 2.27 20.43
1 6.96 6.96 4.50 31.32
1 3.00 3.00 4.50 13.50
1 3.50 3.50 4.50 15.75
1 4.02 4.02 4.50 18.09
passage 1 12.69 12.69 1.45 18.40
Total 117.49 m2
9 Fixing of 4 mm glass with listi
W - 5 no. ( 5*1 ) 5 1.30 6.50 1.27 8.25 m2
10 12.5 mm thick Plaster work in 1:4 on Wall
in side Toilet 8 2.27 18.16 2.75 49.94
room 2 6.95 13.90 2.75 38.22
2 3.00 6.00 2.75 16.50
2 3.50 7.00 2.75 19.25
2 4.00 8.00 2.75 22.00
2 3.72 7.44 2.75 20.46
2 2.00 1.45 2.75 3.98
6 4.50 27.00 2.75 74.25
6 4.50 27.00 2.75 74.25

Estimaded By :- Checked By :- Approved By :-


S.N. Items No. Length T.Length Breadth Height Quantity Unit
2 10.68 21.36 2.75 58.74
outside 2 13.15 26.30 2.75 72.32
2 13.15 26.30 2.75 72.32
1 4.95 4.95 2.75 13.61
Deduction W -10 2.40 -24.00 1.45 -34.80
W 1 -4 1.00 -4.00 1.45 -5.80
V -4 1.00 -4.00 0.50 -2.00
D -12 0.90 -10.80 2.10 -22.68
D 1 -4 0.75 -3.00 2.10 -6.30
D 2 -2 1.45 -2.90 2.10 -6.09
Sill + Suffix W 5 7.70 38.50 0.12 4.62
D 6 5.10 30.60 0.12 3.67
D1 2 4.95 9.90 0.12 1.18
D2 1 5.65 5.65 0.12 0.67
V 2 3.00 6.00 0.12 0.72
pillar Edge 6 0.12 0.72 0.12 0.08
Total 469.11 m2
11 12.5 mm thick Plaster work in 1:3 on Ceiling
Slab room 2 4.50 9.00 2.27 20.43
1 6.96 6.96 4.50 31.32
1 3.00 3.00 4.50 13.50
1 3.50 3.50 4.50 15.75
1 4.02 4.02 4.50 18.09
passage 1 12.69 12.69 1.45 18.40
Projection 2 14.85 29.70 0.95 28.21

2 11.35 22.70 0.95 21.56


Total 167.26 m2
12 Applying 2 Coat of Snowcem Pinting work ceiling + Wall 636.37 m2
13 Applying 2 Coat of Enemal Pinting work
W 5 2.40 12.00 1.45 1.00 17.40
W1 2 1.00 2.00 1.45 1.00 2.90
V 2 1.00 2.00 1.45 1.00 2.90
D 6 0.90 5.40 2.10 2.25 25.51
D1 2 0.75 1.50 2.10 2.25 7.08
D2 1 1.45 1.45 2.10 2.25 6.85
Total 62.64 m2
14 Supplying and Laying of Tile work
Toilet 1 Wall 2 1.20 2.40 1.00 2.40
2 2.27 4.54 1.00 4.54
Floor 1 2.27 2.27 1.00 2.27
Toilet 2 Wall 2 2.22 4.44 1.00 4.44

Estimaded By :- Checked By :- Approved By :-


S.N. Items No. Length T.Length Breadth Height Quantity Unit
2 2.27 4.54 1.00 4.54
Floor 1 2.22 2.22 2.27 5.03
Total 23.22 m2
15 Sanitary Work
A) W.C. Pan 2 2.00 2.00 set
B) Wash Basin 16*20 2 2.00 2.00 set
C) Shower 2 2.00 2.00 set
D) Tap 4 4.00 4.00 set
E) Stop cpck 2 2.00 2.00 set
F) Angle cock 2 2.00 2.00 set
G) Floor trap 2 2.00 2.00 set
H) Looking Mprror 2 2.00 2.00 set
I) Soap dish 2 2.00 2.00 set
J) Glass Self 2 2.00 2.00 set
K) Towel Rod 2 2.00 2.00 set
L) 110 mm dia PVC pipe 30 30.00 30.00 m
M) 50 mm dia PVC pipe 30 30.00 30.00 m
N) 110 mm dia PVC Tee , Bent , Socket 6 6.00 6.00 no
O) 75 mm dia PVC Tee , Bent , Socket 6 6.00 6.00 no
P) 3/4 " mm dia GI Pipe 15 15.00 15.00 m
Q) 1/2 " mm dia GI Pipe 25 25.00 25.00 m
R) 1/2 "* 3/4 " mm dia GI Pipe Fittings 1 1.00 1.00 job
S) 1000 liter Plastic Water Tank 1 1.00 1.00 no
T) Urinals 2 2.00 2.00 no
U) Over Flow System Valve 1 1.00 1.00 no
16 Electricity Work
1) Consiled Wiring work Using standersd Materials 1 60.00 60.00 60.00 Point
Fan - 2*1 = 2
Bulb + Tube - 16*1=16
Dome - 5*1=5
Power Socket - 7*2=14
Five Pin - 8*1=8
Indecator - 8*.5=4
Fuse - 8*.5=4
Main Switch- 1*3=3
MCB - 3*1=3
Total point = 60 Points
2) 48 " Ceiling Fan 6 6.00 6.00 6.00 set
3) 4" Dome light Set 5 5.00 5.00 5.00 set
4) Power Socket 7 7.00 7.00 7.00 set
5) Tube light 8 8.00 8.00 8.00 set
5) MCB 3 3.00 3.00 3.00 set
6) Maib Switch 1 1.00 1.00 1.00 set
17 Site Clearance Before and after Construction 1.00 job

Estimaded By :- Checked By :- Approved By :-

You might also like