BF2 Assignment
BF2 Assignment
You are a financial analyst for the Hittle Company. The director of capital budgeting has asked you to analyze two
proposed capital investments, Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each
project is 12 percent. The projects" expected net cash flows are as follows:
Calculate each project’s payback period, net present value (NPV), internal rate of return (IRR), and modified internal
rate of return (MIRR).
How might a change in the cost of capital produce a conflict between the NPV and IRR rankings of these two
projects? Would this conflict exist if r were 5%? (Hint: Plot the NPV profiles.)
Solution:
Payback period is the time required by the project to recover its costs.
Year 3 project will recover 3000/12 = Rs. 250 / Month, So the remaining Rs. 500 will recover in 2nd month of 3rd yr.
Payback period is the time required by the project to recover its costs.
Year 3 project will recover 3500/12 = Rs. 292 / Month, So the remaining Rs. 3000 will recover in 10.28th month of
3rd yr.
Project X:
Project Y:
= Rs. 631
Project X:
Project Y:
b. Both Projects Should be accepted if they are independant because they have Positive NPV and IRR greater than
12% Cost Of Capital