Pumps Service PSC
Pumps Service PSC
DEPARTMENT
Item Description Qty Unit Rate Amount
Borehole Drilling and Equipping
Mobilization of test pumping unit equipment for
test pumping the borehole including all pumping
plant, generator, rising main and discharge pipe
work and all equipment for measurements of
A discharge, drawdown, recovery; erect dismantle 1 Sum
and demobilize on completion.
D 350 Lm
Insertion and removal of surface temporary casing
Page H 8
Item Description Qty Unit Rate Amount
A Pump
Supply and install submersible borehole pump,
continuously rated and capable of pumping
10m³/hr of water against a total head of 300m.
The entire pump-set body, impellers, shaft etc
shall be made of heavy-duty stainless steel
material and shall be complete with submersible
cable, level controls and their cabling. The pump
shall be as "Grundfos SP 17-20" rated at 0.3kW
with a maximum assembly diameter of 130mm or
equal and approved.
Page H 9
C 25mm diameter heavy gauge PVC ducts 150 Lm
Sub total carried forword to the Collection Page H - 12
Page H 10
Item Description Qty Unit
Drop Pipes
Tenderers must allow for jointings, pipe flanges,
couplings, plugging, reducers, etc necessary for
the proper functioning of the installation when
pricing.
Supply and install 50mm diameter rising main
galvanized mild steel pipes class 'C' complying to
A BS 1387 with screwed and socketed joints to BS 350 Lm
143. Pipework to be comlplete with support
clamps and cable ties
Page H 11
SUMMARY PAGE
Item Description Amount
Total for Borehole Drilling and Equipping carried forward to the Main
Summary Page….H -18
Page H 12
PROPOSED ERECTION OF HIGH AND LOW LEVEL WATER TANKS & BOOSTER
PUMPS INSTALLATION WORKS AT KEBS REGIONAL OFFICES - KISUMU
Amount
Item Description Qty Unit Rate
(Kshs)
Supply, delivery and installation of the following as
maintenance service and parts to the Inline Pressure
boosting Pumps as Grundfos (As on site). The
maintenance servicing and repair should ensure
proper working and controling of the pumping system
and should be carried out as outlined. The work items
should ensure all the necessary supports, fittings and
accessories are restored to tproper working condition
and to the satisfaction of the Engineer.
A Electrical Works
Disconnect the entire power supply to the pump and
controls from the boards, examining all cabling,
accessories and breakers for soundness. Provide all
2 LS 85,000
worn out and replaceable electrical componenets. All
float switching cables to be drawn from their
locations, examined and appropriately replaced.
Amount
Item Description Qty Unit Rate
(Kshs)
Amount
Item Description Qty Unit Rate
(Kshs)
BENDS/ ELBOWS
C/13 100mm bend 4 No.
C/14 65mm ditto 4 No.
C/15 50mm ditto 3 No.
Sub total carried forword to Summary Page F - 12
Amount
Item Description Qty Unit Rate
(Kshs)
TEES
C/16 100mm tee 3 No.
C/17 65mm ditto 2 No.
C/18 50mm ditto 2 No.
Fire Hydrant
Supply and installation of 65mm diameter Hydrant
C/19 outlet c/w cap, valves, and stand pipe to BS standard 1 No.
or approved.
Fire Hydrant Surface Box
Fire Point
STRAINER
STERILIZATION
C/23 Allow for sterilization including flushing out water Sum Item
and chlorinatingt o the satisfaction of the Engineer
Amount
Item Description
(Kshs)
signature ……………………………………