Job Safety Analysis: Kalco Alu System (P) LTD
Job Safety Analysis: Kalco Alu System (P) LTD
JOB SAFETY ANALYSIS Job Title: Fixing of Window Frame & Glass. Date: 21/03/2020
Organization: KALCO ALU Job Location: 603 & 605, ADUGODI, BANGLORE Doc. No: 603&605/HSE/02
SYSTEM (P) LTD.
Name of the Safety Officer: Name of the Project Manager:
S. No BASIC JOB STEPS HAZARDS RECOMMONDED CONTROL MEASURES
1 Assembling of window 1. Unskilled labour. 1. Ensure all personnel are trained and competent
frames. 2. Tripping, Cutting. with appropriate PPE (Safety Helmets, Gloves,
3. Electrical shock. Goggles, Safety jackets and safety boot).
2. TBT to be conducted before start of the activity.
3. Workers have proper job specific PPE’S.
4. 100% supervision at all time.
5. Properly checked and safety tag (Green/Red) should
be placed on tools before starting the work.
2 Fixing of window. 1. Tripping, cutting. 1. Ensure 100% supervision at all time.
2. Electrical shock. 2. Job specific PPE’S (Safety Helmets, Gloves,
3. Window frame fallen.
Goggles, Safety jackets and safety boot) provided to
all workers.
3. No unauthorized person nearby.
4. Adequate working platform.
5. Scaffolding has proper support, green tag, etc.
6. Access to be clear.
7. Properly checked and safety tag (Green/Red) should
be placed on tools before starting the work..
3 Fixing of glass. 1. Slips, Trips & Falls. 1. Keep area clean and clear of obstructions.
2. Sharp edges. 2. Worker’s have proper hand gloves for holding the
glass, and all job specific PPE’s (Safety Helmets,
Gloves, Goggles, Safety jackets and safety boot).
3. Clean the area after completion of work.
4 Using Sealant 1. Inhalation 1. Given to worker job specific training before starting
1|Page
2. Eye-contact the work.
3. Skin contact 2. Worker’s should aware about the hazard.
3. Worker’s should have proper job specific PPE’s
(Safety Helmets, Rubber gloves, Goggles, Safety
jackets, nose mask and safety boot) .
5. Lifting Of Window & 1. Slips, Trips & Falls. 1. Given to worker job specific training before
Glass. 2. Crush hand or leg. starting the work.
2. Worker’s should aware about the hazard.
3. Workers should have hand gloves for lifting the
window.
4. Workers should have hand gloves & suction cup for
lifting the glass.
6. Height work (By Mobile 1. Slips, Trips & Falls. 1. Ensure all personnel are trained and competent for
scaffold) assembling & dismantling of the mobile scaffold.
2. Ensure all personnel have appropriate PPE (Safety
Helmets, Gloves, Goggles, Safety jackets and safety
boot).
3. Competent person (/Supervisor) should be present
at all time assembling & dismantling process going on.
4. Workers should aware about the hazards.
Comments:
2|Page