100% found this document useful (1 vote)
4K views1 page

Plastering Checklist

The quality checklist summarizes plastering and painting tasks for a construction project. It includes checking that preceding activities are complete, required materials like mesh and beads are used, mortar is mixed correctly and applied in the proper thickness and number of coats, and that approved paint make and shade are applied uniformly in the specified number of coats. Any items marked "no" require corrective actions to be specified.

Uploaded by

Budoy Smith
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
4K views1 page

Plastering Checklist

The quality checklist summarizes plastering and painting tasks for a construction project. It includes checking that preceding activities are complete, required materials like mesh and beads are used, mortar is mixed correctly and applied in the proper thickness and number of coats, and that approved paint make and shade are applied uniformly in the specified number of coats. Any items marked "no" require corrective actions to be specified.

Uploaded by

Budoy Smith
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

QUALITY CHECKLIST FOR SITE WORKS

PLASTERING/ PAINTING
ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY

Name of the Customer: Date:

Project Name: Project ID:

Name of the Contractor: Location:

Drawing Ref. No.: Quantity:

CL : 06
Sl.No. Description YES NO NA
1 Check for COMPLETION OF PRECEDING ACTIVITIES like
fixing of service Conduits, Water Supply & sanitation lines, etc.

2 Whether chicken mesh, Corner beads used as per


specifications?
3 Check for MORTAR MIX PROPORTION & Check for Surface
of mortar mixing and addition of water profing compond if
required.
4 Check for THICKNESS & NUMBER OF COATS of Plaster and
required finish for further activities.

PAINTING
1 PRIOR TO PAINTING
Check whether approved make & shade are used?

DURING & AFTER PAINTING


1 Check for APPLICATION of paint. Is it uniform?

2 Check for Number of Coats.

CORRECTIVE ACTION PROPOSED- Item wise.


If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
Comments:

Contractor's Rep.: Client Rep.: Lemcon Rep.: