Section 9
Section 9
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
REVISION A B C
Signature Signature Signature
DATE 06/27/18 09/21/18
ORIG BY C Picken CPP C Picken
APP BY P Darker PJD P Darker
APP BY DM R Freeman BRF R Freeman
TABLE OF CONTENTS
1. INTRODUCTION 7
1.1 Purpose 7
1.2 Reference Standards and Documents 7
1.3 Holds 7
2. ENVIRONMENTAL DATA 8
3. ELECTRICAL SYSTEM CONFIGURATION 8
3.1 Overview 8
3.2 The Key Single Line Diagram 9
3.3 Point of Common Coupling 9
4. MAIN POWER DISTRIBUTION SYSTEM COMPONENTS 9
4.1 230kV GIS Substation 9
4.2 Main Substations 10
4.3 Unit Substations 10
5. OPERATION OF THE POWER SYSTEM 11
5.1 Human Operation of the Power System 11
5.2 Normal Operation 11
5.3 Single Incomer Failure Operation 11
5.4 13.8kV, 4.16kV and LV Switchgear Operating Scenarios 11
6. SHUTDOWN AND STARTING 12
6.1 Planned Shutdown 12
6.2 Unplanned Shutdown (Blackout) 12
6.3 Emergency Generators 13
6.4 Emergency Power Distribution 13
6.5 Start-up 14
7. CHARACTERISTICS OF THE ELECTRICAL POWER SYSTEM 14
7.1 Overview 14
7.2 Saudi Arabian Grid Code Requirements 14
7.3 Voltage Levels 14
7.4 Voltage Quality 14
7.5 Repetitive Voltage Fluctuations Due to TGP 15
7.6 Non-repetitive Voltage Fluctuations Due to TGP 15
7.7 Voltage Flicker Severity 15
7.8 Harmonic Distortion 15
7.9 Frequency Variation 15
7.10 Power Exchange Between TGP and the SEC system 16
7.11 Fault Clearance Times for the SEC System 16
7.12 Fault Ride-through Requirements 16
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
9.1 Studies Required 18
9.2 Load Flow Analysis 18
9.3 Short Circuit Analysis 19
9.4 Arc Flash Analysis 19
9.5 Motor Starting and Volt-drop Analysis 19
9.6 Transient Stability Study 20
9.7 Harmonic Penetration Analysis 20
9.8 Power Factor Correction Study 20
9.9 Switching Transient Analysis, Insulation Coordination 21
9.10 Relay Coordination Study 21
9.11 Electrical System Modelling 21
10. GROUNDING OF STAR-POINTS AND NEUTRALS 22
10.1 SEC 380/230kV Transformer Neutral Grounding 22
10.2 TGP 230kV System Grounding 22
10.3 13.8kV Switchgear 22
10.4 4.16kV Switchgear 22
10.5 Three-phase 480V Switchgear 22
10.6 Generators, Transformers and LV Systems in General 22
11. GROUND GRID DESIGN 23
11.1 Solidly Grounded Systems <1000V 23
11.2 Impedance Grounded Systems >1000V 23
11.3 Solidly Grounded Systems >1000V 23
11.4 Grounding Grids, Rods, Step and Touch Potentials 23
11.5 Substation and Switchyard 23
11.6 Grid Conductor Cross-section 23
11.7 TGP Bulk Distribution and Industrial Areas 24
11.8 Backup Protective Relay Protection 24
11.9 Current Division Factor 24
11.10 Resistivity of Surface Soil 24
11.11 Grounding Earth Rods for Test Purposes 24
11.12 Step and Touch Study 24
11.13 Ground Grid Study 25
11.14 Lightning Protection Study 25
12. GROUNDING OF METALLIC COMPONENTS 25
12.1 Frames of Motors, Generators and Transformers 26
12.2 Free-standing Equipment 26
12.3 Fence Grounding 26
12.4 Tanks, Lightning Protection and Static Electricity 26
12.5 Grounding Electrodes for Non-Process Facilities 26
13. ELECTRICAL LOAD SCHEDULE 27
13.1 Content and Use 27
13.2 Motors 27
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
13.7 Sizing of Static Loads 31
14. ELECTRIC MOTORS 31
15. TRANSFORMERS 32
15.1 Sizing 32
15.2 Tap Changer Range for Transformers 33
16. SWITCHGEAR AND CONTROLGEAR (MCC) 33
16.1 230kV Switchgear Design 33
16.2 13.8kV and 4.16kV HV Switchgear and Controlgear (MCCs) 34
16.3 480V LV Switchgear and Controlgear (MCCs) 34
16.4 Busbar Fault Current Ratings in General 34
16.5 Ringmain Units 35
17. SAFETY INTERLOCKING 35
17.1 Diagrams 35
17.2 Grounding Switches 35
17.3 Switchgear Shutters 35
17.4 Circuit Breaker Test Position 35
17.5 Energising Transformers 36
17.6 De-energising Transformers 36
18. CABLEBUS 36
19. PROTECTIVE RELAYING AND METERING 37
19.1 General 37
19.2 Mandatory Standards and Policies 37
19.3 Protection of Electrical Equipment 37
19.4 Relay Coordination 38
19.5 Circuit Breaker Failure Protection 38
19.6 Metering and Alarms 38
19.7 Events and Tripping of Switchgear 39
19.8 Interfacing with SEC 39
20. HV & LV CABLE SELECTION & INSTALLATION 39
20.1 Sizing 39
20.2 Installation Method - General 40
20.3 Volt Drop 40
20.4 Cable Glands 40
20.5 Cable Trenches 40
20.6 Built Roads 41
20.7 Conduits and Cables Entering Buildings 41
20.8 Crossing and Parallel Clearances from Pipelines 41
21. ARC FLASH PROTECTION 41
21.1 Arc Flash in Switchgear and Controlgear 41
21.2 Operation Local to Switchgear and Controlgear 41
22. HAZARDOUS AREA CLASSIFICATION 42
23. POWER SYSTEM AUTOMATION 42
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
25.1 General 43
25.2 Material Requirements 44
25.3 Temperature Control and Monitoring 44
26. CATHODIC PROTECTION 45
26.1 General 45
26.2 Design Requirements 46
26.3 Material Requirements 46
27. LIGHTING AND SMALL POWER 46
27.1 General 46
27.2 Levels of Luminance 47
27.3 LED Luminaires 47
27.4 Plant Areas and Street Lighting 47
27.5 Task Lighting 47
27.6 Building Lighting 48
27.7 SSD Fence Lighting 48
27.8 Emergency Lighting 48
27.9 Small Power 49
28. INDUSTRIAL SUPPORT FACILITIES (ISF) POWER SYSTEM 49
28.1 Power Supply 49
28.2 Power Distribution 49
29. LIST OF ABBREVIATIONS 50
30. REFERENCES 53
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
1. INTRODUCTION
1.1 Purpose
The purpose of this document is to define the electrical design basis for the
Tanajib Gas Plant (TGP).
This document shall be read in conjunction with the referenced standards and
specifications. A list of key international and Saudi Aramco standards and
other reference documents is given in section 28.
The latest issue dates shall be used for all the referenced International
Standards, e.g. ANSI, IEC, IEEE, NFPA, etc.
The information contained in the Saudi Aramco Engineering Standards
(SAES), Saudi Aramco Engineering Procedures (SAEP), Saudi Aramco
Materials System Specifications (SAMSS) and Saudi Aramco Best Practices
(SABP) shall be incorporated into the electrical design of the TGP where
applicable.
Saudi Aramco standard drawings shall also be used where applicable.
Saudi Electricity Company (SEC) standards and materials systems
specifications shall be used as a basis for the design of the 230kV substation
and 230kV Gas Insulated Switchgear (GIS), and for the selection of 230kV
cable.
1.3 Holds
None
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
2. ENVIRONMENTAL DATA
3.1 Overview
The electrical power supply and distribution systems shall support the
operation of electrically driven process machinery and utilities equipment in a
safe and reliable manner to maintain the gas production targets.
The design work covered by this Electrical Design Basis starts from and
includes the TGP 230kV GIS Substation and includes all downstream
systems.
The Marjan 380/230kV BSP Substation will be designed and built by SEC
under a MOU with Saudi Aramco. The SEC Scope of Work includes the 230kV
interconnecting cabling and terminations between the SEC 380/230kV step-
down auto-transformers (with GIS disconnector switches on the secondary
side) and the TGP 230kV GIS.
The incoming electrical power supply to the TGP consists of three
underground cable feeders from the SEC 380/230kV step-down auto-
transformers to the TGP 230kV GIS Substation. These feeders are configured
as 3x50% to suit a N-1 auto-transformer availability.
The TGP 230kV Gas Insulated Switchgear (GIS) is configured as ‘Breaker-
and-a-Half’ to support high availability of power distribution from the three
number incoming feeders.
The TGP 230kV GIS also provides two 230kV outgoing feeders to the ‘Zuluf
600AH Increment Scope’ (BI-10-12321). The interface point for these Zuluf
feeders is at the Transition Yard located on the north side of the 380kV GIS
Substation.
The TGP 230kV GIS feeds three Main Substations via dual underground cable
feeders and 230/13.8kV step-down transformers to each switchgear assembly.
These Main Substations house the main 13.8kV motor and 13.8kV distribution
switchgear. From these Main Substations, power is distributed to individual
13.8kV motors and Unit Substations located throughout the facility. The
electrical distribution within TGP is at 13.8kV via above ground cables. The
process areas are considered critical so secondary selective switchgear is
provided in the Main Substations and all Unit Substations.
The TGP 230kV GIS Substation also includes extension space for future
additional GIS bays to feed a future fourth Main Substation for future Dorra
13.8kV motor and 13.8kV distribution switchgear.
Unit Substations shall be provided local to the process units, utilities and
miscellaneous plant areas they serve. From the Unit Substations power is
distributed at 4.16kV or 480V from local MCCs to suit the connected load size.
All switchgear shall be provided with a Power System Automation (PSA)
scheme, which shall communicate information to and from with the Central
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
The Key Single Line Diagram T80-P-PP-704001 [Ref 1] shall be the principal
document that pictorially sets out the whole electrical power supply and
distribution system for the TGP. This single line diagram shows the high
voltage distribution system and the associated main high-power components.
The Point of Common Coupling (PCC) of the TGP facility to the SEC Grid
is at the load side of the GIS disconnector switch on the low voltage side of
the SEC 380/230kV step-down auto-transformers located at the SEC
Marjan 380/230kV BSP Substation.
The lower limit of the permissible power factor measured at the Tanajib 380kV
GIS Substation PCC shall be 0.95 (lagging). The range of power factor
permissible shall be obtained from SEC and appropriate power system control
strategies implemented to ensure that operation is within limits.
The TGP 230kV GIS Substation shall house 230kV ‘Breaker-and-a-Half’ Gas
Insulated Switchgear (GIS), associated protection panels and all auxiliary
systems. The substation shall be designed in accordance with SEC and Saudi
Aramco standards, with a subterranean cable basement.
The SEC 230kV incoming feeder cables shall be direct buried and routed from
the associated upstream 380/230kV auto-transformers located at the SEC
Tanajib 380kV GIS Substation. The cables shall enter the 230kV GIS
Substation via a cable basement. Outgoing 230kV feeder circuits to the Main
Substations shall be routed out of the substation via the cable basement and
direct buried.
TGP Main Substations shall house the main distribution and HV motor feeder
13.8kV switchgear, HV transformers and all auxiliary systems.
Each Substation shall be fed via 230/13.8kV transformers and comprises the
following main equipment:
230/13.8kV step-down power transformers (each 100% rated).
13.8kV double ended, secondary selective switchgear to provide power
distribution to Unit Substations.
13.8kV double ended, secondary selective switchgear to provide power
distribution to large HV motors.
13.8kV switchgear dedicated to security systems power (SS-MS1 only).
480V double ended, secondary selective switchgear and controlgear to
provide power to LV auxiliary loads associated with the Main Substation.
Located adjacent to the Main Substations will be a diesel generator to to
provide power to essential consumers, and a diesel generator dedicated to
security systems.
The Unit Substations shall be designed to supply power to the Process Units,
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
13.8/4.16kV step down power transformers.
13.8/0.48kV step down power transformers.
4.16kV double ended, secondary selective switchgear.
4.16kV controlgear (MCCs) to provide power to medium sized motors.
480V double ended, secondary selective switchgear.
480V controlgear (MCCs) to provide power to LV motors and other LV
loads.
Diesel generator to provide power to essential consumers.
The number of diesel generators shall be optimized by the Contractor as part of
Detail Design, taking into account substation locations and the connected
essential loads.
The main point of control for the TGP power system shall be in the Central
Control Room (CCR). A dedicated HMI computer unit/server shall be installed
in the CCR. This HMI shall operate the power distribution control system and
have the following features:
Desk-top multi-colour screen and key board.
Printer.
Server.
Interface to/from the Process Control System PCS.
Interchange information and control commands with the various main
substations.
Display of single line diagrams and key variables such as, voltages,
currents, active power, reactive power, kilo-volt-amperes, system
frequency, switchroom internal temperatures.
Display of equipment open, close, trip and out-of-service status.
Annunciation of warnings and alarms.
Archiving, logging, time-stamping of events.
It shall be possible to transfer control to each substation as required for local
operation and maintenance.
Local substation control shall be carried out at an ‘operations desk’ located
adjacent to the personnel entrance door. Each operation desk shall have an
HMI like the one in the Central Control Building, but with less scope of control.
The normal switching operations of the 13.8kV, 4.16kV and lower voltage
switchgear shall be conventional ‘secondary selective’ as summarised below:
Normal operation of double-ended switchgear is with both incomers
closed and the bus sectionalizer open.
Abnormal operation shall be allowed where one incomer is in service
and the bus sectionalizer closed.
Transfer from normal to abnormal system configuration would occur
only during loss of power to an incomer after verifying that there is no
bus fault (utilizing the automatic transfer system).
Manual transfer shall also be possible in the form of make-before-
break so that there is no loss of supply to a busbar.
The transfer system shall not permit sustained operation with both
incomers and the bus sectionalizer closed.
MCCs fed from upstream switchgear shall be single-ended, i.e. have a
single incoming feeder.
There is one emergency diesel generator (EDG) per substation to feed the critical
and essential services of each substation (number of EDGs to be optimized by
the Contractor as part of Detail Design).
All emergency loads shall be regarded as essential loads. These essential loads
shall be connected to an appropriate emergency MCC in the nearest substation
to the loads. Each emergency MCC shall receive power from two sources, one
being the normal supply from an upstream switchgear and the other being from a
local EDG. An ATS system shall be used to start-up the EDG and energise the
emergency MCCs. The ATS system shall be supported by a selectable
‘Auto/Manual’ switch option.
The EDG shall be sized to supply all the essential loads plus a marginal factor,
and be capable of direct-on-line (DOL) starting the largest individual essential
induction motor, in addition to the base load running, subject to the permissible
limits of volt-drop for starting motors.
6.5 Start-up
The TGP 230kV GIS Substation is connected to the wider Saudi Electricity
Company (SEC) transmission system via the TGP 380kV SEC GIS
Substation. The key electrical SEC transmission system characteristics and
grid connection code requirements are detailed in the following sections. In the
case of any conflicts or omissions the Saudi Grid Code and grid connection
agreement shall take precedence.
The power system has several rated line-to-line voltage levels as shown in
SAES-P-100 Ref [4]. The voltages are (AC) 230kV, 13.8kV, 4.16kV, 480V,
400/230 V, 120 V, and (DC) 125Vdc, 48Vdc and 24Vdc.
Repetitive
voltage fluctuations imposed at 230kV due to load changes within TGP shall
not exceed 1% of the nominal voltage for repetitive step changes. These
voltage changes may be due to thyristor controlled heaters employing burst
firing. Studies shall be undertaken to demonstrate that plant is operating within
limits.
The flicker severity at the PCC required by The Saudi Arabian Grid Code Ref
[6] shall not exceed the perceptibility limits of short-term Pst = 0.8 and long-
term Plt = 0.6, both 95th percentile values measured over a period of one
week. The definitions and descriptions of these quantities are given in ANSI
C84.1-2016 Ref [7].
Levels of harmonic voltage and current distortion at 230kV shall comply with
the Saudi Grid Code. Levels of harmonic voltage and current distortion shall
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
ETAP harmonic studies shall be carried out to confirm that the system design
complies with Saudi Grid Code (Ref 6).
The design of the Tanajib Gas Plant shall be in accordance with Saudi Grid
Code requirements, with all connected loads considered together at the SEC
380kV BSP.
The TGP is a net consumer of active power because it has no main HV
generators. However, the TGP shall be an importer and an exporter of reactive
power and the extent of either shall be a function of the MVA loading at any
sample time-period.
The minimum lagging power factor at the PCC is specified as 0.95 lagging, but
limits on the export of reactive power from the TGP shall be determined in the
detailed design phase. This will require automatic control of the reactive profile
of the synchronous motors.
The fault clearance times of the SEC switchgear are given in Table 3 of Ref [6]
and repeated below in Table 3
From 20 cycles to 10 The plant shall continue at the same level of gas
seconds. production, but receiving its power from only two
feeders.
Beyond 10 seconds The faulted line shall be investigated, reinstated
and made available to be switched-in to the system,
unless severe damage has occurred.
The above tabulated figures take into account the Cogen contribution.
8. MAINTAINABILITY
The power system shall be designed to be easily and safely operated and
maintained.
Switchrooms shall be designed with adequate separation space between
switchgear and from surrounding walls. Spacings shall take account of the
need to replace a complete switchgear cubicle, move a truck around the room
on a trolley, and be well clear of access and emergency exit doors. Double
door access shall be provided in the most convenient location in the
switchroom.
Clearances shall be per SAES-P-116 section 7.2. A clearance of 1.8m shall be
allowed above electrical equipment.
Studies shall be carried out using the Electrical Transient Analysis Program,
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
Load flow.
Short circuit.
Arc flash.
Motor start.
Harmonic analysis.
Power factor correction.
Switching transient analysis and insulation coordination.
Relay coordination.
The Cogen is not included in the Scope of Work for TGP BI-10-09003 and so
the Transient Stability Analysis of the turbine-generator units is not required.
However, the transient stability analysis of the turbine-generator units shall
need to be carried out by the contractor assigned to the Cogen BI-10-12264
(Ref [4], SAES-P-100, 7.7.1). The overall integrated ETAP model for the
Marjan development will include relevant data from the Cogen contractor
analysis.
During the detailed engineering phase of the project all detailed electrical
studies shall be performed by the EPC Contractor in accordance with SAES-
P-100 in two phases:
Shortly after commencing the detail design and using the preliminary data
and information after obtaining quotations from equipment manufacturers.
Towards the end of the detail design phase after the final manufacturers’
data and information has been received.
This will analyse kW, kvar, kVA and Ampere flows in branches and nodal
points such as at switchgear. The total consumption at the SEC 380kV GIS
Substation shall also be given assessed.
The load flow studies shall show system voltages under normal/abnormal
operating conditions, normal load, peak load and low load. Equipment duties
shall be compared to ratings to demonstrate suitability. Tap change ranges
shall be determined and the settings of fixed tap transformers nominated. The
rating of transformers and HV cables shall be checked taking account of
maximum site temperature. Appropriate impedance tolerances (transformers)
and length tolerances (cables) shall be used.
Ref [4], SAES-P-100, 7.6.1.
The Cogen is not included in the Scope of Work for TGP BI-10-09003 and so
the transient stability analysis of the turbine-generator units is not required.
However, the transient stability analysis of the turbine-generator units shall
need to be carried out by the Cogeneration BOOT Contractor.
Ref [4], SAES-P-100 7.7.1.
Cable and transmission line design lengths shall be increased by 20% for load
flow studies and reduced by 20% for short circuit studies.
The maximum conductor resistances shall be used for load flow studies and
minimum conductor resistances shall be used for short circuit studies.
Final detail design studies shall be performed using ‘as-installed’ length and
cable data.
The SEC system is solidly grounded. The magnitude of ground fault currents
at Tanajib 380kV GIS Substation are given in section 7.13. The clearance
times of the SEC switchgear are given in section 7.11.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
The 230kV rated transmission system shall be designed to be grounded
effectively with a ground fault factor of less than 1.4 (line-to-ground). Power
system studies shall be undertaken to ensure that this is achieved.
The 13.8kV switchgear shall be resistance grounded at the star point of the
secondary windings of the associated feeder transformer. The resistor shall
restrict the line-to-ground fault current to 400A amps and shall have a thermal
withstand time of 10 seconds.
The 4.16kV switchgear shall be resistance grounded at the star point of the
secondary windings of the associated feeder transformer. The resistor shall
restrict the line-to-ground fault current to 400A and shall have a thermal
withstand time of 10 seconds.
The 480V switchgear shall be solidly grounded at the star point of the
secondary windings of the associated feeder transformer. The busbar system
for the 480V switchgear shall be 3-wire, so no neutral busbar is required in the
switchgear.
Where a system of rods and a grid is used the ‘resistance to ground’ shall not
exceed 5 ohms.
The neutral conductor shall be rated for 3 seconds fault duration.
Where a system of rods and a grid is used the ‘resistance to ground’ shall not
exceed 5 Ω.
For industrial facilities the grounding impedance shall be a resistor rated at
400 amps and 10 seconds.
The neutral conductor shall be rated for 10 seconds fault duration.
Where a system of rods and a grid is used the ‘resistance to ground’ shall not
exceed one ohm.
The neutral conductor shall be rated for 3 seconds fault duration.
Where a grounding grid and rod system is required, e.g. in and surrounding a
substation, the calculations and design shall be based on IEEE 80 Ref [14].
Initially the calculations shall be based on only using a grid without rods. If the
results are unsatisfactory then rods shall be added to the grid nodes to obtain
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
All electrical equipment in the substation and its yard, and within 5 metres of
the substation boundary fence shall be connected to the grid or to a
substantial ground bus connected to the grid.
The IEEE 80 Ref [14] shall be used to design the ‘grid and rod’ grounding
system for the substation, its yard and the nearby fencing.
The Saudi Aramco SABP-P-045 Ref [14a], which is like SEC standard SES-P-
119.10 Ref [14b], sets out a guideline method of calculation for grounding grid
design. The results of this method and those of the full IEEE 80 standard
should be compared for checking purposes.
To calculate the step and touch potentials the weight of the human body shall
be taken as 50 kg, see sections 6 and 8.4 of IEEE 80.
The conductors of the grid mesh shall be made of stranded copper having a
minimum cross-section of 70 mm2 (2/0 AWG).
If the soil resistivity is less than 70 ohm-metres the copper conductors shall be
tinned.
The back-up protective relay protection device shall operate to clear a fault
within 0.5 second. Two fault situations shall be used and the worst-case
current applied to the design of the grid and rod system:
Line-to-line-to-ground (L-L-G).
Symmetrical line-to-line-to-line-to-ground (L-L-L-G).
A Current Division Factor (Sf) of 1.0 per-unit shall be used unless a lower
figure is justified. See section 15.9 in IEEE 80. A lower figure may be justified
if a significant portion of the current returns to source through the ground wire
of a OHTL.
The resistivity of the surface material used for preliminary calculations of the
allowable step and touch potentials shall be based on Tables 7 and 8 in
IEEE 80. Soil resistivity measurements shall be undertaken in accordance with
IEEE80 ‘Guide for Safety in AC Substation Grounding’.
A Geotechnical survey shall be made at each substation in accordance with
IEEE 81, to obtain soil resistivity data. This shall form part of the survey for the
civil works.
Data shall be obtained at an early stage of the project from a site survey of
actual measurements. The calculations shall then be repeated for the
allowable step and touch potentials.
Should design calculations show that no ground earth rods are required to
achieve maximum resistances, grounding earth rods shall nonetheless be
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
11.13 Ground Grid Study
Equipment grounding shall be based on the I2t fault withstand capability of the
bonding conductors to be used and the upstream rated fault level of the
switchgear that feeds the circuit. The basis of grounding shall be SAES-P-111
Ref [9]. The upstream fault level shall be the ‘Ultimate’ short circuit level. The
duration shall be that of back-up protection operating time.
Equipment grounding covers:
Substation metal-clad enclosures and items such as gantry and tower
steel structures, sub-surface grids and rods, fencing and lightning
protection.
Bonding of power cable armouring and screens (shields): SAES-P-111,
9.8 requires shields and armour of power cables to be grounded at both
ends; continuity at splices shall be maintained by bonding across the
splice; for circuits with single core cables, circulating currents and
associated potential rise shall be minimised; cable shields, sheaths,
joints, braided leads, and grounding bonds shall be rated for the
maximum currents including motor acceleration periods.
Bonding of in-plant items such as cable racking, tanks and vessels,
piping, motor and generator frames, electrical cubicles and panel-
boards, equipment skids that include electrically energized components.
The grounding conductor in each power circuit shall be made of copper
material.
Grounding and bonding of cable racks and trays shall be sized in accordance
with NEC Table 250-66 Ref [12] and for the largest power conductor in the
rack or tray, but with a minimum size of 25 mm2 (#4 AWG).
Both ends of a conduit shall be bonded to a grounding conductor.
Metallic cable racks and trays shall be bonded to a local ground grid or ground
electrode at both end points. The bonding continuity of the ground circuit along
the full length of the rack or tray and its metallic supports shall be ensured.
For other requirements refer to Section 9 in SAES-P-111 Ref [9].
Motors, generators and transformers operating at 1000V and above shall have
two bonding connections to the local grounding bar.
Motors, generators and transformers operating at a nominal voltage of 480V
shall have one bonding connection to the local grounding bar.
Motor Operated Valves (MOVs), low voltage motors and transformers shall be
grounded through the associated equipment grounding conductor.
Substation fences shall not be PVC coated. Each fence shall be grounded by
a minimum of two locations to the local ground grid mesh.
Attention shall be paid to the grounding of fences that enclose substations
which have solidly grounded equipment rated above 1000V line-to-line. The
bonding shall be made to a grounding conductor that is buried one metre
outside the fence and run parallel to the fence. A second conductor shall be
buried one metre inside the fence, also run parallel to the fence if the
substation grid does not extend into this area.
The grounding conductor(s) shall be connected to the substation ground grid
at a minimum of four locations spaced equally around the loop or mesh.
The fence shall be connected to the grounding conductor(s) at intervals not
exceeding 15m.
Corner posts and gateposts shall be connected to the grounding conductor.
Gates shall be bonded to the gateposts using flexible conductors.
Grillwork and gates used to control access to the area under a substation shall
meet the bonding and grounding requirements for substation fencing.
For non-substation fencing refer to section 11.2 in SAES-P-111 Ref [9].
For these subjects refer to sections 12, 13 and 14 in SAES-P-111 [Ref 9].
Each motor and static load shall be detailed in the Electrical Load Schedule.
This schedule shall be regularly updated throughout the duration of the
project. The electrical information in the Electrical Load Schedule shall be
used as the base data for sizing the main electrical equipment, as outlined
below. Various factors in the headings of the schedule have the upper-case
letters, A, B, C, D, E, F and G. These letters are explained below.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
mechanical efficiency of the driven machine. For machines less than 900 HP
the efficiency can be taken as 70%. Above 900 HP the efficiency can be taken
as 80%. The absorbed load (mechanical) is the hydraulic power divided by the
efficiency.
The nameplate rating of the motor, lettered B, is derived from Table 6.
Sizing of the electrical system shall be based upon using 110% of the sum of
the operating loads plus all known future loads.
Operating load shall be equal to the anticipated one-hour demand based on
the plant design conditions.
An Electrical Load Schedule of all electrical loads segregated by each
switchgear shall be maintained so that the individual incoming demands and
the total TGP demand can be calculated, based on the anticipated one-hour
demand. The list shall include all major items of process plant plus any
electrical power required for the general utilities and communication systems.
The following formula shall be used for each load to determine the anticipated
one-hour demand:
a) Maximum normal running plant load = x (%) E + y (%) F.
b) Anticipated one-hour demand = x (%) E + y (%) F + z (%) G
Alternatively,
c) Anticipated one-hour demand = x (%) E + y (%) F + load due the highest
rated standby load
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
x, y and z are duty cycle (diversity) factors, given numerically below
in Table 8 as default values.
The greater of b) or c) is used for calculating the peak load. This applies to both
busbar loads and the total plant load.
These values shall be determined and agreed with the Company for the
diversity appropriate to the type of plant.
The values of the diversity factors x, y and z must take account of the
individual drives or consumers which make up the continuous, intermittent and
stand-by loads respectively. For example, y (%) and z (%) cannot be less than
the largest individual intermittent drive or consumer.
Diversity factors are shown in Table 7.
Factor Definition
100% [For rated plant throughput all driven equipment should
x
be operating at its duty point. However, some diversity may
need to be applied to non-process loads, e.g. offices and
workshop power and lighting (typically 90%)].
y 30% Intermittent loads
The essential system shall be sized to provide power to cater for emergency
loads when a loss of normal power occurs. The word ‘essential’ and ‘emergency’
are regarded as having the same definition. The emergency generators shall
supply all the essential loads, and individual diesel engine kW rating shall be
sized to:
Provide their maximum continuous power during the period when the site
ambient temperature is at its highest expected value as given in Table 2 of
SAES-P-100 Ref [4].
c) Vital Loads.
Vital loads are a sub-set of critical loads and are those associated with
site security systems. These loads are as defined by the Saudi Arabian
Government High Commission for Industrial Security. Refer to SAES-O-
202 Ref [17].
The UPS configuration shall be based on the criticality of the consumers, e.g.
where a fully dual redundant system with manual bypass is justified.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
The Load Factor C = 0.9 and calculates the Absorbed Power A =
11.1kW.
The Efficiency D = 0.9, an assumed Power Factor of 0.9 (between say
0.9 and 1.0)
Finally calculates the continuous kW = 12.3 and kvar = 6.0.
The result of these calculations is two-fold,
i) The rated active power of the lighting system is 10kW.
ii) The continuously consumed power is 12.3kW.
For other static loads the Instrument, HVAC and Telecommunications groups
may need to provide input data.
There are two types of tap changers used in the TGP power system: manually
operated no-load tap changers (2 +/- 2.5%, 2 +/-5% taps) and automatic on-
load tap changers (33 taps with 0.625% steps). In this project, 230-13.8 kV
transformers shall have automatic on-load tap changers (connected to the
PSA), whereas 13.8-4.16 kV, 13.8-0.48 kV transformers shall have manual no-
load tap changers.
Unless otherwise stated in the Data Sheet for a distribution power transformer
the tappings shall be incorporated into the primary windings and shall have the
industry standard values of -5.0%, -2.5%, 0, +2.5% and +5.0%.
For HV transmission the transformers may require a wider range of finer
increments, e.g. 33 x 0.625% taps, which shall be stated in the Data Sheet.
The taps shall be incorporated into the higher voltage windings.
Tap settings shall be selected in line with the ETAP power system studies.
The 230kV Gas Insulated Switchgear (GIS) shall be to IEC standards (SEC
standard 32-TMSS-02 Gas Insulated Switchgear) with double gas tight seals.
In addition to seals between sections an overseal (a Straub seal or equivalent)
shall envelope the sections of switchgear.
GIS monitoring via data logging devices shall include:
Gas pressure.
Offline partial discharge.
The monitoring shall provide alarm and trip levels locally and to the PSA
system.
Maintenance, repair and extension of the GIS shall be possible with all feeders
in service.
13.8kV and 4.16kV high voltage switchgear and controlgaer shall be metal
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
16.3 480V LV Switchgear and Controlgear (MCCs)
The fault current levels of the busbars in all the switchgear shall be calculated
for the worst-case situation when all three 230kV incomers are in service at
the TGP 230kV GIS Substation.
As per SEC standard TES-P-122-01, 230 kV GIS rating can be 50 or 63
kArms symmetrical.
The rated current levels shall be checked against the calculated values as part
of the System Studies in section 9.
Switchracks are low power items intended only for use in LV applications.
Their current rating shall be a maximum of 600 amps and a minimum of 125%
of the maximum operating load.
Switchgear and motor control centres shall be sized to include:
The kVA and corresponding phase current determined in the Electrical
Load Schedule. The phase current shall be used to rate the incoming
circuit breakers, the bus sectionalizer circuit breaker and the busbars.
The chosen continuously rated current for these main items shall be the
next higher standard manufacturable values as quoted in the
international standards.
The symmetrical and asymmetrical fault currents shall be derived from
the Short-circuit Studies outlined in section 9.
The rated time duration for the rated symmetrical short-circuit withstand
current shall be as given in Table 9.
Nominal Short-circuit
voltage, volts
Withstand,
seconds
230000 1
13800 2
4160 2
480 0.5
17.1 Diagrams
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
Interlocking and inter-tripping logic.
Local control and remote-control devices.
Measurements and indication devices.
A grounding switch shall be closed manually to ensure that its circuit is safely
grounded. An electrical or mechanical interlock shall be provided at the circuit
breaker, or its truck if it is a withdrawable breaker, to ensure that the breaker is
open and the circuit is not ‘live’.
Grounding switches shall be provided with pad-locking facilities.
All metal clad withdrawable HV circuit breakers shall be provided with shutters
to shield the live busbar spouts when the breaker is placed in its test position
or it is completely removed. The shutters shall be provided with pad-locking
facilities.
All metal clad withdrawable HV and LV circuit breakers shall be provided with
a ‘test’ position, which is a withdrawn position. It shall be possible to manually
test the open and close functions of the breaker when it is in its test position.
When a breaker is in its operational position, it shall only be possible to close it
remotely.
18. CABLEBUS
Cablebus shall be used for the 13.8kV, 4.16kV and 480V connections between
the secondary windings of the transformers and their downstream switchgear.
The rating of cablebus shall be based on the rating calculated and
subsequently chosen for the switchgear incomer circuit breakers, the bus
sectionalizer circuit breaker and the busbars.
A part of the cablebus shall be outdoors and subject to high summer ambient
temperatures. This situation shall be addressed by suitably de-rating the
ampacity data from manufacturers, and shall be confirmed by the
manufacturers during the quotation stage of procurement.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
section 14.4 Ref [8] for situations where the cablebus needs to pass through a
wall, e.g. in a substation.
19.1 General
The notation of IEEE Standard C37.2 Ref [20], shall be used for all drawings and
documents that address the requirements of relay protection.
The Saudi Aramco document SAES-P-114 Ref [9], shall be used as the
‘base case’ for selecting protective relays for the electrical switchgear and
Controlgear (MCCs).
All relays shall be Intelligent Electronic Device (IED) types.
All relays shall have a communications protocol based on the
requirements of IEC 61850 Ref [21].
Protection requirements for specific equipment is covered within the applicable
SAMSSs and the SAESs. The references listed in Section 3 of SAES-P-114
Ref [9] shall be used for additional guidance and explanations.
Protective relays may be of the multi-function type and may also include
metering functions, alarms and controls.
A main protection function shall be provided with a back-up function.
Where bus-zone protection is used, e.g. in 230kV breaker-and-a-half
switchgear, each element shall be over-lapped by an adjacent element.
All control events, warnings and tripping actions shall be indicated at their
sources, e.g. switchgear panels, and shall be logged, time stamped and
archived by the PSA system. All relays shall be connected to an Ethernet link
and shall use a common communication protocol. Events and tripping shall be
based on SAES-P-126, ‘Power System Automation’.
The incoming power to the TGP shall come from the Saudi Electricity
Company (SEC) through 3x50% 230kV inderground cable circuits. Grounding
facilities for the 230kV phase conductors shall be provided at the terminations
in the 230kV GIS switchgear T80-GIS-SG-701. Signals shall be taken from the
grounding switches and the incoming breakers and converted into fibre-optical
form so that this information of status and protective relay functions can be
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
20.1 Sizing
All power cables shall be de-rated to account for the most onerous conditions
at site. The method of de-rating and sizing the cables shall be in accordance
with either NEC, IEEE 835, IEC 60364, or IEC 60502-2 (2014, Annex B for
grouping in the ground or on trays and racks), see References.
For LV cables, schedules shall be prepared which define the minimum cable
size and maximum cable length for a range of motor ratings, typical power
factors and efficiencies.
For 230kV HV cables, separate cable calculations shall be prepared. These
cables shall be cross-bonded in accordance with IEEE 575, section 5.6.1,
therefore no derating will be applied due to bonding of shields/armour.
For 13.8kV and 4.16kV HV cables, separate cable calculations shall also be
prepared. These cables shall be bonded at both ends with appropriate
derating applied.
Where cables are installed using more than one method, e.g. part direct buried
and part above grade, they shall be rated for the worst-case installation
condition.
SAES-P-100, section 6.3 defines limits on voltage drop in power cables used
for motor loads.
SAES-P-100, section 6.2 defines the steady state voltage range for HV and LV
distribution systems.
Direct buried cables and conduits shall be installed in a single layer, except
where rearrangement is necessary at transitions to multi-layer concrete
encased duct-banks or for entering buildings.
Cables that cross under paved roads, concrete slabs or other areas that would
require extensive or impractical excavations to replace, shall be run in
underground duck-banks consisting of PVC conduit encased in concrete (see
section 10.5 in SAES-P-104).
Conduits and cables that enter buildings shall comply with paragraphs 5.2 and
5.4 in SAES-B-008 Ref [26].
SAES-P-116 Ref [8] covers switchgear but does not mention arc flash and
how to incorporate applicable measures into the design of the switchgear
equipment.
Arc flash protection shall be incorporated in all HV & LV switchgear and
controlgear (MCCs).
IEEE C37.20.7-2007 Ref [28] shall be used as guidance in specifying the
requirements for arc flash mitigation in the design of switchgear and
controlgear rated up to 38kV.
IEEE 1584 Ref [29], or equivalent standard, shall be used for performing the
hazard calculations.
Note that the physical protection of human operators by clothing is covered in
several standards, e.g. NFPA 70E Ref [30], IEC 61482-1-2 Ref [31].
An integrated site wide Power System Automation (PSA) system shall provide
remote control and condition monitoring of the electrical distribution system in
accordance with SAES-P-126 Ref [39].
The PSA main servers, firewalls, and data nodes shall be located in the
Central Control Building (CCB) rack room. Access for Power Systems (PS)
personnel, to perform engineering/maintenance activities, shall be enabled via
the CCB access control system.
The PSA main server shall communicate with local client HMIs located in each
of the TGP substations. The PSA system shall also communicate with the
remote Saudi Aramco Power Systems Department located in Dhahran. The
SCADA communication link between the PSA and SCADA receiving end
(power control center) shall be designed as per SAES-Z-004.
The servers shall communicate with the local Client workstations and monitors
located in the various substations via a dedicated dual-redundant Ethernet
network. The redundant network shall include industrial Ethernet switches and
wire patch-panels in each location.
A signal list shall be prepared by the Detail Design EPC Contractor for the
electrical equipment involved. The Signal List shall include all Inputs, Outputs,
Warning, Alarms and Archiving in the equipment involved, e.g. protective relays,
circuit breaker position status, motor control actions and responses.
24.1 DC Systems
25.1 General
A Skin Effect Current Tracing (SECT) system shall be provided for each of the
two Sulfur lines from the Sulfur Recovery Unit (T75) to the Sulfur Loading and
Handling Facility (T78).
The SECT systems shall derive their power feeds from T75 Unit Substations
SS-SR1 and SS-SR2, with all control panel and transformer equipment
located at the selected substations.
Each SECT system shall include, but not be limited to, the following:
Analysis/calculation of heat loss and heat-up for piping.
Selection of SECT conductor system and accessories.
Engineering package (including isometric drawings and installation
drawings for heater cables, terminations, splices, sensors, etc.).
Installation, testing and commissioning procedures.
Control panel.
Transformer (oil filled, supply voltage 13.8kV).
Distribution panel.
Conductor, heat tube and all accessories.
Fibre optic heat monitoring system.
Technical data for and verification of the pipe support system.
Operation and Maintenance Manuals.
On-site training for field personnel.
The skin effect heat tracing system shall be designed to maximize circuit
lengths in order to minimize requirements for power distribution equipment and
wiring.
The design of the skin effect heating system shall take the following into
consideration:
The heating system shall be designed to produce even heating along the
entire length of pipeline to offset the heat losses and provide the required
heat-up.
The design of the ferromagnetic heat tubes and special electrical
conductors shall provide the required amount of heat for reliable long-term
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
The conductor shall be stranded, Class H, 133 (19X7), nickel-plated copper as
sized by the Heat Tracing Vendor for the specific application. The conductor
shall be insulated with a high temperature (260°C minimum) fluoropolymer
dielectric in such a manner that minimal contact resistance exists between the
conductor strands and the extruded dielectric. The maximum voltage rating for
the conductor shall be 3,500 VAC. In addition to the fluoropolymer primary
dielectric, an outer scuff jacket of fluoropolymer shall also be provided to
protect the cable during installation.
Temperature monitoring for the skin effect system shall be provided by a fibre
optic system running the full length of each sulfur line. This fibre optic
temperature monitoring system shall include, but not be limited to, the
following:
Fibre optic sensing loop for each sulfur line.
Fibre optic terminations, splice boxes and all accessories.
Fibre optic termination panels located in the local PIB.
Dual redundant server (primary and back-up) and data storage drives
located in the local PIB.
Ethernet network interface.
All associated software.
Operator terminal HMI.
The fibre optic temperature monitoring system shall interface to the electronic
temperature controller for each sulfur line. The controller equipment shall be
housed in a common enclosure and shall include, but not be limited to, the
following components:
Circuit protection devices.
Contactors.
On / Off control.
Electronic temperature controllers with high and low temperature alarm,
digital display and high temperature limit switch with manual reset.
Digital voltmeters.
High and low current meter relay with digital display, programmable scale,
and latching for manual reset.
Space heater.
Control power transformer.
Indication lights, Hand-Off-Auto switch, and relays for remote alarms.
26.1 General
27.1 General
The lighting design and illumination levels shall be in accordance with SAES-
P-123 Ref [36], which refers to a set of IESNA lighting documents. The
selection of luminaires shall be based on lifecycle economic analysis per
SAES-P-123, section 5.2.
Lighting and small power shall be derived from 400V distribution panel boards
located either in each of the substations or in the field.
Control of area lighting shall be by photocell with hand/off/auto over-ride
switches. The area lighting shall be operated on a 480/400V, 3-phase, 4-wire,
(230V, 1ph, 60Hz) electrical distribution system derived from a 480/400V
transformer, supplied from the adjacent process area substations.
Fixtures and fittings shall be suitably certified for the electrically classified area
in which they are installed.
LED luminaires shall be used in all indoor and outdoor locations/applications.
During the detail design stage of the project, each luminaire manufacturer
shall provide the test reports listed in sub-section 5.3.3 in SAES-P-123 Ref
[36]. The luminaire manufacturer shall provide a certificate issued by a third
party notifying body that verifies the performance of the luminaire, including
declared lifetime and lumen maintenance based on the ambient temperature.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
The lifetime of a LED luminaire shall be not less than 50,000 hours when
associated with the following:
a) Ambient temperature at the TGP site.
b) Failure rate to be not more than 3% for the entire lifetime period of the
luminaire.
Refer to section 5.7.3 in SAES-P-123 for general lighting in rooms and service
areas.
Battery rooms shall be provided with enclosed and gasketed (i.e. vapour-tight)
corrosion-resistant luminaires.
Lighting shall be provided around the perimeter Safety and Security Directive
(SSD) fence in accordance with SAES-O-204 Ref [38] and National Security
Standards.
Power to the fence lighting shall be to sub-section 4.4 in SAES-O-207 Ref [16].
Light fittings shall be suitable to operate from a 230V 60Hz 1ph power supply,
distributed from lighting panels with a 400-230V, 60Hz, 3ph, 4 wire system.
The security fence lighting system shall be designed using LED lamp fittings
Notes:
1) Perimeter fence lighting for class 1 as mandated by HCIS in SEC-02
section 5.4.3.3. Minimum illumination levels for perimeter fence lighting as
per SEC-04 section 5.1.
2) Area Security lighting for class 4 as mandated by HCIS in SEC-02 section
5.6.3.2. Minimum illumination levels as per SEC-04 section 5.2.
Cabling for the security fence lighting shall be direct buried. The SSD lighting
shall be controlled by a photocell system with a hand/off/auto over-ride switch.
The off-plot Industrial Support Facilities (ISF) shall derive its power from the
TGP power distribution system.
HV power to the ISF shall be provided by two 13.8kV ring feeders fed from the
13.8kV distribution switchgear (T80-MS1-SG-303) located in Main Substation
MS1. These ring feeders shall follow a buried cable route exiting the TGP
industrial facilities into the ISF (T81) area.
Power distribution within the off-plot ISF shall be via a buried 13.8kV ring main
serving loop-in/loop-out Ring Main Units (RMUs).
Power to each ISF building/facility shall be provided by a pad mounted RMU
local to the building, which in turn feeds a single pad mounted 13.8-0.48kV
Saudi Aramco 2616-ENG (03/99)
Fire Station.
Medical Clinic.
Administration Building.
Main Gate Area and Security Check Point.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Each EDG shall connect via an ATS to the associated building switchboard.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
Abbreviation Description
AC Alternating current
ANSI American National Standards Institute
AFD Adjustable frequency drives (see also VFD)
ATS Automatic transfer scheme
AWG American wire gauge
BRA Building risk assessment
BSP Bulk supply point
CB Circuit breaker
CCB Central control building
CRI Colour Rendering Index
CT Current transformer
DC Direct current
DOL Direct-on-line
Electrical Engineering Division, Consulting Services
EED
Department. Saudi Aramco
EDG Emergency diesel generator
ETAP Electrical Transient Analysis Program
F Power system frequency
FEL-3 Front end loading stage 3
Gas insulated busduct or busbars (also known as isolated
GIB
busducts)
GIS Gas insulated switchgear
GOSP Gas and oil separation plant
HCIS High Commission for Industrial Security
HMI Human Machine Interface
HV High voltage
HVAC Heating, ventilation and air conditioning
HP Horse power
HPS High pressure sodium
Hz Electrical frequency in Hertz
IDMT Inverse definite minimum time (protective relay)
IEC International Electrotechnical Commission
IED Intelligent electronic device
IEEE Institute of Electrical and Electronics Engineers
IESNA Illuminating Engineering Society of North America
2
It RMS current-squared-time fault withstand capability
kV Kilo-volts
kVA Kilo-volt-amperes
kvar Kilo-volt-amperes-reactive
kW Kilo-watts
LED Light emitting diode
LV Low voltage
MCB Miniature circuit breaker
MCC Motor control centre
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
Abbreviation Description
NFPA National Fire Protection Association
NO Normally open
OHTL Overhead transmission line
ONAF Oil natural air forced (cooling)
OFAF Oil forced air forced (cooling)
ONAN Oil natural air natural (cooling)
PC Personal computer
PIB Process Interface Building
Plt Long-term time factor
PT Potential transformer
PP Project proposal
PSA Power system automation (system)
Saudi Aramco Power Systems Planning and Engineering
PSP&ED
Department
Pst Short-term time factor
PF Power factor
SABP Saudi Aramco Best Practices
SAES Saudi Aramco Engineering Standard
SAMSS Saudi Aramco Materials System Specifications
SCR Silicon controlled rectifier
SEB Security equipment building
SEC Saudi Electricity Company
SF6 Sulphur hexafluoride
SSD Safety and security directives
TGP Tanajib Gas Plant
THD Total harmonic distortion
TOP Tanajib Oil Plant
TSB Tanajib Substation Building
UPS Uninterruptible power system
VAC Alternating voltage
VFD Variable frequency drives
VT Voltage transformer
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
30. REFERENCES