Dynamic Simulation of Shell and Tube Hea
Dynamic Simulation of Shell and Tube Hea
NOVEMBER 2005
iii
To my beloved father and mother; Hj. Tajuddin Dollah and Hjh. Mariawati Hashim,
siblings; Mohd Zainal, Azlina Aminah, Aisyah, Nurul Natasya
and late brother; Mohd Syahfiq.
iv
..
ACKNOWLEDGEMENT
First of all, I would like to thank to Allah S.W.T., because giving the
opportunity and strength to me to overcome every obstacles to complete this
research.
I would like to thank my supervisor Mr. Mohd Yusri bin Mohd Yunus, who
helped me a lot during the progress of the research project, either in the way of
searching the required information or giving me valuable opinions and
encouragement. Without his continued support and generosity in sparing their
precious time to guide me, this research would not have been the same as presented
here. I would like to express great appreciation my examiner, Puan Wan Hanisah
binti Wan Ibrahim, for giving the professional guidance to me, besides examining
my thesis report.
Last but not least, I am grateful to my beloved parents for always giving me
an enthusiasm and morality support all along my study.
v
ABSTRACT
ABSTRAK
TABLE OF CONTENTS
TITLE PAGE i
DECLARATION ii
DEDICATION iii
ACKNOWLEDGEMENT iv
ABSTRACT v
ABSTRAK vi
LIST OF TABLES x
LIST OF FIGURES xi
1 INTRODUCTION 1
1.1 Introduction 1
1.2 Shell and Tube Heat Exchanger Plant 2
1.3 Benefits of Dynamic Simulation 3
1.4 Problem Statement 4
1.5 Research Objectives 4
1.6 Research Scopes 5
viii
2 LITERATURE REVIEW 6
2.1 Heat Transfer 6
2.1.1 Overall Heat Transfer Coefficient 7
2.2 Shell and Tube Heat Exchanger 8
2.2.1 Single-pass 1-1 Exchanger Design 8
2.2.2 Flow Arrangements 9
2.2.3 Applications of Heat Exchanger 11
2.3 Dynamic Simulation 13
2.4 Aspen Software 14
2.5 Literature Review of Previous Study 15
3 METHODOLOGY 18
3.1 Introduction 18
3.2 Data Collection 19
3.2.1 Shell and Tube Heat Exchanger 20
3.2.2 Water Tank 21
3.2.3 Heating and Cooling Systems 21
3.2.4 Circulation Pumps 22
3.2.5 Other Specifications 22
3.3 Simulation Process 23
3.3.1 Steady-state Simulation 24
3.3.2 Dynamic Simulation 32
3.4 The Experiment 36
3.5 Results Analysis 39
3.6 Results Comparison and Validation 39
9
REFERENCES 59
APPENDIX A 62
APPENDIX B 65
APPENDIX C 66
x
LIST OF TABLES
.
.
LIST OF FIGURES
LIST OF ABBREVIATIONS
SYMBOL DESCRIPTION
ds Shell diameter, m
HV Valve
Lt Length of tubes, m
LB Baffle length, m
NT Number of tubes
P Power, Kw
P Pressure, bar
PT Tube pitch
Q Heat duty, kW
T Temperature, ºC
∆T Temperature drop
t Time, s
V Capacity, L
xvi
..
.
LIST OF APPENDICES
INTRODUCTION
1.1 Introduction
The units or the equipments of shell and tube heat exchanger (STHE) in
today’s plants are much more complex. This situation is happened because of the
improvement to this equipments to increase the production while to make sure the
operation in a safely mode. STHE has more than one type based on it classification
according to the transfer process, construction, flow arrangement, and also heat
transfer mechanisms. Simulation is the best method to train operators to understand
the inner-workings of these complicated processes.
Many refineries are being operated with crude slates that change daily based
on market conditions. This creates constant swings and instabilities in unit
operation. In addition, to maximize profitability, many units such as STHE are run
to capacity limitations. This makes operation much more demanding. The operators
need to be constantly alert with the frequent of operation changes. Training on a
real-time dynamic simulation is the best way to prepare for this situation.
A simulation can be used to ensure that all of the equipment such as STHE
for a new plant is consistently sized. Many past studies have found mis-sized valves
or other mechanical equipment that would have created a capacity limitation. In
addition, the simulation can be used to determine if there will be problems during
startup or shutdown. For example, some complicated heat exchanger trains work
well during normal operation but don’t provide sufficient heat input during startup.
Provided the simulation study is carried out at the right time in the design
phase, the results of the simulation can be used to verify or change equipment design
before it is purchased. In effect, this type of study can prevent the need for costly
debottlenecking after the plant is built.
At this time, there still have plants which run the process by controlling it
manually. So that, dynamic simulation of STHE process is the method to solve this
situation by turn the operation into automatically controlling by using simulation.
The task here is to relate the input and output variables. The simulation method that
is used in the STHE also can be applied for any other equipment by put the required
data according to the equipment that is used.
Another objective is to define whether the simulated process has the same
characteristics in comparison with the real process. In order to validate the results
experiment will be run in the laboratory by comparing the temperature differences
with the simulation results. This analysis is useful to make sure that the plant can be
run in the real situation.
5
Besides that, the scope also is running the STHE experiment to study the
temperature variable that change with time. This project will be just including the
counter-flow exchanger. Certainly by doing the project, the study is more to the
results comparison between the simulation using Aspen software with the
experiment.
.
CHAPTER 2
LITERATURE REVIEW
q = m h C p ∆Th (2.1)
q = UA∆Tm (2.2)
Here m h is the mass flowrate, Cp is specific heat, ∆Th is hot water temperature
differences, U is the overall heat transfer coefficient, A is the heat transfer surface
area, and ∆Tm is the effective mean temperature difference.
In process industries, shell and tube heat exchanger (STHE) are used in great
numbers, far more than any other type of exchanger. More than 90% of heat
exchangers used in industry are of the shell and tube type (Chisholm, D., 1980). The
STHE are the “work horses” of industrial process heat transfer (Minton, P.E., 1990).
They are the first choice because of well-established procedures for design and
manufacture from a wide variety materials, many years of satisfactory service, and
availability of codes and standards for design and fabrication. They are produced in
the widest variety of sizes and styles. There is virtually no limit on the operating
temperature and pressure. STHE very adaptable and flexible and can operate over
the full range of pressures and temperatures encountered in chemical processes
(Kuppan, T., 2000).
Other types of heat exchangers are used when economical. Although the
application of other types of heat exchangers is increasing, the STHE will continue
its popularity for a long time, largely because of its versatility. STHE are used in the
process industries, in conventional and nuclear power stations as condensers, steam
generators in pressurized water reactor power plants, and feed water heaters. They
are also proposed for many alternative energy applications including ocean, thermal
and geothermal.
In this project, the type of STHE used is single-pass 1-1 exchanger which is
the simplest type of STHE. It has one shell-side pass and one tube-side pass, where
one shell serves for many tubes. This kind of STHE is the most common due to its
cheapness, simplicity, and ease of manufacture.
those of the tube-side fluid. To promote cross-flow and raise the average velocity of
the shell-side fluid, baffles are installed in the shell. In the construction shown in
Figure 2.1, baffles consist of circular disks of sheet metal with one side cut away
(McCabe, W. L., et al, 2001). Common practice is to cut away a segment having a
height equal to one-fourth the inside diameter of the shell. Such baffles are called 25
percents baffles. The baffles are supported by one or more guide rods.
In parallel-flow heat exchangers, the two fluid streams enter together at one
end, flow through in the same direction, and leave together at the other end as shown
in Figure 2.2a (Kakaç, S., et al, 2002). In counter-flow heat exchangers, two fluid
streams flow in opposite directions as shown in Figure 2.2b. In a single cross-flow
10
heat exchangers, one fluid flows through the heat transfer surface at right angles to
the flow path of the other fluid. Cross-flow arrangements with both fluids unmixed
or one fluid mixed and the other unmixed are illustrated in Figures 2.2c and 2.2d.
Figure 2.2 Heat Exchanger Flow Arrangement; (a) parallel-flow; (b) counter-
flow; (c) cross-flow, both fluid unmixed; (d) cross-flow, fluid 1 mixed, fluid 2
unmixed
Kakaç, S. and Liu, H., (2002) have discussed that the most common heat
exchangers are two-fluid heat exchangers. Three-fluid heat exchangers are widely
used in cryogenics. They are also used in chemical and process industries such as air
separation systems, purification and liquefaction of hydrogen, ammonia gas
synthesis, etc.
Application Examples
Transportation Car cooling, radiator, and oil cooling.
Converter, amplifier, personal computer, and
Electronics
transformer.
Household Electric heater, hot water tank, and air conditioner.
National defense Aircraft cooling, and engine cooling.
Industry Cooling tower, distiller, and water-heat recovery.
Geothermal energy, boiler, electricity, freezing A/C,
Energy
super-conduction, heat engine, and cogeneration.
Farm and Fishery Freezer, and vacuum fridge.
Environment Engineering Heat recovery, and water-water cooling.
13
The purpose with the dynamic simulations is to make a comparison with the
real experiments. This comparison can only be made if the simulation and real
experiments experience the same condition. Dynamic plant simulation is a powerful
tool that helps managers and engineers link business operations to process operations
and faced the challenging as state above. Dynamic simulation enables manufacturers
to ensure safety and environmental compliance. It is also can improve operability,
start-up and shut-downs while can achieve consistent product quality.
14
Software Company
AspenPlus/AspenDynamics Aspen Technology
HYSIS Hyprotech Inc.
Dymola Dynasim
GPSS/H Wolvrine Software Corporation
SLX Wolvrine Software Corporation
SIMSCRIPT II.5 CACI Products Company
AweSim Symix (formerly Pritsker Corporation)
SIMPLE++ AESOP Corporation
Extend Imagine That Inc.
15
In the research, perturbation was given during the process, to analyze the
effect to the temperature and flow characteristics. The same disturbance also was
done during the experiment to make a comparison. The study on perturbation was
done to verify whether the heat exchanger model is the good description of the real
heat exchanger.
From the research, the temperature and flow differences comparison between
the simulation and experiment was not more or less than ±10%. By pasting the
sampled data into tables that controls the temperatures and the flows in the model,
almost the same disturbance can be performed. Figures 2.3 and 2.4 above are a
comparison between the simulated perturbation and the experimental perturbation
that was done by Kauhanen, P. All simulated perturbations have the same pattern
that is shown in these figures.
CHAPTER 3
METHODOLOGY
3.1 Introduction
Every simulation study begins with a statement of the problem. The task is
already recognizing, which is to run a dynamic simulation of shell and tube heat
exchanger (STHE) process. The first step of simulation process is gathering or
collecting data for each of the equipment and operation condition that will be use in
the simulation. These data is very important, because it will be filled in the dialog
box during the simulation process. This simulation process will be run at Aspen
software. Later, laboratory experiment of STHE will be done. The value that will
use in the simulation process must be same when running the laboratory experiment.
So that, the results from the simulation will be analyze because lastly, it were needed
to compare with the results from the experiment. After that, the validation is to
determine whether the results from the simulation can be used in the real process.
Figure 3.1 is the summary of the methodology of the project. Finally, all the process
and the achievement results will be record in a report.
19
Data Collection
Simulation Process
The Experiment
Data Analysis
Firstly, the data will be collected from a manufacturing company which has
built the model of STHE and has the information that will be needed for the input
parameters to the model. It is helpful when validating a model to have real data to
compare the performance measures of the model with the experimental. These raw
data will provide a basis for establishing the model's input parameters and will help
identify those input parameters requiring more precise data collection. Even when
using raw data, a triangular distribution will be based on a minimum, maximum, and
most likely value, rather than simply use an average value. The data that needed here
is one that related to the equipment that we used in the simulation process. The exact
value that we used is the less assumption can be made for the simulation. This
information data is the variables that use in the STHE such as temperatures,
pressures, heat duty, and flow rates.
20
The information data of STHE that shows in Table 3.1 for that installed in the
laboratory can get from the manual report which is supplied from the manufacturer
that builds this equipment.
Cylindrical water tank type is used to storage for both hot and cold water in
the different tank. Hot water tank is more special because at the bottom inside of this
tank was installed with heater to get the desired temperature before entering the
STHE.
Heater is used to heat up the hot water that out from the STHE. This is
because, the temperature for the hot water outlet from STHE is colder while it must
hotter from it before entering the STHE at the inlet temperature as it decided at
initial. Meanwhile, Air cooler will be used as the cooling system. This air cooler is
used to cool down the cold water that out from the STHE. This is because the
temperature for the cold water inlet to the STHE will be hotter after out from it. So
that, it needs to decrease the temperature by using air cooler before entering the
STHE again.
22
For other specification, there have three things that need to recognize or
decide first that are components, flowsheets, and streams.
The component that is used in this simulation is water (H2O) depends on the
component that used in the real experiment. If the simulation used other component,
make sure while doing the experiment, the same component also must be used.
The flowsheet here is the connection of the streams that used in the
equipment must be right, which the inlet and outlet streams must be in the right
place. For example, where should the streams for both hot and cold water must
connect to after go out from the STHE.
23
Lastly are the streams. Actually, the value for temperature, pressure, total
flow and composition are decided by us but the value that is used must be in the
range of the equipment can operate.
Input Output
disturbance Simulation model disturbance
or process
We interact with a block through its ‘dialog box’. The dialog box is a
window shown by clicking twice on the graphic or ‘Icon’ of the block. The dialog
box can contain variables, buttons, checkboxes, control buttons, data tables, as well
as text. These variables, buttons, and others can be changed by us by typing in new
values or by pointing and clicking with the mouse. A third layer, which normally
would be invisible to us, is the source code. Variables in the dialog box as well as
variables received from other blocks are all available to the source code. A
simulation can also write variables to a report file and or a debugging file. So that,
the input can be modify, insert new model blocks and view results dynamically all
without having to enter or even see a line of code.
Actually, there is another stage before doing a dynamic simulation. The stage
here is steady-state simulation.
24
First thing that need to do in simulation is by open the Aspen software new
file. To open AspenPlus User Interface from the Start, click Start, point to All
Programs, point to Aspen Tech, point to Aspen Engineering Suite, point to
AspenPlus 12.1, and then click AspenPlus User Interface.
1. AspenPlus Startup
i. Choose Template
ii. Click Ok
2. Click New
i. In the Simulation tab, click Gas Processing with Metric Units
ii. Choose Flowsheet for Run type
iii. Click Ok
3. Click Connect to Engine
i. Choose Local PC for Server type
ii. Click Ok
After open the Aspen software new file the interface will be appear as shown
in Figure 3.3. During the simulation process, the important thing that needs to do in
this stage is to fill all the information data that are state in the Aspen software.
Below are the steps to do this steady-state simulation:
1. First equipment, the model of STHE one-pass shell and one-pass tube (1-1,
exchanger) needs to choose from the list of equipment and installed in the
process flowsheet interface. This STHE is get from the Heat Exchanger tab
below the interface. The STHE that is used is type of HeatX.
25
2. After that double click the graphic of STHE, the dialog box will be appearing
as shown in the Figure 3.4. The user can interact with these input data
through its dialog box. Below are the input data that need to filled in to the
dialog box:
The STHE that was installed in the laboratory experiment has no nozzle.
So that, just the specification calculation for shortcut can be choose to fill the
data. While, the calculation for detailed cannot be done because even the box
can be filled with the length, diameter and number of tube, and so on with the
shell, but there is no nozzle data that must be filled in for nozzle required data.
3. The simulation can be run after fill up the entire requirement input data. The
result from control panel must be end with “Simulation calculations
completed”. While from the Results summary, the status must stated with
“Calculations were completed normally”. All the results can be seen at
Streams from Results summary.
4. After the first results are available with no error, so that the second equipment
or block can be installed one by one in the Process Flowsheet Window to
make a complete flowsheet as shown in Figure 3.12. Then, the status must
also state as normal with no error such as in Figure 3.13. The overall results
summary streams can be seen as in Chapter 4.
The steady-state simulation does not need information that has no effect on
steady-state results such as sizes of control valves and others. However, the dynamic
simulation does need this information because the dynamic response of a process
unit depends on the size of the equipment. The time constant of the system is
dictated by its size, volume or mass, relative to the flowrate, heat-transfer rate, etc.
Therefore all equipment must be sized before dynamic simulations can be performed.
The other important aspect of the flowsheet that must be specified in order to
conduct a dynamic simulation of a process is the plumbing. This includes installing
pumps, compressors and control valves. This task was already done during the
steady-state simulation.
There are two types of dynamic simulations that are “Flow Driven Dyn
Simulation” and “Pressure Driven Dyn Simulation”. In this project it will only
consider Flow Driven Dyn Simulation.
There are several steps that must be done in order to do a dynamic simulation.
So those, the first thing that need to do by exporting the steady-state into dynamic
simulation. Below are the steps to save into Flow Driven Dyn Simulation file:
After that, to run this dynamic simulation, the run options must be filled on in
order to control the simulation time. Figure 3.16 below show the example of the
value that need to fill in Run Options window.
Then, the dynamic simulation now can be run. The result in the graph form
can be view from the Simulation Explorer. To view the results:
Figure 3.18 Schematic Diagram for Shell and Tube Heat Exchanger (Model: HE 667) in Laboratory
38
The experimental setup that is show in Figure 3.18; STHE is located to the
middle of the figure. For the cold water flow, FT2, mains cold water, controlled by a
flow controller operating a valve, is used. Temperature indicators measure the cold
water inlet and outlet temperatures, TT3 and TT4. For the hot water flow, FT1, a
pump, controlled by a flow controller, pumps water through a heated tank where a
heater, controlled by a temperature controller, heats the water. Temperature
indicators measure the hot water inlet and outlet temperatures, TT1 and TT2. TI1 is
also used as the input to the temperature controller. The heat exchanger was
originally built to study the principles of heat transfer; its application was then
broadened to study transient dynamic and control. In this initial collaboration, the
focus has been on the controller for the hot water inlet temperature.
During the experimental, of course the same value that was use in the
simulation is also use in the input variables of the experiment. The values of
variables that to use to run the experiment must be same with the data that are fill in
the simulation. After the experiment is done, the results also need to be recorded.
In order to run the experiment, it is important that the user read and fully
understand all the instructions and precautions stated in the manufacturer’s manuals
supplied with the unit prior to operating. In this project, it only counter-current flow
that will be study on. Based on Figure 3.18, the arrangement valve is shown in Table
3.5 below.
For valve HV5 and HV15 are leaving alone because these valves will be open
later and then adjusted to obtain the desired flowrates for both hot water and cold
water streams.
39
So as to get the results, the data must be recorded for variables, both hot and
cold water flowrates and also both inlet and outlet for hot and cold water
temperatures. The data will be stop taken after the results for inlet temperature for
both hot and water streams. These data will be discussed in Chapter 4.
Comparison between the results from the simulation and the experiment is the
main method to know if the simulation is successful or not. The results for both of it
can be compared because the equation such as material and energy balance is
specific and similar that applied for both simulation and experimental. This
comparison also will be discussed in Chapter 4.
CHAPTER 4
The comparison between the results from the simulation and the
experimentation should be the same. But if there is a difference between the results,
the error for getting the same values is expected to be around ±10% (Kauhanen, P.).
This is because, the equations that are used in the simulation process such as material
and energy balances are specific and similar with the shell and tube heat exchanger
(STHE) that will be run in the laboratory experiment. The error mostly happened
because of the experimentation and assumption during the simulation process.
Initially, the temperature for hot water inlet is fixed with 50ºC while 35ºC for
cold water inlet. After the simulation was run, the results show that the temperature
for hot water inlet is 50.2ºC and 35.1ºC for cold water inlet just after two iterations.
This iteration is done until there is no errors occur and the process was balance. The
steady-state simulation results are shown as in Table 4.1.
41
Refer to Table 4.1, the temperature is about 50.2ºC for hot water inlet (HI)
stream to STHE and the temperature is down to 40.1ºC when leave STHE at stream
HO. The temperature was maintained through the valve 5 (HV5) and hot water tank.
While the water passes through the heater, the temperature was increase to 50.0ºC at
stream H3. This is because the water is needed to be heated up before entering
STHE again. The temperature is increase about 0.2ºC to 50.2ºC after passes through
the hot water pump. This is happened because of the effect from the pressure
difference which, more pressure is needed to rise up the water to entering STHE.
While for the temperature for cold water inlet (CI) stream to STHE is about
35.1ºC and the temperature is up to 40.8ºC after passes through the STHE at stream
CO. The temperature was decrease to 35.0ºC at stream C2. This is because the
water is needed to be cool down by air cooler before entering STHE again. Then the
temperature was maintained for stream C3, C4, and C5. The temperature is increase
about 0.1ºC to 35.1ºC after passes through the hot water pump. This phenomenon is
also happened because of to rise up the water.
In this steady-state results, the time that is taken to achieve is not showed.
The results from the steady-state simulation are very important to analyze. This is to
make sure that the available results are seemed to be as existent while run the
experiment later. It means that, the values of the parameters that calculated by the
simulator are not presented as much and much larger or smaller than the common
sense understanding. For example, by viewing Table 4.1, while stream H2 is passing
through the heater, the temperature is increase to achieve certain value that depends
with the required data input to the heater.
44
Table 4.2 Simulation Results Table for Inlet Temperature; (a) Hot Water; (b)
Cold Water
(a) (b)
While in the dynamic table, the time for the temperature reached the steady-
state value are showed. Table 4.2 show the results data from the dynamic simulation.
According to Table 4.2a, hot water inlet temperature achieved the steady-state value
50.186839ºC at 50 seconds. While the cold water inlet temperature, Table 4.2b
achieved the steady-state value 35.104163ºC at 30 seconds.
The value of the simulation results is more accurate with the six decimal
points. The independent variable, time, is run in the seconds’ unit. This is because
the results from the experiment also will be recorded in that unit.
These data were presented in the form of graph as shown in Figures 4.1 and
4.2. The horizontal line is the steady-state values that are not change with time.
45
Figure 4.1 Simulation Graph of Hot Water Inlet Temperature versus Time
Figure 4.2 Simulation Graph of Cold Water Inlet Temperature versus Time
46
Table 4.3 below show the overall results of both inlet and outlet for STHE
equipment.
Table 4.3 Overall Results for STHE; (a) Hot Water Inlet Stream; (b) hot Water
Outlet Stream; (c) Cold Water Inlet Stream; (d) Cold Water Outlet Stream
(a)
(b)
47
(c)
(d)
48
The experiment results were recorded as stated for the experiment stage in the
methodology at Chapter 3. The results were taken from initial until the temperature
for both hot and water inlet temperature does not change over the time. Table 4.3
below show the results of this experiment.
Temperature (ºC)
Time (seconds)
HI CI
0 50.1 32.6
10 50.0 32.8
20 49.9 32.9
30 49.9 33.0
40 49.8 33.0
50 49.5 33.0
60 49.4 33.1
70 49.2 33.1
80 49.2 33.1
90 49.3 33.2
100 49.1 33.3
110 49.0 33.3
120 49.0 33.3
130 49.0 33.3
140 49.0 33.3
150 49.0 33.3
The table shows that the steady-state value for hot water inlet temperature is
49.0ºC at 110 seconds. While the cold water inlet temperature achieved the steady-
state value 33.3ºC at 100 seconds 10 seconds earlier than the hot water inlet
temperature. Figures 4.3 and 4.4 are the results plotted from the table above.
49
50.2
50.0
49.8
Temperature (deg C)
49.6
49.4
49.2
49.0
48.8
0 20 40 60 80 100 120 140
Time (seconds)
Figure 4.3 Experiment Graph of Hot Water Inlet Temperature versus Time
33.4
33.3
33.2
33.1
Temperature (deg C)
33.0
32.9
32.8
32.7
32.6
32.5
32.4
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
Time (seconds)
Figure 4.4 Experiment Graph of Cold Water Inlet Temperature versus Time
50
Equation 4.1 that showed below is how to calculate the percentage error
occurred between simulation and experiment
Simulation − Experiment
% error = × 100% (4.1)
Experiment
By refer to the simulation results, the balances were achieved after two
iterations. That is mean, the calculation by the simulator will be running up until the
material and energy were balanced. By doing the comparison, the hot water inlet
temperature difference between the simulation and experiment are from 49.0ºC to
51
The results from the dynamic simulation also need to compare with the
experiment to examine the time for dynamic and the temperature differences. In the
dynamic simulation, the difference between each result is about three decimal points.
While the results for experiment was digitally showed in one decimal point
difference in control panel.
By doing the comparison, the simulation temperatures for both hot and cold
water inlet were reach the steady-state 60 to 70 seconds earlier than the experiment
temperatures. The errors that are calculated were between 0.17% until 7.68% as
shown in Table 4.6. The calculation was also use the same equation as in the steady-
state comparison. This stated that the error for getting the same values was in the
range target of ±10%. The study on temperature comparison was also successfully
done by achieving the range of expected results.
52
Temperature (ºC)
Time Error (%)
Simulation Experiment
(seconds)
HI CI HI CI HI CI
0 50.186964 35.104038 50.1 32.6 0.17 7.68
10 50.186939 35.104080 50.0 32.8 0.37 7.02
20 50.186914 35.104121 49.9 32.9 0.57 6.70
30 50.186889 35.104163 49.9 33.0 0.57 6.38
40 50.186864 35.104163 49.8 33.0 0.78 6.38
50 50.186839 35.104163 49.5 33.0 1.39 6.38
60 50.186839 35.104163 49.4 33.1 1.59 6.05
70 50.186839 35.104163 49.2 33.1 2.01 6.05
80 50.186839 35.104163 49.2 33.1 2.01 6.05
90 50.186839 35.104163 49.3 33.2 1.80 5.74
100 50.186839 35.104163 49.1 33.3 2.21 5.42
110 50.186839 35.104163 49.0 33.3 2.42 5.42
120 50.186839 35.104163 49.0 33.3 2.42 5.42
130 50.186839 35.104163 49.0 33.3 2.42 5.42
140 50.186839 35.104163 49.0 33.3 2.42 5.42
150 50.186839 35.104163 49.0 33.3 2.42 5.42
Refer to the table above; the temperatures for experiment take longer time
than simulation because the flowrate also still change over the time. It showed that
the flowrate change will affect the temperature results. These results that showed in
Table 4.6 were presented in graph plotted in Figures 4.5 and 4.6
53
Simulation
50.18698 50.2
Experiment
50.18696
50.0
49.8
50.18692
49.6
50.18690
49.4
50.18688
49.2
50.18686
49.0
50.18684
50.18682 48.8
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
Time (seconds)
Figure 4.5 Comparison Graph of Hot Water Inlet Temperature between Simulation and Experiment
54
Simulation
35.10418 33.4
Experiment
33.3
35.10416
33.2
33.1
35.10412
33.0
35.10410 32.9
32.8
35.10408
32.7
35.10406
32.6
35.10404
32.5
35.10402 32.4
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
Time (seconds)
Figure 4.6 Comparison Graph of Cold Water Inlet Temperature between Simulation and Experiment
55
Finally, the last stage on this study is to validate the results. By refer to the
difference calculation by compared the results between simulation and experiment
showed that the percentage errors are not out from the target value. The data from
the simulation process can be used to another application for example in the process
control. The study on process control later no needs to run the experiment to get the
results. Therefore, the plant now can be controlling automatically. This is the more
efficient way to handle the plant rather than controlling it manually.
CHAPTER 5
5.1 Conclusion
Ideally the dynamics of the process should be considered at the very early
stages of the development of the process. Certainly at the pilot plant stage, trade offs
between design and control should be explored, and basic regulatory control
structures should be developed and tested. The engineering time expended at the
early stages can reap enormous economic benefits later in the project in terms of
rapid, trouble-free start-up, reduced product quality variability, less frequent
emergency shutdowns, reduced environmental contamination and safer operation.
Fortunately have the ability to perform plantwide dynamic simulations have also
increased.
57
By doing this project, there are many benefits that can get by study of the
dynamic simulation of STHE process or any other plant. The simulation technique is
the basis step before build up a process plant. Actually, the more study on the
simulation skill, the more understanding, information, and knowledge that can get to
improve the plant.
5.2 Recommendations
It is also recommended that the further study will be continuing with varying
the flowrate. This study will give more understanding during taking the dynamic
results. This is because; the results will show the time of the temperature to achieve
steady-state condition in different flowrates. In addition, the effects of either cold or
hot water flowrate can be study on the heat transfer coefficients if the hot or water
flowrate is constant.
Besides that, the research also can be continuing by studying on the pressure
drop analysis. The pressure drop can be analyzed either in tube-side or shell-side.
58
The recommendations that stated are just three studies on parallel-flow, vary
the flowrate, and pressure drop analysis. There are lots of other analysis can be study
on this dynamic simulation of STHE process.
59
REFERENCES
McCabe, W. L., Smith, J. C., and Harriott, P. (2001). Unit Operations of Chemical
Engineering. 6th edition. New York: McGraw-Hill.
Najim, K. (1989). Process Modeling and Control in Chemical Engineering. New
York: Marcel Dekker.
Penha, R. L., Hines, J. W., and Upadhyaya, B. R. Monitoring and Diagnosis of a
Heat Exchanger Using Hybrid System Modeling.
Robertson, N., and Perera, T. Automated Data Collection for Simulation. Volume 9,
Issues 6-8: 349-362.
Selmer, A., Goodson, M., Kraft, M., Sen, S., McNeill, V. F., Johnston, B. S., and
Colton, C. K. (2004). Process Dynamics and Control Experiment Performed
Across the Atlantic. U.K.: University of Cambridge.
Shah, R. K., and Sekulić, D. P. (2003). Fundamentals of Heat Exchanger Design.
New Jersey: John Wiley & Sons.
Tubular Exchangers Manufacturers Association (TEMA) (1988). Standards of the
Tubular Exchanger Manufacturers Association. 7th edition. New York:
TEMA.
Young, J. of Aspen Technology. Innovative Training Program to Increase Process
Plant Skill Levels While Reducing Costs. Cambridge: Aspen Technology, Inc.
.
61
APPENDICES
62
APPENDIX A
Operating Instructions of Shell and Tube Heat Exchanger
(c) Instrumentations
Measurements of inlet and outlet temperatures for hot and cold water streams.
Height : 2.00 m
Width : 2.00 m
Depth : 1.22 m
APPENDIX B
Schematic Diagram for Shell and Tube Heat Exchanger (Model: HE 667) in Laboratory
66
APPENDIX C
Process Flow Diagram for Shell and Tube Heat Exchanger in Simulation