DRAWING CONTROL PROCEDURE
Page 1 of 4
REVISION HISTORY
Date
Note: The details and the reason of change are documented in the Revision History state above and file at DCC.
This procedure is a “controlled” document and authorized for use. When printed from this share drive, this
document is uncontrolled. Before using a printed copy of this document, ensure that it is the same as the latest
version on share drive.
CSL TECHNOLOGIES (M) SDN BHD Ref. No. CS-P12
LRC TECH (M) SDN BHD Revision No. 01
Effective Date 01/03/2011
DRAWING CONTROL PROCEDURE
Page 2 of 4
1.0 PURPOSE
To ensure all drawings with all dimension and approved by head of department, it shall distributed
to production department used are the latest revision.
2.0 SCOPE
This procedure shall apply to all the drawings received from customer, generated by CSL & LRC
and must be indicate project code and distributed to users.
3.0 DEFINITIONS
4.0 PROCEDURE
4.1 DRAWING CONTROL
Documents
Process Flow Description Personnel
/ Ref.
Retention Method Keep in respective Save in computer hard disc identified with file name:
customer files File Name:
P1 / P2 XXXX (Project No.)/AC/FZ/xxx (Product
Name – Refer to Appendix I)
Retention Period Original drawing shall be kept and obtain approval from HOD before dispose.
Latest revision of obsolete drawings shall be kept and obtain approval HOD
before dispose.