MS Field Instrument Installation
MS Field Instrument Installation
Revision 0
PROJECT NAME _____ Page 1 of 11
METHOD STATEMENT
FOR
FIELD INSTRUMENTS INSTALLATION
INDEX
1. PURPOSE
2. SCOPE
3. REFERENCES
4. DEFINITIONS
5. RESPONSIBILITIES
6. PROCEDURE
8. SAFETY INSTRUCTIONS
9. ATTACHMENTS
DESCON ENGINEERING LIMITED MS/EI/04
Revision 0
PROJECT NAME _____ Page 3 of 11
1. PURPOSE
The objective of this method statement is to provide general guidelines for
calibration and installation of field instrumentation at project site.
2. SCOPE
3. REFERENCES
4. DEFINITIONS
CL Client
PM Project Manager
SM Site Manager
CM Construction Manager
DE Discipline Engineer
ITP Inspection and Test Plan
QC Quality Control
QCI Quality Control Inspector
PQP Project Quality Plan
PPE Personal Protection Equipment
HSE PLAN Health Safety & Environment Plan.
DESCON ENGINEERING LIMITED MS/EI/04
Revision 0
PROJECT NAME _____ Page 4 of 11
5. RESPONSIBILITIES
It is overall responsibility of PM/SM to organize resources to perform
construction activities as per project specification, in compliance with quality,
schedule & safety requirements.
DE will ensure that all the works are performed safely as per latest Approved
for Construction (AFC) drawings & specifications.
The relevant DE and Supervisor will ensure that all the piping work is
conducted in accordance with this method statement and project
specifications
The QC Inspector will ensure that all work is executed according to PQP and
that requirements of quality dossier are full filled.
Safety and Construction activities shall be carried out with the close
coordination of client.
The instruments received from client shall be stored in the designated area of 3
the warehouse. 1
During shifting of the instruments special care shall be taken to protect from
any damage. Proper lifting and transporting equipment shall be used as 3
required. 1
6.2 PROCEDURE
All instruments are to be stored properly, after laboratory tests, safe from
dust, heat and humidity until required for field installation.
Where capillary systems are used, they shall be continuously supported and
protected and any excess length neatly coiled on a former. The installation
shall not introduce any standing errors.
Care shall be taken that the forces developed by the expansion of piping or
vessels shall not damage instruments or impulse piping.
DESCON ENGINEERING LIMITED MS/EI/04
Revision 0
PROJECT NAME _____ Page 6 of 11
Care shall be taken in locating tapping points to keep the impulse lines as
short as possible. Allowance shall also be made for withdrawal as
necessary.
6.2.3 INSPECTION
PRECAUTIONS
6.3.1 Existing Installations
No one shall be allowed to interfere with or work on, or work in the immediate
vicinity of, any existing electrical installations or equipment without a valid
permit to work. This applies to both temporary and permanent electrical
installations and equipment.
The electrical supply to powered hand tools shall not exceed 24 volts. Where
this is not possible, due to the type of tool being used, the approval of the
Client’s Representative must be sought. But these electrical supplies must be
protected by ELCBs (Earth Leak Circuit Breakers)
Electrical lighting for use in confined spaces shall not exceed 24 volts.
Powered hand tools used in confined spaces shall, be air operated. Where
this is not possible, all such tools shall be equipped with a dead-man’s switch.
All E&I equipment in stores, should be safe guarded from fire by placing
suitable fire extinguishers.
All panels shall be kept lock in order to avoid theft of small components
present in the panels.
Panel rooms shall be kept lock and entry should be prohibited for
unauthorized persons.
For excavation in rocky area while using jack hammer ear protection shall be
provided.
Unfilled excavated trenches must be provided with warning lights during night.
Area of cable pulling winch & cable drums jacks should be cordoned off /
guarded. Hand signals shall be used while pulling cables.
Chemical resistance gloves must be used while plugging the cable entries
with chemical sealant.
Splices of cables with cable knife shall be carried by experience workers & not
helpers in order to avoid injury.
Cables in open trenches shall be protected from welding sparks and other
falling objects by using GI sheets etc.
Signs shall be posted after back filling of cable trenches showing “ELECT
CABLE UNDER GROUND”.
Do not operate tags shall be placed on valves of inst. air supply where
necessary.
Hazard data sheet for mercury & air pressure shall be provided in instrument
lab.
Fire extinguisher shall be provided while filling oil in transformer and smoking
should not be allowed in vicinity of oil filling activities.
6.3.3 Scaffolding
Clear name and signature of the authorized scaffold inspector against each
separate scaffold inspected.
If there is any doubt about the security of any anchorage, suspension points
or ties for a scaffold, e.g., strength of existing buildings/structures, or these
under construction, the Client’s representative shall be consulted before
proceeding with erection.
All scaffolds shall be provided with suitable access and where ladders are
used for this purpose. They shall be of an adequate length and properly
secured by lashing or fixing to prevent displacement.
Correct type, size and weight of tool shall be used for each job.
Properly insulated and non-conductive tools shall be used for electrical work.
Screwdrivers - A screwdriver shall have the correct size of tip to fit the slot of
the screw. Screwdrivers shall not be hammered or twisted with pliers or
wrenches. Screwdrivers shall not be carried in the pockets.
Hammers - Right kind of hammer shall be selected for the job. Eye protection
shall be worn when hammering.
Chisels - Cutting edges shall be kept sharp. Chisels heads that have
mushroomed shall be repaired. Eye protection shall be worn when using a
cold chisel.
Spanners and wrenches - Right type and size shall be used. Extension on
spanners and wrenches shall not be used unless the wrenches are designed
for such use. A pipe wrench shall not be used as a hammer. A wrench
(except slugging wrenches) shall not be hammered to tighten a bolt.
Pliers shall not be used as wrenches. It will be ensured that scrap does not
fly off and cause injury when cutting metal with pliers. Only long handled
pliers shall be used to cut wire under tension. Pliers with insulated handles
shall be used for electrical work.
Jacks shall be positioned under the center of the load and placed on a solid
support. Jacks shall be operated slowly. It shall be ensured that no one gets
under items being picked up.
Power Tools - All portable power tools shall be stored in clean dry conditions.
Power tools shall not be left lying around the job site where they may be
damaged.
Rotating tools shall be switched off and held until rotation has completely
stopped before they are set down. Tools shall be disconnected before
changing bits, blades, cutters, or wheels.
All portable power tools shall be equipped with properly functioning "dead-
man switches".
Grinding Machine - Care shall always be taken to ensure that the grinding
wheel is free from defect before mounting.
The proper size and type of wheel shall be fitted to the tool so that the
maximum permissible periphery speed of the wheel does not exceed the
maximum speed displayed on the machine. No grinding machine shall be
used unless the maximum speed is clearly marked on the case. All wheels
shall be fitted with adequate guards.
During the installation all measures shall be adopted to ensure safe working.
Client site management system shall be implemented
Prior to start of job, an HSE (DESCON) person shall deliver the specific safety
instruction to the concerned personnel.
The workers will be made aware of safety requirements related to this activity
through daily, weekly and monthly toolbox and safety talks.
All access ladders and scaffoldings shall be secured and tagged before use.
Welding sets should be checked and maintained regularly for wear and tear.
Waste Management should be strictly followed to keep the job site neat and clean.
9.0 ATTACHMENTS
Nil