(2021) Sgca 61
(2021) Sgca 61
[2021] SGCA 61
Between
Between
GROUNDS OF DECISION
[Insolvency Law] — [Winding up]
[Building and Construction Law] — [Statutes and regulations]
TABLE OF CONTENTS
FACTS...............................................................................................................2
PARTIES AND CONTRACTUAL MATRIX .............................................................2
BACKGROUND TO THE PARTIES’ DISPUTE ........................................................4
PROCEDURAL HISTORY ..................................................................................10
Progress Claim No 17 and Suit 917 of 2019............................................10
Adjudication Application 339 of 2019 .....................................................11
Suit 1282 of 2019 and the Consolidated Suit ...........................................12
OS 223 of 2020.........................................................................................13
CWU 95 and SUM 1577...........................................................................14
i
WHETHER ZK HAS A CROSS-CLAIM AGAINST DGE
WHICH JUSTIFIES THE STAY OR DISMISSAL OF CWU 95 ............44
CONDITIONS OF STAY..............................................................................53
POWER TO ORDER CONDITIONAL STAY ..........................................................54
WHETHER A CONDITIONAL STAY OUGHT TO BE GRANTED .............................55
CONCLUSION...............................................................................................57
ii
This judgment is subject to final editorial corrections approved by the
court and/or redaction pursuant to the publisher’s duty in compliance
with the law, for publication in LawNet and/or the Singapore Law
Reports.
[2021] SGCA 61
21 June 2021
Introduction
judgment entered under s 27(1) of the SOPA (“s 27(1) SOPA Judgment”). DGE
then served a statutory demand on the contractor, Zhong Kai Construction
Company Pte. Ltd (“ZK”), demanding payment of the judgment debt. When ZK
failed to pay the same, DGE filed a petition to wind up ZK in HC/CWU 95/2020
(“CWU 95”).
Facts
2
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
6 The Project was divided into two phases, Phase 1 (an 8-storey
Equipment Building) and Phase 2A (a 2-storey Annex Building, excluding an
Airport Emergency Service Watchroom). The Subcontract was expressed to
commence immediately and, pursuant to cl 4 of the Subcontract, the scheduled
dates for the completion of Phases 1 and 2A of the Project were to be no later
than 31 July 2017 and 20 February 2017 respectively.3 Pursuant to cl 6 of the
Subcontract, DGE was liable to pay liquidated damages for late completion of
the Subcontract Works, calculated at the rate of S$1,800 per day of delay for
Phase 1, and S$800 per day of delay for Phase 2A. Clause 6 also provided that
ZK was “entitled to deduct or set-off against any monies due to [DGE] under
3
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
7 We now proceed to briefly narrate the events which led to the present
proceedings between the parties. It is important to note that we make no binding
or final findings of fact in the following paragraphs or elsewhere in these
grounds of decision. We merely record what we see in contemporaneous
documents put before us and we have borne in mind that the picture is not
complete. All these allegations will no doubt be fully explored during the course
of the legal proceedings between the parties, and we make reference only to the
details that are necessary for our purposes.
9 However, based on the documents before us, we can surmise that the
disagreements between the parties most likely began in early 2018. There is
correspondence showing allegations from DGE that, from that period onwards,
there were delays in its completion of the Subcontract Works because of late
approvals, changes to specifications, unsigned variations and slow or
4
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
inadequate payment by ZK.5 DGE also claimed there was “zero” certification
for work it had completed up until Progress Claim 12, and a “negative”
certification in respect of Progress Claim 13.6 On the other hand, there is
evidence that ZK made advance payments or loans to DGE with repayment
being effected through set-offs or partial set-offs against certified progress
payments and amounts due to DGE.7 ZK also exhibited a number of emails
complaining of DGE’s delays. For example, in an email dated 16 February
2017, ZK complained of, inter alia, DGE’s late delivery of cladding material
and its slow bracket and runner installations, and requested for DGE to catch up
with its work.8 In another email dated 1 March 2018, ZK complained that DGE
had yet to complete outstanding works despite ZK making it advance payments
of S$50,000 on 11 August 2017, S$22,000 on 1 February 2018 and S$30,000
on 13 February 2018 to support DGE’s purchase of material and to assist DGE
in paying its staff and workers in advance.9 In the same email, ZK also noted
that DGE had submitted Payment Claim 11 late on 8 February 2018 even though
it had been due on 28 January 2018. ZK stated that its email was a “[l]ast
warning” for DGE to complete its outstanding works, failing which ZK would
engage third parties to complete the same on their behalf.
5
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
25 April 2018 stating that due to no payments being received, it was unable to
continue to pay for the cabin glass.10 In reply, ZK enclosed the SO’s Instruction
(“SOI”) 033 dated 24 April 2018 issued pursuant to Clause 2.5 of the PSSCOC,
which noted delays to R3 Tower Cabin Glass and their knock-on effects on other
works.11 Observing that “cancel[ling] the purchase order for cabin glass [would
have a] a serious impact… [on] overall completion of work”, ZK stated it would
help DGE purchase the cabin glass, and that the sums spent would be deducted
from DGE’s progress claims.12 Notably, there are two ZK cheques to Singapore
Safety Glass Pte Ltd (“SSG”), one dated 25 May 2018 for S$19,927.56 and the
other dated 27 April 2018 for S$41,713.14 included in the documentary
evidence.13
10 RSCB at p 107.
11 RSCB at p 109.
12 RSCB at p 106.
13 RSCB at pp 114 and 115.
6
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
7
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
(iv) DGE replied again (at 9.29pm on the same day) restating
its position that it did not agree to the figures calculated by ZK.
It also said that since it had yet to be paid by ZK, it was unable
to “proceed for allocation of manpower to site”.17
(c) Three days later, on 29 June 2018, DGE sent ZK a letter by email
stating that it had no choice but to accept ZK’s repudiatory breach and
terminate the Subcontract. However, DGE added that as a gesture of
goodwill, it was willing to move forward on the condition that:
8
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
The letter also stated that this would be the parties’ last correspondence
on the matter as “all [of DGE’s] earlier correspondence ha[d] been
ignored, refuted without justification and/or left unanswered”.18
(i) “We are surprised to see your letter dated 29th June 2018,
in which all the figures and matters reflected are untrue and
misleading” [emphasis added].
(iii) “As informed through our emails dated 22nd June 2018
9:59AM, 26th June 2018 12:21PM & 7:19PM, 27th June 2018
9
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
(e) On 10 July 2018, DGE sent another letter to ZK, explaining that
DGE had stopped work on the Project because ZK had refused to pay
the sum owed to DGE. DGE also stated that ZK’s calculations in the
letter dated 30 June 2018 were incorrect, and reiterated that the contract
between them had been terminated.21
Procedural history
10
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
through their then solicitors, Messrs Peter Ong Law Corporation, against DGE.
In the Statement of Claim for S 917, ZK claimed the sum of S$317,559.90 for
“goods sold and delivered and services rendered to [DGE] at [DGE’s]
requests”.23 Despite ZK’s rather odd characterisation of its claim, the particulars
given show items like “Supply Mobile Crane”, “Mobile Crane Operator
Overtime”, “Supply [of] Workers”, “Safety Issues”, “Annex Building”, “BCA
Submissions”, “Re-erect[ion] [of] scaffold”, “Third Party labour and Material”,
“Supply [of] capping cladding [at] R3 Cabin” and “Rental of Boomlift” making
up the S$317,559.90.
11
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
ZK had to “engage a third party contractor to (i) rectify the defects of [DGE’s]
construction works, (ii) complete [DGE’s] construction works that were left
incomplete, and (iii) prepare the construction works for final handing over”.27
27 ROA Vol IIIB at p 112 (Respondent’s Written Submissions for AA 339 at para 24).
28 ROA Vol IIIB at p 171–173 (Adjudication Determination at paras 152–161).
29 ROA Vol IIIB at p 9 (Rasanathan’s OS 223 Affidavit at para 21).
12
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
declaration that the Adjudicated Amount was not due and owing to DGE and/or
was wrongly determined.30
18 On 11 March 2020, ZK applied for and was granted an order for the
proceedings in S 1282 and S 917 to be consolidated, with S 1282 as the lead
suit. The consolidated proceedings are hereinafter referred to as “the
Consolidated Suit”. The sums claimed in the Consolidated Suit are identical to
those claimed in S 1282.31
OS 223 of 2020
13
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
was precluded from issuing a statutory demand in so far as S 1282 was not
discontinued.34
22 ZK did not meet the Statutory Demand by the stipulated deadline. Thus,
on 23 March 2020, DGE commenced CWU 95 to wind up ZK on the basis that
ZK had not satisfied the Statutory Demand and was deemed under s 254(2)(a)
read with s 254(1)(e) of the Companies Act (Cap 50, 2006 Rev Ed) (“CA”) to
be unable to pay its debts.35 CWU 95 was served on ZK and its solicitors on 24
March 2020.36
Decision below
24 On 24 June 2020, the Judge heard both OS 223 and SUM 1577. The
Judge dismissed OS 223 but allowed ZK’s application in SUM 1577 to stay
CWU 95 until the determination of the Consolidated Suit and any appeal
thereof. Her brief grounds of decision (“Judgment”) are set out in a minute sheet
14
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
dated the same day. For present purposes, we summarise only the Judge’s
findings vis-à-vis SUM 1577.
25 The Judge found that ZK had a bona fide and serious cross-claim against
DGE based on substantial grounds, and that the value of this cross-claim might
exceed the Judgment Debt. In her view, the cross-claim raised triable issues
such as (a) whether it was ZK or DG who was in repudiatory breach of the
Subcontract; (b) whether ZK could rely upon cl 6 of the Subcontract to claim
liquidated damages; (c) whether some of ZK’s claims even arose from the
Subcontract; and (d) whether certain costs and expenses incurred by ZK could
be claimed against DGE. The Judge was also of the view that ZK’s pleadings
were sufficiently particularised to set out its cause of action against DGE
(Judgment at [24]).
26 The Judge further held that it could not be definitively concluded that
ZK was abusing the court process by commencing S 917 and S 1282 against
DGE. Although it was DGE who had first served a payment claim on ZK, ZK
had commenced S 917 even before DGE commenced AA 339 (Judgment at
[25]). Accordingly, the Judge found that it was appropriate to grant the stay
sought by ZK.
28 DGE also made the alternative argument that, even if ZK was found to
have a valid cross-claim against DGE, CWU 95 ought to be stayed only on the
15
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
condition that ZK first paid the sum of S$211,044 (being the value of the
Judgment Debt) into court as security.
(a) ZK’s cross-claim was serious and bona fide as it raised numerous
triable issues;
(c) there were no valid grounds for a conditional stay for CWU 95.
Issues to be determined
30 The appeal before us arises only from SUM 1577 which, as stated at [23]
above, is an application to dismiss CWU 95 or, alternatively, to stay or adjourn
the hearing for CWU 95 pending the disposal of the Consolidated Suit.
31 Before us, both parties accepted that the court is generally empowered
to stay a winding-up application against a debtor on two grounds: (a) first, where
the debtor bona fide disputes the debt in the statutory demand on substantial
grounds (see Pacific Recreation Pte Ltd v S Y Technology Inc and another
appeal [2008] 2 SLR(R) 491 (“Pacific Recreation”) at [16]–[19]); and/or
(b) secondly, where the debtor has a serious cross-claim against the creditor
based on substantial grounds (see Metalform Asia Pte Ltd v Holland Leedon Pte
Ltd [2007] 2 SLR(R) 268 at [82] (“Metalform”)).
32 It should be noted that ZK, correctly in our view, did not attempt to
dispute the debt comprised in the AD or the s 27(1) SOPA Judgment obtained
thereon. It is not open to ZK to dispute that debt at this juncture before this Court
16
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
because s 21(1) of the SOPA confers temporary finality on the AD and there are
presently no legal proceedings afoot to invalidate the AD on legal grounds: see
W Y Steel Construction Pte Ltd v Osko Pte Ltd [2013] 3 SLR 380 (“W Y Steel
Construction”) at [71]. The AD and the s 27(1) SOPA Judgment can only be
challenged before an arbitral tribunal or a court seised of the final resolution and
determination of all disputes between the parties in relation to this project,
which usually takes place after the contract is completed or terminated as the
case may be.
17
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
18
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
suffice to show that his defence is not a frivolous one, or that the debt is
disputed on substantial grounds;
19
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
demand if the company bona fide disputed the debt. However, it was not an
abuse of process for a judgment creditor to serve a statutory demand on a
judgment debtor merely because the judgment was under appeal. If enforcement
of that judgment had not been stayed, the judgment creditor was entitled to take
all legal steps open to him to recover the amount of the judgment debt. Prakash J
also opined that once the matter had been tried at first instance and decided
against the judgment debtor, the prima facie position was that the debtor had no
defence to the claim and any further dispute over the debt would not be bona
fide (at [21]).
20
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
41 The decision in Pacific Recreation did not clarify whether the “triable
issue” standard was distinct from the “unlikely to succeed” standard which had
earlier been held to apply to cross-claims in Metalform. However, the two
standards were treated as equivalent in several High Court cases that followed.
In Denmark Skibstekniske Konsulenter A/S I Likvidation (formerly known as
Knud E Hansen A/S) v Ultrapolis 3000 Investments Ltd (formerly known as
Ultrapolis 3000 Theme Park Investments Ltd) [2011] 4 SLR 997 (“Ultrapolis”),
it was concluded at [26] (referring to Ashworth v Newnote Ltd [2007] EWCA
21
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
Civ 793 at [33]) that any linguistic divergence between the “triable issues”
standard in Pacific Recreation and the “unlikely to succeed” standard in
Metalform was “a distinction without difference”. The same view was later
taken in Strategic Construction Pte Ltd v JH Projects Pte Ltd [2018] 4 SLR
1192 (“Strategic Construction”) (at [20]), and by this Court in AnAn (at [27]).
22
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
23
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
44 In our view, the prima facie standard of review should also apply in
building and construction cases like the present where the cross-claim is not the
subject of an arbitration agreement. It would make little sense for the prima
facie standard of review to apply where the dispute comprised in the cross-claim
or disputed debt is the subject of an arbitration agreement, and for the higher
triable issue standard to apply where it is not. The case for a consistent approach
24
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
25
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
48 The purposes and aims of the statutory adjudication regime under the
SOPA have been well-articulated in many judgments of this Court and need
little rehearsing. The SOPA, inter alia, invalidates the pernicious and hitherto
prevalent pay-when-paid clauses, and facilitates cash flow to contractors,
subcontractors and suppliers in building and construction industry by providing
a quick, low cost adjudication system to resolve interim payment disputes in
construction projects. It is well-recognised that this efficient and speedy process
is necessarily “rough and ready justice” and that, given the compressed
timelines and sometimes voluminous evidence and documents, adjudicators
may get things wrong. However, their adjudication determinations have
temporary finality. This means that unless an adjudication determination is set
aside by a court on legal or technical grounds, it is final and binding on the
parties to the adjudication until their differences are finally and conclusively
determined or resolved by an arbitral tribunal or a court, usually after the project
26
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
50 It is clear that temporary finality ends when the arbitral tribunal or court
finally determines all the parties’ disputes, rights and obligations. When that
happens, any judgment previously obtained under s 27 of the SOPA to enforce
that adjudication determination must also cease to have effect; as common sense
dictates, the fruit must fall with the tree.
51 At the other end of the scale is the situation where the project is ongoing
and the ADJ debtor fails to make payment. This is the classic situation SOPA
was enacted to redress. Besides the remedies spelt out under SOPA and common
27
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
law, the ADJ creditor is entitled to levy execution on its judgment and this
includes serving a statutory demand and failing payment, proceeding to apply
to wind-up the ADJ debtor. Short of having the adjudication determination set
aside on legal or technical grounds, the ADJ debtor is in no position to dispute
the debt comprised in the adjudication determination; it has to pay the
adjudicated sum or face the consequences.
52 The real difficulty comes when the project comes or is coming to an end
or has been terminated, and the downstream party takes out an adjudication
application and secures an adjudication determination. To readily allow the ADJ
debtor to halt enforcement of the adjudication determination by alleging a cross-
claim on the prima facie standard might enable upstream parties to evade their
payment obligations all too easily. This would end up stifling the cash flow and
frustrate the “pay now, argue later” philosophy underlying the SOPA regime.
There is every likelihood that that would revert the law to its position prior to
the enactment of the SOPA, wherein upstream contractors could withhold
payment to downstream contractors simply by asserting a set-off or cross-claim:
see Harmonious Coretrades Pte Ltd v United Integrated Services Pte Ltd [2020]
1 SLR 206 at [50], citing Civil Tech Pte Ltd v Hua Rong Engineering Pte Ltd
[2018] 1 SLR 584 at [23]–[32].
53 It is not surprising to see that this is not the first occasion on which this
conundrum has been in issue before the Singapore courts. There are two prior
High Court decisions which directly address the issue that we have highlighted
above. It is to these decisions which we now turn.
28
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
Local position
54 In Lim Poh Yeoh (alias Lim Aster) v TS Ong Construction Pte Ltd [2016]
5 SLR 272 (“Lim Poh Yeoh”), the respondent commenced an adjudication
application against the appellant under the SOPA and subsequently obtained an
adjudication determination in its favour. The respondent then entered judgment
in the terms of the adjudication determination and issued a statutory demand
against the appellant for the outstanding amount owed under the judgment debt.
The issue was whether the appellant could set aside the statutory demand under
r 98(2) of the Bankruptcy Rules (Cap 20, R 1, 2006 Rev Ed) on the basis that
she had a valid cross-claim against the respondent in a separate High Court suit.
55 One of the respondent’s key contentions was that the court ought not to
set aside the statutory demand, even in the face of an ostensible competing
cross-claim, because this would be contrary to the “pay now, argue later”
philosophy undergirding the SOPA. After considering authorities from
Australia, England and New Zealand, Edmund Leow JC concluded (at [69])
that:
29
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
… She [ie, Dr Amy Khor] also asked why insolvency is not dealt
with here, although payment woes in the construction industry
are indeed a form of injustice. But in the area of insolvency, there
is a higher justice that must be served. There is an established
priority of payments that have to be made to different parties
who have suffered as a result of a party going insolvent. So this
priority should not be upset just because of the payment woes
in the construction industry. So we have therefore left insolvent
cases alone so as not to disrupt a process which is working well.
[emphasis added]
57 In Leow JC’s view, the passages cited above indicated that “to the extent
that there [was] a normative conflict between the legislative policy of
facilitating cash flow in the construction industry and the wider purposes of the
insolvency process… [Parliament was of the view that] the former must yield
to the latter” (at [73]). Thus, Leow JC concluded that a debtor was not precluded
from setting aside a statutory demand on the basis that he had a valid cross-
claim against a creditor which, if successful, would liquidate the debt in the
statutory demand, provided that such a cross-claim did not seek to deny the
validity of the adjudication judgment debt. Since the appellant’s cross-claim
gave rise to triable issues, was sufficiently quantified in monetary terms and was
“clearly broader in scope than the adjudication”, Leow JC held that the statutory
demand could be set aside (at [76]).
30
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
59 Relying on the parliamentary debates for the SOP Bill (see [56] above),
Tan Siong Thye J reached the same conclusion as Leow JC that Parliament had
intended for the insolvency regime to prevail over the SOPA regime in the event
of a conflict between the two. He thus held (at [57]) that:
31
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
actions would not lead to a circumvention of the SOPA (at [60]). Tan J thus
allowed the defendant’s application for a stay on the basis that it had established
a triable issue in the form of a genuine cross-claim, the value of which exceeded
the amount claimed in the statutory demand.
62 In Diploma Construction (WA) Pty Ltd v KPA Architects Pty Ltd [2014]
WASCA 91 (“Diploma”), the applicant debtor was issued with a statutory
demand based on a judgment entered in the terms of two adjudication
determinations under the Construction Contracts Act 2004 (Western Australia)
(“WA CCA”). The applicant sought to aside the statutory demand on the basis
that it had an offsetting claim against the petitioning creditor. The Supreme
Court of Western Australia held that an adjudication determination under the
WA CCA gave rise to debts which were “due and payable” and which,
accordingly, could not be challenged in bankruptcy proceedings on the basis
that there was a “genuine dispute” as to their validity (at [59] and [62]).
However, the court held that where a debtor had “genuine” offsetting claims
against the petitioning creditor “arising from transactions separate from those
that gave rise to judgment debt based upon an adjudication under the [WA
32
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
CCA]”, there was no doubt that the debtor could successfully apply to set aside
the statutory demand (at [68]). As to the test for a “genuine” offsetting claim,
the court held that this meant that the offsetting claim had to be “bona fide… [it
could not be] “spurious, hypothetical, illusory or misconceived” (at [52]).
33
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
already been considered and rejected by the adjudicator during the adjudication.
Robb J held (at [168]) that the NSW SOPA only conferred temporary finality
on the adjudicated amount – it did not “clothe the adjudicator’s reasoning with
any finality that must be accepted by the court” [emphasis added]. Accordingly,
“[t]he apparent determination by the adjudicator that [the debtor] was not
entitled to succeed on its offsetting claims did not in any way bind [the] court
on an application to set aside the statutory demand” (at [171]). On the facts, the
applicant’s cross-claims were genuine, and that it was therefore permitted to
rely on them to set the statutory demand aside.
65 J Group is notable for its, with respect, correct view that, allied to the
concept of temporary finality and rough justice handed down within tight
timelines, decisions by an adjudicator on the validity of cross-claims are not
necessarily binding for all time nor on a court considering the merits of a
winding-up petition.
66 It ought to be noted that in New South Wales, the test for determining
whether a “genuine” offsetting claim exists is whether the court is satisfied that
there is a serious question to be tried that a party has an offsetting claim, or that
the claim is not frivolous or vexatious: see BBB Constructions Pty Ltd v
Frankipile Australia Pty Ltd [2008] NSWSC 982 at [4].
34
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
68 Shaw has been followed in R & S Fire and Security Services Limited v
Fire Defence plc [2013] EWHC 4222 at [13] and Cosmur Construction
(London) Limited v St Lewis Design Limited [2016] EWHC 2678 at [5]. In the
latter case, Christopher Nugee J defined a “genuine” offsetting claim as one that
was “of substance” (citing In re Bayoil S.A. [1999] 1 WLR 147).
35
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
36
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
73 This Court added in BNP Paribas that there were wider public policy
considerations which had to be borne in mind when creditors threatened
companies with winding-up petitions in circumstances where the claims or
debts were not admitted, or where there were bona fide cross-claims equal to or
37
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
exceeding the creditors’ claims. In support of this point, this Court referred to
its earlier decision in Metalform where it observed (at [84]) that a creditor’s
winding-up petition implies insolvency and is likely to damage the company’s
creditworthiness or financial standing with its other creditors or customers (BNP
Paribas at [17]). This Court further elaborated that a winding-up petition might
trigger cross-default clauses in the company’s own financing instruments or in
other companies within the same group as the company. At the end of the day,
many other economic and social interests might be affected, such as those of the
company’s employees, non-petitioning creditors, the company’s suppliers,
customers and shareholders (BNP Paribas at [18]–[19]). As such, in cases
where a company was temporarily insolvent, the winding-up court might
adjourn the hearing of a winding-up application under s 257(1) of the CA to
allow the company time to resolve the issues at hand, or order an injunction of
limited duration to restrain a winding-up petition from being presented if
irreparable harm could flow from its presentation (BNP Paribas at [20]).
75 Having set out the true nature of the winding-up jurisdiction of the court
and the principles upon which that power is exercised, we next turn to the
provisions of SOPA.
38
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
77 The ADJ creditor can also serve a statutory demand giving the ADJ
debtor three weeks to pay the debt, failing which it may, as in this case, proceed
to file a petition to wind-up the ADJ debtor. However, because the winding-up
of a company is a draconian order to make, with, as acknowledged by the courts,
wider economic and social ramifications (not least of all being the complete
demise of the corporate entity in question), different considerations and rules
come into play. As we have seen above, the courts will entertain an application
for an injunction to restrain the ADJ creditor from commencing winding-up
proceedings or, if the ADJ debtor is too late for that, the court will hear
applications for a dismissal of the winding-up petition or a stay of the same.
Needless to say, even if the winding-up application is stayed or dismissed, the
other avenues to obtain satisfaction of the judgment debt still remain.
39
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
78 Despite the court’s strong backing of the “pay now, dispute later”
approach, a blind enforcement of ADs, whatever the facts of circumstances of
a case may be, has never been the rule. In W Y Steel Construction, Sundaresh
Menon CJ (delivering the judgment of this Court) said (at [61]–[62]):
79 Once a project has commenced, the interim payment regime kicks in.
The primary source for the interim payment procedure and obligations will be
40
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
the contract (see Shimizu Corp v Stargood Construction Pte Ltd [2020] 1 SLR
1338 at [2]). Where the contract is deficient or silent, the provisions of the
SOPA, like ss 5–8 and ss 10–12, will apply subject to the terms of the contract.
In the great majority of cases, whilst the project is on-going, interim payments
are made and if necessary, enforced through adjudication applications, leading
to adjudication determinations. Often, the upstream party makes payment in the
interest of getting on with the project. The upstream party can, if it thinks it has
the grounds to do so, challenge the adjudication determination in court
proceedings on legal or technical grounds, whereupon the whole adjudication
determination may be set aside, but until then it cannot dispute the amount stated
in the adjudication determination. If the contract allows a party to commence
arbitral proceedings before the end of the project, it may be possible for that
party to issue a notice of arbitration to challenge the adjudication determination,
but it will have to pay the adjudicated sum first.
80 The first exception to this rule has been referred to above, where the
ADJ debtor applies to court to set aside or annul the adjudication determination
on legal or technical grounds under s 27(6) of the SOPA. As noted above, whilst
it does so, it has to pay the adjudicated sum into court (see s 27(5) of the SOPA).
Not many succeed on the grounds set out under s 27(6) of the SOPA as case law
has gradually ironed out the uncertainties caused by rival interpretations of those
provisions. If the adjudication determination has been set aside, it follows there
is no more debt arising from the adjudication determination.
81 The second exception occurs after the construction project has come to
an end or has been terminated. In this regard, it is worth reiterating this Court’s
remarks in Orion-One at [53] (which we have referred to earlier at [49] above)
that the parties’ rights and obligations will be conclusively determined after the
termination of the contract:
41
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
42
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
parties. Failing to carry out a careful cost-benefit analysis “would only serve to
introduce a further layer of costs with no apparent benefit.” (Orion-One at [4])
and we add that there may be cost consequences in appropriate cases.
84 For completeness, we state our view that we do not think that the
parliamentary debates for the SOP Bill which were referred to in Lim Poh Yeoh
43
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
(see [56] above) and Strategic Construction (see [59] above) go so far as to
imply that the insolvency regime will inevitably prevail over the SOPA regime
in the event of any conflict between the two. We also think it unnecessary, for
present purposes, to determine whether any one regime takes precedence over
the other, because the approach that we have outlined above satisfactorily
reconciles the apparent tensions between the two.
44
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
87 DGE contended that ZK’s cross-claim was not genuine and did not meet
the “triable issue” standard (which, DGE argued, was the relevant standard of
review) for the following reasons:
(b) Both of ZK’s claims were predicated on the assertion that DGE
had repudiated the Subcontract by abandoning the Subcontract Works
from 6 June 2018. However, there was no repudiatory breach on DGE’s
part since DGE had lawfully terminated the Subcontract of 5 June 2018
by virtue of ZK’s repudiatory breach.39
(c) In respect of ZK’s claim for delay, it was primarily ZK’s own
changes to the design and material specifications of the Project which
had resulted in delays to the completion of the Subcontract Works.
Furthermore, the computation of the sum of S$501,800 was based on
cl 6 of the Subcontract, which was an unenforceable penalty clause.40
(d) ZK’s claim for defective and incomplete Subcontract Works was
arbitrary and unsupported by the exhibited invoices. These invoices
“reflect[ed] work which could not have been attributed to DGE at all”.
They were also “sent belatedly and obviously contrived”.41
45
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
the trial judge in the Consolidated Suit. Whilst we may refer to various emails
or letters, these will no doubt be supplemented at trial by more complete
documentation and/or oral evidence. Furthermore, our comments or views must
be seen in the context of the applicable standard of proof, which as stated above,
is the prima facie standard. ZK need only adduce sufficient evidence to meet
that standard in order to justify the granting of a stay of a winding up petition.
89 In our judgment, ZK has clearly met the required prima facie standard
to resist a winding-up order being made. In fact, we would say that on the
evidence put before us, ZK has satisfied the triable issues test, if indeed that was
the standard to be adopted. We elaborate on the reasons for this conclusion
below.
46
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
93 We also add that the sums claimed by ZK are, in our view, clearly
quantified. It is apparent from the Statement of Claim that the claim for
S$501,800 is premised on the rates set out under cl 6 of the Subcontract (see
47
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
paragraph 19 of the Statement of Claim), and that the claim for S$380,870.25 is
derived by adding up the additional costs and expenses which ZK allegedly
incurred in engaging substitute sub-contractors to rectify or complete the
Subcontract Works (see paragraph 14 of the Statement of Claim). Details of
such claims will become clear during discovery.
94 DGE’s second contention was that ZK had refused to pay DGE for the
Subcontract Works in full and that it had thereby renounced the Subcontract
pursuant to Situation 2 in RDC Concrete Pte Ltd v Sato Kogyo (S) Pte Ltd and
another appeal [2007] 4 SLR(R) 413. Consequently, DGE argued, there was no
basis for ZK’s claim that DGE had repudiated the Subcontract by walking off
the Project site and not sending workmen to the site after 6 June 2018. In
response to this argument, ZK averred that there were no payments lawfully due
and owing to DGE, as DGE had “cause[d] delays and defective works in the
course of carrying out the Subcontract Works”.44
96 As noted at [6] above, the contract completion dates for Phases 1 and
2A of the Subcontract were 31 July 2017 and 20 February 2017 respectively.
ZK’s primary contention, which it has maintained throughout these
proceedings, is that DGE walked off site and did not send any workers from 6
48
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
June 2018. Importantly, DGE does not deny this as a fact, but alleges that its
conduct was justified because of ZK’s repudiation of the contract by non-
payment. As a proposition of building and construction law, that is not
necessarily correct. There may be instances in which a persistent course of
payment delays, or a protracted delay in the payment of a very substantial sum
amounts to a repudiation of the contract: see for example AL Stainless Industries
Pte Ltd v Wei Sin Construction Pte Ltd [2001] SGHC 243 at [194], citing Chow
Kok Fong, Law and Practice of Construction Contract Claims (Longman, 2nd
ed, 1993) at p 264. However, not every instance of non-payment by a
contracting party will suffice to constitute repudiation. This was made clear in
Jia Min Building Construction Pte Ltd v Ann Lee Pte Ltd [2004] 3 SLR(R) 288
(“Jia Min”) at [55], where the court stated, citing Lubenham Fidelities and
Investments Co Ltd v South Pembrokeshire District Council (1986) 33 BLR 46:
“[i]t appears settled law that a contractor/subcontractor has no general right at
common law to suspend work unless this is expressly agreed upon. This is so
even if payment is wrongly withheld”. The court also cited Halsbury’s Law of
Singapore, vol 2 (LexisNexis Singapore, 2003 Reissue) at para 30.321, Keating
on Building Contracts (Sweet & Maxwell, 7th ed, 2001) at para 6-96 and
Hudson’s Building and Engineering Contracts, vol 1 (Sweet & Maxwell, 11th
ed, 1995) at para 4-223 for the same principle. The rationale for this, the court
explained, was that “the existence of such a right [to suspend work upon the
other party’s failure to make payment] could create chaos within the building
industry if contractors were to muscle their way through disputes with threats
or actual threats or suspension instead of having their disputes adjudicated” (at
[57]).
49
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
workers (see [9] above). These advances are also alluded to at paragraph 146 of
the AD.45 On the evidence before us, we cannot rule out the possibility that some
of the sums that were allegedly due to DGE were liable to be offset by these
advance payments.
98 DGE’s third contention was that there was no basis for ZK’s claim for
delay. In our view, on the prima facie standard of review, the documents before
us do support the inference that there were delays on DGE’s part. We have
referred to ZK’s emails and one letter from the SO noting delays by DGE (see
[9] above), as well as ZK’s emails and letters complaining of the lack of DGE
workers on site (see [11] above). Moreover, we see that DGE did acknowledge
that there had been delays to the completion of the Subcontract Works. Its
primary defence was that these delays had been occasioned by ZK’s own failure
to obtain approval from the relevant authorities and that ZK had in any event
“agreed by conduct, if not expressly”, to the extensions of time sought by
DGE.46 However, there was no evidence of any such agreement save for a series
of correspondence between the parties ostensibly showing that, despite DGE’s
reminders, ZK had not sought approval from the Building and Construction
Authority for DGE to carry out certain works.47 Even if we accept that these
letters support DGE’s claims, we do not think that it can be conclusively
determined, based on this single instance, that DGE cannot be held liable for
any delay on its part.
99 The Subcontract clearly sets out the rates of liquidated damages for
delays on DGE’s part. We do not, without more, see that such provisions or
50
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
101 On the other hand, we note that ZK’s case, as well as the sums claimed
by ZK, fluctuated several times during the course of the proceedings between
the parties. Prior to commencing court proceedings against DGE, ZK had
asserted, in its letter to DGE dated 30 June 2018, that there had been delays on
DGE’s part, and that some of the Subcontract Works were defective and
incomplete. In respect of the latter, ZK claimed “costs incurred on site”
aggregating S$42,623.50.49 However, in its Statement of Claim for S917 dated
14 September 2019, ZK claimed S$317,559.90. That sum was, rather
inappropriately, stated to be for “goods sold and delivered and services rendered
to [DGE] at [DGE’s] requests” (see [13] above).50 In its payment response for
the adjudication submitted two days later, on 16 September 2019, ZK again
appeared to change its story – this time, it raised issues pertaining to incomplete
and defective works, but failed to mention any delay on DGE’s part.51
51
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
102 In our view, the discrepancies in ZK’s case do not mean that its cross-
claim against DGE fails to meet the prima facie standard of review. As we
commented at [13] above, notwithstanding the strange formulation of the
Statement of Claim in S 917, the particulars that were pleaded therein show the
nature of ZK’s claim. ZK had changed solicitors before filing S 1282, and it was
therefore only in the Statement of Claim for S 1282 and the Consolidated Suit
that ZK’s claims crystallised into their current and more coherent form.
103 The correspondence between the parties also gives us reason to believe
that ZK’s cross-claim is bona fide. As noted at [11(a)] above, DGE had sent ZK
an ultimatum on 30 May 2018, demanding payment of S$149,436.99 by 12pm
on 5 June 2018 failing which it would treat the Subcontract as terminated. DGE
subsequently withdrew its workmen from site from 6 June 2018 onwards.
Although there was some grandstanding between the parties, DGE did not send
any more workmen to the site and on 30 June 2018, ZK sent a letter to DGE,
stating that since DGE had not deployed manpower on site since 6 June 2018
and its works were defective and incomplete, ZK would mobilise third parties
to complete the remaining and defective works and hold DGE responsible for
all consequences (see [11(d)] above). That letter could evince ZK’s acceptance
of DGE’s repudiation or termination of the Subcontract as expressed in DGE’s
email dated 30 May 2018. It is also significant that the key facets of ZK’s claim
– comprising delay on DGE’s part, as well as incomplete and defective
Subcontract Works – were raised as early as 30 June 2018, well before DGE
served PC 17 on ZK, some 14 months later, on 28 August 2019. In the
circumstances, we find that, contrary to DGE’s assertions, there was nothing to
show that ZK’s cross-claims were conjured up simply to stave off the winding-
up petition. ZK’s failure to mention DGE’s alleged delay in its payment
52
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
response, as well as its unsubstantiated claim for “goods sold and delivered” in
the Statement of Claim for S 917, is only a factor to be taken into account.
Conditions of stay
105 It was argued by DGE that, even if this Court were to grant a stay of
CWU 95, it ought to do so only on the condition that ZK paid the Judgment
Debt of S$211,044 into court as security pending the outcome of the
Consolidated Suit.
106 Two reasons were proffered for this contention. The first was that,
pursuant to s 27(5) of the SOPA read with O 95 r 3 of the ROC, a party seeking
to set aside an adjudication determination made under the SOPA had to pay the
outstanding portion of the adjudicated amount into court as security. According
to DGE, since the Consolidated Suit was, in effect, commenced by ZK to
challenge the AD, granting an unconditional stay of CWU 95 would “defeat the
legislative intent of SOPA and render the adjudication determination
nugatory”.52
53
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
107 DGE also asserted that ZK might be at risk of insolvency given that the
value of the Judgment Debt was S$211,044 and ZK had a paid-up capital of
only S$300,000. Thus, “given time, it would be possible for ZK to clear its other
liabilities and close down, therefore totally abandoning its responsibility to pay
[the Judgment Debt] to DGE”.53
[emphasis added]
It cannot be made more plain by the words italicised above that the court’s
discretion as to what directions it may give in relation to a winding-up
proceeding is very wide, viz. as the court “thinks fit.” Indeed, our courts have
previously stayed winding up proceedings on condition that the sum of the debt
claimed in the statutory demand be paid into court: see for example Strategic
Construction at [62].
54
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
109 We note that this position is also consistent with that expressed in the
bankruptcy regime: see Mohd Zain bin Abdullah v Chimbusco International
Petroleum (Singapore) Pte Ltd and another appeal [2014] 2 SLR 446 (“Mohd
Zain”) at [18], where this Court held that it was empowered to impose
conditions on a stay of bankruptcy proceedings pursuant to ss 64(1), 65(4) and
65(5) of the Bankruptcy Act (Cap 20, 2009 Rev Ed).
110 Under s 27(5) of the SOPA, an ADJ debtor who applies to court to set
aside an adjudication determination or the judgment obtained for its
enforcement pursuant to s 27(1) of the SOPA must pay into court the unpaid
portion of the adjudicated amount as security. However, we do not think it
appropriate to lay down a general rule that parties in the position of ZK should
pay the adjudicated amounts into court pending the resolution of the arbitral
tribunal or the court.
111 There may be circumstances which make this a just condition, yet there
may be other circumstances where making such an order would be unjust. One
example of the latter type of situation is where the project is at an end or in the
defects liability phase or has been terminated, and the downstream party
launches its payment claim which is, in effect, its final accounts for the project.
Many adjudicators dread this scenario where they are under tremendous
pressure to decide the final accounts of a project within the time strictures of
SOPA, as this task is well-nigh impossible except in the simplest construction
contracts. In such cases, the adjudicator’s endeavour to achieve rough and ready
justice may produce an erroneous adjudication determination which may be
very large in value. To make an ADJ debtor pay this sum into court may cause
55
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
great financial stress; it can result in tying up large sums of money whilst the
matter is arbitrated or litigated.
112 Turning to the facts of this case, we take the view that it is appropriate
to require ZK to pay the sum of the Judgment Debt into court. We have borne
in mind ZK’s lack of a response to DGE’s payment claim, the strange pleadings
in S 917, the failure to state a total response amount and the varying amounts of
ZK’s alleged cross-claims. Some of these factors were ameliorated by the filing
of S 1282 and the Consolidated Suit which placed ZK’s cross-claim on a more
secure footing. We also note that the Judgment Debt was not inordinately high
or crippling. Although we are of the view that the evidence before us more than
meets the prima facie test, we consider it just to order ZK to pay the ADJ sum
into court on the analogy of s 27(5) of the SOPA. Upon ZK paying the sum of
the Judgment Debt into court, there can be no justification to presume that ZK
is insolvent on the basis that it is unable to pay its debts (see BNP Paribas at
[7], cited at [72] above).
113 For completeness, we clarify that we do not see any merit in DGE’s
submission that ZK is at real risk of insolvency as DGE did not offer anything,
apart from bare assertions, to support this claim. Clearly, the fact that ZK had a
paid-up capital of S$300,000 does not in itself demonstrate that ZK did not have
enough assets to discharge its liabilities. On the contrary, ZK’s balance sheet as
at 30 September 2019 shows that its total assets of S$3,156,585.31 far exceeded
its total liabilities of S$356,334.17.54 Further, there was no evidence before us
that any creditors aside from DGE had taken out winding-up applications
against ZK. We thus find that this particular contention is not an appropriate
reason to grant a conditional stay in the present case.
56
Diamond Glass Enterprise Pte Ltd v [2021] SGCA 61
Zhong Kai Construction Co Pte Ltd
Conclusion
114 For the reasons set out above, we varied the High Court’s decision and
upheld the stay only on the condition that ZK paid the sum of S$211,044 into
court within 14 days from the date of the hearing before us. As an alternative to
payment into court, we allowed parties to agree on any other form of security,
failing which the first order of payment into court would stand.
Quentin Loh
Judge of the Appellate Division
Luo Ling Ling and Sharifah Nabilah binte Syed Omar (Luo Ling
Ling LLC) for the appellant;
Kris Chew Yee Fong and Isabel Su Hongling (Zenith Law
Corporation) for the respondent.
57